J5127- KAWALAN PEMBUATAN SULIT

2
SOALAN 1

a) Namakan TIGA (3) teknik ramalan.
(6 markah)

b) Berpandukan jadual di bawah, tentukan ramalan bagi bulan 5 hingga 7 dengan
menggunakan n = 4 dan wajaran 0.4, 0.3, 0.2 dan 0.1.
Bulan Permintaan Sebenar Ramalan
1 110
2 102
3 108
4 121
5 112
6 105
7

(11 markah)

c) Nyatakan EMPAT (4) aktiviti utama pengurusan.
(8 markah)



QUESTION 1

a) Named THREE (3) method of forecasting.
(6 marks)

b) Base on the table below, determine the forecasting for months 5 to 7 using
n = 4 and weight moving average 0.4, 0.3, 0.2 and 0.1.
Month Actual Demand Forecasting
1 110
2 102
3 108
4 121
5 112
6 105
7

(11 marks)

c) Named FOUR (4) management activities.
(6 marks)
J5127- KAWALAN PEMBUATAN SULIT

3

SOALAN 2


Jadual S2 di bawah menunjukkan senarai aktiviti dan jangkamasa bagi sebuah projek.

Aktiviti Jangkamasa (hari) Aktiviti sebelum
A 3 -
B 2 A
C 5 A
D 5 A
E 7 B
F 7 C,D
G 6 E,F
H 3 D
I 5 G,H
Jadual S2

Tentukan:
a) Lukiskan gambarajah rangkaian laluan kritikal bagi projek ini.
b) Tunjukkan masa mula/siap terawal dan masa mula/ siap terakhir.
c) Tentukan laluan kritikal.
d) Apakah yang terjadi jika aktiviti F mengambil masa empat hari.
(25 markah)















J5127- KAWALAN PEMBUATAN SULIT

4

QUESTION 2

The Table S2 below shows the activities and waiting time of a project.

Activities Time (days) Activities before
A 3 -
B 2 A
C 5 A
D 5 A
E 7 B
F 7 C,D
G 6 E,F
H 3 D
I 5 G,H
Table S2

Determine:
a) Construct the critical path for the project.
b) Shows the starting time / early finishing and starting time / final finishing.
c) Determine the critical path.
d) What will happens if F activities took four days ?

(25 marks)













J5127- KAWALAN PEMBUATAN SULIT

5

SOALAN 3

a) Nyatakan EMPAT (4) maklumat yang diperlukan bagi membina sebuah Jadual
Pengeluaran Induk.
( 4 markah)

b) Firma Cahaya Bulan mengeluarkan beberapa model kereta mainan untuk
pasaran tempatan. Firma perlu memenuhi permintaan terhadap empat model
kereta mainan iaitu A1, A2, A3 dan A4. Model A1 perlu diproses di stesen kerja
1 dan 2. Model A2 pula diproses di stesen kerja 3 dan 4. Model A3 diproses di
stesen kerja 1 dan 3. Model A4 perlu diproses pada stesen kerja 2,4 dan 5.
Jumlah pengeluaran ialah A1 = 1500 unit, A2 = 1200 unit, A3 = 2400 unit dan
A4 = 1800 unit. Tunjukkan bagaimana Jadual Pengeluaran Utama dibina dan
nyatakan masa setiap model di pasarkan.

Stesen
Baki jam masih ada
dalam sebulan
Masa piawai (jam)
1 165 0.55
2 150 0.5
3 300 0.5
4 360 0.4
5 300 0.5

( 21 markah)












J5127- KAWALAN PEMBUATAN SULIT

6

QUESTION 3

a) State FOUR (4) information need to build a Master Production Schedule (MPS).
(4 marks)

b) Cahaya Bulan produce a number of toy car domestic market. Firm must fulfill
demand for four toy car model: A1, A2, A3 and A4. Model A1 need to process
at St. 1 and St.2. Model A2 will be process at St.3 and 4. While Model A3 at St
1 and 3 and lastly model A4 at 2,4 and 5. The demand for A! = 1500 units, A2=
1200 unit. A3= 2400 unit and A4 = 1800 unit. Show how to build Master
Production Schedule (MPS) and when each model will be release.














