CHAPTER ONE
INTRODUCTION
The ability of the human race to develop sources of energy needed to accomplish useful work has played an essential
role in the continual improvement in the standard of living of societies around the globe. The use of energy can be seen
in everyday devices such as home appliances and machinery. Energy consumption in homes and industries increased
beyond the point where useful forms of energy could be produced at the locations at which energy was being used.
Hence, centralised energy processing and generating stations, together with elaborate transmission and distribution
systems, were developed and the electric power system emerged as a tool for converting and transmitting energy. Energy
is converted from its basic source, such as fossil fuel or hydro, into electric energy at places remote from population
centres. Then the electric energy is sent over transmission and distribution systems to various locations, where it is
converted to light, heat, and mechanical energy.
An electric power system is designed to generate, control, dispatch and distribute electrical energy to consumers
economically and with minimum ecological disturbance and to transfer this energy over transmission lines and
distribution networks with maximum efficiency and reliability to deliver to consumers at virtually fixed voltage and
frequency.
Chapter two describes the typical structure of power systems as well the principles of bulk power generation. In chapter
three an overview of the principles of power systems analysis is presented. Chapter four explains the need for power
factor correction and the principle techniques available for doing so. Computations of the required rating of power factor
correction gear are illustrated with several examples.
Chapter five presents electrical load characteristics and some aspects of power station operating economics. Chapter six
presents some of the common techniques for pricing the cost of generating and delivering electrical energy to consumers
of electricity. Chapter seven expounds on the essentials of power flow analysis. Finally chapter eight introduces the
essential features of power system protection
2
CHAPTER TWO
POWER SYSTEM STRUCTURE AND POWER GENERATION
2.1 Introduction
Electric energy is produced in large quantities at various electric power plants by converting different forms of energy-
fossil fuels, nuclear energy, water power, etc. Electric energy is transformed by the use of transformers to different
voltage levels most suitable for transmission, distribution and consumption.
Electric power is transmitted using overhead or cable lines to customers at varied distances from its sources. Electric
energy is utilized by various conversion devices such as electric motors, electric ovens, lighting systems, air condition
units, etc. The need for power transmission lines arises from the fact that bulk electric power generation is done at
electric power plants remote from consumers. However, consumers require small amounts of energy and they are
scattered over wide areas. Thus the transmission of energy over a distance offers a number of advantages such as the
following:
1. Use of remote energy sources.
2. Reduction of the total power reserve of generations
3. Utilization of the time difference between various time zones when the peak demands are not coincidence.
4. Improved reliability of electric power supply.
The different power stations located in different geographical locations are interconnected by transmission lines thereby
forming a power system network usually referred to as the GRID. This chapter presents an overview of the power system
structure and principles of power generation.
For economical and technological reasons, individual power systems are organized in the form of electrically connected
areas or regional grids (also called power pools). Each area or regional grid operates technically and economically
independently, but these are eventually interconnected* to form a national grid (which may even form an international
grid) so that each area is contractually tied to other areas in respect to certain generation and scheduling features. Nigeria
has a 330kV national grid.
The location of hydro power stations is determined by the natural water power sources. The choice of site for fossil-fuel
fired thermal stations is more flexible. The following two alternatives are possible.
1. Power stations may be built close to sources of fossil fuel (coal mines or petroleum refineries) and electric
energy is evacuated over transmission lines to the load centres.
2. Power stations may be built close to the load centres and coal is transported to them from the mines by rail road.
In practice, however, power station location will depend upon many factors—technical, economical and environmental.
As it is considerably cheaper to transport bulk electric energy over extra high voltage (EHV) transmission lines than to
transport equivalent quantities of gas or oil over rail road, the recent trend is to build super (large) thermal power stations
near sources of natural gas. Bulk power can be transmitted to fairly long distances over transmission lines of 400kV and
above. However, the Nigeria’s gas resources are located mainly in the southern belt and some thermal power stations
will continue to be sited in distant western and southern regions.
