A Project Study Submitted in Partial Fulfillment of the Requirements for the Course CE 5102 Civil Engineering Project by:
Ruby Faith D. Espinosa Mark B. Kho Yute Charles C. Suobiron
Engr. Erwin L. Rizardo Adviser
Civil Engineering Department College of Engineering Central Philippine University Jaro, Iloilo City October 2013 ACKNOWLEDGMENT
We would like to thank the following: Engr. Erwin Rizardo, our adviser, and Engr. Shevanee Ruth Dela Cruz, the coordinator of the course subject, for helping us throughout the making of the study. Engr. Mary Earl Daryl Grio and Engr. Gerardo Gepulango, faculty of CPU Civil Engineering Department, for sharing their knowledge to us every time we seek technical advice; Also, Engr. Vitini Edhard Idemne, faculty of CPU Electronics and Communications Engineering, for helping us in our electrical estimates; Engr. Emmanuel Juanitas, Municipal Engineer of Barbaza, for becoming our main consultant in Antique. Former Mayor Faith Francisco, the municipal officials, and residents of Barbaza for responding to our data gathering; CPU Math and Physics Department for helping us in the analysis of our data; Department of Public Works and Highways and Ceres Liner Maintenance Department for providing us the necessary information for the study; Our families and friends who warmly supported us throughout the making of this project study; Kho Yutes family who always welcomed us to their residence which became the major place in the making of the study; Our classmates, CPU Civil Engineering Batch 2014, for helping us in many different ways, from sharing their knowledge and resources to simply encouraging us. Above all, the Almighty God, whom by His grace made all these things possible.
The Research Team TABLE OF CONTENTS
TITLE PAGE .. APPROVAL SHEET .. ACKNOWLEDGMENT . TABLE OF CONTENTS LIST OF FIGURES AND TABLES ....... ABSTRACT CHAPTER I: INTRODUCTION .... 1.1 Background and Rationale of the Study .. 1.2 Problem Definition .. 1.3 Ultimate Objective .. 1.4 Specific Objectives .. 1.5 Operational Variable and Key Terms .. 1.6 Significance of the Study .... 1.7 Scope and Limitation .. CHAPTER II: REVIEW OF RELATED LITERATURE ...... 2.1 The Function of Transport Terminals . 2.2 Design of Transport Terminals ... CHAPTER III: METHODOLOGY 3.1 Data Gathering 3.2 Data Analysis .. 3.3 Resources and Facilities .. i ii iii iv vi viii 1 1 6 8 9 9 10 11 12 12 14 15 15 16 18 CHAPTER IV: PROJECT AREA ... 4.1 Physical Features . 4.2 Infrastructure Resources .. 4.3 Economic Structure . 4.4 Proposed Site of the Transport Terminal CHAPTER V: THE PROPOSED PROJECT .. 5.1 Project Description .. 5.2 Architectural Plans .. 5.3 Structural Plans ... 5.4 Electrical Plans .... 5.5 Plumbing Plans 5.6 Traffic Design . 5.7 Construction Specifications . 5.8 Project Cost and Work Schedule . CHAPTER VI: PROJECT IMPLEMENTATION .. CHAPTER VII: CONCLUSIONS AND RECOMMENDATIONS ... REFERENCES .... APPENDICES ..... Appendix A Structural Design and Analysis ... Appendix B Detailed Estimates .. Appendix C Topographic Survey Appendix D Questionnaire Survey .. 19 19 24 25 27 29 29 29 31 32 32 33 67 74 79 80 81 84 84 149 158 163
LIST OF FIGURES AND TABLES
List of Figures
Figure 1.1 Map of Philippines showing the location of Antique ..... Figure 1.2 Map of Panay Island showing the location of Barbaza .. Figure 1.3 Map of Panay Island showing its towns . Figure 1.4 National road along Barbaza .. Figure 1.5 Bus unloading a passenger along the national road ... Figure 1.6 Tricycles parking along the national road .. Figure 4.1 Slope map ... Figure 4.2 Soil map .
Figure 4.3 Location of the proposed terminal (right view) . Figure 4.4 Location of the proposed terminal (left view)
List of Tables
Table 1.1 Tourist destinations . Table 1.2 Types and number of registered vehicles Table 4.1 Slope distribution . Table 4.2 Soil type distribution ...
Table 5.1 Summary of estimates . Table 5.2 Work schedule .
2 2 3 5 7 8 21 23 27 28
4 6 20 22 67 68
A PROPOSED INTEGRATED TRANSPORT TERMINAL FOR BARBAZA, ANTIQUE
ABSTRACT
A terminal may be defined as any facility where passengers and freight are assembled or dispersed. Terminals are central and intermediate locations in the movements of passengers and a necessary part of any transport system. By using schedule of services and a common loading and unloading area for public vehicles, terminals generally provide comfort, speed, and efficiency to passengers. An integrated transport terminal is proposed at Brgy. Poblacion, Barbaza, Antique to address problems of delays, missed trips, and inconvenience caused by uncertainty of travel schedule and loading of passengers along the highway. The transport terminal will cater services for nearby municipalities and can accommodate four different modes of land transportation: bus (local and RORO bus), public utility jitney (PUJ), van (PUV), and tricycle. The project study is supported with architectural, structural, electrical and plumbing plans, construction specifications, cost estimates, and work schedule. The structure was designed using the codes and specifications of the National Structural Code of the Philippines (NSCP 2010). Ultimate Stress Design and Allowable Stress Design methods were used in designing concrete and steel members respectively. The project cost is estimated to 15,314,438.45 with 82 working days to finish. The project will be funded by the Municipality of Barbaza through the Department of Finance in Manila. Chapter I
INTRODUCTION
This chapter presents the background, rationale, objectives, significance of the study of
the study, and scope and limitations of the study
1.1 Background and Rationale of the Study
Terminals are a necessary part of any transport system. It may be defined as any facility where passengers and freight are assembled or dispersed. Terminals are designed to insure a continuity of the flows that will generally provide comfort, speed, and efficiency. Transportation terminals are also focal points of economic activity. Transportation terminals are also focal points of economic activity. The traffic flowing through terminals and the need to transfer freight between the modes gives opportunities to other activities to use locational advantages. Manufacturing firms can locate near terminals. Also, terminals are linked with the service sector because terminal activity creates demands for a very wide range of transport services. Barbaza is a 4th Class municipality located at the central part of the province of Antique in Region VI (Western Visayas). Barbaza is situated along the Philippine National Highway linking the four provinces of Panay Island. The total population of Barbaza as of 2010 is 21,775. Previous censuses of population show a continual increase in number since 1970. By the year 2022, Barbaza has a projected population of 27,425.
2
Figure 1.1 Map of Philippines Showing the Location of Antique
Figure 1.2 Map of Panay Island Showing the Location of Barbaza 3
Figure 1.3 Map of Panay Island Showing its Towns
Barbaza is an agricultural and coastal community. It is the 3 rd largest rice- producing municipality in the province of Antique and exports rice to provincial and regional markets. Barbazas geographical location and nearness to different economic centers such as Kalibo, Aklan, Roxas City, Passi City, and Iloilo City makes the municipality within reach to a variety of economic investments.
4
Tourism in Barbaza relies on nature spots and on historical sites and structures. Coral reefs, beaches, forest parks, waterfalls, caves, and spring abound for tourism development. Macalbag Water Falls in Brgy. Mablad and Cadiao Falls in Brgy. Cadiao are sites where people visit during summer time. Caves can be found in Brgy. Mablad and Brgy. Esparar. They are abodes of limestone where intricate stalactite and stalagmite are found.
Historical Jinalinan Plaza (the site of the peace treaty between Gen. Fullon and the American Forces in Panay Island) Natural Esparar Cave Makalbag Falls Mablad Caves Cadiao Falls Batabat Coral Reef Religious Barbaza Catholic Church Man-Made Kaigangan Diversion Dam Villa Alianza Resort Welbeck Inland Resort
Table 1.1Tourist Destinations
Barbaza is known for its Abaca Fiber being declared by FIDA as a world class fiber which can be found in the upland barangays of the municipality. Being the largest producer of Abaca Fiber in the province, the product serves as the theme of the annual agro-industrial fair being celebrated every 2nd week of March named as Kigihan Festival. The festival brings back Barbaza balikbayans bringing with them their foreign friends. 5
Figure 1.4 National Road Along Barbaza
Transportation services in Barbaza are generally provided by tricycles, public utility jitneys (PUJs), public utility vans (PUVs), and buses. The public utility vehicles are used to transport passengers from Barbaza to Kalibo, San Jose, and Iloilo or vice versa. Tricycle, on the other hand, is the common means of transportation to most barangays. There are also daily buses available going back and forth to Manila that pass by the town via the roll-on/roll-off (RORO) nautical highway. A total of 647 motor vehicles are accounted for in the Municipality of Barbaza.
6
Type of vehicle Number Type of vehicle Number Jitney 20 Owner-type jeep 47 Private Public 17 3 Private Public 46 1 Automobile 28 Truck 18 Private Government 26 2 Private Government 16 2 Motorcycle 87 Bus 4 Tricycle 321 Van 11 Private Public 17 302 Private Public 2 9 Ambulance 2 TOTAL 647
Table 1.2Types and Number of Registered Vehicles
1.2 Problem Definition
The municipality has no terminal for public utility jitneys, tricycles, and motorcycles. At present, the existing parking area or terminal for public utility jitneys and tricycles is located in front of the public market which becomes more crowded with the increasing number of utility vehicles operating every year. A site visit and opinion survey of the residents of Barbaza resulted in the following identification of problems: Passengers in Barbaza purchase tickets through ticketing businesses (e.g. Dimple Stars) found on different sari-sari stores and they are given estimated time of arrival of the RORO buses. Delays are usually encountered by the passengers. There are also cases where they miss the bus due to the wrong estimation of arrival time. In the case of other public vehicles that do not use a ticketing system, like buses of Ceres Liners and tricycles, waiting passengers do not have the assurance that there are available and not fully occupied vehicles to ride on at specific times of day. These uncertainty problems 7
with regard to arrival time of RORO buses and availability of vehicles are most important to be considered for the safety of the passengers who travel during the night. These problems also result to inefficient use of time and effort of the passengers. Current transportation system in Barbaza shows an unsafe and disorganized traffic flow. Public vehicles load and unload passengers anytime and anywhere along the national road of the town. Because of the narrow highway, buses load and unload the passengers on the vehicle lane. With the absence of designated loading and unloading area, accidents are more probable to take place. Moreover, PUJs and tricycles usually park in front of the market and the school which becomes more crowded with the increasing number of utility vehicles operating every year.
Figure 1.5 Bus Unloading a Passenger Along the National Road
8
The present tricycle system of Barbaza is not organized. Tricycles comprise majority of the public vehicles yet there is no terminal to organize their services and load the passengers properly. Thus, drivers tend to compete in picking the passengers. Also, since they roam around the municipality looking for passengers, it results to high consumption of gasoline, and ultimately to a low profit.
Figure 1.6 Tricycles Parking Along the National Road
1.3 Ultimate Objective
The ultimate objective of this study is to design an integrated transport terminal for Barbaza, Antique.
9
1.4 Specific Objectives
To achieve the ultimate objective, the following specific objectives were met: 1. Coordinated with the Municipality Engineer; 2. Obtained necessary data from the municipality regarding the project area like population census and registered vehicles; 3. Conducted visual inspection of the site and surveyed the area; 4. Interviewed municipal officials, drivers, passengers, vendors and other residents regarding the existing transportation system; and 5. Prepared complete plans, detail specifications, work program, and cost estimates.
1.5 Operational Variable and Key Terms
A terminal is any facility where passengers and freight are assembled or dispersed in the transportation process. A tricycle is a 3-wheeled vehicle propelled by a motor. It is often used for public transportation. Public Utility Van (PUV) is a multipurpose enclosed motor vehicle having a boxlike shape, rear or side doors, and side panels (often with windows) used for public transportation. Public Utility Jitney (PUJ) is a vehicle smaller than a bus that carries passengers over a regular route on a flexible schedule and is available for use by the general public. Buses are large motor vehicles designed to carry passengers usually along a fixed route according to a schedule. 10
The Roll-on, Roll-off, popularly known as RORO, is an inter-island system of transportation that involves the driving of a motorized land vehicle in and out of an inter- island ferry or cargo ship. It is basically a mode of transportation designed to carry wheeled vehicles such as cars, trucks, cargo trucks, trailers, etc. over a body of water. Some RORO vessels also transport passengers. Ceres Liner is a bus line under Vallacar Transit Inc., the largest public land transportation company in the island of Negros, Philippines. It operates bus transport service to the whole island of Negros from Bacolod City to Panay, Cebu and Samar- Leyte islands. A municipality is a local government unit in the Philippines. Municipalities are also called towns.
1.6 Significance of the Study
The construction of the terminal will provide an organized system of transportation in Barbaza. It will provide the passengers a more convenient and efficient transportation service while preventing loss of their time and effort. Because of the scheduling of services and continuity of transport services, the terminal will provide public vehicle drivers the assurance of having passengers in their trips, and help the tricycle drivers reduce their high fuel consumption caused by roaming around, looking for passengers. The terminal, therefore, will help increase the income of PUJ and tricycle drivers in Barbaza in a time-efficient manner. 11
The terminal will help decrease the accident rates in Barbaza by providing a separate loading area for public vehicles and a safe waiting area for passengers that would mostly benefit the night-time travelers. The terminal will improve the economic status of Barbaza by increasing the employment rate through hiring necessary people for the needed terminal services. It will also bring locational advantages like the operation of different businesses in the vicinity. An organized system of transportation through terminals will also bring good accommodation for tourists and therefore boost the tourism of the municipality.
1.7 Scope and Limitation
This study includes all architectural, structural, electrical, and plumbing plans, structural analysis and details, construction specifications, project cost and estimates, and work schedule of the proposed integrated transport terminal. The actual construction, implementation and maintenance of the project are not included in the study. The study does not include any view regarding the administration and management of the terminal and the assessment regarding its environmental impacts.
Chapter II
REVIEW OF RELATED LITERATURES
This chapter presents the review of literature and other related studies
2.1 The Function of Transport Terminals
2.1.1 The Nature of Transport Terminals
Terminals are a necessary part of any transport system. A terminal may be defined as any facility where passengers and freight are assembled or dispersed. Both cannot travel individually, but in batches. Terminals may be points of interchange involving the same mode of transport. They may also be points of interchange between different modes of transportation. Transport terminals are central and intermediate locations in the movements of passengers and freight. They often require specific facilities and equipment to accommodate the traffic they handle.
2.1.2 Economic Advantages of Transport Terminals
Transportation terminals are focal points of economic activity. The traffic flowing through terminals and the need to transfer freight between the modes gives opportunities to other activities to use locational advantages. There have been long standing advantages for certain types of manufacturing to locate near terminals. Also, terminals are linked with the service sector. Terminal activity creates demands for a very wide range of transport services. These include activities as diverse as locomotive repair, kitchens, warehousing, duty free stores, and freight forwarders. Together they comprise 13
an important business sector that contributes to the overall effectiveness of the terminal. In addition to the linkages with manufacturing and the service sector, terminals are major employers in their own right. In order to operate a major terminal requires a wide range of employee skills. Terminals, therefore, is a source of employment and benefit regional economic activities, notably by providing accessibility to suppliers and customers. They become foci of economic activity because they generate links to other sectors of the economy. Terminals are frequently considered as growth poles.
2.1.3 Terminal Costs
Because they jointly perform transfer and consolidation functions, terminals are important economically because of the costs incurred in carrying out these activities. Terminal costs represent an important component of total transport costs. They are fixed costs that are incurred regardless of the length of the eventual trip, and vary significantly between the modes. They can be considered as: 1. Infrastructure costs. Include construction and maintenance costs of structures. 2. Transshipment costs. The costs of loading and unloading passengers or freight. 3. Administration costs. Many terminals are managed by institutions. Administration costs are incurred. A truck or a passenger bus can be loaded much more quickly, and hence the terminal costs for road transport are the lowest.
14
2.2 Design of Transport Terminals
An important factor which determines the level of transportation service is the design of a transport terminal. Apart from comfort, speed, and efficiency in trunk movement, what contributes to passenger satisfaction is the planning of the terminal in such a manner that its internal layout minimizes the possible disorientation of a passenger as he alights from his vehicle and rushes into the terminal building desiring that he be enabled to proceed to the destination without undue loss of time. Layouts and activities taking place in passenger terminals tend to be simple and require relatively little equipment. This is because individual mobility is the means by which passengers access buses, ferries or trains. They may appear congested at certain times of the day, but the flows of people can be managed successfully with good design of platforms and access points, and with appropriate scheduling of arrivals and departures. The amount of time passengers spend in such terminals tends to be brief. Transport terminal facilities may include: arrival and departure lanes; traffic control facilities; terminal administration areas; terminal operations, maintenance, safety, and security areas; parking areas for terminal personnel, customers, and visitors; and transport vehicle servicing areas.
Chapter III
METHODOLOGY
This chapter presents the methodology of the study, specifically the site visit, data
gathering, surveying, architectural plans, and structural design and analysis
3.1 Data Gathering
3.1.1 Site Visit
Site visits were conducted to investigate the present situation around the vicinity. Informal interviews with the Mayor, the municipal officials, and the residents were conducted regarding their opinion and ideas about the current transportation system of Barbaza. With the help of the Municipal Engineer, the proposed site of the terminal was inspected visually and observations were noted regarding the flow of traffic, and the characteristics of the site and its surroundings. The boundaries for the proposed project were also located.
3.1.2 Questionnaire Survey
To determine the acceptability of the residents on the proposed project, questionnaires were made and distributed to 50 drivers and 50 passengers by convenience sampling. The sample questionnaire and the summary of the results are found in Appendix E.
16
3.1.3 Topographic Survey
The site was surveyed using inclined sights. Different points were located within the proposed site, its boundaries, and its surroundings. The values obtained, the detailed computations, and the resulting topographic map are found in Appendix D.
3.2 Data Analysis
3.2.1 Development of Plans
Architectural plans were conceptualized using the data on the registered vehicles of Barbaza. The dimensions of the design vehicle for the bus lane was based on the largest RORO bus that passes by Barbaza (data obtained from the Maintenance Department of Ceres Liner at Buhang, Jaro). Architectural, electrical, and plumbing plans were aided by able professionals.
3.2.2 Structural Design and Analysis
Details were prepared with utmost simplicity, accuracy, and clarity for easy understanding in construction. Beams are designed to have uniform dimensions for aesthetic and economic purposes.
3.2.2.1 Material Properties and Data Specifications
Compressive strength of concrete (fc) and yield stress of steel (fy) used were based on the usage of the structure and availability of materials in the market. Unit weight of soil was based on construction practices in Antique.
17
For beams and slabs, fc = 28 MPa For columns, fc = 21 MPa For all structural members, fy = 275 MPa Weight of concrete, Wc = 23.5 KN/m 3
Allowable soil bearing capacity, qa = 50 kPa Unit weight of soil = 15.7 KN/m 3
3.2.2.2 Design Code, Standards, and Method
The structure was designed using the codes and specifications of the National Structural Code of the Philippines (NSCP 2010). The design for terminal slabs was based on the standards set by the Department of Public Works and Highway. The properties of steel are based on ASEP Steel Manual. Ultimate Stress Design (USD) method was used in the design and analysis of reinforced concrete members. While Allowable Stress Design (ASD) method was used for steel. Throughout the design of structural members, all columns and footings are assumed to be axially loaded.
