ID Task

Mode
Task Name Duration Start Finish Successors Predecessors
0
Reliance Twin Tower Project 2003 840.09 days?Apr 9 8:30 AM Sep 1 10:30 AM
1 Project Start Date 1 day Apr 9 8:30 AM Apr 9 8:30 PM 5FS+156 days,494FS+361 days,3
2 Tower A1 579.91 days?Apr 10 8:30 AM Dec 5 12:30 PM
3 <New Task> 1 day? Apr 10 8:30 AM Apr 10 8:30 PM 5 1
4 Core Wall For Tower A1 385.91 days Sep 19 11:30 AM Oct 26 5:30 PM
5 Core Wall Ground Floor to 1st Floor 17 days Sep 19 11:30 AM Oct 7 9:30 AM 6 1FS+156 days,3
6 Core Wall 1st Floor to 2nd Floor 17 days Oct 8 8:30 AM Oct 25 3:30 PM 7,39 5
7 Core Wall 2nd Floor to 3rd Floor 20 days Oct 25 3:30 PM Nov 15 12:30 PM 8,43 6
8 Core Wall 3rd Floor to 4th Floor 17 days Nov 15 12:30 PM Dec 3 10:30 AM 9,47 7
9 Core Wall 4th Floor to 5th Floor 15 days Dec 3 10:30 AM Dec 18 5:30 PM 10,51 8
10 Core Wall 5th Floor to 6th Floor 14 days Dec 18 5:30 PM Jan 2 11:30 AM 11,55 9
11 Core Wall 6th Floor to 7th Floor 15 days Jan 2 11:30 AM Jan 17 6:30 PM 12,59 10
12 Core Wall 7th Floor to 8th Floor 15 days Jan 17 6:30 PM Feb 2 12:30 PM 13,63 11
13 Core Wall 8th Floor to 9th Floor 13 days Feb 2 12:30 PM Feb 15 7:30 PM 14,67 12
14 Core Wall 9th Floor to 10th Floor 12 days Feb 15 7:30 PM Feb 28 2:30 PM 15,71 13
15 Core Wall 10th Floor to 11th Floor 13 days Feb 28 2:30 PM Mar 13 8:30 PM 16,75 14
16 Core Wall 11th Floor to 12th Floor 22 days Mar 14 8:30 AM Apr 5 6:30 PM 17,79 15
17 Core Wall 12th Floor to 13th Floor 10 days Apr 5 6:30 PM Apr 16 12:30 PM 18,83 16
18 Core Wall 13th Floor to 14th Floor 10 days Apr 16 12:30 PM Apr 27 4:30 PM 19,87 17
19 Core Wall 14th Floor to 15th Floor 10 days Apr 27 4:30 PM May 8 10:30 AM 20,91 18
20 Core Wall 15th Floor to 16th Floor 11 days May 8 10:30 AM May 19 5:30 PM 21,95 19
21 Core Wall 16th Floor to 17th Floor 22 days May 19 5:30 PM Jun 11 3:30 PM 22,99 20
22 Core Wall 17th Floor to 18th Floor 10 days Jun 11 3:30 PM Jun 21 6:30 PM 23,103 21
23 Core Wall 18th Floor to 19th Floor 17 days Jun 21 6:30 PM Jul 9 4:30 PM24,107 22
24 Core Wall 19th Floor to 20th Floor 9 days Jul 9 4:30 PMJul 18 7:30 PM 25,111 23
7/8 10/28 2/17 6/9 9/29
February 11 October 1 May 21
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 1
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
ID Task
Mode
Task Name Duration Start Finish Successors Predecessors
25 Core Wall 20th Floor to 21th Floor 8 days Jul 18 7:30 PM Jul 27 10:30 AM 26,115 24
26 Core Wall 21th Floor to 22nd Floor 9 days Jul 27 10:30 AM Aug 5 5:30 PM 27,119 25
27 Core Wall 22nd Floor to 23rd Floor 9 days Aug 5 5:30 PM Aug 14 8:30 PM 28,123 26
28 Core Wall 23th Floor to 24th Floor 8 days Aug 15 8:30 AM Aug 23 11:30 AM 29,127 27
29 Core Wall 24th Floor to 25th Floor 9 days Aug 23 11:30 AM Sep 1 6:30 PM 30,131 28
30 Core Wall 25th Floor to 26th Floor 7 days Sep 1 6:30 PM Sep 9 9:30 AM 31,135 29
31 Core Wall 26th Floor to 27th Floor 8 days Sep 9 9:30 AM Sep 17 12:30 PM 32,139 30