3
As nuclear stations are not constrained by the problems of fuel transport and air pollution, a greater flexibility exists in
their location, so that these stations are located close to load centres while avoiding high density pollution areas to reduce
the risks, however remote, of radio-activity leakage.
In Nigeria, as of now, the largest fraction of electric power used is generated in thermal plants. The remaining smaller
fraction comes from hydro stations. Oil/natural gas is the fuel for most of the steam plants; the rest depends upon hydro
and coal.
Electric power is generated at a voltage of 11 to 25kV which then is stepped up to the transmission levels in the range of
66 to 330kV (or higher). As the transmission capability of a line is proportional to the square of its voltage, research is
continuously being carried out to raise transmission voltages. Some countries are already employing 765kV. The
voltages are expected to rise to 1200kV in the near future.
For very long distances (over 600km), it is economical to transmit bulk power by DC transmission. It also obviates some
of the technical problems associated with very long distance AC transmission. The DC voltages used are 400kV and
above, and the line is connected to the AC systems at the two ends through a transformer and converting/inverting
equipment (silicon controlled rectifiers are employed for this purpose). Several DC transmission lines are in use in
Congo, India, Europe and the U.S.A.
The first stepdown of voltage from transmission level is at the bulk power substation, where the reduction is to a range of
33 to 132kV, depending on the transmission line voltage. Some industries may require power at these voltage levels.
This stepdown is from the transmission and grid level to subtransmission level.
The next stepdown in voltage is at the distribution substation. Normally, two distribution voltage levels are employed:
1. The primary or feeder voltage (11kV)
2. The secondary or consumer voltage (415 V three phase/ 230 V single phase).
The distribution system, fed from the distribution transformer stations, supplies power to the domestic, or industrial and
commercial consumers. Thus, the power system operates at various voltage levels separated by transformers. Fig 2.2
illustrates the Nigerian power system structure.
4
Fig 2.2 The Nigerian power system structure
The efficiency of the overall conversion process is poor and its maximum value is about 40% because of the high heat
losses in the combustion gases and the large quantity of heat rejected to the condenser which has to be given off in
cooling towers or into a stream/lake in the case of direct condenser cooling. The team power station operates on the
Rankine cycle, modified to include superheating, feed-water heating and steam reheating. The thermal efficiency
(conversion of heat to mechanical energy) can be increased by using steam at the highest possible pressure and
temperature. With steam turbines of this size, additional increase in efficiency is obtained by reheating the steam after it
has been partially expanded by an external heater. The reheated steam is then returned to the turbine where it is expanded
through the final states of bleeding.
To take advantage of the principle of economy of scale (which applies to units of all sizes), the present trend is to go in
for larger sizes of units. Larger units can be installed at much lower cost per kilowatt. They are also cheaper to operate
because of higher efficiency. They require lower labour and maintenance expenditure. There may be a saving of as high
as 15% in capital cost per kilowatt by going up from a 100 to 250MW unit size and an additional saving in fuel cost of
about 8% per kWh. Since larger units consume less fuel per kWh, they produce less air, thermal and waste pollution, and
this is a significant advantage in our concern for environment. The only trouble in the case of a large unit is the
tremendous shock to the system when outage of such a large capacity unit occurs. This shock can be tolerated so long as
this unit size does not exceed 10% of the on-line capacity of a large grid.
5
Fig. 2.3 Schematic diagram of a coal fired steam plant
Today’s maximum generator unit size is (nearly 1200MW) limited by the permissible current densities used in rotor and
stator windings. Efforts are on to develop super conducting machines where the winding temperatures will be nearing
absolute zero. Extreme high current and flux densities obtained in such machines could perhaps increase unit sizes to
several GWs which would result in better generating economy.
Air and thermal pollution is always present in a coal fired steam plant. The air polluting agents (consisting of particulates
and gases such as NOX, oxides of sulphur, etc.) are emitted via the exhaust gases and thermal pollution is due to the
rejected heat transferred from the condenser to cooling water. Cooling towers are used in situations where the
stream/lake cannot withstand the thermal burden without excessive temperature rise. The problem of air pollution can be
minimized through scrubbers and precipitators and by resorting to minimum emission dispatch and passing Clean Air
Act like that passed in USA in the 1970s.