3.2.2.3 Design Load Specifications
Roofing (arched beam) Dead load: G.I. sheet = 0.08 KPa
Roofing (diagonal beam) Dead load: G.I. sheet = 0.08 KPa
Background information of the project area was taken from the two Comprehensive Land Use Plans of Barbaza (2004-2014 and 2012-2022) obtained at the Office of the Municipality. The CLUP contains the record of the registered local vehicles, maps, physical features of Barbaza, and its human resources and economic structure. Reference books, online articles, and past project studies of CPU Civil Engineering Department were also used to support the study. Theodolite and stadia rods were used in the topographic survey. AutoCAD software was used to draft all plans and the topographic map. Spreadsheet software Microsoft Office Excel (MS Excel) was used in the computation of elevations, structural analysis, and cost estimates. Statistical Product and Service Solutions (SPPS) tool was used in analyzing the results of the questionnaire survey. Cameras were used to document opinion surveys and pictures of the site. Laptops were used to secure all data and prepare all required reports. Chapter IV
PROJECT AREA
This chapter profiles the project area of the proposed project plan
4.1 Physical Features
4.1.1 Land Area
Barbaza is located in the central part of Antique. It has a total land area of 15,436.333 hectares, of which 9,207.964 (60%) hectares are timberland and 5,674.951 (40%) hectares, alienable and disposable lands.
4.1.2 Geographic Location
The municipality is located at 11 11 48 855 N latitude 122 0214 191 E longitude. It is bounded in the north by the municipality of Tibiao, on the east by the municipality of Tapaz, Capiz, on the south by the municipality of Laua-an, and the Cuyo East Pass on the west. It is 60 kilometers away from San Jose de Buenavista, the provincial capital and 160 kilometers away from Iloilo City.
4.1.3 Political Subdivision
Barbaza is one of the 18 municipalities in the Province of Antique. It is composed of 39 barangays, which are divided into two categories, the lowland and the upland areas.
20 4.1.4 Geology
The underlying rocks of the Municipality of Barbaza are mostly igneous. These rocks are metamorphic and igneous rock in nature and mostly found on the eastern section of the municipality. The parent materials of these rocks belong to Lumboyan Formation, Baloy Volcanics and Qauternary Alluvium. Aside from this basalt formation, coralline limestone rock deposits are also found in Barbaza and are mostly concentrated in the hills of the southern and eastern parts of the municipality.
4.1.5 Elevation and Slope
The municipality has the highest elevation of 2,325m found in Mt. Nangtud, Barangay Mayabay. The 0-3% slope which is equal to 2,375.70 hectares is considered to be alienable and disposable area based on the topographic map of National Mapping and Research Institute Agency (NAMRIA). The slope 18% and above accounts for 12,282.97 hectares. These areas include the proclaimed timberland (9,207.96 has.).
Range Land Area (ha) % Distribution 0-3% (Level to Nearly Level) 2,375.70 15.39 3%- 18 % ( Gently to Undulating) 777.34 5.04 18-30% ( Strongly Sloping to Moderate Steep) 508.40 3.29 30-50% (Steep Hills & Mountainous) 1,193.12 7.73 50% & Above (Very Steep Hills & Mountainous) 10,581.45 68.55 TOTAL 15,436.33 100%
Table 4.1Slope Distribution Figure 4.1 Slope Map 4.1.6 Soils
There are five soil types found in the Municipality of Barbaza namely: Alimodian Sandy Loam, Umingan Sandy loam, San Manuel Clay, Beach Sand and Mountain Soil Undifferentiated.
Soil Type Land Area (has) % Distribution Alimodian Sandy Clay 6,599.47 42.75 Umingan Sandy Loam 729.05 4.72 San Manuel Clay 1,013.11 6.56 Beach Sand 129.29 0.84 Mountain Undifferentiated Soils 6,932.49 44.91 River sand 32.6 0.21 TOTAL 15,436.01 100.00
Table 4.2Soil Type Distribution
4.1.7 Mineral Resources
The mountainous area of the municipality are rich in Manganese, Copper, Gold and Marble which can be found in the upland barangays of Mayabay, Lombuyan, Marigne, Mablad, Idao, Igpalge and Esparar. Other mineral deposits such as limestone can be found in Esparar. Sand and gravel is being extracted in identified rivers and is being used for infrastructure projects.
4.1.8 Water Resources
The main river, Dalanas River is 43 kilometers long, 23 kilometers falls under the jurisdiction of the municipality. A substantial number of rivers, creeks and small tributaries lead to Dalanas River. Six of them are within the jurisdiction of Barbaza.
Figure 4.2 Soil Map Natural springs and ground water, which are common sources for potable water, abound in different barangays in the municipality. The Barbaza Water District (gravity type serving 10 barangays) is taking its source from natural springs in Sitio Atabay and Sitio Bay-ang, and a pumping station in Bantayan, Brgy. Gua. There are other natural springs in the municipality which are also sources of potable water and irrigation system.
4.2 Infrastructure Resources
4.2.1 Roads
The Municipality of Barbaza is linked to the adjacent municipalities of Laua-an on the south and Tibiao on the north through the national highway. The provincial road has a total length of 52.60 kilometers. The municipal road can be found in Poblacion and Jinalinan and these cover 3.834 kilometers. Barangay roads have a total length of 69.93 kilometers.
4.2.2 School Buildings
Barbaza School District has 18 elementary schools. There are 16 public and 2 private schools. It has two secondary schools, one private and one public. All secondary schools, Barbaza National High School and Saint Anthonys High School are strategically located along the national highway. Most of the barangays have Day Care Centers except for some remote barangays.
4.2.3 Health Services
There is a municipal hospital being managed by the Antique Provincial Health 24 Office in Brgy. Lisub admitting patients for consultations and confinement. Barbaza Rural Health Unit is in Poblacion, where basic services can be availed of. Ten Barangay Health Stations are located in catchment barangays. A government dentist is available at the municipal hospital. Private dental practitioners are also available, one in the Poblacion, one in Sitio Aligtos, Barangay Igpalge, and two in Brgy. Capoyu-an.
4.2.4 Public Building & Facilities
Barbaza has a municipal building for 200 employees, a covered court, and a PNP building housing 24 PNP personnel.
4.2.5 Utilities
Antique Electric Cooperative (ANTECO) provides power services for the 27 barangays. Town based information and communication facilities are made up of the Philippine Postal Office, Globe, Smart and Sun cellular sites. Other courier companies service the municipality, although their offices are based in other towns in the province.
4.3 Economic Structure
4.3.1 Public Markets
There are two public markets in the municipality. The Poblacion Daily Market, in Poblacion, is along the national highway, and Palma Public Market with Bagsakan Center located in Brgy. Palma leading to the northern part of Antique.
25 4.3.2 Industry
Barbaza is known for its Abaca Fiber being declared by FIDA as a world class fiber. Dalanas River is a major source of aggregates and identified by the Provincial Engineering District DPWH-Antique as one of the two main sources of gravel, boulders and sand in the province. Several quarry operators are operating in the area, exporting aggregates to other parts of the country. One multi-pass and five mobile rice mills are operating in the locality. Two hollow blocks producers and three bakeries are situated within the lowland area. Two wood-furniture makers, one bamboo craft producer, and one noodles fruit processing plant in Brgy. Esparar. All these, including the chain saw operators, comprise the various industries in the municipality. There are approximately 230 commercial wholesale and retail establishments, recreational parlors, hollow block factory, refilling stations, warehouses and shops operating in the entire municipality.
4.3.3 Agriculture
Barbaza is the 3rd leading rice producing municipality in the province of Antique. Four thousand five hundred forty four hectares (4,544 or 29.44 %) of its land is fertile agricultural land planted to different crops.
4.3.4 Employment
Farming and fishing are the occupation of the majority of Barbazeos. To estimate the monetary value of per diems of an ordinary farmer or laborer, this cannot 26 augment the daily operating expenses of one household with a member of five. The same scenario was also revealed during the National Household Targeting System for Poverty Reduction, conducted by the DSWD, which they have identified 35.54% (1,520) of the total households belong to poor households during their assessment last 2008.
4.4 Proposed Site of the Transport Terminal
The site is located along the plaza area and near the national road. Majority of the land is vacant but a part is currently being rented by local eateries made of nipa and bamboo. The land is legally owned by the municipality of Barbaza.
Figure 4.3 Location of the Proposed Terminal (right view)
27
Figure 4.4 Location of the Proposed Terminal (left view)
Chapter V
THE PROPOSED PROJECT
This chapter presents the project description, architectural plans, structural plans,
electrical plans, plumbing plans, traffic design, and construction specifications
5.1 Project Description
The proposed project is a transportation terminal with an administration office, public rest rooms, waiting area, storage room, and guardhouse. The transport terminal is located at Poblacion, Barbaza, Antique. The proposed project has an area of 800 square meters (m 2 ), 40 meters by 20 meters. It is expected to accommodate four different modes of transportation: 4 buses (RORO and local buses), 3 public utility jitneys (PUJs) or vans (PUVs), and 18 tricycles. Vehicles have separate lanes for parking. The administration office will serve as the information center of passengers and the office for over-all administrator. The storage room may be used for janitorial supplies.
5.2 Architectural Plans
The architectural plans include the perspective, the vicinity map and site development plan, the elevations of the terminal, the schedule of doors and windows and details of gate, and the ground floor plan indicating the traffic flow and positions of vehicles in the terminal.
Site Church Saint Anthony's High School Pharmacy Plaza Municipal Hall National Road going North VICINITY MAP SCALE : N.D.T.S. 31
5.3 Structural Plans
Structural plans include the foundation plan, roof framing plans, and structural details of beams, columns, and footings. Detailed computations for the structural analysis and design are found on Appendix B.
5.3.1 Design of Purlins
Purlins are used over the arched and inclined wide-flange beams of the roof. The purlins are C 8 x 13.5. Weld is E 60 XX Electrode (4.76 mm or 3/16 in) with the length of 224.4 mm.
5.3.2 Design of Slabs
5.3.2.1 Roof slab
One-way slab design is used for the waiting area. One-way slab has a thickness of 165 mm. Two-way slabs are used for the office, comfort room, storage room, and the guard house. These slabs have thickness of 125 mm.
5.3.2.2 Floor slab
Floor slabs of the terminal have thickness of 150 mm with 12 mm diameter reinforcing bars spaced at 750 mm based on DPWH standard for terminal slabs.
5.3.3 Design of Beams
The beams of the roof (arched, inclined, and horizontal) are wide-flange beams. The beams are W 10 x 15. The beams for the minor structure are reinforced concrete 32
with dimensions of 330 x 150 mm.
5.3.4 Design of Columns
The columns of major structure are composite members of steel and concrete joined with base plates. The columns are W 6 x 12 joined with reinforced concrete columns with dimensions of 250 x 250 mm. Base plates have dimensions of 200 x 200 x 10 mm. The long wide-flange columns are W 6 x 12. The columns of minor structure are reinforced concrete with dimensions of 150 x 150 mm.
5.3.5 Design of Footing
All footings are designed as square footings. Footings under the composite columns have dimensions of 1.6 m x 1.6 m and 1.4 m x 1.4 m. Footings for the reinforced concrete columns of the minor structure have dimensions of 1.2 m x 1.2 m.
5.3.6 Design of Bolts and Stirrups
Design of bolts and stirrups with detailed computations are found in Appendix B.
5.4 Electrical Plans
The electrical plans include the electrical layout, schedule of loads, and design analysis.
5.5 Plumbing Plans
The plumbing plans include the plumbing layout, septic vault detail, and catch 33
basin detail.
5.6 Traffic Design
5.6 1 Parking space
Length of 11.5 meters and width of 3.5 meters are provided for each bus. Dimensions of 7.5 meters by 2.5 meters are provided for each PUJ/PUV, while 2 meters by 2 meters are provided for each tricycle.
5.6.2 Pavement
The surface will be paved with concrete. The pavement will have a 2% slope. Slope in the pavement is necessary to drain water and prevent it from staying at the center of pavement.
5.6.3 Lights
Lights are provided for guidance and safety of drivers and passengers.
ARCHITECTURAL PLANS
PERSPECTIVE FRONT ELEVATION SCALE : N.D.T.S. 1 2 3 4 5 EXIT ENTRANCE 11.56 m 11.50 m 1 1 .8 7 m 5 . 5 0
m 3 . 0 0
m 2 . 3 5
m 1 1 . 2 0
m 0 . 3 0
m 3 . 4 5
m 2 . 7 5
m 3 . 0 0
m 2 . 3 0
m SEE BLOW UP A 3 5 2 1 4 REAR ELEVATION SCALE : 1 1 . 2 0
m 2 . 0 0
m 3 . 9 0
m 3 . 0 0
m 2 . 3 0
m N.D.T.S. LEFT ELEVATION SCALE : N.D.T.S. A B C 0 . 3 0
m 3 . 1 5
m 2 . 7 5
m 3 . 0 0
m 1 . 3 0
m 1 1 . 2 0
m SEE BLOW UP B A B C RIGHT ELEVATION SCALE : N.D.T.S. 3 . 1 5
m 2 . 7 5
m 2 . 6 0
m 1 . 3 0
m 0 . 3 0
m 1 1 . 2 0
m WAITING AREA OFFICE STORAGE 3 2 1 GUARDHOUSE SCALE : N.D.T.S. R O A D ENTRY EXIT PROPERTY LINE PROPERTY LINE P R O P E R T Y L IN E P R O P E R T Y L IN E 1 2 3 4 5 A A' A'' B B' B'' C A D1 D1 D2 D2 D3 D3 D3 W1 W2 W2 W3 W4 W4 10.00 m 10.00 m 10.00 m 10.00 m 3 . 6 0
m 3 . 4 0
m 3 . 0 0
m 4 . 5 0
m 3 . 0 0
m 2 . 5 0
m 3.00 m 5.00 m 5.00 m 1 0 . 0 0
m 1 0 . 0 0
m 3.30 m GROUND FLOOR PLAN BUS LANE JEEPNEY LANE TRICYCLE LANE SEE BLOW UP A OF GROUND FLOOR PLAN SCALE : N.D.T.S. R O A D ENTRY EXIT PROPERTY LINE PROPERTY LINE P R O P E R T Y
L I N E P R O P E R T Y
L I N E 1 2 3 4 5 A B C 10.00 m 10.00 m 10.00 m 10.00 m 5.00 m 1 0 . 0 0
m 1 0 . 0 0
m TRAFFIC FLOW DIAGRAM BUS LANE JEEPNEY LANE TRICYCLE LANE 1 0 . 0 0
m 1 0 . 0 0
m 5.00 m 40.00 m 3 2 1 SCALE : N.D.T.S. P R O P E R T Y
L I N E 1 A A' A'' B B' B'' C D1 D1 D2 D2 D3 D3 D3 W1 W2 W2 W3 W4 W4 3 . 6 0
m 3 . 4 0
m 3 . 0 0
m 4 . 5 0
m 3 . 0 0
m 2 . 5 0
m 3.00 m 3.30 m BLOW UP A OF GROUND FLOOR PLAN GUARD HOUSE OFFICE WAITING AREA COMFORT ROOM STORAGE ROOM D1 D2 D3 W1 W2 W3 W4 0.73 0.68 1.40 2.90 0.60 0.60 1.20 0.50 0.80 0.70 0.50 FINISH OFFICE FLOOR LINE SCHEDULE OF DOORS MARK DESCRIPTION D - 1 SOLID WOOD KD PANEL DOOR HEIGHT 2.10 WIDTH 0.80 NO. OF SETS 2 D - 2 2.10 0.70 2 SCHEDULE OF WINDOWS MARK DESCRIPTION HEIGHT WIDTH NO. OF SETS W - 1 1.20 2.90 1 6MM THK. FIXED GLASS WINDOW ON ALUM. FRAME SOLID WOOD KD PANEL DOOR D - 3 2.10 0.50 3 PVC DOOR W/ LOUVER W - 2 1.20 1.40 2 6MM THK. SLIDING GLASS WINDOW ON ALUM. FRAME W - 3 1.20 1.20 1 6MM THK. SLIDING GLASS WINDOW ON ALUM. FRAME W - 4 .50 .50 2 6MM THK. AWNING GLASS WINDOW ON ALUM. FRAME SCHEDULE OF DOORS & WINDOWS SCALE : N.D.T.S. BLOW UP A SCALE : BLOW UP B SCALE : GATE DETAIL SCALE : NDTS BRICKS ROAD LINE FINISH TERM. FLOOR LINE TOP OF SQUARE BAR TOP OF SQUARE BAR POST 1/4" THK X 4" SQUARE TUBE 1/4" THK. X 2" SQUARE TUBE 1/4 " THK X 6" SQUARE TUBE 2.35 2.36 4.71 TOP OF FENCE 1.92 1.97 3.89 1/4" THK. X 1" ANGLE BAR 2.45 2.45 0.15 1.35 0.10 0.70 0.15 0.15 1.35 0.10 0.70 0.15 1/4" THK. X 2" SQUARE TUBE NDTS NDTS
STRUCTURAL PLANS
1 2 3 4 5 A B C FOUNDATION PLAN SCALE N.D.T.S. C1F1 C3F2 C1F1 C1F1 C2F3 C2F3 C2F3 C2F3 C2F3 C2F3 C2F3 C2F3 C2F3 10.00m 10.00m 10.00m C3F2 C3F2 C3F2 C3F2 C3F2 C3F2 C3F2 C3F2 C3F2 C3F2 C3F2 C2F3 WF1 WF1 WF1 WF2 WF2 WF2 WF2 WF2 WF1 WF1 WF1 WF1 WF1 WF1 WF1 WF2 WF2 WF2 WF2 WF1 WF1 WF1 WF1 WF1 WF1 7.00m 3.00m 1 0 . 0 0 m 1 0 . 0 0 m 2 . 5 0 m 3 . 0 0 m 4 . 5 0 m 3 . 0 0 m 3 . 4 0 m 3 . 6 0 m 3.30m 8 - 16mm O.C.B.W. NGL 0 . 8 0
