IPP Project Total E&P Indonesie Area.

Location Area. PPA area for install Metering skid and Pig launcher complete with all piping and structure PPA Technical Building or install Metering Panel, Shutdown system and Process control.

IPP Project Total E&P Indonesie Area.


Overall Progress. Progress installation on PPA area are 70%. Job has done: Installation Pig launcher Pipe line from TEPI to IPP Pamedas. Some Piping and structure . Tie in Point for gas supply. Electrical and Instrument cable has been pulled.

IPP Project Total E&P Indonesie Area.


Continue. Pigging FCG and IP. Remaining Job. Hydrotest. Up load program PCS (process control system and SSS (safety shutdown system). Electrical Power supply tie in. Install Metering skid. Welding remaining Piping work.

IPP Project Total E&P Indonesie Area.


Continue. PAGA installation. Installation ESDV valve and manual Valve. Pre-commissioning and Commissioning.

IPP Project Total E&P Indonesie Area.


Docummentation. Pre-commissioning dossier has been created. Tie in Procedure has been ready. Operguide Procedure for piping tie-in has been created.

IPP Project Total E&P Indonesie Area


METERING PIG LAUNCHER

IPP Project Area - PPA

IPP Project Total E&P Indonesie Area.

Tie in gas supply for Metering to IPP Pemedas

IPP Project Total E&P Indonesie Area.

Pig Launcher at PPA Area and venting system

IPP Project Total E&P Indonesie Area.

Pipeline at PPA Area to IPP Pemedas 5 km

IPP Project Total E&P Indonesie Area.

E&I work at IT Room

IPP Project Total E&P Indonesie Area.