Fluidized-bed Boiler
The main problem with coal is its high ash content (up to 40% max). To solve this, fluidized-bed combustion technology
is being developed and perfected. The fluidized-bed boiler is undergoing extensive development and is being preferred
due to its lower pollutant level and better efficiency. Direct ignition of pulverized coal is being introduced but initial oil
firing support is needed.
Cogeneration
Considering the tremendous amount of waste heat generated in thermal power generation, it is advisable to save fuel by
the simultaneous generation of electricity and steam (or hot water) for industrial use or space heating. Now called
cogeneration, such systems have long been common, here and abroad. Currently, there is renewed interest in these
because of the overall increase in energy efficiencies which are claimed to be as high as 65%
Cogeneration of steam and power is high energy efficient and is particularly suitable for chemicals, paper, textiles, food,
fertilizer and petroleum refining industries. Thus, these industries can solve energy shortage problem in a big way.
Further, they will not have to depend on the grid power which is not so reliable. Of course they can sell the extra power
to the government for use in deficient areas. They may also sell power to the neighbouring industries, a concept called
wheeling power.
There are two possible ways of cogeneration of heat and electricity: (i) Topping cycle (ii) Bottoming cycle. In the
topping cycle, fuel is burnt to produce electrical and mechanical power and the waste heat from the power generation
provides the process heat. In the bottoming cycle, fuel first produces process heat and the waste heat from the processes
is then used to produce power.
Coal-fired plants share environmental problems with some other types of fossil-fuel plants; these include “acid rain” and
the “greenhouse” effect.
6
the heavy civil engineering construction works involved. Also it requires a long gestation period of about five to eight
years as compared to four to six years for steam plants. Hydroelectric stations are designed, mostly, as multipurpose
projects such as river flood control, storage of irrigation and drinking water, and navigation. A simple block diagram of a
hydro plant is given in Fig. 2.4. The vertical difference between the upper reservoir and tail race is called the head.
Hydro plants are of different types such as run-of-river (use of water as it comes), pondage (medium head) type, and
reservoir (high head) type. The reservoir type plants are the ones which are employed for bulk power generation. Often,
cascaded plants are also constructed, i.e., on the same water stream where the discharge of one plant becomes the inflow
of a downstream plant.
Different types of turbines such as Pelton, Francis and Kaplan are used for storage, pondage and run-of-river plants,
respectively. Hydroelectric plants are capable of starting quickly—almost in five minutes. The rate of taking up load on
the machine is of the order of 20 MW/min. Further, no losses are incurred at standstill. Thus, hydro plants are ideal for
meeting peak loads. The time from start up to the actual connection to the grid can be as short as 2 min.
In areas where sufficient hydro generation is not available, peak load may be handled by means of pumped storage. This
consists of an upper and lower reservoirs and reversible turbine-generator sets, which can also be used as motor-pump
sets. The upper reservoir has enough storage for about six hours of full load generation. Such a plant acts as a
conventional hydro plant during the peak load period, when production costs are the highest. The turbines are driven by
water from the upper reservoir in the usual manner.
During the light load period, water in the lower reservoir is pumped back into the upper one so as to be ready for use in
the cycle of the peak load period. The generators in this period change to synchronous motor action and drive the
turbines which now work as pumps. The electric power is supplied to the sets from the general power network or
adjoining thermal plant. The pumped storage scheme, in fact, is analogous to the charging and discharging of a battery. It
has the added advantage that the synchronous machine can be used as synchronous condensers for VAR compensation of
7
the power network, if required. In a way, from the point of the thermal sector of the system, the pumped storage scheme
“shaves the peaks” and “fills the troughs” of the daily load-demand curve.