m 4 - 16mm RSB w/ 10mm LAT. TIES @ 2 - 0.05m,. 2-0.10m., @ 0.15m., O.C. 8 - 16mm O.C.B.W. 4 - 16mm 1 . 6 0
m 0.25 m DETAIL OF C1F1 SCALE N.D.T.S. 5 - 16mm O.C.B.W. NGL 0 . 8 0
m 3 - 16mm O.C.B.W. NGL 0 . 8 0
m 0 . 2 4
m 1 . 4 0
m 0.25 m DETAIL OF C3F2 SCALE N.D.T.S. DETAIL OF C2F3 SCALE N.D.T.S. 0 . 1 8
m 250 mm x 250 mm Column 250 mm x 250 mm Column 250 mm x 250 mm Column 4 - 16mm RSB w/ 10mm LAT. TIES @ 2 - 0.05m,. 2-0.10m., @ 0.15m., O.C. 4 - 16mm RSB w/ 10mm LAT. TIES @ 2 - 0.05m,. 2-0.10m., @ 0.15m., O.C. 0 . 2 5 m 0.40m 0 . 6 0 m Finish Grade Line 10mm RSB @ 0.6m O.C.B.W. WALL FOOTING FOR 100mm AND 150mm CHB WALL SCALE N.D.T.S. ROOF FRAMING PLAN SCALE : N.D.T.S. 1 2 3 4 5 A B C Purlins 11.50 m 10.20 m 11.50 m 10.20 m INCLINED WIDE FLANGE INCLINED WIDE FLANGE ARCHED WIDE FLANGE ARCHED WIDE FLANGE HORIZONTAL WIDE FLANGE HORIZONTAL WIDE FLANGE 10.00 m 10.00 m 10.00 m 10.00 m 1 0 . 0 0
m 1 0 . 0 0
m 1 . 0 0
m 1 . 0 0
m 1.12 m 1.12 m 1.12 m 1.12 m ROOF BEAM FRAMING PLAN (ARCHED AND INCLINED BEAM) SCALE N.D.T.S. 1 2 3 4 5 A B C C5 B6 B7 40.00 m 10.00 m 10.00 m 10.00 m 10.00 m 1 0 . 0 0
m 1 0 . 0 0
m B6 B6 B6 B6 B6 B7 B7 B7 B7 B7 C5 C5 C4 C4 C4 C4 C4 C4 C4 C4 C4 C4 C4 C4 1.12 m 1.12 m ROOF BEAM FRAMING PLAN AT C5 SCALE N.D.T.S. 1 2 3 4 5 A B C B8 40.00 m 10.00 m 10.00 m 10.00 m 10.00 m 40.00 m 10.00 m 10.00 m 10.00 m 10.00 m 1 0 . 0 0
m 1 0 . 0 0
m C4 C4 C4 C4 C4 C4 C4 C4 C4 C4 C4 C4 C5 C5 C5 B8 B8 B8 B8 B8 B8 B8 B8 B8 B8 B8 B8 B8 B8 B8 B8 B8 B8 B8 B8 B8 B2 B2 B3 B3 B2 B3 B1 B1 B1 B4 B5 B4 B5 B1 B4 B5 C1 C2 C2 C2 C2 C2 C2 C2 C2 C2 C1 C1 C3 C3 ROOF BEAM FRAMING PLAN (MINOR STRUCTURE) SCALE N.D.T.S. C3 1 2 3 4 5 A A' A'' B B' B'' C S2 S3 S1 S4 S5 B1 40.00 m 10.00 m 10.00 m 10.00 m 10.00 m 3.30 m C3 C3 C3 C3 C3 C3 C3 C3 C3 C2 3.00 m 3 . 6 0
m 3 . 4 0
m 3 . 0 0
m 4 . 5 0
m 3 . 0 0
m 2 . 5 0
m Scale 0.15mm BEAM DETAILS N.D.T.S. 0.33 mm Vertical Stirrups 10mm, 4 @ 80mm, 5 @ 120mm and rest @ 160mm 2-16mm Top Bars 2-16mm Bottom Bars 0 . 0 7 5
m 12 mm Straight Bars @ 150 mm O.C. 10 mm Shrinkage and Temperature Bars @ 175 mm O.C. 0 . 0 7 5
m 3.30 m 7 . 5 0
m WAITING AREA ONE-WAY ROOF SLAB Scale N.D.T.S. 170mm thk Concrete Slab 0 . 0 7 5
m 3 . 4 m 0 . 0 7 5
m 12 mm Bent @ Straight Bars @ 200 mm O.C. 12 mm Straight Bars @ 200 mm O.C. 12 mm Bent @ Straight Bars @ 200 mm O.C. 12 mm Straight Bars @ 200 mm O.C. 0.075 m 0 . 0 8
m 3 . 6 0
m 3.00 m 12 mm Bent @ Straight Bars @ 200 mm O.C. 12 mm Straight Bars @ 200 mm O.C. 12 mm Bent @ Straight Bars @ 200 mm O.C. 125 mm thk Concrete Slab Scale N.D.T.S. OFFICE AND GUARD HOUSE TWO-WAY ROOF SLAB 3 . 0 0
m 0 . 0 7 5
m 3.30 m 2 . 5 0
m 0.075 m 12 mm Bent @ Straight Bars @ 200 mm O.C. 12 mm Straight Bars @ 200 mm O.C. 12 mm Bent @ Straight Bars @ 200 mm O.C. 12 mm Straight Bars @ 200 mm O.C. Scale N.D.T.S. STORAGE ROOM AND COMFORT ROOM TWO-WAY ROOF SLAB 125 mm thk Concrete Slab
ELECTRICAL PLANS
WAITING AREA MECHANICS RM. 3 2 1 ELECTRICAL LAYOUT SCALE : NDTS ENTRY EXIT PROPERTY LINE P R O P E R T Y
L I N E P R O P E R T Y
L I N E S3 ABC E A B C C B B S1 D D S3 EFG F G S1 H S1 I S1 J H I J H I S3 KLM S2 NO K L M N O S3 PQR S3 STU O O P P Q S Q R R S T T U U V V W W X X S3 VWX C.O. POWER LINE L.O. POWER LINE 13W PINLIGHT CIRCUIT HOMERUN PANEL BOARD DUPLEX SWITCH TRIPLEX SWITCH CONVENIENCE OUTLET SINGLE POLE SWITCH S1 S2 S3 30W ELDFL FLOOD LIGHT 32W CIRCULAR LIGHT LEGEND: 22W DOME TYPE REFLECTOR W A I T I N G
A R E A M E C H A N I C S
R M . 3 2 1 PROPERTY LINE S 3
A B C E A B C C B B S 1
D D S 3
E F G F G S 1
H S 1
I S 1
J H I J H I S 3
K L M S 2
N O S 3
P Q R S 3
S T U S 3
V W X SECTION A OF ELECTRICAL LAYOUT SCALE : N.D.T.S. DESIGN ANALYSIS: C1 : LIGHT OUTLET I = 20(30W)+5(22)+6(40)+9(16.25) = 750+137.50+240+146.25=1,273.75/230 = 5.53 A Ic = 5.53 A x 1.25 = 6.91 A USE: 2 - 3.5mm THWN STRANDED 20mm UPVC 15A 2PCB BOLT-ON C2 : CONVENIENCE OUTLET I = 6(180)= 1,080 / 230 = 4.69 A Ic = 4.69 A x 1.25 = 5.86 A USE: 2 - 3.5mm THWN STRANDED 20mm UPVC FLEX. CONDUIT 20A 2PCB BOLT-ON C2,& C3:SPARE I = 500 VA 2.17AmP MAIN BREAKER: IT =3,353.75VA I LOAD = 3,353.75/230=14.58A = 14.58 A USE: 2 - 14mm THWN 60A 2P C.B. BOLT-ON 30 mm RSC 1 LOAD DESCRIPTION LIGHT OUTLETS S1 L.O. EF EL SP AMPERE CIRCUIT PROTECTION SIZE & TYPE & STRANDED CU CONDUCTOR SIZE OF CONDUIT UPVC 20mm UPVC OUTLETS SCHEDULE OF LOADS 15A 2 3 4 CIRCUIT NO. V/A SWITCHES SPARE 500.00 S2 S3 C.O. 5.53 4.69 SPARE 20A 15A 2.17 2.17 1080 2-3.5mm THWN S3W 14.56 40 6 2-14mm THWN 30mm RSC 60A 40 6 2 TOTAL 1,273.75 3,353.75 CONVENIENCE OUTLETS MAIN 20mm UPVC flex 20mm UPVC 2-3.5mm THWN 2-3.5mm THWN 500.00 1 1 SINGLE LINE DIAGRAM 15 A 2 - 3.5 mm THWN C1 C2 2 - 14 mm THWN SERVICE ENTRANCE 220V 60Hz 1 CO 2 - 3.5 mm THWN 20 A 30 mm RSC 2PCB THWN LO C9 C10 60 A SPARE SPARE
PLUMBING PLANS
PLUMBING LAY-OUT SCALE : N.D.T.S. ENTRY EXIT PROPERTY LINE P R O P E R T Y
L I N E P R O P E R T Y
L I N E 1 2 3 4 5 A A' A'' B B' B'' C C.O. URI.URI. LAV. LAV. W.C. W.C. W.C. FD. 100 rr0 30Ll0 PlPE LlNE 50 rr0 wA3TE PlPE LlNE 100 rr0 30lL PlPE LlNE 150 mm DRAINAGE SYSTEM TO STREET DRAINAGE TO STREET DRAINAGE TO STREET DRAINAGE FD. FD. FD. FD. FD. SOLID, WASTE ,SOIL & WATER PIPE LINE 50 rr0 wATER PlPE LlNE GV. GV. 150 mm DRAINAGE SYSTEM FD. SEPTIC VAULT 50 rr0 v3TR CB CB CB CB CB CB CB CB CB CB CB CB CB CB SEE BLOW UP OF CR PLUMBING LAYOUT BLOW UP OF CR PLUMBING LAYOUT SCALE : N.D.T.S. A' A'' C.O. URI.URI. LAV. LAV. W.C. W.C. W.C. FD. 100 rr0 30Ll0 PlPE LlNE 50 rr0 wA3TE PlPE LlNE FD. FD. FD. FD. FD. 50 rr0 wATER PlPE LlNE GV. GV. FD. 50 rr0 v3TR CB BLOW UP OF CR ISOMETRIC PLUMBING LAYOUT SCALE : N.D.T.S. 2000 1000 1000 4000 750 500 750 MANHOLE 250 500 250 250 500 250 10mm REINF. BARS AT 200 O.C. B.W. MANHOLE MANHOLE 500 500 500 500 100 X 200 X 400 CHB 10mm HOR. BARS @ 600 O.C. 10mm VERTICAL BARS @ 600 O.C. 4" PVC INLET 4" PVC OUTLET DIGESTIVE CHAMBER LEACHING CHAMBER LEACHING CHAMBER 600X600 MANHOLE 600X600 MANHOLE 600X600 MANHOLE 2000 1000 1000 4000 750 500 750 MANHOLE 250 500 250 250 500 250 MANHOLE MANHOLE 10mm REINF. BARS AT 200 O.C. B.W. PLAN N.G.L. N.G.L. 1 % SLOPE 4" PVC INLET SEPTIC VAULT DETAIL SCALE : N.D.T.S. 10mm REINF. BARS AT 200 O.C. B.W. 100 X 200 X 400 CHB 600 SECTION PLAN 10mm REINF. BARS AT 100 O.C. B.W. 6" CONC. PIPE 6" CONC. PIPE 6" CONC. PIPE 6" CONC. PIPE CATCH BASIN DETAIL SCALE : N.D.T.S. 67
5.7 Construction Specifications
5.7.1 Site Work The work shall include furnishing of all labor, materials, equipment, and other facilities and satisfactory performance of all work necessary to complete all the site work.
5.7.2 Preparation of the Site 5.7.2.1. Alignments 1. Lines must be staked out correctly. 2. Reference marks shall not be disturbed or moved on wrong alignment during the construction.
5.7.2.2. Excavation 1. The volume of embankment shall be 1950 m 3 . 2. The specific depth of embankment shall be levelled before concrete is placed.
5.7.3 Concrete and Masonry Works 5.7.3.1 Material 1. The mixture for all classes of concrete shall be designed and approved by the Engineer to obtain concrete having a compressive strength of 28 MPa for beams and slabs, and 21 MPa for columns, at the age of 28 days. 2. Cement shall conform to the requirements of the standard specification and test for Portland cement (ASTM C-150). 68
3. Water used for mixing shall be clean and potable, free from organic materials and acids. 4. Aggregates must be hard, tough, durable, uncoated particles, generally rounded or cubical and free from organic materials. a. Fine aggregates shall be natural sand, clean, free from injurious amount of clay, loam, and vegetables matter. b. Coarse aggregates shall be river run gravel or crushed stone. The minimum size shall be 38 mm and do not exceed 50 mm. It should be washed gravel. 5. All the mortar to be used for cement plaster shall be mixed. 6. Concrete Hollow Block units shall conform to the latest requirements of ASTM C-129. They shall be non-load bearing with minimal sizes of 100-150mm thick. Hollow block units shall be true size, without cracks, splits or other defects, which may impair the strength and durability.
5.7.3.2 Proportioning and Mixing All materials shall be proportioned as followed: Class A (1:2:4) cement, sand, gravel Mortar (1:3)
5.7.3.3 Forms 1. Forms shall be sufficient in strength to withstand the pressure resulting from placement and vibration of concrete, and shall be maintained rigidly in correct position. 69
2. Removing of forms shall be done after the concrete has attained its strength to prevent the concrete from damage.
5.7.3.4 Conveying and Placing of Concrete 1. Concrete shall be conveyed from the mixer to the place of final deposit that will prevent segregation of materials. 2. In placing of concrete it shall be tamped or vibrated to minimize the air voids that will develop after the hardening of the concrete.
5.7.3.5. Curing 1. Fresh placed concrete shall be protected from harmful action of the sun and rain. 2. Curing must be started as soon as free water has disappeared from the surface of the concrete. 3. Maintain all forms containing concrete in a wet condition until all forms are removed. All concrete shall be moist cured for a period of not less than 7 days by an approved method.
5.7.3.6 Finishing Exposed concrete surfaces shall present a smooth finished appearance except for minor defects which can easily be repaired with patching of cement mortar.
70
5.7.3.7 Concrete Hollow Block Wall All concrete hollow block walls shown on the drawings shall have 10mm vertical reinforcing bars spaced at 40cm o.c. and 10mm horizontal reinforcing bars at every three layers. All holes of the blocks shall be filled with mortar. CHB walls shall be plain finished unless otherwise indicated in the plans.
5.7.4 Structural Steel Works 1. The work included are the furnishing, erection, and installation of all bolts and other structural steel works indicated in the plan. 2. All steel reinforcement shall be structural grade, new billet stock conforming to ASTM Designation A-15 and deformed in accordance with ASTM Designation A-305. It shall conform to the ASTM-36 Latest Revision (Specification for Structural Steel), for rolled and built-up sections. 3. 16 mm diameter bars for beams with 10 mm diameter stirrups shall be provided. 4. Steel reinforcement shall be provided with all necessary tie wires to properly install the rebar in correct location. 5. All welding electrodes shall conform to the requirements of the American Welding Society (Specifications for Iron and Steel Arc-welding Electrodes). 6. Surfaces to be welded shall be free from loose scale, rust, grease, paint, and other foreign materials. Joint surfaces shall be free from fins and tears. 7. Finished members shall be true to line and free from twists, bends, and open joints. Erection shall include the setting of all structural steel as called for by the 71
plans and specifications and shall be in accordance with good engineering practice. Erection procedure shall be approved by the Engineer.
5.7.5 Electrical Works 1. The work included in electrical works shall consist of furnishing of all labor, materials, lighting fixtures, equipment, tools, and safety devices. And to make ready for the operations of electrical power and lighting as specified. 2. All works shall be done in accordance with the latest edition of the Philippine Electrical Code, the rules and regulation of the local enforcing authorities, and with the requirements of the electric utility company. 3. All materials and equipment to be used shall be of approved standard. 4. Nature of services shall be 220 V, single phase, 60 Hz. 5. Type of wiring shall be THW C, wire in rigid metal conduit for service entrance, and THHN Cu for circuit and switch lines in non-metallic conduit concealed on ceiling and embedded on concrete walls and slabs. 6. Mounting heights for the following shall be not less than as follows: MTS/Panelboard .1.20 m AFFL Pole switches ...............................1.40 m AFFL Duplex convenience outlet.. 0.30 m AFFL Counter height D.C.O. .... 0.30 m AFFL Others ...as indicated in the plan 7. All work shall be done under the direct supervision of a duly registered Electrical Engineer or Master Electrician. 72
5.7.6 Plumbing Works 1. All plumbing works shall conform to the provisions of R.A.1378, National Plumbing Code of the Philippines 1985 and the rules and regulations of the local health office. 2. All materials shall be brand new and applicable for approved location. 3. All plumbing fixtures, pipes, fittings, and accessories shall be approved quality, free from all defects and deformations. 4. All vent thru roof pipes shall be extended from roofing at least 300 mm. 5. Septic vault shall be constructed watertight or waterproofed to eliminate seepage and located at the safe distance from an existing water supply well. 6. Outflow from septic vault shall be supplied from existing municipal or city water works system as per section 102, chapter 9 of the national building code. 7. All plumbing works shall be by experienced plumbers under the direct supervision of a registered Master Plumber or Sanitary Engineer.
5.7.7. Roofing & Ceiling 1. G.I. sheets shall be used in covering of the roof of the arched beam. 2. Use C 8 x 13.75 on the I-beams of roof. 3. Gypsum board shall be used for the roofing of the minor structure. 1 cm fiber board shall be provided for insulation.
73
5.7.8. Doors & Windows 1. 6 mm glass windows on aluminium frame shall be used. Sliding doors shall be used in the entrance to the mechanics room and the office. 2. PVC door with louver shall be used for the cubicles in the rest rooms. 3. Solid wood panel doors shall be used for other doors.
5.7.9 Painting Works 1. All painting materials shall meet the requirements of the standard specification as approved for use by the Institute of Science and Technology. 2. All paints shall be delivered at the job site in their original containers, with labels intact and seals unbroken. All pints shall be specified by its brand manufacturer. 3. Surfaces to be painted shall be clean, dry, smooth, and free from dust, rust, grease or oils. 4. Skilled painters shall do all the work in a workmanlike manner. All paints shall be evenly applied, free from crawling and other defects. 5. All exterior works shall receive three coatings. 6. All metal works shall be coated with lead primer before applying the topcoat. 7. Concrete surfaces shall be treated with a coat of zinc sulphate then a coat of concrete paint to finish. 8. Paint shall be thoroughly dried before the succeeding coat is to be applied. Allow 24 hours or more between coats. 9. Colour shall be in accordance with the colour schemes to be supplied by the Engineer. 74
5.8 Project Cost and Work Schedule
The total cost of materials was estimated based on the unit cost of each material and the quantity required. The estimated cost for the project is 15,314,438.45. Project cost is subject to change because of the changes in prices of materials and cost of labor. The contingencies, which include the amount agreed for equipment, tools, temporary materials, and other miscellaneous count to 10% of the total cost. See Appendix C for detailed estimates.
General Requirements 24,600 Site Development 156,556.44 Earthworks 388,598.00 Structural Works 11,088,908.99 Civil Works and Architectural 512,541.70 Electrical 80,022.48 Plumbing 166,103.60 Contingency, 10% 1,243,053.12 VAT, 12% 1,640,854.12 TOTAL 15,314,438.45
Table 5.1Summary of Estimates
The Critical Path Method (CPM) was used for work scheduling of the project. It includes the activities and the duration of the activity from the start up to the completion of the project. The project has a duration of 82 working days. The critical path is indicated in the CPM diagram. A Gannt chart is also provided to guide the construction with activities to finish each day.
