Sei sulla pagina 1di 8

TABLE OF CONTENT

ITEM NO. TITLE PAGE



- TABLE OF CONTENT

1.0 OBJECTIVE 3

2.0 SCOPE 3

3.0 HANDLING AND STORAGE 3

4.0 WORK METHODOLOGY 3-4

5.0 RESPONSIBILITY 6

6.0 EQUIPMENT 7

7.0 TYPICAL INSTALLATION ARRANGEMENT LAYOUT 8

8.0 SAFETY, HEALTH, SECURITY AND ENVIRONMENT 9








METHOD STATEMENT
Title : Method Statement For Installation Of
Electric PVC Conduits And Accessories
Page : 2 of 9
Reference :




1.0 OBJECTIVE
This method statement explains the detailed requirements and procedures for the
installation of PVC Conduits and accessories in the concrete slabs, columns, block works
and concrete walls.

2.0 SCOPE
This procedure applies to project site which requires installation of electric PVC conduits
and its accessories inside and outside the building.

2.0 HANDLING AND STORAGE
2.1 Deliver components parts and material to site, completely identified in accordance
with approved brand and supplier and also comply with certified drawings
prepared for this work.

2.2 Store in accordance with the manufacturers instructions, above ground, properly
protected from the weather and construction activities.


3.0 WORK METHODOLOGY


3.1 Material: Material used will be as approved by the engineer. The sizes and routes
routing will be as per the approved shop drawing.

3.2 Installation

1. During the course of the installation of the conduit system, procedures for
working and dressing the installation as recommended shall be employed.

2. All bends and sets shall be in accordance with IEE regulation 522-08
formed with the aid of a helical spring fitted internally, with if necessary,



METHOD STATEMENT
Title : Method Statement For Installation Of
Electric PVC Conduits And Accessories
Page : 3 of 9
Reference :





3. Conduit system shall be installed so as to ensure compliance with the
requirements of Specified Standard and Regulation.

4. Joints between PVC conduit + fittings shall be made with suitable
adhesive, but expansion couplings shall be installed where any length of
conduit, inclusive of draw in boxes etc, exceeds five meters in length.

5. The minimum and maximum sizes of conduit to be employed shall be
inch and 1 inch respectively, unless otherwise stated in subsequent
sections of the specification.

6. Conduits in floors shall be routed and installed so as to avoid the fixings of
floor standing equipment to be installed on the floor.


3.3 Fixing of Conduits

1. When conduits are run on shuttering, prior to the laying of concrete in-situ,
additional security must be provided near to every box and at intervals of not
more than 1.2 meters by binding short lengths of steel wire, of not less than
2mm diameter twisted around the conduit and reinforcing steel. The conduits
shall be adequately fixed to prevent excessive movement and damage during
the pouring and setting of concrete and shall be protected from mechanical
damage. Check there is no damage before screed / concrete is poured. Unless
otherwise indicated to cast in conduits shall not be less than 30mm.cores to
plastered over conduits shall not be less than 5mm.

2. Where conduits are left "open ended" prior to wiring they shall be protected
by caps or plugs to prevent the ingress of building material.

3. All conduits runs must be designed to permit wiring to be readily installed
after the complete erection of the conduits through the available draw-in,
accessory and luminary suspension boxes.

4. Where surface mounted equipment (other than luminaries) is specified, all
concealed conduits shall be terminated and an adaptable box installed recessed
into the wall at every surface mounted equipment position.


METHOD STATEMENT
Title : Method Statement For Installation Of
Electric PVC Conduits And Accessories
Page : 4 of 9
Reference :



5. Where conduits pass through an external wall/roof the conduit box shall be
fitted on the side and after wiring filled with an inert, permanently plastic
compound having a high insulation value.
6. Make provision in conduit and trunking, installation where building expansion
joints are crossed or settlement is likely.

7. Ensure conduits are not concealed until works has been inspected and
approved. Ensure that conduit and fittings buried in concrete or behind plaster
are protected against corrosion or electrolytic action prior to rendering.

