BEL503: Power system I
Tutorial Sheet: 01
Course instructor: Nishant Saxena

Q:1 the section bus bar A and B are linked by a bus bar reactor rated at 5000 KVA with 10%
reactance. On bus bar A, there are two generators each of 10,000 KVA with 10%reactance and
on B Two generator each of 8000 KVA with 12% reactance. Find the Steady MVA fed into a
dead short circuit between all phases on B with Bus bar reactor in the circuit.

Q2: A 33 KV bus bar of a station are in two sections A and B seperated by a reactor. Section A
is fed from Four 10 MVA geenrators each having 20% reactance ans section B is fed from the
grid through 50 MVA reactance of the reactor to prevent the circuit breakers being overloaded if
a symmetrical short circuit occurs on an ongoing feeder connected to it.
Ans: [ 1.45 ohm].

Q3. A single phase two winding transformer is rated 25 kVA , 1100/440 volts , 50 Hz, the
equivalent leakage reactance of the transformer reffered to the low voltage side is 0.06|78 ohm.
Using transformer rating as base values, determine the per unit leakage impedence refered to low
voltage winding and refered to high voltage winding.
Ans: 7.74 x 103 |78 pu

Q4:

Ans: Ztotal(pu)= 0.4058|64.86, V(pu) = 0.956|0

Q5:

Ans :

I(pu) = 2.355|-64.86

I=59.83|-64.86