75
Activity Duration Cost Weight in % A General Requirements 1 24,600.00 0.11 B Site Development Works under Demolition 4 13,200.00 3.13 C Earthworks 7 388,598.00 1.08 D Footing 5 134,079.01 0.27 E Concrete Columns 7 33,059.83 3.92 F Steel Columns 5 486,887.42 18.13 G Steel Beams 10 2,253,539.90 29.33 H Steel Purlins 3 3,645,600.00 26.84 I GI-Sheet 2 3,336,952.67 5.60 J Concrete Floor Slab 7 696,518.39 1.09 K Concrete Beams 7 135,442.48 0.39 L Walls 7 47,876.59 1.31 M Concrete Roof Slabs 7 162,968.13 0.60 N Doors and Windows 5 75,088.00 0.25 O Septic Vault 10 31,360.26 0.64 P Electrical Works 5 80,022.48 1.34 Q Plumbing and Sanitary Works 5 166,103.60 0.32 R Ceiling (Gypsum Board) 7 39,966.51 0.66 S Grates: Wall and Roof 7 82,566.66 0.34 T Gates 5 42,057.66 1.70 U Finishing, Plastering and Tiling Works 7 210,982.01 1.50 V Painting Works 14 186,505.18 1.26 W Site Development Works under Landscaping 7 156,556.44
Contingency, 10% 1,243,053.12
VAT, 12% 1,640,854.12
TOTAL 15,314,438.45 100% Table 5.2Work Schedule A B C D E Duration =82 days Critical Path: A-B-C-D-E-F-G-H-I-O-R-S-V-W CONSTRUCTION PROJ ECT MANAGEMENT DIAGRAM SCALE N.D.T.S. F G H I J K L M N O P Q R S T U V W 1 4 7 5 7 5 10 3 2 7 7 7 7 5 10 5 5 7 7 5 7 14 7
GANTT CHART
Duration Cost Weight in % A General Requirements 1 24,600.00 0.20 B Site Devlopment Works under Demolition 4 13,200.00 0.11 C Earthworks 7 388,598.00 3.13 D Footing 5 134,079.01 1.08 E Concrete Columns 7 33,059.83 0.27 F Steel Columns 5 486,887.42 3.92 G Steel Beams 10 2,253,539.90 18.13 H Steel Purlins 3 3,645,600.00 29.33 I GI-Sheet 2 3,336,952.67 26.84 J Concrete Floor Slab 7 696,518.39 5.60 K Concrete Beams 7 135,442.48 1.09 L Walls 7 47,876.59 0.39 M Concrete Roof Slabs 7 162,968.13 1.31 N Doors and Windows 5 75,088.00 0.60 O Septic Vault 10 31,360.26 0.25 P Electrical Works 5 80,022.48 0.64 Q Plumbing and Sanitary Works 5 166,103.60 1.34 R Ceiling (Gypsum Board) 7 39,966.51 0.32 S Grates: Wall and Roof 7 82,566.66 0.66 T Gates 5 42,057.66 0.34 U Finishing, Plastering and Tiling Works 7 210,982.01 1.70 V Painting Works 14 186,505.18 1.50 W Site Development Works under Landscaping 7 156,556.44 1.26 TOTAL 100.00 Contingency, 10% %Complete VAT, 12%of Sumof Total Amount with Contingency %Cumulative Projected Cumulative Critical Path Non-Critical Path Float LEGEND Activity 1.20 56.15 19.57 7.91 4.66 3.86 1.20 96.24 94.87 11.66 3.25 0.80 2.66 3.41 33.57 36.58 1.96 1.38 1.74 0.90 0.90 93.12 89.72 99.10 98.20 100.00 148,828.00 216,636.69 423,494.01 4,172,581.92 4,547,015.96 1,449,501.43 403,678.44 111,826.03 480,029.61 11,575,640.11 11,152,146.09 12,207,365.77 11,963,411.75 11,792,276.80 99,338.74 331,201.61 983,046.78 579,368.34 111,339.40 243,954.02 171,134.95 Week 2 Week 1 Week 13 Week 12 Week 11 Week 10 Week 7 Week 6 Week 5 Week 4 Week 3 Week 9 Week 8 TOTAL VALUE PHP 15,314,438.45 PHP 12,430,531.21 PHP 1,243,053.12 PHP 1,640,854.12 12,430,531.21 12,318,705.18 148,828.00 6,979,564.17 2,432,548.21 ` Chapter VI
PROJECT IMPLEMENTATION
This chapter presents the project implementation and construction management
The project study will be presented to the Local Government Unit of Barbaza. Upon their approval, the LGU will loan from the Department of Finance in Manila. The LGU of Barbaza will then publish an invitation to bid at the website of Philippine Government Electronic Procurement System (PHILGEPS) for interested bidders. The project study shall undergo the bidding before it can be implemented. Proper supervision shall be implemented and supervised by the Municipal Engineering Office throughout the project. A representative of the Municipal Engineers Office may be assigned to monitor the contractor and the workers whether they comply with the conditions agreed on the contract.
CHAPTER VII
CONCLUSIONS AND RECOMMENDATIONS
A Proposed Integrated Transport Terminal for Barbaza, Antique will provide a common loading area of public vehicles for Barbaza and nearby towns. The terminal is able to provide loading spaces for the four different modes of public transportation available in Antique: bus, van, jeep, and tricycle. The project cost is within the budget recommended by the municipality. Statistically-analyzed results of the questionnaire survey shows the approval of both the drivers and passengers regarding the project. Opinion surveys of the residents and municipal officials also yielded positive responses. It is recommended that the transport terminal will be a priority project of Barbaza to avoid inflation of prices since the project is estimated using prices of commercially available materials on the year 2013. Traffic control devices like signs and markings are recommended for safety. It is recommended that an organizational chart should be provided for an orderly management. It is also recommended that a security personnel will be assigned at the terminal.
81
REFERENCES
Beral, E., Macavinta, N., Tumale, F.J. (2010). A Proposed Bus and Shuttle Vans Terminal in Dalipe, San Jose, Antique. Civil Engineering Department, College of Engineering, Central Philippine University, Iloilo, PH.
Escoderos, M.P., Gico, P.T., Nolido, A.R. (2011). A Proposed Constuction of Jeepney Transport Terminal in San Miguel, Iloilo. Civil Engineering Department, College of Engineering, Central Philippine University, Iloilo, PH.
Gallo, R., Mata, P., Tabera, G.I., Timbas, K.L. (2011). A Proposed Transport Terminal in the Municipality of Jordan, Guimaras. Civil Engineering Department, College of Engineering, Central Philippine University, Iloilo, PH.
Gillesania, D.I.T. (2006). Fundamentals of Structural Steel Design with Theory of Structures.
Gumapon, F. (2012). PPA bares major RO-RO routes. Philippine Information Agency. Retrieved on 03-26-2013. Available: [http://www.pia.gov.ph/news/index.php?article=1431337066034]
Litman, T.A. (2012). Evaluating Accessibility for Transportation Planning: Measuring Peoples Ability to Reach Desired Goods and Activities. Victoria Transport Policy Institute. Retrieved on 03-26-2013. Available: [http://www.vtpi.org/access.pdf]
82
Modak, S. K., Patkar, V.N. (1984). Transport Terminal Design and Passenger Orientation. Retrieved on 03-26-2013. Available: [www.tandfonline.com/doi/pdf/10.1080/03081068408717275]
Municipality of Barbaza, Antique (2012). Comprehensive Land Use Plan.
Official Antique Website (2012). Barbaza. Retrieved on 03-26-2013. Available: [http://www.antique.gov.ph/barbaza/]
Panay (2012). Discover the Wonders of Panay Island: Barbaza. Retrieved on 03-26-2013. Available: [http://www.panay.org/barbaza/]
Rodrigue, J. (1999). Globalization and the Synchronization of Transport Terminals. Hofstra University, Hempstead, New York, USA. Retrieved on 03-26-2013. Available: [http://people.hofstra.edu/jean paul_rodrigue/downloads/Synchronization.PDF]
Rodrigue, J., Slack, B. (2013). The Function of Transport Terminals. Department of Global Studies and Geography, Hofstra University, New York, USA. Retrieved on 03-26-2013. Available: [http://people.hofstra.edu/geotrans/eng/ch4en/conc4en/ch4c1en.html]
Stevens, A. (2012). Transport Terminals, Stations, Ports. University of New Brunswick, Canada. Retrieved on 03-26-2013. Available: [http://www.unb.ca/transpo/mynet/mty97.htm]
83
WikiPilipinas (2008). Roll-on/Roll-off. Retrieved on 03-26-2013. Available: [http://en.wikipilipinas.org/index.php?title=Roll-on/_Roll-off]
Yang, J. (2007). Processes for Evaluating the Optimum Inter-Modal Terminal Location. Queensland University of Technology. Retrieved on 03-26-2013. Available: [http://eprints.qut.edu.au/16474/1/Jianfeng_Yang_Thesis.pdf]
APPENDIX A: STRUCTURAL DESIGN AND ANALYSIS
85
I. WIND LOAD Computation of Wind Load
For Inclined Wide-Flange: Wind Load from NSCP 2010 Worig.wind 0.5 kPa Length of Wide Flange L 11.50 m Rise of Wide Flange H 1.9 m Slope = arctan(H/L) 9.39 deg Wind Load normal to Wide-Flange Wwind = Worig.wind*sin 81.51 N/m 2
For Curved Wide-Flange: Projected Horizontal Length of Wide-Flange L 9.60 m Rise of Wide Flange H 3.00 m Slope = arctan(H/L) 17.36 deg Wind Load normal to Wide-Flange Wwind = Worig.wind*sin 149.14 N/m 2
Arched beam 17.36 0 . 5
K P a ( v a l u e
b a s e d
f r o m
N S C P
2 0 1 0 ) Midpoint of beam
86
Arched beam Midpoint of beam 0 .1 4 9 K P a o r 1 4 9 .1 4 N /s q .m 17.36
8.43 0 . 5
K P a ( v a l u e
b a s e d
f r o m
N S C P
2 0 1 0 ) Inclined beam
8.43 0.082 KPa or 81.51 N/sq.m Inclined beam
87
II. DESIGN OF PURLINS Design of Purlins over Arched Wide-Flange Beam
Basic Requirements: Yield Strength of Steel Fy 275.00 MPa Length of Purlin L 10.00 m Roof Live Load RLL 450.00 N/m Wind Load Wwind 149.14 N/m 2
Inclination 17.36 deg Assumed spacing s 0.60 m Roofing GI Sheet 80.00 Pa Uniform Roofing Load Roofing 48.00 N/m
Selection of any Section: Chosen section C8x13.75 Weight of Section Wsection 20.50 kg/m Section Modulus at X-axis Sx 147,890.00 mm 3
Section Modulus at Y-axis Sy 14,020.00 mm 3
Weight of Purlin Wpurlin in N/m 201.11 N/m
Computation of Loads: Total Dead Load Tdl = Wpurlin + Roofing 249.11 N/m Total Gravity Load TGL = Tdl + RLL 699.11 N/m Total Tangential Load TTL = TGLsin 208.49 N/m Total Normal Load TNL = TGLcos + Wwind(s) 756.74 N/m
Computation of Interaction Value: Moment with respect to X-axis Mx = wL 2 /8 = TNL(L 2 )/12 6,306.19 N-m Moment with respect to Y-axis My = TTL(L 2 )/12 1,737.44 N-m Actual Flexure at X-axis fbx = Mx/Sx 42.64 MPa Actual Flexure at Y-axis fby = My/Sy 123.93 MPa NSCP Limits of Flexure at X-axis Fbx = 0.66Fy 181.50 MPa NSCP Limits of Flexure at Y-axis Fby = 0.75Fy 206.25 MPa Interaction value (fbx/Fbx) + (fby/Fby) 0.84 Since interaction value is less than 1, the chosen section is allowed to be used. 88
Design of Purlins over Inclined Wide-Flange
Basic Requirements: Yield Strength of Steel Fy 275.00 MPa Length of Purlin L 10.00 m Roof Live Load RLL 450.00 N/m Wind Load Wwind 81.51 N/m 2
Inclination 9.39 deg Assumed spacing s 0.60 m Roofing GI Sheet 80.00 Pa Uniform Roofing Load Wroofing = GI Sheet*s 48.00 N/m
Selection of any Section: Chosen section C8x13.75 Weight of Section Wsection 20.50 kg/m Section Modulus at X-axis Sx 147,890.00 mm 3
Section Modulus at Y-axis Sy 14,020.00 mm 3
Weight of Purlin Wpurlin in N/m 201.11 N/m
Computation of Loads: Total Dead Load Tdl = Wpurlin + Roofing 249.11 N/m Total Gravity Load TGL = Tdl + RLL 699.11 N/m Total Tangential Load TTL = TGLsin 114.00 N/m Total Normal Load TNL = TGLcos + Wwind(s) 738.64 N/m
Computation of Interaction Value: Moment with respect to X-axis Mx = wL 2 /12 = TNL(L 2 )/12 6,155.35 N-m Moment with respect to Y-axis My = TTL(L 2 )/12 950.04 N-m Actual Flexure at X-axis fbx = Mx/Sx 41.62 MPa Actual Flexure at Y-axis fby = My/Sy 67.76 MPa NSCP Limits of Flexure at X-axis Fbx = 0.66Fy 181.50 MPa NSCP Limits of Flexure at Y-axis Fby = 0.75Fy 206.25 MPa Interaction value (fbx/Fbx) + (fby/Fby) 0.56 Since interaction value is less than 1, the chosen section is allowed to be used.
89
III. DESIGN OF ROOF SLABS One-Way Slab Design (Waiting Area)
Material Properties: Concrete Compressive Strength F'c 28.00 MPa Yield Strength of Steel Fy 275.00 MPa Weight of Concrete c 23.60 kN/m 3
Slab Description: Simple Span L 3300.00 mm Service Dead Load DL 0.31 kPa Service Live Load LL 1.00 kPa
Estimated Slab Size: Estimated Slab Height h = L/20 165.00 mm Assumed Concrete Cover c 25.00 mm Effective Depth d = h - c 140.00 mm Base of Slab b 1000.00 mm Estimated Slab Weight Pslab 3.89 kPa
Load Computations: Total Dead Load, DLtotal = DL + Pslab 13.16 kN/m Total Live Load LLtotal 1.00 kN/m Total Factored Load Wu = 1.2DLtotal + 1.6LLtotal 17.39 kN/m Max Ultimate/Design Moment Mu 23.67 kN-m Coefficient of Resistance Rn = Mu / bd 2 ; = 0.9 1.34 MPa Required Steel Ratio, = (0.85F'c / Fy) * {1-sqrt[1 - (2Rn / 0.85F'c)]} 0.00503
Minimum Steel Ratio, min1 pmin2 min1 = sqrt(F'c) / 4Fy 0.00481 min2 = 1.4 / Fy 0.00509 Maximum Steel Ratio, max max = (0.85F'c / Fy) * [0.003 / (0.003 + bal)]; bal = 0.005 0.02759
Factor defined in NSCP 2010 Section 5.10.2.7.3 = 0.85 if 17MPa < F'c < 28MPa; = 0.85 - (0.05/7)(F'c - 28) if F'c > 28MPa
Adopted Steel Ratio adopt 0.00503 90
One-Way Slab Design (Waiting Area) - continuation
Computation of Amount of Main Rebars and its Spacing: Amount of Steel Required As = bd 703.60 mm 2
Main Reinforcing Steel Diameter db 12.00 mm Area of Bars Total Ab 113.10 mm 2
Number of Bars Required n 6.22 Computed spacing s
150.0 mm Maximum Spacing 1 smax1 = 3h or 450mm 495.00 mm Maximum Spacing 2 smax2 450.00 mm Adopted Spacing sadopted 150.00 mm
Computation of Amount of Shrinkage and Temperature Rebars and its Spacing: for fy > 415, = (0.0018*415)/fy adopted for S&T 0.00272 for fy = 415, = 0.0018 for fy = 280 and fy = 530, = 0.002
minimum from NSCP 0.00140 Area of S&T Bars AS&T = bh 448.20 mm 2
Diamater of S&T Bars dS&T 10.00 mm Area of Bars Ab S&T 78.54 mm 2
Number of Bars n 6.00 pc Spacing s 166.67 mm Maximum Spacing smax = 5h 825.00 mm Adopted spacing sadopted 150.00 mm
91
Two-Way Slab Design (Office)
Material Properties: Concrete Compressive strength, F'c 28.00 MPa Yield strength of steel, Fy 275.00 MPa Weight of Concrete 23.60 KN/m 3
Diameter of RSB 12.00 mm
Longer Beam Description: Length of Beam, Llong 3400.00 mm Height of Beam, hlong (L/10 of the beam length) 340.00 mm Concrete Cover 75.00 mm Effective Depth, dlong 265.00 mm Beam Width, blong 200 mm
Shorter Beam Description: Length of Beam, Lshort 3300.00 mm Height of Beam, hshort (L/10 of the beam length) 330.00 mm Concrete Cover 75.00 mm Effective Depth, dshort 255.00 mm Beam Width, bshort 175.00 mm
Computation of Slab Thickness: Clear Span in the Long Direction, Ln 3225.00 mm Clear Span Ratio of Long to Short Direction, 1.04032 Assumed Thickness of the Slab, hassume
71.15 mm Assumed Thickness of the Slab, hassume
75.00 mm
Solving for m: Moment of Inertia of Longer Beam, Ilong
655.1E+6 mm 4 Moment of Inertia of Shorter Beam, Ishort 524.1E+6 mm 4
92
Two-Way Slab Design (Office) - continued
For Shorter Beam (Interior), 1
4.38447 For Longer Beam (Interior), 2
5.64637 For Longer Beam (Edge), 3
11.29273 For Interior Slabs, m
6.42701
Estimated Slab Size: Thickness of the Slab, hslab
47.32 mm Minimum Thickness of Slab, hmin = hassume 71.15 mm Maximum Thickness of Slab, hmax
89.65 mm Adopted Slab Thickness, (but should not be less than 125mm) 75.00 mm Adopted Slab Thickness, hadopt 125.00 mm Concrete Cover 20.00 mm Effective Depth, dslab 100.00 mm
Computation of Loads: Dead Load, DL 0.31 kPa Live Load, LL 1.00 kPa Weight of Slab 1.77 kPa Total Dead Load, WDL = DL + Slab Wt 2.08 kPa Total Live Load, WLL 1.00 kPa Total Ultimate/Factored Load, WU = 1.2WDL + 1.6WLL 4.09 kPa
93
Two-Way Slab Design (Office) continued
Movement along the Long Span (Interior): Ln 3225.00 mm L2 3300.00 mm Moment, Mo
17.56 kN-m Negative Factored Moment, Mo(-) = -0.65Mo -11.42 kN-m Positive Factored Moment, Mo(+) = 0.35Mo 6.15 kN-m L2/L1 0.97 1 ( in the direction of L1) 5.64637 1 (L2/L1) 5.48
% Of Interior (-) Moment To Be Resisted By Column Strips: 75.88 % (-) Interior Moment to be Resisted by the Column Strip -8.66 kN-m (-) Moment to be Resisted by the Beam (85% of Column Strip) -7.36 kN-m (-) Moment to be Resisted by the Slab (15% of Column Strip) -1.30 kN-m (-) Moment to be Resisted by the Middle Strip (Mo - Column Strip) -2.75 kN-m
% Of Interior (+) Moment To Be Resisted By Column Strips: 75.88 % (+) Interior Moment to be Resisted by the Column Strip 4.66 kN-m (+) Moment to be Resisted by the Beam 3.96 kN-m (+) Moment to be Resisted by the Slab 0.70 kN-m (+) Moment to be Resisted by the Middle Strip 1.48 kN-m