32 Core Wall 27th Floor to 28th Floor 8 days Sep 17 12:30 PM Sep 25 4:30 PM 33,143 31
33 Core Wall 28th Floor to 29th Floor 8 days Sep 25 4:30 PM Oct 3 7:30 PM 34,147 32
34 Core Wall 29th Floor to 30th Floor 7 days Oct 3 7:30 PM Oct 11 10:30 AM 35,151 33
35 Core Wall 30th Floor to 31th Floor 7 days Oct 11 10:30 AM Oct 18 2:30 PM 36,155 34
36 Core Wall 31th Floor to 32nd Floor 8 days Oct 18 2:30 PM Oct 26 5:30 PM 159 35
37 Slab For Tower A1 370 days Oct 25 3:30 PM Nov 15 3:30 PM
38 Ground Floor 20 days Oct 25 3:30 PM Nov 15 12:30 PM
42 1st Floor 17 days Nov 15 12:30 PM Dec 3 10:30 AM
46 2nd floor 15 days Dec 3 10:30 AM Dec 18 5:30 PM
50 3rd floor 14 days Dec 18 5:30 PM Jan 2 11:30 AM
54 4th floor 15 days Jan 2 11:30 AM Jan 17 6:30 PM
58 5th floor 15 days Jan 17 6:30 PM Feb 2 12:30 PM
62 6th floor 13 days Feb 2 12:30 PM Feb 15 7:30 PM
66 7th floor 12 days Feb 15 7:30 PM Feb 28 2:30 PM
70 8th floor 13 days Feb 28 2:30 PM Mar 13 8:30 PM
74 9th floor 22 days Mar 14 8:30 AM Apr 5 6:30 PM
78 10 th floor 10 days Apr 5 6:30 PM Apr 16 12:30 PM
82 11 th floor 10 days Apr 16 12:30 PM Apr 27 4:30 PM
7/8 10/28 2/17 6/9 9/29
February 11 October 1 May 21
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 2
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
ID Task
Mode
Task Name Duration Start Finish Successors Predecessors
86 12 th floor 10 days Apr 27 4:30 PM May 8 10:30 AM
90 13 th floor 11 days May 8 10:30 AM May 19 5:30 PM
94 14 th floor 22 days May 19 5:30 PM Jun 11 3:30 PM 172,197
98 15 th floor 10 days Jun 11 3:30 PM Jun 21 6:30 PM 173,198
102 16th floor 17 days Jun 21 6:30 PM Jul 9 4:30 PM 174,199
106 17th floor 9 days Jul 9 4:30 PM Jul 18 7:30 PM 175,200
110 18th floor 8 days Jul 18 7:30 PM Jul 27 10:30 AM 176,201
114 19th floor 9 days Jul 27 10:30 AM Aug 5 5:30 PM 177,178FS+3 days,202
118 20th floor 9 days Aug 5 5:30 PM Aug 14 8:30 PM 179,180FS+3 days,203
122 21st floor 8 days Aug 15 8:30 AM Aug 23 11:30 AM 181,204
126 22nd floor 9 days Aug 23 11:30 AM Sep 1 6:30 PM 182,205
130 23rd floor 7 days Sep 1 6:30 PM Sep 9 9:30 AM 183,206
134 24th floor 8 days Sep 9 9:30 AM Sep 17 12:30 PM 184,207
138 25th floor 8 days Sep 17 12:30 PM Sep 25 4:30 PM 185,208
142 26th floor 8 days Sep 25 4:30 PM Oct 3 7:30 PM 186,209
146 27th floor 7 days Oct 3 7:30 PM Oct 11 10:30 AM 187,210,211
150 28th floor 7 days Oct 11 10:30 AM Oct 18 2:30 PM 188,212,213,189
154 29th floor 7 days Oct 18 2:30 PM Oct 25 5:30 PM 190,214,215,191
158 30th floor 6 days Oct 27 8:30 AM Nov 1 8:30 PM 192,216,217,193,163
162 31th floor 6 days Nov 2 8:30 AM Nov 8 11:30 AM 194,218,195,167
166 32nd floor 7 days Nov 8 11:30 AM Nov 15 3:30 PM
170 Staircase 170 days Jun 11 3:30 PM Dec 5 12:30 PM
171 ST 6 170 days Jun 11 3:30 PM Dec 5 12:30 PM
196 ST 7 158 days Jun 11 3:30 PM Nov 22 6:30 PM
219 Finish of Tower A1 1 day Nov 15 3:30 PM Nov 16 3:30 PM 567 218,169
7/8 10/28 2/17 6/9 9/29
