Sei sulla pagina 1di 4

Project: Proposed 10 Storey Renovation

Location:
Subject: Material Quantity and Labor Cost Estimate (Civil Works)
Item
A

Description
Chipping Works
Ground Floor
2nd Floor
3rd Floor
4th Floor
5th Floor
6th Floor
7th Floor
8th Floor
9th Floor
10th Floor

Unit

Qty.

sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

228.00
216.78
231.57
231.57
231.57
238.19
237.54
231.57
233.21
59.66

Material Cost
Unit
Total

Labor Cost
Unit
Total

Demolition Works
Ground Floor Masonry Walls
2nd Floor Masonry Walls
3rd Floor Masonry Walls
4th Floor Masonry Walls
5th Floor Masonry Walls
6th Floor Masonry Walls
7th Floor Masonry Walls
8th Floor Masonry Walls
9th Floor Masonry Walls
10th Floor Masonry Walls

l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.

41.87
80.09
80.95
81.81
82.69
83.57
84.47
85.37
86.28
22.43

12,825.00
12,193.88
13,025.81
13,025.81
13,025.81
13,398.19
13,361.63
13,025.81
13,118.06
3,355.88
120,355.88

56.25
56.25
56.25
56.25
56.25
56.25
56.25
56.25
56.25
56.25

12,825.00
12,193.88
13,025.81
13,025.81
13,025.81
13,398.19
13,361.63
13,025.81
13,118.06
3,355.88
120,355.88

150.00
150.00
150.00
150.00
150.00
150.00
150.00
150.00
150.00
150.00

6,280.05
12,013.50
12,142.04
12,271.96
12,403.27
12,535.99
12,670.12
12,805.69
12,942.72
3,365.11
109,430.46

150.00
150.00
150.00
150.00
150.00
150.00
150.00
150.00
150.00
150.00

6,280.05
12,013.50
12,142.04
12,271.96
12,403.27
12,535.99
12,670.12
12,805.69
12,942.72
3,365.11
109,430.46

91.61
91.61
91.61
91.61
91.61
91.61
91.61
91.61
91.61
91.61

20,887.08
19,859.22
21,214.13
21,214.13
21,214.13
21,820.59
21,761.04
21,214.13
21,364.37
5,465.45
196,014.25

91.61
91.61
91.61
91.61
91.61
91.61
91.61
91.61
91.61
91.61

20,887.08
19,859.22
21,214.13
21,214.13
21,214.13
21,820.59
21,761.04
21,214.13
21,364.37
5,465.45
196,014.25

Sub Total
C

Concrete Floor Finishing (Floor Tile Placement Preparation)


Ground Floor
sq.m.
228.00
2nd Floor
sq.m.
216.78
3rd Floor
sq.m.
231.57
4th Floor
sq.m.
231.57
5th Floor
sq.m.
231.57
6th Floor
sq.m.
238.19
7th Floor
sq.m.
237.54
8th Floor
sq.m.
231.57
9th Floor
sq.m.
233.21
10th Floor
sq.m.
59.66

Total Cost

56.25
56.25
56.25
56.25
56.25
56.25
56.25
56.25
56.25
56.25
Sub Total

Unit Cost

Sub Total
D1 Masonry Works (Ground Floor)
100mm thick C.H.B.
40 kg. Portland Cement (Mortar)
River sand (Mortar)
40 kg. Portland Cement (Plaster)
River sand (Mortar)
10mm x 6m Deformed Bar
Gage 16. Galvanized Iron Wire

pcs.
bag
cu.m.
bag
cu.m.
pcs.
kg.