When Uranium-235 is bombarded with neutrons, fission reaction takes place releasing neutrons and heat energy. These
neutrons then participate in the chain reaction of fissioning more atoms of 235U. In order that the freshly released
neutrons be able to fission the uranium atoms, their speeds must be reduced to a critical value. Therefore, for the reaction
to be sustained, nuclear fuel rods must be embedded in neutron speed reducing agents (like graphite, heavy water, etc.)
called moderators. For reaction control, rods made of neutron-absorbing material (boron-steel) are used which, when
inserted into the reactor vessel, control the amount of neutron flux thereby controlling the rate of reaction. However, this
rate can be controlled only within a narrow range. The schematic diagram of a nuclear power plant is shown in Fig 2.5.
The heat released by the nuclear reaction is transported to a heat exchanger via primary coolant (CO2, water, etc.).
Steam is then generated in the heat exchanger, which is used in a conventional manner to generate electric energy by
means of a steam turbine. Various types of reactors are being used in practice for power plant purposes, viz., advanced
gas reactor (AGR), boiling water reactor (BWR), heavy water moderated reactor, etc.
The associated merits and problems of nuclear power plants as compared to conventional thermal plants are mentioned
below:
Merits
1. A nuclear power plant is totally free from Air pollution.
2. It requires little fuel in terms of volume and weight, and therefore poses no transportation problems and may be
sited, independently of nuclear fuel supplies, close to load centres. However, safety consideration requires that
they be normally located away from populated areas.
Problems
1. Nuclear reactors produce radioactive fuel waste, the disposal of which poses serious environmental hazards.
2. The rate of nuclear reaction can be lowered only by a small margin, so that the load on a nuclear power plant
can only be permitted to be marginally reduced below its full load value. Nuclear power stations must,
therefore, be reliably connected to a power network, as tripping of the lines connecting the station can be quite
serious and may require shutting down of the reactor with all its consequences.
3. Because of relatively high capital cost as against running cost, the plant should operate continuously as a base
load station. Wherever possible, it is preferable to support such a station with a pumped storage scheme
mentioned earlier.
8
The world uranium resources are quite limited, and at the present rate may not last much beyond 50 years. However,
there is a redeeming feature. During the fission of 235U, some of the neutrons are absorbed by the more abundant uranium
isotope 238U (enriched uranium contains only about 3% of 235U while most of it is 238U) converting it to plutonium (239U),
which in itself is a fissionable material and can be extracted from the reactor fuel waste by a fuel reprocessing plant.
Plutonium would then be used in the next generation reactors (fast breeder reactors—FBRs), thereby considerably
extending the life of nuclear fuels. The FBR technology is been intensively developed it will extend the availability of
nuclear fuels at predicted rates of energy consumption to several centuries.
Figure 2.5 shows the schematic diagram of an FBR. It is essential that for breeding operation, conversion ratio (fissile
material generated/fissile material consumed) has to be more unity. This is achieved by fast moving neutrons so that no
moderator is needed. The neutrons do slow down a little through collisions with structural and fuel elements. The energy
density/kg of fuel is very high and so the core is small. It is therefore necessary that the coolant should possess good
thermal properties and hence liquid sodium is used. The fuel for an FBR consists of 20% plutonium plus 8% uranium
oxide. The coolant liquid sodium leaves the reactor at 650oC at atmospheric pressure. The heat so transported is led to a
secondary sodium circuit which transfers it to a heat exchanger to generate steam at 540oC.
With a breeder reactor release of plutonium, an extremely toxic material, would make the environmental considerations
most stringent.
Typical power densities (MW/m3) in fission reactor cores are: gas cooled 0.53, high temperature gas cooled 7.75, heavy
water 18.0, boiling water 29.0, pressurized water 54.75, fast breeder reactor 760.0.
Fusion
Energy is produced in this process by the combination of two light nuclei to form a single heavier one under sustained
conditions of extremely high temperatures (in millions of degree centigrade). Fusion is futuristic. Generation of
electricity via fusion would solve the long term energy needs of the world with minimum environmental problems. A
commercial reactor is expected by 2000 AD. Considering radioactive wastes, the impact of fusion reactors would be
much less than the fission reactors.