February 11 October 1 May 21
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 3
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
ID Task
Mode
Task Name Duration Start Finish Successors Predecessors
220 ATRIUM 108.36 days Mar 15 8:30 AM Jul 6 8:30 PM
221 Pour 1 31 days Mar 15 8:30 AM Apr 16 12:30 PM 223FS-2 days
222 Pour 2 59 days Apr 14 12:30 PM Jun 15 3:30 PM
223 Marking for staging 3 days Apr 14 12:30 PM Apr 17 12:30 PM 224SS,245SS+3 days,246SS+3 days 221FS-2 days
224 Installation of staging HD tower 14 days Apr 14 12:30 PM Apr 29 7:30 PM 225SS+12 days 223SS
225 Column rebar termination 3 days Apr 27 4:30 PM Apr 30 7:30 PM 226,289,290 224SS+12 days
226 Column capping with GP2 4 days Apr 30 7:30 PM May 5 10:30 AM 227 225
227 Drilling for pinned connection 1 day May 5 10:30 AM May 6 10:30 AM 228 226
228 Fixing of circular plates 1 day May 6 10:30 AM May 7 10:30 AM 229 227
229 Rebar anchoring with HILTI 2 days May 7 10:30 AM May 9 10:30 AM 230FS-9 days 228
230 Beam bottom fixing 10 days Apr 29 7:30 PM May 10 10:30 AM 231FS-5 days 229FS-9 days
231 Beam rebar fixing 15 days May 5 10:30 AM May 20 5:30 PM 232FS-2 days 230FS-5 days
232 PT profiling/threading in beams 6 days May 18 2:30 PM May 24 5:30 PM 233 231FS-2 days
233 Beam side fixing 10 days May 24 5:30 PM Jun 4 11:30 AM 234FS-5 days 232
234 Slab decking 5 days May 30 8:30 AM Jun 4 11:30 AM 235 233FS-5 days
235 Slab bottom rebar laying 2 days Jun 4 11:30 AM Jun 6 11:30 AM 236 234
236 PT profiling in slabs 1 day Jun 6 11:30 AM Jun 7 11:30 AM 237 235
237 Slab top rebar laying 2 days Jun 7 11:30 AM Jun 9 3:30 PM 238FS-5 days 236
238 External board fixing 5 days Jun 4 11:30 AM Jun 9 3:30 PM 239 237FS-5 days
239 Supporting 3 days Jun 9 3:30 PM Jun 12 3:30 PM 240FS-13 days 238
240 Walkway arrangement for inspection 3 days May 30 8:30 AM Jun 2 11:30 AM 241 239FS-13 days
241 Repropping 4 days Jun 2 11:30 AM Jun 6 11:30 AM 242FS+6 days 240
242 Final inspection 2 days Jun 12 3:30 PM Jun 14 3:30 PM 243 241FS+6 days
243 Concreting 1 day Jun 14 3:30 PM Jun 15 3:30 PM 242
244 Pour 3 67 days Apr 17 12:30 PM Jun 27 9:30 AM
7/8 10/28 2/17 6/9 9/29
February 11 October 1 May 21
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 4
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
ID Task
Mode
Task Name Duration Start Finish Successors Predecessors
245 Marking for staging 3 days Apr 17 12:30 PM Apr 20 12:30 PM 223SS+3 days
246 Installation of staging HD tower 15 days Apr 17 12:30 PM May 3 7:30 PM 247FS-2 days,267,268 223SS+3 days
247 Column rebar termination 4 days May 1 7:30 PM May 6 10:30 AM 248 246FS-2 days
248 Column capping with GP2 6 days May 6 10:30 AM May 12 2:30 PM 249 247
249 Drilling for pinned connection 2 days May 12 2:30 PM May 14 2:30 PM 250 248
250 Fixing of circular plates 3 days May 14 2:30 PM May 17 2:30 PM 251 249
251 Rebar anchoring with HILTI 3 days May 17 2:30 PM May 20 5:30 PM 252FS-16 days 250
