ASSEMBLY OF AIR PRE HEATER BLOCKS WORK.

The Following steps should be adhered by the Work Crew for the Assembly of Air-Pre Heater Blocks
Assembly Work.
TOOLS REQUIRED MANDATORY.
1. Steel Rule.
2. Measurement Tape ( 5 Mtr.)
3. Spirit Level.
4. Linedori (or ) Piano wire.
5. Hammer. (Small as required) .
6. Wooden Plank.

1. Assembly Drawing of APH should kept Ready and Fitter should understand it clearly.
2. Both the side Tube Sheets to be fixed as per the Drawing (Refer the Distance given in the Drg).
3.It is