In case of success in fusion technology sometime in the distance future or a break through in the pollution-free solar
energy, FBRs would become obsolete. However, there is an intense need today to develop FBR technology as an
insurance against failure to develop these two technologies.
In the past few years, serious doubts have been raised about the safety claims of nuclear power plants. There have been
as many as 150 near disaster nuclear accidents from the Three-mile accident in USA to the recent Chernobyl accident in
the former USSR. There is a fear that all this may put the nuclear energy development in reverse gear. If this happens
9
there could be serious energy crisis in the third world countries which have pitched their hopes on nuclear energy to meet
their burgeoning energy needs. France and Canada are possibly the two countries with a fairly clean record of nuclear
generation.
In a MHD generator, electrically conducting gas at a very high temperature is passed in a strong magnetic field, thereby
generating electricity. High temperature is needed to ionize the gas, so that it has good electrical conductivity. The
conducting gas is obtained by burning a fuel and injecting a seeding material such as potassium carbonate in the product
of combustion. The principle of MHD power generation is illustrated in Fig. 2.6. About 50% efficiency can be achieved
if the MHD generator is operated in tandem with a conventional steam plant.
Though the technological feasibility of MHD generation has been established, its economic feasibility is yet to be
demonstrated. India had started a research and development project in collaboration with the former USSR to install a
pilot MHD plant based on coal and generating 2 MW power. In Russia, a 25 MW MHD plant which uses natural gas as
fuel has been in operation for some years.
There are currently many installations in the world with 100 MW generators. Recently a 6 x 30 MW gas turbine station
has been put up in Delhi. A gas turbine unit can also be used as synchronous compensator to help maintain flat voltage
profile in the system.
10
The present installed geothermal plant capable in the world is about 500 MW and the total estimated capacity is only
about 2000 MW. Since the pressure and temperatures are low, the efficiency is even less than the conventional fossil
fuelled plants, but the capital cost are less and the fuel is available free of cost.
2.4.2 Wind Power Stations
Winds are essentially created by the solar heating of the atmosphere. Several attempts have been made since 1940 to use
wind to generate electric energy and development is still going on. However, techno-economic feasibility has yet to be
satisfactorily established.
Wind as a power source is attractive because it is plentiful, inexhaustible and non-polluting. Further, it does not impose
extra heat burden on the environment. Unfortunately, it is non-steady and undependable. Control equipment has been
devised to start the wind power plant whenever the wind speed reaches 30km/h. Methods have also been found to
generate constant frequency power with varying wind speeds and consequently varying speeds of wind mill propellers.
Wind power may prove practical for small power needs in isolated sites. But for maximum flexibility, it should be used
in conjunction with other methods of power generation to ensure continuity.
For a rotor of 17m diameter and a velocity of 48 km/h the theoretical power is 265kW and the practical would be roughly
half of this value.
There are some distinctive energy end-use features of wind power systems:
1. Most wind power sites are in remote rural, island or marine areas.
2. Rural grid systems are likely to be ‘weak’ in these areas, since they carry relatively low voltage supplies (e.g.
33kV).
3. There are always periods without wind.
At present, two technologies are being developed for conversion of solar energy to the electrical form. In one
technology, collectors with concentrators are employed to achieve temperatures high enough (700oC) to operate a heat
engine at reasonable efficiency to generate electricity. However, there are considerable engineering difficulties in
building a single tracking bowl with a diameter exceeding 30m to generate perhaps 200kW. The scheme involves large
and intricate structures involving huge capital outlay and as of today is far from being competitive with conventional
electricity generation.
The solar power tower generates steam for electricity production. There is a 10 MW installation of such a tower by the
Southern California Edison Co. in USA using 1818 plane mirrors, each 7m x 7m reflecting direct radiation to the raised
boiler.