1,623.00
52.00
6.00
59.00
4.00
135.00
16.00

12.00
220.00
1,000.00
220.00
1,000.00
135.00
75.00
Sub Total

19,476.00
11,440.00
6,000.00
12,980.00
4,000.00
18,225.00
1,200.00
73,321.00

3.60
66.00
300.00
66.00
300.00
40.50
22.50

5,842.80
3,432.00
1,800.00
3,894.00
1,200.00
5,467.50
360.00
21,996.30

15.60
286.00
1,300.00
286.00
1,300.00
175.50
97.50

25,318.80
14,872.00
7,800.00
16,874.00
5,200.00
23,692.50
1,560.00
95,317.30

D2 Masonry Works (2nd Floor)


100mm thick C.H.B.
40 kg. Portland Cement (Mortar)
River sand (Mortar)
40 kg. Portland Cement (Plaster)
River sand (Mortar)
10mm x 6m Deformed Bar
Gage 16. Galvanized Iron Wire

pcs.
bag
cu.m.
bag
cu.m.
pcs.
kg.

1,552.00
49.00
6.00
56.00
4.00
129.00
15.00

12.00
220.00
1,000.00
220.00
1,000.00
135.00
75.00
Sub Total

18,624.00
10,780.00
6,000.00
12,320.00
4,000.00
17,415.00
1,125.00
70,264.00

3.60
66.00
300.00
66.00
300.00
40.50
22.50

5,587.20
3,234.00
1,800.00
3,696.00
1,200.00
5,224.50
337.50
21,079.20

15.60
286.00
1,300.00
286.00
1,300.00
175.50
97.50

24,211.20
14,014.00
7,800.00
16,016.00
5,200.00
22,639.50
1,462.50
91,343.20

D3 Masonry Works (3rd Floor)


100mm thick C.H.B.
40 kg. Portland Cement (Mortar)
River sand (Mortar)
40 kg. Portland Cement (Plaster)
River sand (Mortar)
10mm x 6m Deformed Bar
Gage 16. Galvanized Iron Wire

pcs.
bag
cu.m.
bag
cu.m.
pcs.
kg.

1,569.00
50.00
6.00
57.00
4.00
131.00
16.00

12.00
220.00
1,000.00
220.00
1,000.00
135.00
75.00
Sub Total

18,828.00
11,000.00
6,000.00
12,540.00
4,000.00
17,685.00
1,200.00
71,253.00

3.60
66.00
300.00
66.00
300.00
40.50
22.50

5,648.40
3,300.00
1,800.00
3,762.00
1,200.00
5,305.50
360.00
21,375.90

15.60
286.00
1,300.00
286.00
1,300.00
175.50
97.50

24,476.40
14,300.00
7,800.00
16,302.00
5,200.00
22,990.50
1,560.00
92,628.90

pcs.

1,586.00

12.00

19,032.00

3.60

5,709.60

15.60

24,741.60

D4 Masonry Works (4th Floor)


100mm thick C.H.B.
Prepared by:
Engr. Mark Gregory A. Rimando. MSCE
Civil Engineer-Structural Engineer

D4
40 kg. Portland Cement (Mortar)
River sand (Mortar)
40 kg. Portland Cement (Plaster)
River sand (Mortar)
10mm x 6m Deformed Bar
Gage 16. Galvanized Iron Wire

bag
cu.m.
bag
cu.m.
pcs.
kg.

50.00
6.00
58.00
4.00
132.00
16.00

220.00
1,000.00
220.00
1,000.00
135.00
75.00
Sub Total

11,000.00
6,000.00
12,760.00
4,000.00
17,820.00
1,200.00
71,812.00

66.00
300.00
66.00
300.00
40.50
22.50

3,300.00
1,800.00
3,828.00
1,200.00
5,346.00
360.00
21,543.60

286.00
1,300.00
286.00
1,300.00
175.50
97.50

14,300.00
7,800.00
16,588.00
5,200.00
23,166.00
1,560.00
93,355.60

D5 Masonry Works (5th Floor)


100mm thick C.H.B.
40 kg. Portland Cement (Mortar)
River sand (Mortar)
40 kg. Portland Cement (Plaster)
River sand (Mortar)
10mm x 6m Deformed Bar
Gage 16. Galvanized Iron Wire

pcs.
bag
cu.m.
bag
cu.m.
pcs.
kg.