Movement along the Long Span (Edge): Ln 3225.00 mm L2 1750.00 mm Moment, Mo
9.31 kN-m Negative Factored Moment, Mo(-) = -0.65Mo -6.05 kN-m Positive Factored Moment, Mo(+) = 0.35Mo 3.26 kN-m L2/L1 0.97 3 ( in the direction of L1) 11.29273 3 (L2/L1) 10.96
94
Two-Way Slab Design (Office) - continued
% Of Exterior (-) Moment To Be Resisted By Column Strips: 75.88 % (-) Exterior Moment to be Resisted by the Column Strip -4.59 kN-m (-) Moment to be Resisted by the Beam -3.90 kN-m (-) Moment to be Resisted by the Slab -0.69 kN-m (-) Moment to be Resisted by the Middle Strip -1.46 kN-m
% Of Exterior (+) Moment To Be Resisted By Column Strips: 75.88 % (+) Interior Moment to be Resisted by the Column Strip 2.47 kN-m (+) Moment to be Resisted by the Beam 2.10 kN-m (+) Moment to be Resisted by the Slab 0.37 kN-m (+) Moment to be Resisted by the Middle Strip 0.79 kN-m
570.7E+6
mm 4
75.88
Movement along the Shorter Span (Interior): Ln 3100.00 mm L2 3400.00 mm Moment, Mo
% Of Interior (-) Moment To Be Resisted By Column Strips: 70.89 % (-) Interior Moment to be Resisted by the Column Strip -8.30 kN-m (-) Moment to be Resisted by the Beam -7.05 kN-m (-) Moment to be Resisted by the Slab -1.24 kN-m (-) Moment to be Resisted by the Middle Strip -3.41 kN-m
95
Two-Way Slab Design (Office) - continued
% Of Interior (+) Moment To Be Resisted By Column Strips: 123.65 % (+) Interior Moment to be Resisted by the Column Strip 11.78 kN-m (+) Moment to be Resisted by the Beam 10.02 kN-m (+) Moment to be Resisted by the Slab 1.77 kN-m (+) Moment to be Resisted by the Middle Strip -2.25 kN-m
392.6E+6 mm 4
1.69190
% Of Exterior (-) Moment To Be Resisted By Column Strips: 80.30 % (-) Exterior Moment to be Resisted by the Column Strip -2.15 kN-m (-) Moment to be Resisted by the Beam -1.83 kN-m (-) Moment to be Resisted by the Slab -0.32 kN-m (-) Moment to be Resisted by the Middle Strip -0.53 kN-m
96
Two-Way Slab Design (Comfort Rooms)
Material Properties: Concrete Compressive strength, f'c 28.00 MPa Yield strength of steel, fy 275.00 MPa Weight of Concrete 23.60 KN/m 3 Diameter of RSB 12.00 mm
Longer Beam Description: Length of Beam, Llong 3300.00 mm Height of Beam, hlong (L/10 of the beam length) 330.00 mm Concrete Cover 75.00 mm Effective Depth, dlong 255.00 mm Beam Width, blong 175.00 mm
Shorter Beam Description: Length of Beam, Lshort 3000.00 mm Height of Beam, hshort (L/10 of the beam length) 300.00 mm Concrete Cover 75.00 mm Effective Depth, dshort 225.00 mm Beam Width, bshort 150.00 mm
MINIMUM SLAB THICKNESS Clear Span in the Long Direction, Ln 3150.00 mm Clear Span Ratio of Long to Short Direction, 1.11504 Assumed Thickness of the Slab, hassume
68.48 mm Assumed Thickness of the Slab, hassume 75.00 mm
SOLVING FOR m Moment of Inertia of Longer Beam, Ilong
524.1E+6 mm 4
Moment of Inertia of Shorter Beam, Ishort
337.5E+6 mm 4
97
Two-Way Slab Design (Comfort Rooms) - continued
For Shorter Beam (Interior), 1
2.90909 For Longer Beam (Interior), 2
4.96907 For Longer Beam (Edge), 3
9.93813 For Interior Slabs, m
5.18135
ESTIMATED SLAB SIZE Thickness of the Slab, hslab 49.55 mm Minimum Thickness of Slab, hmin = hassume 68.48 mm Maximum Thickness of Slab, hmax 87.57 mm Adopted Slab Thickness, (but should not be less than 125mm) 75.00 mm Adopted Slab Thickness, hadopt 125.00 mm Concrete Cover 20.00 mm Effective Depth, dslab 100.00 mm
LOAD COMPUTATIONS Dead Load, DL 0.31 kPa Live Load, LL 1.00 kPa Weight of Slab 1.77 kPa Total Dead Load, WDL = DL + Slab Wt 2.08 kPa Total Live Load, WLL 1.00 kPa Total Ultimate/Factored Load, WU = 1.2WDL + 1.6WLL 4.09 kPa
98
Two-Way Slab Design (Comfort Rooms) - continued
MOMENT ALONG THE LONG SPAN (INTERIOR) Ln 3150.00 mm L2 3000.00 mm Moment, Mo
15.23 kN-m Negative Factored Moment, Mo(-) = -0.65Mo -9.90 kN-m Positive Factored Moment, Mo(+) = 0.35Mo 5.33 kN-m L2/L1 0.91 1 ( in the direction of L1) 4.96907 1 (L2/L1) 4.52
% OF INTERIOR (-) MOMENT TO BE RESISTED BY COLUMN STRIPS 77.73 % (-) Interior Moment to be Resisted by the Column Strip -7.70 kN-m (-) Moment to be Resisted by the Beam (85% of Column Strip) -6.54 kN-m (-) Moment to be Resisted by the Slab (15% of Column Strip) -1.15 kN-m (-) Moment to be Resisted by the Middle Strip (Mo - Column Strip) -2.21 kN-m
% OF INTERIOR (+) MOMENT TO BE RESISTED BY COLUMN STRIPS 77.73 % (+) Interior Moment to be Resisted by the Column Strip 4.14 kN-m (+) Moment to be Resisted by the Beam 3.52 kN-m (+) Moment to be Resisted by the Slab 0.62 kN-m (+) Moment to be Resisted by the Middle Strip 1.19 kN-m
MOMENT ALONG THE LONG SPAN (EDGE) Ln 3150.00 mm L2 1587.50 mm Moment, Mo
8.06
kN-m Negative Factored Moment, Mo(-) = -0.65Mo -5.24 kN-m Positive Factored Moment, Mo(+) = 0.35Mo 2.82 kN-m L2/L1 0.91 3 ( in the direction of L1) 9.93813 3 (L2/L1) 9.03
99
Two-Way Slab Design (Comfort Rooms) - continued
% OF EXTERIOR (-) MOMENT TO BE RESISTED BY COLUMN STRIPS 77.73 % (-) Exterior Moment to be Resisted by the Column Strip -4.07 kN-m (-) Moment to be Resisted by the Beam -3.46 kN-m (-) Moment to be Resisted by the Slab -0.61 kN-m (-) Moment to be Resisted by the Middle Strip -1.17 kN-m
% OF INTERIOR (+) MOMENT TO BE RESISTED BY COLUMN STRIPS 77.73 % (+) Interior Moment to be Resisted by the Column Strip 2.19 kN-m (+) Moment to be Resisted by the Beam 1.86 kN-m (+) Moment to be Resisted by the Slab 0.33 kN-m (+) Moment to be Resisted by the Middle Strip 0.63 kN-m
392.6E+6 mm 4
3.38380
MOMENT ALONG THE SHORT SPAN (INTERIOR) Ln 2825.00 mm L2 3300.00 mm Moment, Mo
% OF INTERIOR (-) MOMENT TO BE RESISTED 72.00 % (-) Interior Moment to be Resisted by the Column Strip -6.79 kN-m (-) Moment to be Resisted by the Beam -5.77 kN-m
100
Two-Way Slab Design (Comfort Rooms) - continued
(-) Moment to be Resisted by the Slab -1.02 kN-m (-) Moment to be Resisted by the Middle Strip -2.64 kN-m
% OF INTERIOR (+) MOMENT TO BE RESISTED 72.00 % (+) Interior Moment to be Resisted by the Column Strip 5.53 kN-m (+) Moment to be Resisted by the Beam 4.70 kN-m (+) Moment to be Resisted by the Slab 0.83 kN-m (+) Moment to be Resisted by the Middle Strip 2.15 kN-m 231.2E+6 mm 4
1.09600
% OF EXTERIOR (-) MOMENT TO BE RESISTED BY COLUMN STRIPS 87.72 % (-) Exterior Moment to be Resisted by the Column Strip -1.89 kN-m (-) Moment to be Resisted by the Beam -1.61 kN-m (-) Moment to be Resisted by the Slab -0.28 kN-m (-) Moment to be Resisted by the Middle Strip -0.26 kN-m
101
Two-Way Slab Design (Storage Room)
MATERIAL PROPERTIES Concrete Compressive strength, f'c 28.00 MPa Yield strength of steel, fy 275.00 MPa Weight of Concrete 23.60
KN/m 3 Diameter of RSB 12.00 mm LONGER BEAM DESCRIPTION Length of Beam, Llong 3300.00 mm Height of Beam, hlong (L/10 of the beam length) 330.00 mm Concrete Cover 75.00 mm Effective Depth, dlong 255.00 mm Beam Width, blong 175.00 mm SHORTER BEAM DESCRIPTION Length of Beam, Lshort 2500.00 mm Height of Beam, hshort (L/10 of the beam length) 250.00 mm Concrete Cover 75.00 mm Effective Depth, dshort 175.00 mm Beam Width, bshort 125.00 mm
MINIMUM SLAB THICKNESS Clear Span in the Long Direction, Ln 3175.00 mm Clear Span Ratio of Long to Short Direction, 1.36559 Assumed Thickness of the Slab, hassume 65.80 mm Assumed Thickness of the Slab, hassume 75.00 mm
SOLVING FOR m Moment of Inertia of Longer Beam, Ilong
524.1E+6
mm 4 Moment of Inertia of Shorter Beam, Ishort
162.8E+6
mm 4
For Shorter Beam (Interior), 1
1.40292
102
Two-Way Slab Design (Storage Room) - continued
For Longer Beam (Interior), 2
5.96288 For Interior Slabs, m
3.68290
ESTIMATED SLAB SIZE Thickness of the Slab, hslab
53.20 mm Minimum Thickness of Slab, hmin = hassume 65.80 mm Maximum Thickness of Slab, hmax
88.26 mm Adopted Slab Thickness, (but should not be less than 125mm) 75.00 mm Adopted Slab Thickness, hadopt 125.00 mm Concrete Cover 20.00 mm Effective Depth, dslab 100.00 mm
LOAD COMPUTATIONS Dead Load, DL 0.31 kPa Live Load, LL 1.00 kPa Weight of Slab 1.77 kPa Total Dead Load, WDL = DL + Slab Wt 2.08 kPa Total Live Load, WLL 1.00 kPa Total Ultimate/Factored Load, WU = 1.2WDL + 1.6WLL 4.09 kPa
MOMENT ALONG THE SHORT SPAN (INTERIOR) Ln 2325.00 mm L2 3300.00 mm Moment, Mo
9.13 kN-m
103
Two-Way Slab Design (Storage Room) - continued
Negative Factored Moment, Mo(-) = -0.65Mo -5.93 kN-m Positive Factored Moment, Mo(+) = 0.35Mo 3.19 kN-m L2/L1 1.32 1 ( in the direction of L1) 1.40292 1 (L2/L1) 1.85
% OF INTERIOR (-) MOMENT TO BE RESISTED BY COLUMN STRIPS 65.40 % (-) Interior Moment to be Resisted by the Column Strip -3.88 kN-m (-) Moment to be Resisted by the Beam (85% of Column Strip) -3.30 kN-m (-) Moment to be Resisted by the Slab (15% of Column Strip) -0.58 kN-m (-) Moment to be Resisted by the Middle Strip (Mo - Column Strip) -2.05 kN-m
% OF INTERIOR (+) MOMENT TO BE RESISTED BY COLUMN STRIPS 65.40 % (+) Interior Moment to be Resisted by the Column Strip 2.09 kN-m (+) Moment to be Resisted by the Beam 1.78 kN-m (+) Moment to be Resisted by the Slab 0.31 kN-m (+) Moment to be Resisted by the Middle Strip 1.11 kN-m
MOMENT ALONG THE LONG SPAN (INTERIOR) Ln 3175.00 mm L2 2500.00 mm Moment, Mo
12.90 kN-m Interior Negative Factored Moment, Mo(-) = 0.65Mo -8.38 kN-m Positive Factored Moment, Mo(+) = 0.35Mo 4.51 kN-m L2/L1 0.76 2 ( in the direction of L1) 5.96288 2 (L2/L1) 4.52
% OF INTERIOR (-) MOMENT TO BE RESISTED BY COLUMN STRIPS 82.27 % (-) Interior Moment to be Resisted by the Column Strip -6.90 kN-m (-) Moment to be Resisted by the Beam -5.86 kN-m
104
Two-Way Slab Design (Storage Room) - continued
(-) Moment to be Resisted by the Slab -1.03 kN-m (-) Moment to be Resisted by the Middle Strip -1.49 kN-m
% OF INTERIOR (+) MOMENT TO BE RESISTED BY COLUMN STRIPS 82.27 % (+) Interior Moment to be Resisted by the Column Strip 3.71 kN-m (+) Moment to be Resisted by the Beam 3.16 kN-m (+) Moment to be Resisted by the Slab 0.56 kN-m (+) Moment to be Resisted by the Middle Strip 0.80 kN-m 105
Two-Way Slab Design (Guardhouse)
MATERIAL PROPERTIES Concrete Compressive strength, f'c 28.00 MPa Yield strength of steel, fy 275.00 MPa Weight of Concrete 23.60 KN/m 3 Diameter of RSB 12.00 mm
LONGER BEAM DESCRIPTION Length of Beam, Llong 3600.00 mm Height of Beam, hlong (L/10 of the beam length) 360.00 mm Concrete Cover 75.00 mm Effective Depth, dlong 286.00 mm Beam Width, blong 200.00 mm SHORTER BEAM DESCRIPTION Length of Beam, Lshort 3000.00 mm Height of Beam, hshort (L/10 of the beam length) 300.00 mm Concrete Cover 75.00 mm Effective Depth, dshort 225.00 mm Beam Width, bshort 150.00 mm
MINIMUM SLAB THICKNESS Clear Span in the Long Direction, Ln 3460.00 mm Clear Span Ratio of Long to Short Direction, 1.23571 Assumed Thickness of the Slab, hassume
73.48 mm Assumed Thickness of the Slab, hassume 75.00 mm
SOLVING FOR m Moment of Inertia of Longer Beam, Ilong
784.1E+6 mm 4
337.5E+6 mm 4
106
Two-Way Slab Design (Guardhouse) continued
For Shorter Beam (Interior), 1
2.65928 For Longer Beam (Interior), 2
7.43441 For Interior Slabs, m
5.04685
ESTIMATED SLAB SIZE Thickness of the Slab, hslab
52.59 mm Minimum Thickness of Slab, hmin = hassume 73.48 mm Maximum Thickness of Slab, hmax
96.18 mm Adopted Slab Thickness, (but should not be less than 125mm) 75.00 mm Adopted Slab Thickness, hadopt 125.00 mm Concrete Cover 20.00 mm Effective Depth, dslab 100.00 mm
LOAD COMPUTATIONS Dead Load, DL 0.31 kPa Live Load, LL 1.00 kPa Weight of Slab 1.77 kPa Total Dead Load, WDL = DL + Slab Wt 2.08 kPa Total Live Load, WLL 1.00 kPa Total Ultimate/Factored Load, WU = 1.2WDL + 1.6WLL 4.09 kPa
MOMENT ALONG THE SHORT SPAN (INTERIOR) Ln 2800.00 mm L2 3610.00 mm
107
Two-Way Slab Design (Guardhouse) - continued
Moment, Mo
14.48 kN-m Negative Factored Moment, Mo(-) = -0.65Mo -9.41 kN-m Positive Factored Moment, Mo(+) = 0.35Mo 5.07 kN-m L2/L1 1.20 1 ( in the direction of L1) 2.65928 1 (L2/L1) 3.20
% OF INTERIOR (-) MOMENT TO BE RESISTED BY COLUMN STRIPS 68.90 % (-) Interior Moment to be Resisted by the Column Strip -6.49 kN-m (-) Moment to be Resisted by the Beam (85% of Column Strip) -5.51 kN-m (-) Moment to be Resisted by the Slab (15% of Column Strip) -0.97 kN-m (-) Moment to be Resisted by the Middle Strip (Mo - Column Strip) -2.93 kN-m
% OF INTERIOR (+) MOMENT TO BE RESISTED BY COLUMN STRIPS 68.90 % (+) Interior Moment to be Resisted by the Column Strip 3.49 kN-m (+) Moment to be Resisted by the Beam 2.97 kN-m (+) Moment to be Resisted by the Slab 0.52 kN-m (+) Moment to be Resisted by the Middle Strip 1.58 kN-m
MOMENT ALONG THE LONG SPAN (INTERIOR) Ln 3460.00 mm L2 3000.00 mm Moment, Mo
18.38 kN-m Interior Negative Factored Moment, Mo(-) = 0.65Mo -11.95 kN-m Positive Factored Moment, Mo(+) = 0.35Mo 6.43 kN-m L2/L1 0.83 2 ( in the direction of L1) 7.43441 2 (L2/L1) 6.18
108
Two-Way Slab Design (Guardhouse) - continued
% OF INTERIOR (-) MOMENT TO BE RESISTED BY COLUMN STRIPS 80.07 % (-) Interior Moment to be Resisted by the Column Strip -9.56 kN-m (-) Moment to be Resisted by the Beam -8.13 kN-m (-) Moment to be Resisted by the Slab -1.43 kN-m (-) Moment to be Resisted by the Middle Strip -2.38 kN-m % OF INTERIOR (+) MOMENT TO BE RESISTED BY COLUMN STRIPS 80.07 % (+) Interior Moment to be Resisted by the Column Strip 5.15 kN-m (+) Moment to be Resisted by the Beam 4.38 kN-m (+) Moment to be Resisted by the Slab 0.77 kN-m (+) Moment to be Resisted by the Middle Strip 1.28 kN-m
109
IV. DESIGN OF BEAMS Design of B1 (Beam over Waiting Area)
Properties of Materials: Concrete Compressive Strength F'c 28.00 MPa Yield Strength of Steel Fy 275.00 MPa Weight of Concrete c 23.50 kN/m 3
Beam Description: Simple Span L 3.30 m Service Dead Load including Slab DL 4.19 kPa Service Live Load LL 1.00 kPa Tributary width of Span TW 3.75 m
Estimated Beam Size: Estimated beam height h (1/10 of span) 330.00 mm Concrete cover c 75.00 mm Effective depth d = h - c 255.00 mm Estimated beam width b = 1/2 d 150.00 mm
Load Computations: Estimated beam weight (to be added to DL) Wbeam=Wc*Areabeam 1.16 kN/m Total Dead Load Wdl = DL + beam wt 16.86 kN/m Total Live Load Wll 3.75 kN/m Total factored load Wu = 1.2Wdl + 1.6Wll 26.23 kN/m Max ultimate/design moment Mu 23.80 kN-m
Computation of Steel Ratio: Coefficient of Resistance Rn = Mu/bd 2 2.71 Required Steel Ratio required = (0.85F'c/Fy){1- sqrt[1-2Rn/(0.85F'c)]} 0.01049735
Computation of Amount of Steel: Required Steel amount As = bd 401.52 mm 2
Main Reinforcing Steel Diameter db 16.00 mm Area of Bars Total Ab 201.06 mm 2
110
Design of B1 (Beam over Waiting Area) - continued
Number of Bars required n 2.00 To be used Number of Bars (rounded off) nf 2.00 Amount of Steel Supplied As = nAb 402.12 mm 2
supplied sup = As/bd 0.01
Checking Steel Ratio: Minimum min = sqrt(Fy) / (4Fy) 0.0048 NSCP limit of min min = 1.4 / Fy 0.0051 maximum where bal = 0.005 max = (0.85f'c/Fy) x [0.003/(0.003+bal)] 0.0276 if F'c 28MPa, = 0.85 0.8500 if F'c > 28MPa, = 0.85 - 0.008(F'c - 28) 0.65
0.8500
min 0.0048 sup 0.0105 max 0.0276 min max
111
Design of B4 (Shorter Beam over Office)
Properties of Materials: Concrete Compressive Strength F'c 28.00 MPa Yield Strength of Steel Fy 275.00 MPa Weight of Concrete c 23.50 kN/m 3
Beam Description: Simple Span L 3.30 m Service Dead Load with Slab DL 4.19 kPa Service Live Load LL 1.00 kPa Tributary width of Span TW 3.75 m Slab height SH 75.00 mm
Estimated Beam Size (use 330x150 dimension to conform with beam supporting one-way slab): Assumed height h 330.00 mm Assumed concrete cover c 75.00 mm Effective depth d 255.00 mm Assumed beam width b 150.00 mm
Load Computations: Estimated Beam Weight (to be added to DL) Wbeam=Wc*Areabeam 1.16 kN/m Superimposed Dead Load (Service Load) DL 4.19 kPa Subtotal Factored Load w/o Beam weight
