Sei sulla pagina 1di 4

PROJECT : Proposed Bleacher Area & Firing Range

OWNER : Philippine AirForce


LOCATION : Fernando Airbase, Lipa City
I a. Site Works
Clearing & Grubbing lot
Excavation lot
Backfilling lot
P
II. Concrete Works
a. Footing & Pedestal & Partition
Qty = l.s.
I. MATERIAL:
700 pcs. Chb #5 @ P
120 bags Cement @ P
7.5 cu.m. Sand P
14 cu.m. Gravel P
45 pcs.
10mm RSB
P
30 pcs. 12mm RSB P
6 pcs. " thk Plywood P
320 bd.ft. Cocolumber 2 x 3 x 8 (77 pcs) P
12 kgs. Tie Wire P
15 kgs. CWN (Asstd) P
P
II. EQUIPMENT:
1 Bagger Mixer @ 7 days P
1 Misc. Hand Tools P
P
III. LABOR: P
P
b. Slab on fill
Qty = l.s.
I. MATERIAL:
85 bags Cement @ P
5 cu.m. Sand P
10 cu.m. Gravel P
1 lot Formworks P
P
II. EQUIPMENT:
1 Bagger Mixer @ 2 days P
1 Concrete Vibrator 2 days P
1 lot Misc. Hand Tools P
III. LABOR: P
Total Cost
III. Fabricated Materials
a.1. Doors
1 set D-1 0.70m x 2.10m Sliding Door 7,000.00 P
2 sets D-2 0.60m x 2.10m pvc door w/jamb 2,500.00
Materials Cost
Labor
P
b. Window
( Labor & Materials)
2 sets W-1 1.20 x 1.20 PVC w/screen 8,500.00 P
Window Sliding Type (30.96 ft
2
)
2 sets W-2 0 .60 x 0.60 PVC w/screen 3,500.00
Sliding Window (7.74 ft
2
)
IV. Structural Steel Works
Qty = L.S.
I. MATERIAL:
18 pcs. 3" dia. G.i. Pipe sch. 40 @ P
12 pcs. 4" dia. G.i. Pipe sch. 40 P
36 pcs. 1 1/2" dia. G.i. Pipe sch. 40 P
30 pcs. 1" dia. G.i. Pipe sch. 40 P
50 pcs. 12mm Square Bar P
145 pcs. 2 x 3 x 1.5mm C Purlins P
8 pcs. 2 x 4 x 1.5 mm C Purlins P
24 pcs. 12mm Plain Bar P
3 boxes Welding Rod P
12 gals Red Oxide Primer P
12 gals Paint Thinner P
5 sets Oxy - Acetylene P
P
II. EQUIPMENT:
1 Welding Machine @ 12 days P
1 Boom Truck 2 days P
1 Bar Cutter 6 days P
P
III. LABOR: P
V. Tinsmithry
Qty = L.S.
I. MATERIAL:
530.25 lmts. 0.40mm x 1.01m x L.S. Curve Rib @ P
16 pcs. 0.40mm x 0.24m x 2.44 Flashing P
4500 pcs. Tekscrew P
4 box Blind Rivets P
12 ctgs. S. Sealant P
Total Cost
Total Cost
Total Cost
P
III. LABOR: P
VI. Hardwares
2 sets Cylindrical Lockset 850.00 P
1 set Lever type Lockset 1,200.00 P
4 boxes Loose Pin Hinges 3" x 3" (stanley) 230.00 P
Labor
Item Cost P
XIV. Plumbing Works
Materials:
2 sets Water Closet w/Fittings 6,500.00 P
2 sets Standard Floor Drain Strainer (4"x4") 250.00
2 sets Lavatory Faucet 4,400.00 P
5 rolls Tapelon (Big) 27.50
1 lot Miscellaneous 2,500.00
Materials
Labor: Labor
Item Cost P
V.Painting Works
Qty. = l.s.
2 tincans Flat Latex White 1,700.00 P
2 tincans Semi - Gloss Latex White 2,000.00
1 tincans Flat Wall Enamel 1900.00
1 tincans Quick Dry Enamel 2600.00
4 gals Masonry Putty 300.00
5 kgs Patching Compound 20.00
2 ltrs Acry Colors 150.00
5 gals Paint Thinner 200.00
3 pcs Masking Tape 30.00
10 kgs Rag 80.00
5 mtr Sand Paper #100 (3M) 170.00
10 pcs Sand Paper #120 (3M) 20.00
3 pcs Paint Roller #9 100.00
3 pcs Paint Brush #2 50.00
3 pcs Paint Brush #3 80.00
3 pcs Paint Brush #4 100.00
1 gals Concrete Netrulizer 410.00
2 ltrs Polituff 170.00
P
Labor
Item Cost P
SUMMARY
I. Excavation P
Total Cost
II. Concrete Works
a. Footing & Pedestal
b. Slab on Fill
III. Pre-Fabricated Materials
IV. Structural Steel Works
V. Tinsmithry
VI. Hardwares
VI. Plumbing Works
VI. Painting Works
TOTAL P