LOCATION : Fernando Airbase, Lipa City I a. Site Works Clearing & Grubbing lot Excavation lot Backfilling lot P II. Concrete Works a. Footing & Pedestal & Partition Qty = l.s. I. MATERIAL: 700 pcs. Chb #5 @ P 120 bags Cement @ P 7.5 cu.m. Sand P 14 cu.m. Gravel P 45 pcs. 10mm RSB P 30 pcs. 12mm RSB P 6 pcs. " thk Plywood P 320 bd.ft. Cocolumber 2 x 3 x 8 (77 pcs) P 12 kgs. Tie Wire P 15 kgs. CWN (Asstd) P P II. EQUIPMENT: 1 Bagger Mixer @ 7 days P 1 Misc. Hand Tools P P III. LABOR: P P b. Slab on fill Qty = l.s. I. MATERIAL: 85 bags Cement @ P 5 cu.m. Sand P 10 cu.m. Gravel P 1 lot Formworks P P II. EQUIPMENT: 1 Bagger Mixer @ 2 days P 1 Concrete Vibrator 2 days P 1 lot Misc. Hand Tools P III. LABOR: P Total Cost III. Fabricated Materials a.1. Doors 1 set D-1 0.70m x 2.10m Sliding Door 7,000.00 P 2 sets D-2 0.60m x 2.10m pvc door w/jamb 2,500.00 Materials Cost Labor P b. Window ( Labor & Materials) 2 sets W-1 1.20 x 1.20 PVC w/screen 8,500.00 P Window Sliding Type (30.96 ft 2 ) 2 sets W-2 0 .60 x 0.60 PVC w/screen 3,500.00 Sliding Window (7.74 ft 2 ) IV. Structural Steel Works Qty = L.S. I. MATERIAL: 18 pcs. 3" dia. G.i. Pipe sch. 40 @ P 12 pcs. 4" dia. G.i. Pipe sch. 40 P 36 pcs. 1 1/2" dia. G.i. Pipe sch. 40 P 30 pcs. 1" dia. G.i. Pipe sch. 40 P 50 pcs. 12mm Square Bar P 145 pcs. 2 x 3 x 1.5mm C Purlins P 8 pcs. 2 x 4 x 1.5 mm C Purlins P 24 pcs. 12mm Plain Bar P 3 boxes Welding Rod P 12 gals Red Oxide Primer P 12 gals Paint Thinner P 5 sets Oxy - Acetylene P P II. EQUIPMENT: 1 Welding Machine @ 12 days P 1 Boom Truck 2 days P 1 Bar Cutter 6 days P P III. LABOR: P V. Tinsmithry Qty = L.S. I. MATERIAL: 530.25 lmts. 0.40mm x 1.01m x L.S. Curve Rib @ P 16 pcs. 0.40mm x 0.24m x 2.44 Flashing P 4500 pcs. Tekscrew P 4 box Blind Rivets P 12 ctgs. S. Sealant P Total Cost Total Cost Total Cost P III. LABOR: P VI. Hardwares 2 sets Cylindrical Lockset 850.00 P 1 set Lever type Lockset 1,200.00 P 4 boxes Loose Pin Hinges 3" x 3" (stanley) 230.00 P Labor Item Cost P XIV. Plumbing Works Materials: 2 sets Water Closet w/Fittings 6,500.00 P 2 sets Standard Floor Drain Strainer (4"x4") 250.00 2 sets Lavatory Faucet 4,400.00 P 5 rolls Tapelon (Big) 27.50 1 lot Miscellaneous 2,500.00 Materials Labor: Labor Item Cost P V.Painting Works Qty. = l.s. 2 tincans Flat Latex White 1,700.00 P 2 tincans Semi - Gloss Latex White 2,000.00 1 tincans Flat Wall Enamel 1900.00 1 tincans Quick Dry Enamel 2600.00 4 gals Masonry Putty 300.00 5 kgs Patching Compound 20.00 2 ltrs Acry Colors 150.00 5 gals Paint Thinner 200.00 3 pcs Masking Tape 30.00 10 kgs Rag 80.00 5 mtr Sand Paper #100 (3M) 170.00 10 pcs Sand Paper #120 (3M) 20.00 3 pcs Paint Roller #9 100.00 3 pcs Paint Brush #2 50.00 3 pcs Paint Brush #3 80.00 3 pcs Paint Brush #4 100.00 1 gals Concrete Netrulizer 410.00 2 ltrs Polituff 170.00 P Labor Item Cost P SUMMARY I. Excavation P Total Cost II. Concrete Works a. Footing & Pedestal b. Slab on Fill III. Pre-Fabricated Materials IV. Structural Steel Works V. Tinsmithry VI. Hardwares VI. Plumbing Works VI. Painting Works TOTAL P