Ts=1.2(Wslab+DL)+1.6(LL) 6.62 kPa Uniform load on short span Ws = Wu(s)/3 7.29 kN/m Total Load including beam wt Wdl = Ts + beam wt; Ts is multiplied by 2 when same beam is lying on the other side. 15.97 kN/m Max ultimate/design moment Mu 14.49 kN-m
Computation of Steel Ratio: Coefficient of Resistance, Rn where = 0.9 Rn = Mu/bd 2
1.65 112
Design of B4 (Shorter Beam over Office) - continued
Required Steel Ratio required = (0.85F'c/Fy){1- sqrt[1-2Rn/(0.85F'c)]} 0.00623
Computation of Amount of Steel: Required Steel amount As = bd 238.16 mm 2
Main Reinforcing Steel Diameter db 16.00 mm Area of Bars Total Ab 201.06 mm 2
Number of Bars required n 1.18 To be used Number of Bars (rounded off) nf 2.00 Amount of Steel Supplied As = nAb 402.12 mm 2
supplied sup = As/bd 0.01051
Checking Steel Ratio: Minimum min = sqrt(Fy) / (4Fy) 0.00481 NSCP limit of min min = 1.4 / Fy 0.00509 maximum where bal = 0.005 max = (0.85f'c/Fy) x [0.003/(0.003+bal)] 0.02759 if f'c 28MPa, = 0.85 0.85 if f'c > 28MPa, = 0.85 - 0.008(f'c - 28) 0.65
0.85
min 0.00509 sup 0.01051 max 0.02759 min max
113
Design of B5 (Longer Beam over Office)
Properties of Materials: Concrete Compressive Strength F'c 28.00 MPa Yield Strength of Steel Fy 275.00 MPa Weight of Concrete c 23.50 kN/m 3
Beam Description: Simple Span L 3.6 m Service Dead Load with Slab DL 4.19 kPa Service Live Load LL 1.00 kPa Tributary width of Span TW 3.75 m Slab height SH 75.00 mm
Estimated Beam Size (use 330x150 dimension to conform with beam supporting one-way slab): Assumed height h 330.00 mm Assumed concrete cover c 75.00 mm Effective depth d 255.00 mm Assumed beam width b 150.00 mm
Load Computations: Estimated Beam Weight (to be added to DL) Wbeam=Wc*Areabeam 1.16 kN/m Superimposed Dead Load (Service Load) DL 4.19 kPa Subtotal Factored Load w/o Beam weight Ts=1.2(Wslab+DL)+1.6(LL) 6.62 kPa Uniform load on short span Ws = Wu(s)/3 7.35 kN/m Total Load including beam wt Wdl = Ts + beam wt; Ts is multiplied by 2 when same beam is lying on the other side. 16.10 kN/m Max ultimate/design moment Mu 14.88 kN-m
Computation of Steel Ratio: Coefficient of Resistance, Rn where = 0.9 Rn = Mu/bd 2 1.69 114
Design of B5 (Longer Beam over Office) - continued
Required Steel Ratio required = (0.85F'c/Fy){1- sqrt[1-2Rn/(0.85F'c)]} 0.00640
Computation of Amount of Steel: Required Steel amount As = bd 244.77 mm 2
Main Reinforcing Steel Diameter db 16.00 mm Area of Bars Total Ab 201.06 mm 2
Number of Bars required n 1.22 To be used Number of Bars (rounded off) nf 2.00 Amount of Steel Supplied As = nAb 402.12 mm 2
supplied sup = As/bd 0.01051
Checking Steel Ratio: Minimum min = sqrt(Fy) / (4Fy) 0.00481 NSCP limit of min min = 1.4 / Fy 0.00509 maximum where bal = 0.005 max = (0.85f'c/Fy) x [0.003/(0.003+bal)] 0.02759 if f'c 28MPa, = 0.85 0.85 if f'c > 28MPa, = 0.85 - 0.008(f'c - 28) 0.65
0.85
min 0.00509 sup 0.01051 max 0.02759 min max
115
Design of B3 (Shorter Beam over CR)
Properties of Materials: Concrete Compressive Strength F'c 28.00 MPa Yield Strength of Steel Fy 275.00 MPa Weight of Concrete c 23.50 kN/m 3
Beam Description: Simple Span L 3.00 m Perpendicular short span L 3.30 m Service Dead Load including Slab DL 4.19 kPa Service Live Load LL 1.00 kPa Slab height SH 75.00 mm Tributary width of Span TW 3.50 m
Estimated Beam Size (use 330x150 dimension to conform with beam supporting one-way slab): Assumed height H 330.00 mm Assumed concrete cover C 75.00 mm Effective depth d = h c 255.00 mm Assumed beam width B 150.00 mm
Load Computations: Estimated Beam Weight (to be added to DL) Wbeam=Wc*Areabeam 1.16 kN/m Superimposed Dead Load (Service Load) DL 4.19 kPa Subtotal Factored Load w/o Beam weight Ts=1.2(DL)+1.6(LL) 6.62 kPa Uniform load on short span Ws = Wu(s)/3 1.79 kN/m Total Load including beam wt Wdl = Ts + beam wt; Ts is multiplied by 2 when same beam is lying on the other side. 3.19 kN/m Max ultimate/design moment Mu 2.39 kN-m
Computation of Steel Ratio: Coefficient of Resistance, Rn where Rn = Mu/bd 2 0.27 116
Computation of Amount of Steel: Required Steel amount As = bd 38.08 mm 2
Main Reinforcing Steel Diameter db 16.00 mm Area of Bars Total Ab 201.06 mm 2
Number of Bars required N 0.19 To be used Number of Bars (rounded off) nf 1.00 Amount of Steel Supplied As = nAb 201.06 mm 2
supplied sup = As/bd 0.00526
Checking Steel Ratio: Minimum min = sqrt(Fy) / (4Fy) 0.00481 NSCP limit of min min = 1.4 / Fy 0.00509 maximum where bal = 0.005 max = (0.85f'c/Fy) x [0.003/(0.003+bal)] 0.02759 if f'c 28MPa, = 0.85 0.85 if f'c > 28MPa, = 0.85 - 0.008(f'c - 28) 0.65
0.85
min 0.00481 sup 0.00526 max 0.02759 min max
117
Design of B2 (Longer Beam over Storage Room)
Properties of Materials: Concrete Compressive Strength F'c 28.00 MPa Yield Strength of Steel Fy 275.00 MPa Weight of Concrete c 23.50 kN/m 3
Beam Description: Simple Span L 3.30 m Perpendicular short span L 3.30 m Service Dead Load including Slab DL 4.19 kPa Service Live Load LL 1.00 kPa Slab height SH 75.00 mm Tributary width of Span TW 3.50 m
Estimated Beam Size (use 330x150 dimension to conform with beam supporting one-way slab): Assumed height h 330.00 mm Assumed concrete cover c 75.00 mm Effective depth d = h - c 255.00 mm Assumed beam width b 150.00 mm
Load Computations: Estimated Beam Weight (to be added to DL) Wbeam=Wc*Areabeam 1.16 kN/m Superimposed Dead Load (Service Load) DL 4.19 kPa Subtotal Factored Load w/o Beam weight Ts=1.2(DL)+1.6(LL) 6.62 kPa Uniform load on short span Ws = Wu(s)/3 2.00 kN/m Total Load including beam wt Wdl = Ts + beam wt; Ts is multiplied by 2 when same beam is lying on the other side. 3.40 kN/m Max ultimate/design moment Mu 3.08 kN-m
Computation of Steel Ratio: Coefficient of Resistance, Rn Rn = Mu/bd 2 0.35 118
Design of B2 (Longer Beam over Storage Room) - continued
Computation of Amount of Steel: Required Steel amount As = bd 49.20 mm 2
Main Reinforcing Steel Diameter db 16.00 mm Area of Bars Total Ab 201.06 mm 2
Number of Bars required n 0.24 To be used Number of Bars (rounded off) nf 1.00 Amount of Steel Supplied As = nAb 201.06 mm 2
supplied sup = As/bd 0.0053
Checking Steel Ratio: Minimum min = sqrt(Fy) / (4Fy) 0.0048 NSCP limit of min min = 1.4 / Fy 0.0051 maximum where bal = 0.005 max = (0.85f'c/Fy) x [0.003/(0.003+bal)] 0.0276 if f'c 28MPa, = 0.85 0.8500 if f'c > 28MPa, = 0.85 - 0.008(f'c - 28) 0.65
0.8500
min 0.0048 sup 0.0053 max 0.0276 min max
119
Design of B6 (Arched Wide-Flange Beam)
Basic Requirements: Yield Strength of Steel Fy 275.00 MPa Length of Purlin Lp 10.00 m Length of Wide Flange Lw 10.20 m
Computation of Number of Purlin over Beam: a Total Normal Load for Purlin TNL 756.74 N/m Reaction at simple support Rp = wL/2 = TNL*L/2 3,783.71 N Number of Purlins Np 18.00 pcs
Computation of Max Moment, applied with Progression for Concentrated Loads due to Purlin: Summation of Arithmetic Progression Sn 28.60 m Difference d -0.50 m Number of Terms n 11.00 First Progression A1 5.10 m Reaction at support or Max Shear Vmax = Rw = Np*Rp/2 34,053.40 N Moment Max Mmax 42,755.94 N-m
Choosing of Section assuming Flange and Web is Compact: Flexure Fb = 0.66Fy 181.50 MPa Section Modulus S = Mmax / Fb 235.57 x10 3 mm 3
Choose Section near to computed S W10x15
Check the compactness of the chosen section: Base of Flange bf 101.60 mm Thickness of Flange tf 6.90 mm Width Thickness Ratio bf/(2tf) 7.36 NSCP Limits of Width Thickness Ratio 170/sqrt(Fy) 10.25 Since 7.36 < 10.25, Flange is Compact. Depth of Web d 253.70 mm Thickness of Web tw 5.80 mm Width Thickness Ratio d/tw 43.74 120
Design of B6 (Arched Wide-Flange Beam) - continued
NSCP Limits of Width Thickness Ratio 1680/sqrt(Fy) 101.31 Since 43.74 < 101.31, Web is Compact.
Check for Shear Stress: Clear Distance between Flanges h = d - 2tf 239.90 mm Width Thickness Ratio h/tw 41.36 NSCP Limit for Width Thickness Ratio 998/sqrt(Fy) 60.18 Since 57.08 < 60.18, Fvall 0.40Fy Actual Shear Stress fv = Vmax / dtw 23.14 NSCP Limit for Allowable Shear Stress Fv = 0.40Fy 110.00 Since 23.14 < 110, chosen section can resist the actual shearing stress.
121
Design of B7 (Inclined Wide-Flange Beam)
Basic Requirements: Yield Strength of Steel Fy 275.00 MPa Length of Purlin Lp 10.00 m Length of Wide Flange Lw 10.00 m
Computation of Number of Purlin over Beam: a Total Normal Load for Purlin TNL 738.64 N/m Reaction at simple support Rp = wL/2 = TNL*L/2 3,693.21 N Number of Purlins Np 17.00 pcs
Computation of Max Moment, applied with Progression for Concentrated Loads due to Purlin: Summation of Arithmetic Progression Sn 27.50 m Difference d -0.50 m Number of Terms n 10.00 First Progression A1 5.00 m Reaction at support or Max Shear Vmax = Rw = Np*Rp/2 31,392.28 N Moment Max Mmax 46,165.12 N-m
Choosing of Section assuming Flange and Web is Compact: Flexure Fb = 0.66Fy 181.50 Section Modulus S = Mmax / Fb 254.35 x10 3 mm 3
Choose Section near to computed S W10x15
Check the compactness of the chosen section Base of Flange bf 101.60 mm Thickness of Flange tf 6.90 mm Width Thickness Ratio bf/(2tf) 7.36 NSCP Limits of Width Thickness Ratio 170/sqrt(Fy) 10.25 Since 7.36 < 10.25, Flange is Compact. Depth of Web d 253.70 mm Thickness of Web tw 5.80 mm Width Thickness Ratio d/tw 43.74 122
Design of B7 (Inclined Wide-Flange Beam) - continued
NSCP Limits of Width Thickness Ratio 1680/sqrt(Fy) 101.31 Since 43.74 < 101.31, Web is Compact.
Check for Shear Stress: Clear Distance between Flanges h = d - 2tf 239.90 mm Width Thickness Ratio h/tw 41.36 NSCP Limit for Width Thickness Ratio 998/sqrt(Fy) 60.18 Since 57.08 < 60.18, Fvall 0.40Fy Allowable Shear Stress Fvall = Vmax / dtw 21.33 NSCP Limit for Allowable Shear Stress Fv = 0.40Fy 110.00 Since 21.33 < 110, chosen section can resist the actual shearing stress.
Design of B8 (Horizontal Wide-Flange Beam)
Selection of Section depends upon the designer because this beam does not carry any load except its own weight. Section was based on the arched and inclined beam for aesthetic purposes. Chosen Section W10x15 Weight of Section W 21.11 kg/m
123
V. DESIGN OF COLUMNS Design of C4 (Long Wide-Flange Column)
The chosen column to be designed is on the center of the terminal where it receives loads directed by 4 beams on it.
Basic Requirements: Yield Strength of Steel Fy 275.00 MPa Length of Column L 9.4 m Tributary Area TA = L x W = 10m x 10m 100.00 m 2
Weight of 2 Inclined Beam over Column W10x15 has 22.38kg/m divided by 2 for Rsupport 2,537.97 N Weight of 2 Horizontal Beam over Column W10x15 has 22.38kg/m divided by 2 for Rsupport 2,195.48 N a Transferred Load (not normal) from Beams Rw or Vmax multiply by 2 (two-sided) 62,784.56 N Inclination of Reaction from Beam 9.45 deg Reaction from Beam (Normal to Surface) Rn = (R + WInclined Beam)*cos + Whor. beam 66,631.53 N Young's Modulus E 200.00 Gpa
Choose any Section: Chosen Section W6 x 12 Area A 2,290.00 mm 2
Radius of Gyration rt 26.67 mm
Properties of Section: Stiffness, k Top Hinged and Bottom Fixed 0.70 Slenderness Ratio kL/r 246.46 Critical Slenderness Ratio 119.82 MPa
Check if it passed: Allowable Stress Stressallowable = (12pi 2 E) / [23(kL/r) 2 ] 16.96 MPa Actual Stress Stressactual = Pactual / Area 29.10 MPa Since Actual Stress < Allowable Stress, Design passed!
124
Design of C5 (Intermediate Wide-Flange Column)
The chosen column to be designed is on the center of the terminal where it receives loads directed by 4 beams on it.
Basic Requirements: Yield Strength of Steel Fy 275.00 MPa Length of Column L 2.75 m Tributary Area TA = L x W = 10m x 5m 50.00 m 2
Weight of Arched Beam over Column W10x15 has 22.38kg/m divided by 2 for Rsupport 1,119.69 N Weight of 2 Horizontal Beam over Column W10x15 has 22.38kg/m divided by 2 for Rsupport 2,195.48 N Transferred Load (not normal) from Beams Rw or Vmax from previous computations of WF Beam 34,053.40 N Inclination of Reaction from Beam 17.36 deg Reaction from Beam (Normal to Surface) Rn = (R + Warched beam)*cos + Whor. beam 35,766.39 N Young's Modulus E 200.00 Gpa
Choose any Section: Chosen Section W6 x 12 Area A 2,290.00 mm 2
Radius of Gyration rt 26.67 mm
Properties of Section: Stiffness, k Top Hinged and Bottom Fixed 0.70 Slenderness Ratio SR = kL/r 71.65 Critical Slenderness Ratio CSR = sqrt[(2pi 2 E/Fy)] 119.82 MPa
Check if it passed: Slenderness ratio over Critical = (kL/r)/C 0.60 FS FS = (5/3) + (3/8)() - 3 /8 1.86 MPa Allowable Stress Stressallowable = (1 - 0.5 2 )(Fy/FS) 121.14 MPa Actual Stress Stressactual = Pactual / Area 15.62 MPa Since Actual Stress < Allowable Stress, Design passed!
125
Design of C1 (RC Column under C5)
Material Properties: Concrete Compressive Strength F'c 21.00 MPa Yield Strength of Steel Fy 275.00 MPa Weight of Concrete c 23.60 kN/m 3
Computation of Column Dimension: a Transferred Load from Columns Ptransferred 35.77 kN Weight of Steel Column over RC Column
Wsteel col. = WW6x12*g*L; WW6x12 = 18.01kg/m 0.48 kN Dead Load including Slab Load DL 5.51 kPa Dead Load converted to kN DL * TA; TA = (3.3/2)*(4.5+3)/2 26.13 kN Shear from Beam Load carried by column Vbeam; solved through SAP2000 11.32 kN Summation of Loads over RC Column Psum = P + Wsteel col. + DL + Vbeam 73.70 kN Steel Ratio = 1.4 / Fy 0.0051 Main Reinforment Bar Diameter Drebar 16.00 mm Stirrup Bar Diameter Dstirrup 10.00 mm Pu = [0.85f'c(Ag-Ast)+fyAst] Strength Reduction Factor 0.65 Factor 0.80 Actual Gross Area
Ag from Pu = [0.85f'c(Ag- Ast)+fyAst] 7,397.73 mm 2
Dimension of Square Column Ncolumn 2 = Ag 100.00 mm But this dimension should be greater than the baseplate which the steel column is attached. c Dimension of Square Base Plate s 200.00 mm d Dimension of Beam over Column b x h 150mm x 330mm
Therefore, make an allowance to the dimension of Base Plate by rounding up to signigicant 50 units. Therefore, use 250mm x 250mm Reinforced Concrete Column. 126
Design of C1 (RC Column under C5) - continued Computation of Number of Rebars: Gross Area from Computed Dimension Ag supply = Ncolumn 2 62,500.00 mm 2
Total Compression in the Concrete c1 = Total Load / (*) 68,781.53 N Total Compression in the Steel c2 = c1 - 0.85*f'c*Agsupply - 1,046,843 .47 N Area of Steel Required Asreqd -4070.9 mm 2
Number of Rebars N -20 Since N < 4, use 4-16mm Rebars.
Computation of Spacing of Stirrups: First Criteria 48 Tie Diameter 480.00 Mm Second Criteria 16 Main Diameter 256.00 Mm Third Criteria Least Dimension of Column 150.00 Mm Since Third Criteria is least, use 150mm for maximum spacing of ties.
Design of C3 (RC Column under C4)
Material Properties: Concrete Compressive Strength F'c 21.00 MPa Yield Strength of Steel Fy 275.00 MPa Weight of Concrete c 23.60 kN/ m 3
Computation of Column Dimension: a Transferred Load from Columns Ptransferred 37.18 kN Shear from Beam Load carried by column Vbeam; solved through SAP2000 11.32 kN Summation of Loads over RC Column Psum = P + Wsteel col. + DL + Vbeam 48.50 kN Steel Ratio = 1.4 / Fy 0.0051
Main Reinforment Bar Diameter Drebar 16.00 mm Stirrup Bar Diameter Dstirrup 10.00 mm Pu = [0.85f'c(Ag-Ast)+fyAst] 127
Strength Reduction Factor 0.65 Factor 0.80 Actual Gross Area Ag from Pu=[0.85f'c(Ag- Ast)+fyAst] 4,868.12 mm 2
Dimension of Square Column Ncolumn 2 = Ag 100.00 mm But this dimension should be greater than the baseplate which the steel column is attached. c Dimension of Square Base Plate s 200.00 mm d Dimension of Beam over Column b x h 150mm x 330mm Therefore, make an allowance to the dimension of Base Plate by rounding up to signigicant 50 units. Therefore, use 250mm x 250mm Reinforced Concrete Column.
