BUILD A H

Start Date Duration


Foundation 1-Jun 10
Walls 12-Jun 7
Roof 20-Jun 10
Windows, Doors 1-Jul 5
Plumbing 7-Jul 3
Electric 7-Jul 3
Painting 11-Jul 2
Flooring 13-Jul 2
1-Jun 8-Jun 15-Jun
Foundation
Walls
Roof
Windows, Doors
Plumbing
Electric
Painting
Flooring
22-Jun 29-Jun 6-Jul 13-Jul