11
Electricity may be generated from a Solar Pond by using a special ‘low temperature’ heat engine coupled to an electric
generator. A solar pond at Ein Borek in Isreal produces a steady 150kW from 0.74 hectare at a busbar cost of about
$0.10/kWh.
Solar power potential is unlimited.
Solar energy could, at the most, supplement up to 5-10% of the total energy demand. It has been estimated that to
produce 1012kWh per year, the necessary cells would occupy about 0.1% of US land area as against highways which
occupy 1.5% (in 1975) assuming 10% efficiency and a daily insolation of 4kWh/m2.
In all solar thermal schemes, storage is necessary because of the fluctuating nature of sun’s energy. This is equally true
with many other unconventional sources as well as sources like wind. Fluctuating sources with fluctuating loads
complicate still further the electricity supply.
12
CHAPTER THREE
FUNDAMENTAL THEORY
3.1 INTRODUCTION
The main components that make up a power system are generating sources, transmission and distribution networks, and
loads. For the purpose of analysis, the power system is treated as a network of circuit elements contained in branches
radiating from nodes to from closed loops or meshes. The system variables are current and voltage, and in steady state
analysis, they are regarded as time varying quantities at a single and constant frequency. The network parameters are
impedance and admittance; these are assumed to be linear, bilateral (independent of current direction) and constant for a
constant frequency. The analysis of electric power systems involves the study of the performance of the system under
both normal and abnormal conditions. Such analysis considers single phase and three phase circuits. This chapter deals
with steady state ac (alternating current) analytical techniques.
It may be resolved into two components at right angles to each other, in this case x and y. The magnitude or scalar value
of vector Z is known as the modulus or amplitude, Z and the angle θ is the argument, and is written as arg Z . The
conventional method of expressing a vector Z is to write simply: Z ∠ θ.
This form completely specifies a vector for graphical representation or conversion into other forms.
For vectors to be useful, they must be expressed algebraically. In figure 3.1, the vector Z is the resultant of vectorially
adding its components x and y; algebraically this vector may be written as:
Z = x + jy (3.1)
where the operator j indicates that the component y is perpendicular to component x. In electrical nomenclature, the axis
OX is the ‘real’ or ‘in-phase’ axis, and the vertical axis OY is called the ‘imaginary’ or ‘quadrature’ axis. The operator j
rotates a vector anti-clockwise through 90o. If the vector is made to rotate anti-clockwise through 180o, then the operator
j has performed its function twice, and since the vector has reversed its sense, then:
j x j or j2 = -1
Hence, j = − 1 .
When a vector quantity is expressed in terms of its rectangular co-ordinates it is called a ‘complex quantity’. Therefore, x
+ jy is a complex quantity and is the rectangular form of the vector Z ∠ θ where:
13
Z = (x 2 + y 2 ) ⎫
⎪
y ⎪
θ = tan ⎪
x ⎬ (3.2)
x = Z cos θ ⎪
⎪
y = Z sin θ ⎪⎭
From equations (3.1) and (3.2):
Z = Z (cos θ + j sin θ ) (3.3)
and since cosθ and sinθ may be expressed in exponential form by the identities:
e jθ − e − jθ e jθ − e − jθ
sinθ = and cosθ =
2j 2
it follows that Z may also be written as:
Z = Z e jθ (3.4)
Therefore, a vector quantity may also be represented trigonometrically and exponentially.
14
Given a complex quantity Z=X+jY the complex conjugate of Z is denoted by Z* and is obtained by changing the sign of
the imaginary part of Z, i.e, Z*=X-jY.
EXAMPLE:
Determine the rate of change of the real component of vector Z ∠ (ωt) with
time.
Solution
The vector is given as:
Z ∠(ωt ) = Z (cosωt + jsinωt)
= Z ejωt
The real component of the vector is Z cosωt.
Thus, the rate of change of the real component of the vector Z ∠ωt is:
- Z ωsinωt
3.3.2 Complex Numbers
A complex number may be defined as a constant that represents the real and imaginary components of a physical
quantity. The impedance parameter of an electric circuit is a complex number having real and imaginary components,
which are described as resistance and reactance, respectively.