Computation of Number of Rebars: Gross Area from Computed Dimension Ag supply = Ncolumn 2 62,500.00 mm 2
Total Compression in the Concrete c1 = Total Load / (*) 71,499.65 N Total Compression in the Steel c2 = c1 - 0.85*f'c*Agsupply -1,044,125.35 N Area of Steel Required Asreqd -4060.35 mm 2
Number of Rebars N -20 Since N < 4, use 4-16mm Rebars.
Computation of Spacing of Stirrups: First Criteria 48 Tie Diameter 480.00 mm Second Criteria 16 Main Diameter 256.00 mm Third Criteria Least Dimension of Column 150.00 mm Since Third Criteria is least, use 150mm for maximum spacing of ties.
Design of C2 (RC Column of Minor Structure)
Primary data herein are taken from previous computations of the beam.
Material Properties: Concrete Compressive Strength F'c 21.00 MPa Yield Strength of Steel Fy 275.00 MPa Weight of Concrete c 23.60 kN/m 3
128
Computation of Column Dimension: Tributary Area TA = L*W; L = (4.5+3)/2; W = 3.3/2 6.24 m 2
Max Shear of Beam Load BL = cbhL/2; beam dim = 330mm x 150mm 4.42 kN Dead Load including Slab Load DL 5.51 kPa Live Load From NSCP 2010 for Flat Roof 1.00 kPa Summation of Load Psum = (DL + LL)*TA + BL 36.79 kN Steel Ratio = 1.4 / Fy 0.0051 Main Reinforment Bar Diameter Drebar 16.00 mm Stirrup Bar Diameter Dstirrup 10.00 mm Pu = [0.85f'c(Ag - Ast) + fyAst] Strength Reduction Factor 0.65 Factor 0.80 Actual Gross Area Ag from Pu = [0.85f'c(Ag - Ast) + fyAst] 3,692.34 mm 2
Dimension of Square Column Ncolumn 2 = Ag 70.00 mm Dimension of Beam over Column bxh 150mm x 330 mm Therefore, use 150mm x 150mm Reinforced Concrete Column.
Computation of Number of Rebars: Gross Area from Computed Dimension Ag supply = Ncolumn 2 22,500.00 mm 2
Total Compression in the Concrete c1 = Total Load / (*) 70,741.97 N Total Compression in the Steel c2 = c1 - 0.85*f'c*Agsupply -330,883.03 N Area of Steel Required Asreqd -1,286.70 mm 2
Number of Rebars N -6.40 Since N < 4, use 4-16mm Rebars.
Computation of Spacing of Stirrups: First Criteria 48 Tie Diameter 480.00 mm Second Criteria 16 Main Diameter 256.00 mm Third Criteria Least Dimension of Column 150.00 mm Since Third Criteria is least, use 150mm for maximum spacing of ties.
129
VI. DESIGN OF FOOTINGS Design of F1 (Square Footing under C1 and C5)
Unfactored Dead Loads: a Load over Column LC from previous computation of RC Column 73.70 kN RC Column Weight C = 23.6*H*Dimensions 7.54 kN Total Unfactored Dead Load TDL 81.24 kN Unfactored Live Load: Roof Live Load RLL 0.0675 kN Total Unfactored Live Load TLL 0.0675 kN
Computation of Dimension of Square Footing: Allowable Soil Presurre qall based on NSCP 2010 50.00 kPa Area of footing Aftg = L 2 = Punfactored / qa 1.63 m 2
Dimension of footing Lfooting 900.00 mm Depth of Footing dsupplied = 0.2 (L); if failed, redesign 180.00 mm Concrete cover c 100.00 mm Thickness of footing tfooting 280.00 mm Thickness of soil tsoil 800.00 mm dimension of column N 2 300.00 mm
Computation of Effective Bearing Capacity: Unit weight of concrete c 23.60 kN/m 3
unit weight of soil s 15.60 kN/m 3
effective bearing capacity qe = qa - h 35.28 kPa
Computation of Ultimate Bearing Capacity: Area of footing, Aftg Aftg = L 2 = Punfactored / qa 2.30 m 2
Dimension of footing Lfooting 1,600.00 mm ultimate bearing capacity, qu qu = Pfactored / Aftg 0.03812 MPa 130
Design of F1 (Square Footing under C1 and C5) - continued
Checking for One-Way Shear: Ultimate Shear Vu = qu*Ashear length of shear, Lshear 1,600.00 mm width of shear, Wshear 650 - d mm Ashear 0.039(1600)( 650 - d) N Vc Vc = (/6)(f'c)(bd) 916.5151389 91168d for Vc = Vu coeff. of d 16.03 num. coeff. 650.00 Required Depth dreqd 40.56 mm
Since depth required < depth of footing, design is allowable.
Vu Vu = qu*Ashear coeff of d 2 -0.03812 coeff of d -22.87 numerical coeff 94,167.15 Vc Vc = (/3)(f'c)(bd) coeff of d 2 4.58 coeff of d 1,374.77 for Vc = Vu coeff of d 2 4.62 coeff. of d 1,397.65 num. coeff. -94,167.15 dreqd (+) 56.73 mm dreqd (-) -359.21 mm
Since positive required depth < depth of footing, design passed.
Computation of Number of Rebars: Mu Mu = qu (L) (L - dcolumn) 2 / 2 12.89 kN - m Ru Ru = Mu / ( b d 2 ) 0.27619 MPa 131
Design of F1 (Square Footing under C1 and C5) - continued
0.001012229 min 1.4 / fy 0.005090909 adopt 0.005090909 As As = bd 1,466.18 mm 2
diameter of RSB dRSB 16.00 mm area of RSB Arsb 201.06 mm 2
number of bars, n n = As /Arsb 7.29 say 8.00 pcs
132
Design of F2 (Square Footing under C3 and C4)
Basic Requirements: Concrete Compressive Strength F'c 21.00 MPa Yield Strength of Steel Fy 275.00 MPa Unfactored Dead Loads: a Transferred Load over Column Load from previous computaion of column 66.63 kN Column Weight Wsteel col. = WW6x12*g*L; WW6x12 = 18.01kg/m 1.66 kN Total Unfactored Dead Load TDL 68.29 kN
Unfactored Live Load: Roof Live Load RLL 0.0675 kN Total Unfactored Live Load TLL 0.0675 kN
Computation of Dimension of Square Footing: Allowable Soil Presurre qall based on NSCP 2010 50.00 kPa Area of footing Aftg = L 2 = Punfactored / qa 1.37 m 2
Dimension of footing Lfooting 700.00 mm Depth of Footing dsupplied = 0.2 (L); if failed, redesign 140.00 mm Concrete cover c 100.00 mm Thickness of footing tfooting 240.00 mm Thickness of soil tsoil 800.00 mm dimension of column N 2 300.00 mm
Computation of Effective Bearing Capacity: unit weight of concrete c 23.60 kN/m 3
unit weight of soil s 15.60 kN/m 3
effective bearing capacity qe = qa - h 35.60 kPa
Computation of Ultimate Bearing Capacity: Area of footing, Aftg Aftg = L 2 = Punfactored / qa 1.92 m 2
Dimension of footing Lfooting 1,400.00 mm ultimate bearing capacity, qu qu = Pfactored / Aftg 0.04187 MPa
133
Design of F2 (Square Footing under C3 and C4) - continued
Checking for One-Way Shear: Ultimate Shear Vu = qu*Ashear length of shear, Lshear 1,400.00 mm width of shear, Wshear 550 - d mm Ashear 0.042(1400) (550 - d) N Vc Vc = (/6)(f'c)(bd) 801.950746 617272d for Vc = Vu coeff. of d 14.68 num. coeff. 550.00 Required Depth dreqd 37.46 mm Since depth required < depth of footing, design is allowable. Vu Vu = qu*Ashear coeff of d 2 -0.04187 coeff of d -25.12 numerical coeff 78,288.74 Vc Vc = (/3)(f'c)(bd) coeff of d 2 4.58 coeff of d 1,374.77 for Vc = Vu coeff of d 2 4.62 coeff. of d 1,399.89 num. coeff. -78,288.74 dreqd (+) 48.24 mm dreqd (-) -350.95 mm Since positive required depth < depth of footing, design passed.
Computation of Number of Rebars: Mu Mu = qu (L) (L - dcolumn) 2 / 2 8.87 kN - m Ru Ru = Mu / ( b d 2 ) 0.35897 MPa 0.00131873 min 1.4 / fy 0.005090909 adopt 0.005090909 134
Design of F2 (Square Footing under C3 and C4) - continued
As As = bd 997.82 mm 2
diameter of RSB dRSB 16.00 mm area of RSB Arsb 201.06 mm 2
number of bars, n n = As /Arsb 4.96 say 5.00 pcs
135
Design of F3 (Square Footing under C2)
Basic Requirements: Concrete Compressive Strength F'c 21.00 MPa Yield Strength of Steel Fy 275.00 MPa Unfactored Dead Loads: Load over Column LC from previous computation of RC Column 45.02 kN RC Column Weight C = 23.6*H*Dimensions; H = 3.55m 1.31 kN Total Unfactored Dead Load TDL 38.09 kN
Unfactored Live Load: Roof Live Load RLL 0.0675 kN Total Unfactored Live Load TLL 0.0675 kN
Computation of Dimension of Square Footing: Allowable Soil Presurre qall based on NSCP 2010 50.00 kPa Area of footing Aftg = L 2 = Punfactored / qa 0.76 m 2
Dimension of footing Lfooting 400.00 mm Depth of Footing dsupplied = 0.2 (L); if failed, redesign 80.00 mm Concrete cover c 100.00 mm Thickness of footing tfooting 180.00 mm Thickness of soil tsoil 800.00 mm dimension of column N 2 300.00 mm
Computation of Effective Bearing Capacity: unit weight of concrete c 23.60 kN/m 3
unit weight of soil s 15.60 kN/m 3
effective bearing capacity qe = qa - h 36.08 kPa
Computation of Ultimate Bearing Capacity: Area of footing, Aftg Aftg = L 2 = Punfactored / qa 1.06 m 2
Dimension of footing Lfooting 1,200.00 mm ultimate bearing capacity, qu qu = Pfactored / Aftg 0.03787 MPa
136
Design of F3 (Square Footing under C2) - continued
Checking for One-Way Shear: Ultimate Shear Vu = qu*Ashear length of shear, Lshear 1,100.00 mm width of shear, Wshear 400 - d mm Ashear 0.038(1100)( 400 - d) N Vc Vc = (/6)(f'c)(bd) 630.1041580 56428d for Vc = Vu coeff. of d 16.13 num. coeff. 400.00 Required Depth dreqd 24.80 mm
Since depth required < depth of footing, design is allowable.
Vu Vu = qu*Ashear coeff of d 2 -0.03787 coeff of d -22.72 numerical coeff 42,413.63 Vc Vc = (/3)(f'c)(bd) coeff of d 2 4.58 coeff of d 1,374.77 for Vc = Vu coeff of d 2 4.62 coeff. of d 1,397.49 num. coeff. -42,413.63 dreqd (+) 27.80 mm dreqd (-) -330.25 mm
Since positive required depth < depth of footing, design passed.
Computation of Number of Rebars: Mu Mu = qu (L) (L - dcolumn) 2 / 2 3.33 kN - m Ru Ru = Mu / ( b d 2 ) 0.52596 MPa
137
Design of F3 (Square Footing under C2) - continued
0.00194 min 1.4 / fy 0.00509 adopt 0.00509 As As = bd 448.00 mm 2
diameter of RSB dRSB 16.00 mm area of RSB Arsb 201.06 mm 2
number of bars, n n = As /Arsb 2.23 say 3.00 pcs
138
VII. DESIGN OF VERTICAL STIRRUPS Design of Vertical Stirrups for Beams over Waiting Area
Primary data herein are taken from previous computations of the Beam.
Material Properties: Concrete Compressive Strength F'c 28.000 MPa Yield Strength of Steel Fy 275.000 MPa Weight of Concrete Wc 23.600 kN/m 3
Beam Description: Simple Span L 3.300 m Total Uniform Load W 26.000 kN/m
Computed Beam Size from Beam Computations: Height h 330.000 mm Concrete cover c 75.000 mm Effective depth d = h - c 255.000 mm Beam Width b 125.000 mm
Computation of the Spacing of Stirrup: Maximum Shear Vmax or Vu = WL/2 42.900 kN Spacing of Stirrup s 165.000 mm
Computation of Area of Stirrups: Concrete Shear Force Vc 36.379 kN Factored Concrete Shear Force Phi Vc 30.922 kN Minimum Area of Stirrup Av 25.000 mm 2
Diameter of Stirrup ds 10.000 mm Area of Stirrup Bars As 78.540 mm 2
Since As > Av, it passed!
139
Design of Vertical Stirrups for Beams over Guardhouse
Primary data herein are taken from previous computations of the Beam.
Material Properties: Concrete Compressive Strength F'c 28.000 MPa Yield Strength of Steel Fy 275.000 MPa Weight of Concrete Wc 23.600 kN/m 3
Beam Description: Simple Span L 3.300 m Total Uniform Load W 12.095 kN/m
Computed Beam Size from Beam Computations: Height h 330.000 mm Concrete cover c 75.000 mm Effective depth d = h - c 255.000 mm Beam Width b 125.000 mm
Computation of the Spacing of Stirrup: Maximum Shear Vmax or Vu = WL/2 19.957 kN Spacing of Stirrup s 165.000 mm
Computation of Area of Stirrups: Concrete Shear Force Vc 36.379 kN Factored Concrete Shear Force Phi Vc 30.922 kN Minimum Area of Stirrup Av 25.000 mm 2
Diameter of Stirrup ds 10.000 mm Area of Stirrup Bars As 78.540 mm 2
Since As > Av, it passed!
140
Design of Vertical Stirrups for Beams over Office
Primary data herein are taken from previous computations of the Beam.
Material Properties: Concrete Compressive Strength F'c 28.000 MPa Yield Strength of Steel Fy 275.000 MPa Weight of Concrete Wc 23.600 kN/m 3
Beam Description: Simple Span L 3.4 m Total Uniform Load W 12.095 kN/m
Computed Beam Size from Beam Computations: Height h 330.000 mm Concrete cover c 75.000 mm Effective depth d = h - c 255.000 mm Beam Width b 125.000 mm
Computation of the Spacing of Stirrup: Maximum Shear Vmax or Vu = WL/2 20.138 kN Spacing of Stirrup s 165.000 mm
Computation of Area of Stirrups: Concrete Shear Force Vc 36.379 kN Factored Concrete Shear Force Phi Vc 30.922 kN Minimum Area of Stirrup Av 25.000 mm 2
Diameter of Stirrup ds 10.000 mm Area of Stirrup Bars As 78.540 mm 2
Since As > Av, it passed!
141
Design of Vertical Stirrups for Beams over Storage Room
Primary data herein are taken from previous computations of the Beam.
Material Properties: Concrete Compressive Strength F'c 28.000 MPa Yield Strength of Steel Fy 275.000 MPa Weight of Concrete Wc 23.600 kN/m 3
Beam Description: Simple Span L 3.000 m Total Uniform Load W 12.095 kN/m
Computed Beam Size from Beam Computations: Height h 330.000 mm Concrete cover c 75.000 mm Effective depth d = h - c 255.000 mm Beam Width b 125.000 mm
Computation of the Spacing of Stirrup: Maximum Shear Vmax or Vu = WL/2 18.143 kN Spacing of Stirrup s 165.000 mm
Computation of Area of Stirrups: Concrete Shear Force Vc 36.379 kN Factored Concrete Shear Force Phi Vc 30.922 kN Minimum Area of Stirrup Av 25.000 mm 2
Diameter of Stirrup ds 10.000 mm Area of Stirrup Bars As 78.540 mm 2
Since As > Av, it passed!
142
Design of Vertical Stirrups for Beams over CR
Primary data herein are taken from previous computations of the Beam.
Material Properties: Concrete Compressive Strength F'c 28.000 MPa Yield Strength of Steel Fy 275.000 MPa Weight of Concrete Wc 23.600 kN/m 3
Beam Description: Simple Span L 3.300 m Total Uniform Load W 12.095 kN/m
Computed Beam Size from Beam Computations: Height h 330.000 mm Concrete cover c 75.000 mm Effective depth d = h - c 255.000 mm Beam Width b 125.000 mm
Computation of the Spacing of Stirrup: Maximum Shear Vmax or Vu = WL/2 19.957 kN Spacing of Stirrup s 165.000 mm
Computation of Area of Stirrups: Concrete Shear Force Vc 36.379 kN Factored Concrete Shear Force Phi Vc 30.922 kN Minimum Area of Stirrup Av 25.000 mm 2
Diameter of Stirrup ds 10.000 mm Area of Stirrup Bars As 78.540 mm 2
Since As > Av, it passed!
143
VIII. DESIGN OF BOLTS
Design of Base Plate and Bolts of C1 with Fillet Computation
The base plate rests on full area of a square concrete column.
Relevant Properties: Concrete Compressive Strength F'c 21.00 MPa Yield Strength of Steel Fy 275.00 MPa Steel Section W6 x 12 Flange Width bf 101.60 mm Depth d 153.20 mm Web Thickness tw 5.80 mm Flange Thickness tf 7.10 mm Weight of Steel Column W 18.01 kg/m Length of Steel Column L 2.73 m Load due to Weight of Steel Column Psteel column = WLg 482.33 N Load carried by Steel Column DL x 2 since 2 beams act on both sides. 33,747.07 N Total Load TL = 2DL + Psteel column 34,229.40 N
Computation of Base Plate Dimension: Allowable Bearing Stress on Concrete Fp = 0.35F'c 7.35 MPa Allowable Bearing Stress on Steel Fb = 0.75Fy 206.25 MPa Area of Base Plate A = TL / Fp 4,657.06 mm 2
Dimension of Base Plate N 2 = A; N = ? 68.24 mm Dimension of Base Plate (rounded up per tenths)) Nf 70.00 mm Square Dimension of Wide Flange bf x (2tf + d) 101.6mm x 167.4mm Therefore, make an allowance to the dimension of Wide Flange by rounding up to signigicant 50 units. Use 200mm x 200mm.
144
Design of Base Plate and Bolts of C1 with Fillet Computation - continued
Computation of Base Plate Thickness: Base Plate Outboard paralled to Flange m = (N - 0.95d) / 2 -38.65 mm Base Plate Outboard paralled to Web n = (N - 0.8bf) / 2 -6.52 mm Actual Bearing Pressure fp = P / Aactual; Aactual = Nf 2 0.86 MPa Plate Thickness t = sqrt[(3fpx 2 )/(Fb)] 2.13 mm Plate Thickness (rounded up per tenths) tf 10.00 mm Therefore, use 10mm thick base plate.
Computation of Bolts: Wind Load from NSCP 2010 Worig.wind 0.5 kPa Tributary Area TA = (TW)*Length of Curve Beam 102 m 2
Wind Load convert to kN to get shear P = Worig.wind*TA 51.00 kN Chosen Bolt A325 whose threads are not excluded from shear plane. Total Area of Bolts on Shear Abolts; d = 12mm 452.39 mm 2
Actual Shear Stress acting on Bolts fv = P/Abolts 112.73 MPa Allowable Shear Stress from NSCP 2010 Fv 145.00 MPa Since fv < Fv, design of bolts passed.
Computation of Fully Weld (Fillet) between Plate and Column (assume equal-leg fillet): Choose size and electrode no. E60 XX Electrode, 4.76mm or 3/16in Allowable Load on Weld Pweld all. 0.42 kN/mm Total Length of Weld Lweld = 2*(bf+d-tw+2*tf) 500.60 mm Actual Load on Weld Pweld = TL / Lweld 0.07 kN/mm Since Pweld < Pweld all., design of fillet passed.
