Amount (Rs Lakh) 1 Foundation Excavation (a) Excavation overburden 469 m 3 99.00 0.46 (b) Excavation in hard rock 0 m 3 286.00 0.00 2 Concrete in foundation, abutments (M15 with 40 MSA) 727.5 m 3 2618.00 19.05 3 Concrete M20 in deck slab 161 m 3 3284.00 5.29 4 Reinforcement steel 18.5 MT 39092.00 7.23 5 Structural steel in trusses 87 MT 43280.00 37.65 6 Wearing coat concrete (M25) 244 m 3 3716.00 9.07 7 Reinforcement for wearing coat 1.22 MT 39092.00 0.48 8 Bearings 4 no 17550 0.70 9 Hand railings 150 RM 639.00 0.96 Sub Total 80.89 Cost after due escalation 84.45 10 Launching of truss at site@ 25% cost of steel Lump Sum 9.83 11 Architectural treatment Lump Sum 2.00 12 De-watering charges including connected operations of laying pipelines, providing pumps etc. @ 3% of cost of Bridge. Lump Sum 2.53 14 Add 2% for W.C. Establishment (excluding lump sum provision) 1.69 15 Add 3% for contingencies (excluding lump sum provision) 2.53 Total Cost (Rs. Lakh) 103.03 TABLE 20 COST ESTIMATE STEEL APPROACH BRIDGE ON DHAWLIGANGA RIVER (50m single span)