( 21 marks)

















Stesyen Remaining hours in a
month
Standard Time
(hours)
1 165 0.55
2 150 0.5
3 300 0.5
4 360 0.4
5 300 0.5
J5127- KAWALAN PEMBUATAN SULIT

7

SOALAN 4

a) Perodua merupakan pembekal kereta buatan tempatan, ingin mengurangkan
kadar kos inventori dengan mengenalpasti bilangan optimal MyVi yang
diperolehi bagi setiap pesanan. Permintaan tahunan terhadap MyVi ini adalah
15000 unit, kos memesan adalah RM 3000/ pesanan dan kos menyimpan adalah
RM500. Anggap syarikat ini beroperasi selama 300 hari bekerja setahun dan 6
hari seminggu. Kirakan:

i. Bilangan optimal bagi satu pesanan ( EOQ)
(5 markah)
ii. Jangkaan tempoh per pesanan
(2markah)
iii. Jangkaan bilangan ulangan pesanan dalam setahun
(4 markah)
iv. Jumlah kos
(5 markah)
v. Titik pesanan semula
(4 markah)

b) Terangkan DUA(2) kaedah yang digunakan dalam Kawalan Inventori.
(5 markah)











J5127- KAWALAN PEMBUATAN SULIT

8

QUESTION 4

a) Perodua deals with supplying local made motorcars, would like to reduce its
inventory cost by determining the optimal number of MyVi to obtain per order.
The annual demand is 15000 units, the ordering cost is RM 3000 and the holding
cost per unit per year is RM500. Assuming in this company, there is a 300
working days per year and 6 working days per week. Calculate:

i. The optimal number of units per order, EOQ. (5 marks)
ii. The expected time per between order. (2 marks)
iii. The expected number of order per year. (4 marks)
iv. Total cost. (5 marks)
v. Reorder point. (4 marks)

b) Explain TWO (2) method that being used in Inventory Control.
(5 marks)

















J5127- KAWALAN PEMBUATAN SULIT

9

SOALAN 5

a) Nyatakan EMPAT (4) kegunaan Kajian Kerja dalam sesebuah organisasi.
(8 markah)

b) Apakah tujuan Pengukuran Kerja dilakukan.
(2 markah)

c) Data yang ditunjukkan dalam jadual yang berikut mewakili kajian masa yang
dilakukan terhadap proses metalworking. Berdasarkan pemerhatian yang
berikut, dapatkan masa piawai dan anggap masa kelegaan adalah 25%.

Pemerhatian ( minit per kitar ) Elemen Kadar
Prestasi
(%)
1 2 3 4 5 6 7
1 90 1.80 1.70 1.66 1.91 1.85 1.77 1.60
2 100 6.9 7.3 6.8 7.1 15.3* 7.0 6.4
3 115 3.0 9.0* 9.5* 3.8 2.9 3.1 3.2
4 90 10.1 11.1 12.3 9.9 12.0 11.9 12.0
*Abaikan pemerhatian yang luar biasa
( 15markah)












J5127- KAWALAN PEMBUATAN SULIT

10

QUESTION 5

a) Give FOUR (4) usage of work sampling in an organisation?
(8 marks)

b) What is the main purpose of work scheduling?
(2 marks)

c) The data in the following table represent time-study observations for a
metalworking process. On the basis of these observations, find the standard time
for the process, assuming a 25% allowance factor.

Observations ( minutes per cycle ) Element Performance
rating (%) 1 2 3 4 5 6 7
1 90 1.80 1.70 1.66 1.91 1.85 1.77 1.60
2 100 6.9 7.3 6.8 7.1 15.3* 7.0 6.4
3 115 3.0 9.0* 9.5* 3.8 2.9 3.1 3.2
4 90 10.1 11.1 12.3 9.9 12.0 11.9 12.0
*Disregard unusual observation
(15 marks)












J5127- KAWALAN PEMBUATAN SULIT

11

SOALAN 6

a) Terangkan Perancangan Keperluan Bahan (MRP).
(4 markah)

b) Jadual S6b menunjukkan bahan-bahan yang diperlukan bagi menghasilkan
satu unit produk akhir A. Syarikat TFK bercadang untuk membekalkan 100 unit
produk akhir pada minggu ke 20 pada tahun 2006.

Bahan
Masa mendulu
(minggu)
Bahan tersandar
A 2 1B & 2C
B 1 2D & 1E
C 2 2H, 1G &1E
D 3 1F & 1G
E 1
F 2
G 1
H 2
Jadual S6b

i. Lukiskan pohon struktur bagi produk A.
ii. Dapatkan bilangan setiap bahan bagi 100 unit produk A.
iii. Tentukan Rancangan Keperluan Bahan Kasar.
(21 markah)







J5127- KAWALAN PEMBUATAN SULIT

12

QUESTION 6

a) Define Material Requirement Planning.
(4 marks)

b) The Table S6b shows the required components to produce one unit of product
A. TFK company were thinking to supply 100 units of product A in week-20 in
year 2006.

Material
Lead Time
(minggu)
Following components
A 2 1B & 2C
B 1 2D & 1E
C 2 2H, 1G &1E
D 3 1F & 1G
E 1
F 2
G 1
H 2
Table S6b

i. Construct the Bill of Material product structure.
ii. Get the amound for each component for 100 units A products.
iii. Construct Gross Material Requirement Plan.
(21 marks)