1,603.00
51.00
6.00
58.00
4.00
134.00
16.00

12.00
220.00
1,000.00
220.00
1,000.00
135.00
75.00
Sub Total

19,236.00
11,220.00
6,000.00
12,760.00
4,000.00
18,090.00
1,200.00
72,506.00

3.60
66.00
300.00
66.00
300.00
40.50
22.50

5,770.80
3,366.00
1,800.00
3,828.00
1,200.00
5,427.00
360.00
21,751.80

15.60
286.00
1,300.00
286.00
1,300.00
175.50
97.50

25,006.80
14,586.00
7,800.00
16,588.00
5,200.00
23,517.00
1,560.00
94,257.80

D6 Masonry Works (6th Floor)


100mm thick C.H.B.
40 kg. Portland Cement (Mortar)
River sand (Mortar)
40 kg. Portland Cement (Plaster)
River sand (Mortar)
10mm x 6m Deformed Bar
Gage 16. Galvanized Iron Wire

pcs.
bag
cu.m.
bag
cu.m.
pcs.
kg.

1,620.00
52.00
6.00
59.00
4.00
135.00
16.00

12.00
220.00
1,000.00
220.00
1,000.00
135.00
75.00
Sub Total

19,440.00
11,440.00
6,000.00
12,980.00
4,000.00
18,225.00
1,200.00
73,285.00

3.60
66.00
300.00
66.00
300.00
40.50
22.50

5,832.00
3,432.00
1,800.00
3,894.00
1,200.00
5,467.50
360.00
21,985.50

15.60
286.00
1,300.00
286.00
1,300.00
175.50
97.50

25,272.00
14,872.00
7,800.00
16,874.00
5,200.00
23,692.50
1,560.00
95,270.50

D7 Masonry Works (7th Floor)


100mm thick C.H.B.
40 kg. Portland Cement (Mortar)
River sand (Mortar)
40 kg. Portland Cement (Plaster)
River sand (Mortar)
10mm x 6m Deformed Bar
Gage 16. Galvanized Iron Wire

pcs.
bag
cu.m.
bag
cu.m.
pcs.
kg.

1,637.00
52.00
6.00
59.00
4.00
136.00
16.00

12.00
220.00
1,000.00
220.00
1,000.00
135.00
75.00
Sub Total

19,644.00
11,440.00
6,000.00
12,980.00
4,000.00
18,360.00
1,200.00
73,624.00

3.60
66.00
300.00
66.00
300.00
40.50
22.50

5,893.20
3,432.00
1,800.00
3,894.00
1,200.00
5,508.00
360.00
22,087.20

15.60
286.00
1,300.00
286.00
1,300.00
175.50
97.50

25,537.20
14,872.00
7,800.00
16,874.00
5,200.00
23,868.00
1,560.00
95,711.20

D8 Masonry Works (8th Floor)


100mm thick C.H.B.
40 kg. Portland Cement (Mortar)
River sand (Mortar)
40 kg. Portland Cement (Plaster)
River sand (Mortar)
10mm x 6m Deformed Bar
Gage 16. Galvanized Iron Wire

pcs.
bag
cu.m.
bag
cu.m.
pcs.
kg.

1,655.00
53.00
6.00
60.00
4.00
138.00
16.00

12.00
220.00
1,000.00
220.00
1,000.00
135.00
75.00
Sub Total

19,860.00
11,660.00
6,000.00
13,200.00
4,000.00
18,630.00
1,200.00
74,550.00

3.60
66.00
300.00
66.00
300.00
40.50
22.50

5,958.00
3,498.00
1,800.00
3,960.00
1,200.00
5,589.00
360.00
22,365.00

15.60
286.00
1,300.00
286.00
1,300.00
175.50
97.50

25,818.00
15,158.00
7,800.00
17,160.00
5,200.00
24,219.00
1,560.00
96,915.00

D9 Masonry Works (9th Floor)


100mm thick C.H.B.
40 kg. Portland Cement (Mortar)
River sand (Mortar)
40 kg. Portland Cement (Plaster)
River sand (Mortar)
10mm x 6m Deformed Bar
Gage 16. Galvanized Iron Wire

pcs.
bag
cu.m.
bag
cu.m.
pcs.
kg.