252 Beam bottom fixing 11 days May 3 7:30 PM May 15 2:30 PM 253 251FS-16 days
253 Beam rebar fixing 16 days May 15 2:30 PM May 31 8:30 PM 254FS-3 days 252
254 PT profiling/threading in beams 6 days May 29 8:30 AM Jun 4 11:30 AM 255 253FS-3 days
255 Beam side fixing 11 days Jun 4 11:30 AM Jun 15 3:30 PM 256FS-5 days 254
256 Slab decking 5 days Jun 10 3:30 PM Jun 15 3:30 PM 257 255FS-5 days
257 Slab bottom rebar laying 2 days Jun 15 3:30 PM Jun 17 6:30 PM 258 256
258 PT profiling in slabs 1 day Jun 17 6:30 PM Jun 18 6:30 PM 259 257
259 Slab top rebar laying 2 days Jun 18 6:30 PM Jun 20 6:30 PM 260FS-5 days 258
260 External board fixing 5 days Jun 15 3:30 PM Jun 20 6:30 PM 261 259FS-5 days
261 Supporting 2 days Jun 20 6:30 PM Jun 23 9:30 AM 262FS-12 days 260
262 Walkway arrangement for inspection 4 days Jun 10 3:30 PM Jun 14 3:30 PM 263 261FS-12 days
263 Repropping 4 days Jun 14 3:30 PM Jun 18 6:30 PM 264FS+4 days 262
264 Final inspection 2 days Jun 23 9:30 AM Jun 25 9:30 AM 265 263FS+4 days
265 Concreting 2 days Jun 25 9:30 AM Jun 27 9:30 AM 264
266 Pour 4 61.36 days May 3 7:30 PM Jul 6 8:30 PM
267 Marking for staging 1 day May 3 7:30 PM May 5 10:30 AM 246
268 Installation of staging HD tower 13 days May 3 7:30 PM May 17 2:30 PM 269FS-2 days 246
269 Column rebar termination 2 days May 15 2:30 PM May 17 2:30 PM 270 268FS-2 days
7/8 10/28 2/17 6/9 9/29
February 11 October 1 May 21
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 5
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
ID Task
Mode
Task Name Duration Start Finish Successors Predecessors
270 Column capping with GP2 2 days May 17 2:30 PM May 19 5:30 PM 271 269
271 Drilling for pinned connection 1 day May 19 5:30 PM May 20 5:30 PM 272 270
272 Fixing of circular plates 1 day May 20 5:30 PM May 21 5:30 PM 273 271
273 Rebar anchoring with HILTI 1 day May 21 5:30 PM May 22 5:30 PM 274FS-5 days 272
274 Beam bottom fixing 12 days May 17 2:30 PM May 29 8:30 PM 275 273FS-5 days
275 Beam rebar fixing 9 days May 30 8:30 AM Jun 8 11:30 AM 276FS-2 days 274
276 PT profiling/threading in beams 3 days Jun 6 11:30 AM Jun 9 3:30 PM 277 275FS-2 days
277 Beam side fixing 11 days Jun 9 3:30 PM Jun 20 6:30 PM 278FS-5 days 276
278 Slab decking 12 days Jun 15 3:30 PM Jun 28 9:30 AM 279 277FS-5 days
279 Slab bottom rebar laying 1 day Jun 28 9:30 AM Jun 29 9:30 AM 280 278
280 PT profiling in slabs 1 day Jun 29 9:30 AM Jun 30 12:30 PM 281SS 279
281 Slab top rebar laying 1 day Jun 29 9:30 AM Jun 30 12:30 PM 282FS-2 days 280SS
282 External board fixing 3 days Jun 28 9:30 AM Jul 1 12:30 PM 283 281FS-2 days
283 Supporting 3 days Jul 1 12:30 PM Jul 4 12:30 PM 284FS-11 days 282
284 Walkway arrangement for inspection 2 days Jun 23 9:30 AM Jun 25 9:30 AM 285 283FS-11 days
285 Repropping 1 day Jun 25 9:30 AM Jun 26 9:30 AM 286FS+8 days 284
286 Final inspection 2 days Jul 4 12:30 PM Jul 6 12:30 PM 287SS 285FS+8 days