145
Design of Bolts between C4 and B6
Basic Requirements: Yield Strength of Steel Fy 275.00 MPa Chosen bolt A325 Bolt with threads excluded from shear plane. Allowable Shearing Stress of chosen bolt Fv 145.00 MPa
Computation of Actual Shearing Stress and Allowable Tensile Stress: a Shear Max carried by Inclined Beam Vmax 33,900.71 N b Shear caused by weight of Inclined Beam Vweight = Wbeam*g*Lbeam; Wbeam = 21.11kg/m 2,112.31 N Load acting on bolt Pbolt = Vmax + Vwt. of beam 36,013.02 N Area on Shear Av; dbolt = 20mm 452.39 mm 2
Actual Shearing Stress fv = P / Av 79.61 MPa Since fv < Fv, design of bolts for shear passed. Allowable Tensile Stress Ft = sqrt(303 2 -2.15fv 2 ) 279.61 MPa Moment caused by eccentricity M = Pe; e is 200mm 7,202,603.83 N-mm Distance of Centroid of Bolt to NA y 75.00 mm Actual Tensile Force T = My / (summation of y 2 ) 24,008.68 N Maximum Tensile Stress ft = P / At; At is area of single bolt. 212.28 MPa Since ft < Ft, design of bolts for tension passed.
Computation of Safe Load: Moment M 200P N-mm Tensile Force T = My / (summation of y 2 ) (2/3)*P N Actual Shearing Stress fv = P / Av P/(100) MPa Allowable Tensile Stress Ft = sqrt(303 2 -2.15fv 2 ) sqrt(303 2 - 2.15(P/(100)) 2 ) MPa Solve for P by eq'n T = Ft x A (2/3)*P = sqrt(303 2 - 2.15(P/(100)) 2 ) x Av 61,906.90 N Check fv fv = P / Av 136.84 MPa Since fv < Fv = 145 MPa, design passed.
146
Design of Bolts between C4 and B7
Basic Requirements: Yield Strength of Steel Fy 275.00 MPa Chosen bolt A325 Bolt with threads excluded from shear plane. Allowable Shearing Stress of chosen bolt Fv 145.00 MPa
Computation of Actual Shearing Stress and Allowable Tensile Stress: a Shear Max carried by Inclined Beam Vmax 31,181.55 N b Shear caused by weight of Inclined Beam Vweight = Wbeam*g*Lbeam; Wbeam = 21.11kg/m 2,070.89 N Load acting on bolt Pbolt = Vmax + Vwt. of beam 33,252.44 N Area on Shear Av; dbolt = 12 mm 452.39 mm 2
Actual Shearing Stress fv = P / Av 73.50 MPa Since fv < Fv, design of bolts for shear passed. Allowable Tensile Stress Ft = sqrt(303 2 -2.15fv 2 ) 283.18 MPa Moment caused by eccentricity M = Pe; e is 200mm 6,650,488.69 N-mm Distance of Centroid of Bolt to NA y 75.00 mm Actual Tensile Force T = My / (summation of y 2 ) 22,168.30 N Maximum Tensile Stress ft = P / At; At is area of single bolt. 196.01 MPa Since ft < Ft, design of bolts for tension passed.
Computation of Safe Load: Moment M 200P N-mm Tensile Force T = My / (summation of y 2 ) (2/3)*P N Actual Shearing Stress fv = P / Av P/(100) MPa Allowable Tensile Stress
Ft = sqrt(303 2 -2.15fv 2 )
sqrt(303 2 - 2.15(P/(100)) 2 ) MPa Solve for P by eq'n T = Ft x A
(2/3)*P = sqrt(303 2 - 2.15(P/(100)) 2 ) x Av 61,906.90 N Check fv fv = P / Av 136.84 MPa Since fv < Fv = 145 MPa, design passed. 147
Design of Bolts between C4 and B8
Basic Requirements: Yield Strength of Steel Fy 275.00 MPa Chosen bolt A325 Bolt with threads excluded from shear plane. Allowable Shearing Stress of chosen bolt Fv 145.00 MPa
Computation of Actual Shearing Stress and Allowable Tensile Stress: Load from Beam W12x14 has 21.11 kg/m divided by 2 for Vmax 1,035.45 N Area on Shear Av; dbolt = 12mm 452.39 mm 2
Actual Shearing Stress fv = P / Av 2.29 MPa Since fv < Fv, design of bolts for shear passed. Allowable Tensile Stress Ft = sqrt(303 2 -2.15fv 2 ) 302.98 MPa Moment caused by eccentricity M = Pe; e is 200mm 207,089.10 N-mm Distance of Centroid of Bolt to NA y 75.00 mm Actual Tensile Force T = My / (summation of y 2 ) 690.30 N Actual Maximum Tensile Stress ft = P / At; At is area of single bolt. 6.10 MPa Since ft < Ft, design of bolts for tension passed.
Computation of Safe Load: Moment M 200P N-mm Tensile Force T = My / (summation of y 2 ) (2/3)*P N Actual Shearing Stress fv = P / Av P/(100) MPa Allowable Tensile Stress Ft = sqrt(303 2 -2.15fv 2 ) sqrt(303 2 - 2.15(P/(100)) 2 ) MPa Solve for P by eq'n T = Ft x A (2/3)*P = sqrt(303 2 - 2.15(P/(100)) 2 ) x Av 61,906.90 N Check fv fv = P / Av 136.84 MPa Since fv < Fv = 145 MPa, design passed.
148
IX. DESIGN OF WELD Computation of Fully Weld (Fillet) between Purlins and B6
Properties of Steel Sections: a Base of WF parallel to length of purlin bWF 100.80 mm Base of purlin bpurlin 61.80 mm
Computation and checking of Allowable and Actual Load: b Total Normal Load carrie by Purlin TNL; including its weight 753.35 N/m Load acting on Weld Vmax = TNL*L/2; L = 10m 3.77 kN Choose size and electrode no. E60 XX Electrode, 4.76mm or 3/16in Allowable Load on Weld Pweld all. 0.42 kN/mm Total Length of Weld or Perimeter Lweld = 2*(0.5*bWF + bpurlin) 224.40 mm Actual Load on Weld Pweld = Vmax / Lweld 0.02 kN/mm Since Pweld < Pweld all., design of fillet passed.
Computation of Fully Weld (Fillet) between Purlins and B7
Properties of Steel Sections: a Base of WF parallel to length of purlin bWF 100.80 mm Base of purlin bpurlin 61.80 mm
Computation and checking of Allowable and Actual Load: b Total Normal Load carrie by Purlin TNL; including its weight 733.80 N/m Load acting on Weld Vmax = TNL*L/2; L = 10m 3.67 kN Choose size and electrode no. E60 XX Electrode, 4.76mm or 3/16in Allowable Load on Weld Pweld all. 0.42 kN/mm Total Length of Weld or Perimeter Lweld = 2*(0.5*bWF + bpurlin) 224.40 mm Actual Load on Weld Pweld = Vmax / Lweld 0.02 kN/mm Since Pweld < Pweld all., design of fillet passed.
APPENDIX B: DETAILED ESTIMATES
150
Item No. Description Qty Unit Unit Cost Total Amount Material Cost Labor Cost Total Cost
I. General Requirements Mobilization (including gen. cleaning) 1.00 lot 24,000.00 600.00 24,600.00 24,600.00 Subtotal General Requirements 24,600.00
II. Site Development 1.0 Landscape 1.1 Trees 4.00 pcs 500.00 100.00 600.00 2,400.00 2.0 Demolition of Existing Slab 1.00 lot 5,000.00 4,000.00 9,000.00 9,000.00 3.0 Hauling and Disposal of Debris 1.00 lot 3,000.00 1,200.00 4,200.00 4,200.00 4.0 Sidewalk (150mm thk concrete with 10mm diameter rebars at 300mm on center on both ways) 4.1 Concrete 12.50 m 3 3,420.00 1,026.00 4,446.00 55,575.00 4.2 Rebars 346.32 kg 35.00 3.50 38.50 13,333.32 4.3 Formworks 3.00 m 2 395.75 158.30 554.05 1,662.15 4.4 Floor Finish: Plain Cement 50.00 m 2 55.00 22.00 77.00 3,850.00 4.5 Floor Finish: Crashed Gravel 50.00 m 2 1,200.00 360.00 1,560.00 78,000.00 Subtotal Site Development 168,020.47
III. Earthworks Excavation 0.00 m 3 0.00 0.00 0.00 151
Backfilling and Compaction 1,942.99 m 3 200.00 200.00 388,598.00 Subtotal Earthworks 388,598.00
IV. Structural Works 1.0 Concrete Works 0.00 0.00 1.1 Footings (S1 + S2 + S3 + S4) 7.62 m 3 4,191.00 1,257.30 5,448.30 41,522.58 1.2 Wall Footing 13.06 m 3 4,191.00 1,257.30 5,448.30 71,171.14 1.3 Columns 1.22 m 3 3,586.00 1,075.80 4,661.80 5,688.85 1.4 Beams 2.59 m 3 3,586.00 1,075.80 4,661.80 12,076.39 1.5 Roof Slab of Minor Structure (One Way Slab) 4.12 m 3 3,586.00 1,075.80 4,661.80 19,189.93 1.6 Roof Slab of Minor Structure (Two Way Slab) 3.00 m 3 3,586.00 1,075.80 4,661.80 13,974.68 1.7 Slab on Grade 120.00 m 3 3,420.00 1,026.00 4,446.00 533,520.00 1.8 Septic Vault 1.44 m 3 3,586.00 1,434.40 5,020.40 7,229.38 2.0 Rebars 2.1 Footings 407.38 kg 35.00 3.50 38.50 15,684.21 2.2 Wall Footing 148.08 kg 35.00 3.50 38.50 5,701.08 2.3 Columns 123.16 kg 35.00 3.50 38.50 4,741.74 2.4 Beams 397.91 kg 35.00 3.50 38.50 15,319.46 2.5 Roof Slab of Minor Structure 512.18 kg 35.00 3.50 38.50 19,719.08 2.6 Slab on Grade 3,974.69 kg 35.00 3.50 38.50 153,025.49 2.7 Septic Vault 192.50 kg 35.00 3.50 38.50 7,411.40 2.8 Masonry Works 100mm thk CHB Interior 388.71 kg 35.00 3.50 38.50 14,965.34 152
150mm thk CHB Exterior Wall and Exterior 159.84 kg 35.00 3.50 38.50 6,153.84 3.0 Stirrups and Ties 3.1 Columns 107.36 kg 35.00 3.50 38.50 4,133.28 3.2 Beams 181.40 kg 35.00 3.50 38.50 6,983.90 4.0 Formworks 4.1 Columns 28.40 m 2 465.19 186.08 651.27 18,495.95 4.2 Beams 20.72 m 2 465.19 186.08 651.27 13,496.84 4.3 Roof Slab of Minor Structure 134.19 m 2 439.44 175.78 615.22 82,558.79 4.4 Slab on Grade 18.00 m 2 395.75 158.30 554.05 9,972.90 4.5 Septic Vault 21.60 m 2 395.75 158.30 554.05 11,967.48 5.0 Steel Works 5.1 Column (W6x12) 115.56 m 3,142.00 628.40 3,770.40 435,707.42 5.2 Beam (W10x15) 350.56 m 5,357.00 1,071.40 6,428.40 2,253,539.90 5.3 Purlins (C8x13.75) 700.00 m 4,340.00 868.00 5,208.00 3,645,600.00 5.4 GI Currogated Sheet (Prepainted Beige) 9,656.00 m 2 287.99 57.60 345.58 3,336,952.67 5.5 Wall Grate, Square Tube (1/4" thk x 2") 75.36 m 413.40 82.68 496.08 37,384.59 (1/4" thk x 4") 7.80 m 826.80 165.36 992.16 7,738.85 (1/4" thk x 6") 9.42 m 1,240.20 248.04 1,488.24 14,019.22 5.6 Roof Grate, Mild Angle Bar (1/4" thk x 1") 40.00 m 488.00 97.60 585.60 23,424.00 5.7 Gate, (1/4" thk x 2") 84.78 m 413.40 82.68 496.08 42,057.66 5.8 Anchor Bolts 12.00 pc 45.00 9.00 54.00 648.00 5.9 Steel Plate (10mm-thk, 200mm x 200mm) 3.00 sheet 16,644.00 200.00 16,844.00 50,532.00 6.0 Masonry Works 153
V. Civil Works and Architectural 1.0 Floor Slab Floor Finish: Plain Cement 734.00 m 2 55.00 22.00 77.00 56,518.00 Traffic Markings 96.00 m 45.32 24.12 69.44 6,666.12
Mariwasa Floor Tile (12"x12"x3mm) for Office, Waiting Area and Guard House 45.77 m 2 574.00 114.80 688.80 31,525.00 Ceramic Floor Tiles of CR 9.90 m 2 828.80 331.52 1,160.32 11,487.17 2.0 Walls and Ceilings 2.1 Interior and Exterior (Inside Face) Walls of Minor Structure
Wall Finish: Plastering of all inside walls and storage room's ceiling 253.87 m 2 109.60 43.84 153.44 38,954.50
Paint of Interior Walls (Outside face, Acrylic Semi gloss latex paint without scaffolding) 58.18 m 2 68.01 54.00 122.01 7,099.21
Paint of Walls of Office (Acrylic Semi gloss latex paint without scaffolding) 47.07 m 2 68.01 54.00 122.01 5,743.48
Paint of Walls of Guard House (Acrylic Semi gloss latex paint without scaffolding) 46.93 m 2 68.01 54.00 122.01 5,726.15
Paint of Walls of Waiting Area (Acrylic Semi gloss latex paint without scaffolding) 48.71 m 2 68.01 54.00 122.01 5,942.72 Ceramic Wall Tiles of CR 29.82 m 2 453.80 181.52 635.32 18,945.24 154
Paint of Upper Walls of CR (Acrylic Semi gloss latex paint without scaffolding) 14.91 m 2 68.01 54.00 122.01 1,819.20 2.2 Exterior Walls of Minor Sturcture (Outside Face) Wall Finish: Plastering 71.00 m 2 109.60 43.84 153.44 10,894.24
Acrylic Semi gloss latex paint without scaffolding 71.00 m 2 68.01 54.00 122.01 8,662.86 2.3 Other Exterior Walls Wall Finish: Plain Cement 278.01 m 2 109.60 43.84 153.44 42,657.85
Acrylic Semi gloss latex paint without scaffolding 278.01 m 2 68.01 54.00 122.01 33,920.59 2.4 Ceiling of Office, Guard House, Waiting Area and CR (Gypsum Board) 64.92 m 2 473.58 142.07 615.66 39,966.51 3.0 Steel Paints 3.1 Wall Grate, Square Tube (Black Acrylic Semi gloss latex paint without scaffolding) (1/4" thk x 2") 15.32 m 2 68.01 54.00 122.01 1,869.23 (1/4" thk x 4") 3.17 m 2 68.01 54.00 122.01 386.78 (1/4" thk x 6") 5.74 m 2 68.01 54.00 122.01 700.35 3.2 Roof Grate, Mild Angle Bar 1/4" thk x 1" (Black Acrylic Semi gloss latex paint without scaffolding) 4.06 m 2 68.01 54.00 122.01 495.86 3.3 Gate, 1/4" thk x 2" (Black Acrylic Semi gloss latex paint without scaffolding) 17.22 m 2 68.01 54.00 122.01 2,101.05 3.4 Column, W6x12 (White Acrylic Semi gloss latex paint with scaffolding) 60.83 m 2 68.01 74.00 142.01 8,638.60 3.5 Beam, W10x15 (White Acrylic Semi gloss latex paint with scaffolding) 254.72 m 2 68.01 74.00 142.01 36,173.33 155
3.6 Purlins, C8x13.75 (White Acrylic Semi gloss latex paint with scaffolding) 426.44 m 2 68.01 74.00 142.01 60,559.65 4.0 Doors and Windows 4.1 1.2 X 2.9 6mm Thk. Fixed Glass Window On Alum. Frame 1.00 pc. 3710.00 1,113.00 4,823.00 4,823.00
Contingen cy, 10% 1,243,053.12 VAT, 12% 1,640,854.12 TOTAL 15,314,438.45
APPENDIX C: TOPOGRAPHIC SURVEY
159
OCC OBS VER U M L S HI (meas) HD 0 1 -0.048316531 2.89 2.745 2.605 0.285 1.51 28.43352 0 2 -0.01225609 3.025 2.96 2.9 0.125 1.51 12.49812 2 3 0.049266766 2.02 2 1.75 0.27 1.5 26.93452 2 4 -0.008203047 1.7 1.605 1.51 0.19 1.5 18.99872
Where: OCC = station occupied OBS = station observed VER = vertical angle (radians) U, M, L = upper, middle, lower stadia hair reading S = stadia intercept FS = foresight HD = horizontal distance from the center of the instrument to the rod held VD = vertical distance from the instruments horizontal line of sight to apparent position of the horizontal cross hair on the rod held HI (meas) = height of instrument measured
160
Equations used: HD = Ks cos 2 * VD = Ks cos sin * *K = 100, stadia interval factor of the instrument HI = Elevation + BS Elevation = HI - FS
Please answer YES or NO. 1. Is it hard to get on a public vehicle along the road? (In terms of waiting time and comfort.) 2. Is the area (near the municipal hall) where the tricycles gather destructs the highway? 3. Do you find it unsafe to wait along the road for buses? 4. If there is a terminal, are you willing to go there to get a bus ride? 5. Are you in favor of having a terminal for buses, PUJs, PUVs, and tricycles here in Barbaza?
Statistical Average
Modal approach of statistical average considers the response of the person as either yes or no depending on the majority of his/her response to the set of questions. CENTRAL PHILIPPINE UNIVERSITY COLLEGE OF ENGINEERING Jaro, Iloilo City
Palihog sabat OO ukon INDI. 1. Budlay bala magsakay sa kilid dalan? 2. Ang kadya nga lugar nga ginatambayan ka mga tricycles (rapit sa munisipyo) gapagutok sa ginagamit nga dalan? 3. Delikado bala para sa imu maghulat sa kilid dalan para magsakay sang bus? 4. Willing bala kamu magkadto sa terminal para magsakay bus? 5. Pabor bala kamu magpatindog sang terminal para sa lain-lain nga salakyan (jeep, tricycle, vans, bus) diri sa Barbaza?
165
Results show that 80% of the population of Barbaza is in favor of constructing the proposed terminal.
Average Results for 5 questions TOTAL Responses TOTAL Yes No f % f % f % Drivers 19 76% 6 24% 25 50% Passengers 21 84% 4 25% 25 50% TOTAL 40 80% 10 20% 50 100%
Individual Results (Question 1) Question 1 Responses TOTAL Yes No f % f % f % Drivers 19 76 6 24 25 50% Passengers 21 84 4 16 25 50% TOTAL 40 80 10 20 50 100%
Individual Results (Question 2) Question 2 Responses TOTAL Yes No f % f % f % Drivers 16 64 9 36 25 50% Passengers 15 60 10 40 25 50% TOTAL 31 62 19 38 50 100%
166
Individual Results (Question 3) Question 3 Responses TOTAL Yes No f % f % f % Drivers 18 72 7 28 25 50% Passengers 19 76 6 24 25 50% TOTAL 37 74 13 26 50 100%
Individual Results (Question 4) Question 4 Responses TOTAL Yes No f % f % f % Drivers 24 96 1 4 25 50% Passengers 21 84 4 16 25 50% TOTAL 45 90 5 10 50 100%
Individual Results (Question 5) Question 5 Responses TOTAL Yes No f % f % f % Drivers 25 100 0 0 25 50% Passengers 24 96 1 4 25 50% TOTAL 49 98 1 2 50 100%