Confusion often arises between vectors and complex numbers. A vector, as previously defined, may be complex number.
In this context, it is simply a physical quantity of constant magnitude acting in a constant direction. A complex number
that is a physical quantity relating stimulus and response in a given operation is known as a ‘complex operator’. In this
context, it is distinguished from a vector by the fact that it has no direction of its own.
Because complex numbers assume a passive role in any calculation, the form taken by the variables in the problem
determines the method of representing them.
15
Mathematical operators are complex numbers that are used to move a vector through a given angle without changing the
magnitude or character of the vector. An operator is not a physical quantity; it is dimensionless.
The symbol j, which has been compounded with quadrature components of complex quantities, is an operator that rotates
a quantity anti-clockwise through 90o. Another useful operator is one which moves a vector anti-clockwise through 120o,
commonly represented by the symbol a.
Operators are distinguished by one further feature; they are the roots of unity. Using De Moivre’s theorem, the nth root of
unity is given by solving the expression:
11 / n = (cos 2 π m + j sin 2 π m)1 / n
where m is any integer.
Hence:
2π m 2π m
11 / n = cos + j sin
n n
where m has values 1,2,3,… (n-1)
From the above expression j is found to be the 4th root and a the 3rd root of unity, as they have four and three distinct
values, respectively. Some useful functions of the a operator are listed below:
2π
1 3 j
a=− + j =e 3
2 2
4π
1 3 j
a2 = − − j =e 3
2 2
1=1 + j0 = ej0
1 + a + a2 = 0
2
1 – a = j 3a
1 – a2 = - j 3a
a – a2 = j 3
a − a2
j=
3
When a circuit exists, there is an interchange of energy; a circuit may be described as being made up of ‘sources’ and
‘sinks’ for energy. The parts of a circuit are described as elements; a ‘source’ may be regarded as an ‘active’ element and
a ‘sink’ as a ‘passive’ element. Some circuit elements are dissipative, that is, they are continuous sinks for energy, for
example, resistance. Other circuit elements may be alternately sources and sinks, for example, capacitance and
inductance. The elements of a circuit are connected together to form a network having nodes (terminals or junctions) and
branches (series groups of elements) that form closed loops (meshes).
In steady state ac circuit theory, the ability of a circuit to accept a current flow resulting from a given driving voltage is
called the impedance of the circuit. Since current and voltage are duals the impedance parameter must also have a dual,
called admittance.
16
For example, the instantaneous value, e, of a voltage varying sinusoidally with time is expressed mathematically as:
e = E m sin( wt + δ ) (3.8)
where:
Em is the maximum amplitude of the waveform;
ω = 2πf, the angular velocity in rad/s.
δ is the argument defining the amplitude of the voltage at a time t = 0
f is the frequency in hertz (Hz)
At t = 0, the actual value of the voltage is Emsinδ. So if Em is regarded as the modulus of a vector, whose argument is δ,
then Emsinδ is the imaginary component of the vector E m ∠δ . Figure 3.3 illustrates this quantity as a vector and as a
sinusoidal function of time.
The current resulting from applying a voltage to a circuit depends upon the circuit impedance. If the voltage is a
sinusoidal function at a given frequency and the impedance is constant the current will also vary harmonically at the
same frequency, so it can be shown on the same vector diagram as the voltage vector, and is given by the equation
Em
i= (3.9)
Z sin(wt + δ − φ )
where:
⎫
Z = R2 + X 2 ⎪
⎪
⎛ 1 ⎞⎪
X = ⎜ ωL − ⎟⎬ (3.10)
⎝ ωC ⎠⎪
X ⎪
φ = tan −1 ⎪
R ⎭
From equations (3.9) and (3.10) it can be seen that the angular displacement φ between the current and voltage
vectors and the circuit magnitude I m = E m ⁄ Z is dependent upon the impedance Z . In complex form the impedance
may be written as Z = R + jX . The ‘real component’, R, is the circuit resistance, and the ‘imaginary component’, X, is
1
the circuit reactance. When the circuit reactance is inductive (that is, ωL > ), the current ‘lags’ the voltage by an
ωC
1
angle φ, and when it is capacitive (that is, ωL < ) it ‘leads’ the voltage by an angle φ.