287 Concreting 1 day Jul 5 5:30 PMJul 6 8:30 PM 286SS
288 Pour 5 58 days Apr 30 7:30 PM Jun 30 12:30 PM
289 Marking for staging 3 days Apr 30 7:30 PM May 3 7:30 PM 225
290 Installation of staging HD tower 15 days Apr 30 7:30 PM May 16 2:30 PM 291FS-2 days 225
291 Column rebar termination 3 days May 14 2:30 PM May 17 2:30 PM 292 290FS-2 days
292 Column capping with GP2 3 days May 17 2:30 PM May 20 5:30 PM 293 291
293 Drilling for pinned connection 1 day May 20 5:30 PM May 21 5:30 PM 294 292
294 Fixing of circula r plates 2 days May 21 5:30 PM May 23 5:30 PM 295 293
7/8 10/28 2/17 6/9 9/29
February 11 October 1 May 21
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 6
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
ID Task
Mode
Task Name Duration Start Finish Successors Predecessors
295 Rebar anchoring with HILTI 1 day May 23 5:30 PM May 24 5:30 PM 296FS-8 days 294
296 Beam bottom fixing 12 days May 16 2:30 PM May 28 8:30 PM 297 295FS-8 days
297 Beam rebar fixing 10 days May 29 8:30 AM Jun 8 11:30 AM 298FS-2 days 296
298 PT profiling/threading in beams 4 days Jun 6 11:30 AM Jun 10 3:30 PM 299 297FS-2 days
299 Beam side fixing 8 days Jun 10 3:30 PM Jun 18 6:30 PM 300FS-5 days 298
300 Slab decking 7 days Jun 13 3:30 PM Jun 20 6:30 PM 301 299FS-5 days
301 Slab bottom rebar laying 2 days Jun 20 6:30 PM Jun 23 9:30 AM 302 300
302 PT profiling in slabs 1 day Jun 23 9:30 AM Jun 24 9:30 AM 303 301
303 Slab top rebar laying 1 day Jun 24 9:30 AM Jun 25 9:30 AM 304FS-4 days 302
304 External board fixing 3 days Jun 20 6:30 PM Jun 24 9:30 AM 305 303FS-4 days
305 Supporting 3 days Jun 24 9:30 AM Jun 27 9:30 AM 306FS-11 days 304
306 Walkway arrangement for inspection 3 days Jun 15 3:30 PM Jun 18 6:30 PM 307 305FS-11 days
307 Repropping 2 days Jun 18 6:30 PM Jun 20 6:30 PM 308FS+6 days 306
308 Final inspection 2 days Jun 27 9:30 AM Jun 29 9:30 AM 309 307FS+6 days
309 Concreting 1 day Jun 29 9:30 AM Jun 30 12:30 PM 308
310 Business centre 1 day? Apr 9 8:30 AM Apr 9 8:30 PM
325 Tower A2 420 days Jun 20 8:30 AM Aug 31 10:30 AM 567
326 Core Wall For Tower A2 384 days Jun 20 8:30 AM Jul 24 3:30 PM
327 Core Wall Ground Floor to 1st Floor 18 days Jun 20 8:30 AM Jul 8 6:30 PM328
328 Core Wall 1st Floor to 2nd Floor 20 days Jul 8 6:30 PMJul 29 4:30 PM 329 327
329 ACS Assembly 45 days Jul 29 4:30 PM Sep 14 11:30 AM 330FS+5 days 328
330 Core Wall 2nd Floor to 3rd Floor 15 days Sep 19 3:30 PM Oct 5 9:30 AM 331 329FS+5 days
331 Core Wall 3rd Floor to 4th Floor 15 days Oct 5 9:30 AM Oct 20 7:30 PM 332,359 330
332 Core Wall 4th Floor to 5th Floor 15 days Oct 20 7:30 PM Nov 5 2:30 PM 333,363 331
333 Core Wall 5th Floor to 6th Floor 14 days Nov 5 2:30 PM Nov 19 8:30 PM 334,367 332
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
7/8 10/28 2/17 6/9 9/29
February 11 October 1 May 21
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 7
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