1,672.00
53.00
6.00
61.00
4.00
139.00
16.00

12.00
220.00
1,000.00
220.00
1,000.00
135.00
75.00
Sub Total

20,064.00
11,660.00
6,000.00
13,420.00
4,000.00
18,765.00
1,200.00
75,109.00

3.60
66.00
300.00
66.00
300.00
40.50
22.50

6,019.20
3,498.00
1,800.00
4,026.00
1,200.00
5,629.50
360.00
22,532.70

15.60
286.00
1,300.00
286.00
1,300.00
175.50
97.50

26,083.20
15,158.00
7,800.00
17,446.00
5,200.00
24,394.50
1,560.00
97,641.70

D10 Masonry Works (10th Floor)


100mm thick C.H.B.
40 kg. Portland Cement (Mortar)
River sand (Mortar)
40 kg. Portland Cement (Plaster)
River sand (Mortar)
10mm x 6m Deformed Bar
Gage 16. Galvanized Iron Wire

pcs.
bag
cu.m.
bag
cu.m.
pcs.
kg.

435.00
14.00
2.00
16.00
1.00
37.00
5.00

12.00
220.00
1,000.00
220.00
1,000.00
135.00
75.00
Sub Total

5,220.00
3,080.00
2,000.00
3,520.00
1,000.00
4,995.00
375.00
20,190.00

3.60
66.00
300.00
66.00
300.00
40.50
22.50

1,566.00
924.00
600.00
1,056.00
300.00
1,498.50
112.50
6,057.00

15.60
286.00
1,300.00
286.00
1,300.00
175.50
97.50

6,786.00
4,004.00
2,600.00
4,576.00
1,300.00
6,493.50
487.50
26,247.00
675,914.00
628,574.79
1,304,488.79
130,448.88
39,134.66
81,109.68
1,555,182.01

Total Material Cost


Total Labor Cost
Direct Cost
Contractor's Profit (10% of Direct Cost)
Contingencies (3% of Direct Cost)
VAT 12% of Material Cost
Grand Total Cost
Terms of Payment:
30% Of Direct Cost DownPayment (Mobilization) =

Prepared by:
Engr. Mark Gregory A. Rimando. MSCE
Civil Engineer-Structural Engineer

466,554.60

less 10% Retention Cost =


155,518.20
Monthly Progress Billing = [(Grand Total Cost) -(Down Payment) - (Retention)]

Prepared by:
Engr. Mark Gregory A. Rimando. MSCE
Civil Engineer-Structural Engineer

Demolition of Trusses
Removal of Asphalt Shingles (Front)
Removal of Asphalt Shingles (Rear)
Installation of Trusses and Purlins (Front)
Retrofitting
Addiitional Purlins at Rear Rooofing
Perimeter Purlins
Total

BOQ
45,000.00
45,000.00
50,000.00
80,000.00
95,780.15
60,000.00
20,640.00
12,384.00
408,804.15

Work to be finished in 18 days (3 weeks)


10% Retention to be deducted from Approved Contract Cost
Scope of Works:
Layout
Fabrication and Erection of Trusses
Installation of Purlins
Installation of Additional Purlins (Rear)
Retroffiting of Existing Trusses

Nino
15,000.00
10,000.00
10,000.00

SAVINGS
30,000.00
35,000.00
40,000.00

70,000.00

198,804.15

105,000.00

303,804.15

Potrebbero piacerti anche