4.0 RESPONSIBILITY

Project Manager:

o To ensure that all the preparation and application works are carried out according to
the Contract Specification and with the approved drawings.
o To ensure that the progressing of work is carried out according to the planned program
and as per the approved method of statement.
o To ensure that all the equipment and materials required executing the work are
available according to the planned construction program.
o To co ordinate with the Main contractor, MEP Coordinator and Safety Officer, for a
safe and proper execution of the works.

Site Engineer:

o To ensure that the works are carried out according to the Contract Specifications,
approved method statement and the shop drawings.
o To provide all necessary information and distribute responsibilities to his construction
team.
o To monitor the progress of work in relation with the work program and to report to the
Project Manager.
o To co-ordinate with the safety officer and to ensure that the works are carried out in
safe practicing methods.

Foreman:

o The foreman will carry out his duties by maintaining continuous coordination with the
site engineer on daily basis, and ensure proper distribution of the workforce in the
required and planned locations.


METHOD STATEMENT
Title : Method Statement For Installation Of
Electric PVC Conduits And Accessories
Page : 5 of 9
Reference :





o To ensure that his assistant foreman/ charge hand are aware of the job requirements
and they have enough information to carry out their duties properly.
o To ensure in consultation with the site engineer that the manpower involved in the
works are moving as agreed and planned for the work.
o To ensure that the daily work is progressing as planned and advice the site engineer of
any requirement for additional resources.
o To control disposal of waste materials according to the instructions received from the
site engineer.
o To ensure full coordination with the safety officer to maintain safe working and proper
housekeeping of the site, following the approved safety measures and further ensure
that all his working team are aware of the same to prevent accident and losses.
o To inform the site engineer and of the areas ready for inspection.
o Distribution and the control of material shall be monitored by foreman and store
keeper.


5.0 EQUIPMENT
The requirements that will be engaged for PVC conduiting works will be as follows:
1. Hack saw
2. Measuring tape
3. Cutting plier
4. Knipex (End cutter)
5. Bending spring
6. Drilling Machine









METHOD STATEMENT
Title : Method Statement For Installation Of
Electric PVC Conduits And Accessories
Page : 6 of 9
Reference :


6.0 TYPICAL INSTALLATION ARRANGEMENT LAYOUT




Method Statement for Installation Of Electrical PVC Conduits And Accessories In The Concrete Slabs, Columns,
Block Works And Concrete Walls




METHOD STATEMENT
Title : Method Statement For Installation Of
Electric PVC Conduits And Accessories
Page : 7 of 9
Reference :



7.0 QUALITY ASSURANCE PLAN

ITP
Clause
No.
Inspection
Description
Type of
Inspection
Reference
Document
Testing
Requirement/
Acceptance
Criteria
Verifying /
Control
Data Forms
1
Design and
Drawings
Review of
Documents
Design
Drawings
All the
Drawings
Design
Drawings,
Authorities
Departments
Requirements
2
Material
Approval
Review of
Documents
Approved
Drawing,
Specification
Should be as
per the
approved
drawing and
Specification
Documents
Submittals
3
Check
installation
of PVC
Conduits
Visual
Approved
Method
Statement
Proper bends
correct height
and Location,
material
should have
minimum
status on No
Objection
with
comments (2)
Approved
Drawing
Method
Statement
4
Raise
inspection
request
Visual
Measurement
instrument
Approved
Drawings
NO
obstructions
height, Proper
position
Approved
Drawings


METHOD STATEMENT
Title : Method Statement For Installation Of
Electric PVC Conduits And Accessories
Page : 8 of 9
Reference :



8.0 SAFETY, HEALTH, SECURITY AND ENVIRONMENT
Strictly follow as per the manufacturers Health and Safety recommendations for handling and
used of the materials. Ensure all involved personnel shall be aware of the same.
A special safety inspector is assigned; all personnel involved in this work shall use
the mandatory P.P.E as follows.
a. Safety Helmet
b. Safety Shoes/Boots
c. Safety glasses.
d. All other PPE as required by the risk assessment.

All work will be undertaken by qualified competent persons with experience of the type of work
described above, and in all cases in full accordance with safety procedures specified in the
company's health and safety Policy.




METHOD STATEMENT
Title : Method Statement For Installation Of
Electric PVC Conduits And Accessories
Page : 9 of 9
Reference :

Potrebbero piacerti anche