ID Task
Mode
Task Name Duration Start Finish Successors Predecessors
334 Core Wall 6th Floor to 7th Floor 14 days Nov 20 8:30 AM Dec 4 3:30 PM 335,371 333
335 Core Wall 7th Floor to 8th Floor 13 days Dec 4 3:30 PM Dec 18 9:30 AM 336,375 334
336 Core Wall 8th Floor to 9th Floor 12 days Dec 18 9:30 AM Dec 30 4:30 PM 337,379 335
337 Core Wall 9th Floor to 10th Floor 12 days Dec 30 4:30 PM Jan 12 10:30 AM 338,383 336
338 Core Wall 10th Floor to 11th Floor 11 days Jan 12 10:30 AM Jan 23 2:30 PM 339,387 337
339 Core Wall 11th Floor to 12th Floor 11 days Jan 23 2:30 PM Feb 3 8:30 PM 340,391 338
340 Core Wall 12th Floor to 13th Floor 10 days Feb 4 8:30 AM Feb 14 11:30 AM 341,395 339
341 Core Wall 13th Floor to 14th Floor 10 days Feb 14 11:30 AM Feb 24 6:30 PM 342,399 340
342 Core Wall 14th Floor to 15th Floor 10 days Feb 24 6:30 PM Mar 7 9:30 AM 343,403 341
343 Core Wall 15th Floor to 16th Floor 12 days Mar 7 9:30 AM Mar 19 4:30 PM 344,407 342
344 Core Wall 16th Floor to 17th Floor 12 days Mar 19 4:30 PM Apr 1 10:30 AM 345,411 343
345 Core Wall 17th Floor to 18th Floor 10 days Apr 1 10:30 AM Apr 11 2:30 PM 346,415 344
346 Core Wall 18th Floor to 19th Floor 10 days Apr 11 2:30 PM Apr 21 8:30 PM 347,419 345
347 Core Wall 19th Floor to 20th Floor 9 days Apr 22 8:30 AM May 1 11:30 AM 348,423 346
348 Core Wall 20th Floor to 21th Floor 9 days May 1 11:30 AM May 10 3:30 PM 349,427 347
349 Core Wall 21th Floor to 22nd Floor 9 days May 10 3:30 PM May 20 9:30 AM 350,431 348
350 Core Wall 22nd Floor to 23rd Floor 9 days May 20 9:30 AM May 29 12:30 PM 351,435 349
351 Core Wall 23th Floor to 24th Floor 9 days May 29 12:30 PM Jun 7 4:30 PM 352,439 350
352 Core Wall 24th Floor to 25th Floor 9 days Jun 7 4:30 PM Jun 17 10:30 AM 353,443 351
353 Core Wall 25th Floor to 26th Floor 9 days Jun 17 10:30 AM Jun 26 2:30 PM 354,447 352
354 Core Wall 26th Floor to 27th Floor 9 days Jun 26 2:30 PM Jul 5 5:30 PM355,451 353
355 Core Wall 27th Floor to 28th Floor 9 days Jul 6 8:30 AM Jul 15 11:30 AM 356,455 354
356 Core Wall 28th Floor to Terrace Floor 9 days Jul 15 11:30 AM Jul 24 3:30 PM 459 355
357 Slab For Tower A2 302 days Oct 20 7:30 PM Aug 31 10:30 AM
474 Basement 578 days? Apr 9 8:30 AM Dec 2 2:30 PM
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
7/8 10/28 2/17 6/9 9/29
February 11 October 1 May 21
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 8
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
ID Task
Mode
Task Name Duration Start Finish Successors Predecessors
567 End of Project 1 day Aug 31 10:30 AM Sep 1 10:30 AM 325,219
7/8 10/28 2/17 6/9 9/29
February 11 October 1 May 21
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 9
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
9/29 1/19 5/11 8/31 12/21 4/12 8/2 11/22 3/13 7/3 10/23 2/12 6/4 9/24 1/14 5/6 8/26 12/16 4/7 7/28 11/17 3/8
May 21 January 11 September 1 April 21 December 11 August 1 March 21 November 11 July 1 February 21 October 11
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 10
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
9/29 1/19 5/11 8/31 12/21 4/12 8/2 11/22 3/13 7/3 10/23 2/12 6/4 9/24 1/14 5/6 8/26 12/16 4/7 7/28 11/17 3/8
May 21 January 11 September 1 April 21 December 11 August 1 March 21 November 11 July 1 February 21 October 11
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 11
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
9/29 1/19 5/11 8/31 12/21 4/12 8/2 11/22 3/13 7/3 10/23 2/12 6/4 9/24 1/14 5/6 8/26 12/16 4/7 7/28 11/17 3/8
May 21 January 11 September 1 April 21 December 11 August 1 March 21 November 11 July 1 February 21 October 11
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 12
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
9/29 1/19 5/11 8/31 12/21 4/12 8/2 11/22 3/13 7/3 10/23 2/12 6/4 9/24 1/14 5/6 8/26 12/16 4/7 7/28 11/17 3/8
May 21 January 11 September 1 April 21 December 11 August 1 March 21 November 11 July 1 February 21 October 11
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 13
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
9/29 1/19 5/11 8/31 12/21 4/12 8/2 11/22 3/13 7/3 10/23 2/12 6/4 9/24 1/14 5/6 8/26 12/16 4/7 7/28 11/17 3/8
May 21 January 11 September 1 April 21 December 11 August 1 March 21 November 11 July 1 February 21 October 11
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 14
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
9/29 1/19 5/11 8/31 12/21 4/12 8/2 11/22 3/13 7/3 10/23 2/12 6/4 9/24 1/14 5/6 8/26 12/16 4/7 7/28 11/17 3/8
May 21 January 11 September 1 April 21 December 11 August 1 March 21 November 11 July 1 February 21 October 11
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 15
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
9/29 1/19 5/11 8/31 12/21 4/12 8/2 11/22 3/13 7/3 10/23 2/12 6/4 9/24 1/14 5/6 8/26 12/16 4/7 7/28 11/17 3/8
May 21 January 11 September 1 April 21 December 11 August 1 March 21 November 11 July 1 February 21 October 11
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 16
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
9/29 1/19 5/11 8/31 12/21 4/12 8/2 11/22 3/13 7/3 10/23 2/12 6/4 9/24 1/14 5/6 8/26 12/16 4/7 7/28 11/17 3/8
May 21 January 11 September 1 April 21 December 11 August 1 March 21 November 11 July 1 February 21 October 11
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 17
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
9/29 1/19 5/11 8/31 12/21 4/12 8/2 11/22 3/13 7/3 10/23 2/12 6/4 9/24 1/14 5/6 8/26 12/16 4/7 7/28 11/17 3/8
May 21 January 11 September 1 April 21 December 11 August 1 March 21 November 11 July 1 February 21 October 11
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 18
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
3/8 6/28 10/18 2/7 5/30 9/19 1/9 5/1 8/21 12/11 4/2 7/23 11/12 3/3 6/23 10/13 2/2 5/25 9/14 1/4 4/26 8/16
October 11 June 1 January 21 September 11 May 1 December 21 August 11 April 1 November 21 July 11 March 1
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 19
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
3/8 6/28 10/18 2/7 5/30 9/19 1/9 5/1 8/21 12/11 4/2 7/23 11/12 3/3 6/23 10/13 2/2 5/25 9/14 1/4 4/26 8/16
October 11 June 1 January 21 September 11 May 1 December 21 August 11 April 1 November 21 July 11 March 1
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 20
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
3/8 6/28 10/18 2/7 5/30 9/19 1/9 5/1 8/21 12/11 4/2 7/23 11/12 3/3 6/23 10/13 2/2 5/25 9/14 1/4 4/26 8/16
October 11 June 1 January 21 September 11 May 1 December 21 August 11 April 1 November 21 July 11 March 1
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 21
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
3/8 6/28 10/18 2/7 5/30 9/19 1/9 5/1 8/21 12/11 4/2 7/23 11/12 3/3 6/23 10/13 2/2 5/25 9/14 1/4 4/26 8/16
October 11 June 1 January 21 September 11 May 1 December 21 August 11 April 1 November 21 July 11 March 1
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 22
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
3/8 6/28 10/18 2/7 5/30 9/19 1/9 5/1 8/21 12/11 4/2 7/23 11/12 3/3 6/23 10/13 2/2 5/25 9/14 1/4 4/26 8/16
October 11 June 1 January 21 September 11 May 1 December 21 August 11 April 1 November 21 July 11 March 1
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 23
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
3/8 6/28 10/18 2/7 5/30 9/19 1/9 5/1 8/21 12/11 4/2 7/23 11/12 3/3 6/23 10/13 2/2 5/25 9/14 1/4 4/26 8/16
October 11 June 1 January 21 September 11 May 1 December 21 August 11 April 1 November 21 July 11 March 1
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 24
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
3/8 6/28 10/18 2/7 5/30 9/19 1/9 5/1 8/21 12/11 4/2 7/23 11/12 3/3 6/23 10/13 2/2 5/25 9/14 1/4 4/26 8/16
October 11 June 1 January 21 September 11 May 1 December 21 August 11 April 1 November 21 July 11 March 1
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 25
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
Concrete[270],Rebar[54],Shuttering[1,069],Carpenter(C+H) for Shuttering[10],Fitter(F+H) for Rebar[8],Unskilled Labour for Concreting[15]
3/8 6/28 10/18 2/7 5/30 9/19 1/9 5/1 8/21 12/11 4/2 7/23 11/12 3/3 6/23 10/13 2/2 5/25 9/14 1/4 4/26 8/16
October 11 June 1 January 21 September 11 May 1 December 21 August 11 April 1 November 21 July 11 March 1
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 26
Project: Reliance Twin Tower Proj
Date: Sep 1 6:37 AM
3/8 6/28 10/18 2/7 5/30 9/19 1/9 5/1 8/21 12/11 4/2 7/23 11/12 3/3 6/23 10/13 2/2 5/25 9/14 1/4 4/26 8/16
October 11 June 1 January 21 September 11 May 1 December 21 August 11 April 1 November 21 July 11 March 1
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 27