ωC
When drawing phasor diagrams, one phasor is chosen as the ‘reference’ and all other phasors are drawn relative to the
reference phasor in terms of magnitude and angle. The circuit impedance Z is a complex operator and is distinguished
from a phasor only by the fact that it has no direction of its own.
17
A further convention is that sinusoidally varying quantities are described by their ‘effective’ or ‘root-mean-square’ (rms)
values; these are usually written using the relevant symbol without a suffix.
Thus,
Im ⎫
I= ⎪
2 ⎪
⎬ (3.11)
Em ⎪
E=
2 ⎪⎭
The ‘root-mean-square’ value is that value which has the same heating effect as a direct current quantity of that value in
the same circuit, and this definition applies to non-sinusoidal as well as sinusoidal quantities.
Voltage rise is a rise in potential measured in the direction of current flow between two points in a circuit. Voltage drop
is the converse. A circuit element with a voltage rise across it acts as a source of energy. A circuit element with a voltage
drop across it acts as a sink of energy. Voltage sources are usually active circuit elements, while sinks are usually passive
circuit elements. The positive direction of energy flow is from sources to sinks.
Kirchhoff’s first law states that the sum of the driving voltages must equal the sum of the passive voltages in a closed
loop. This is illustrated by the fundamental equation of a series RLC circuit:
di 1
dt C ∫
iR + L + idt = e (3.12)
where the terms on the left-hand side of the equation are voltage drops across the circuit elements and the term on the
right-hand side is the driving voltage (i.e. source voltage). Expressed in steady state terms equation (3.12) may be written
as:
∑E = ∑IZ (3.13)
It is the equation most usually adopted in electrical network calculations, since it equates the driving voltages, which are
known, to the passive voltages, which are functions of the currents to be calculated.
In describing circuits and drawing phasor diagrams, for formal analysis or calculations, it is necessary to adopt a notation
which defines the positive direction of assumed current flow, and establishes the direction in which positive voltage
drops and voltage rises act. Two methods are available; one, the double suffix method, is used for symbolic analysis, the
other, the single suffix or diagrammatic method, is used for numerical calculations.
In the double suffix method the positive direction of current flow is assumed to be from node a to node b and the current
is designated Iab.With the diagrammatic method, an arrow indicates the direction of current flow.
The voltage rises are positive when acting in the direction of current flow. It can be seen from figure 3.4 that E 1 and
E an are positive voltage rises and E 2 and E bn are negative voltage rises. In the diagrammatic method their direction
of action is simply indicated by an arrow, whereas in the double suffix method, E an and E bn indicate that there is a
potential rise in directions na and nb.
18
Fig 3.4 Methods of representing a circuit
Voltage drops are also positive when acting in the direction of current flow. From figure 3.4 (a) it can be seen that
( Z 1 + Z 2 + Z 3 ) I is the total voltage drop in the loop in the direction of current flow, and must equate to the total
voltage rise, E 1 − E 2 . In figure 3.4 (b), the voltage drop between nodes a and b, designated V ab , indicates that point b
is at a lower potential than a, and is positive when current flows from a to b. Conversely V ba is a negative voltage drop.
Symbolically:
V ab = V an − V bn ⎫⎪
⎬ (3.14)
V ba = V bn − V an ⎪⎭
where n is a common reference point.
If the same current I passes through a pure inductance L, the voltage drop across the inductor is given by
19
di
v=L
dt
= ωLI m cos ωt
= ωLI m sin(ωt + 90 0 )
Thus for an inductor, the current phasor lags the voltage phasor by 90o.
If the same current passes through a pure capacitor, the voltage drop across the capacitor is given by
1
C∫
v= idt
1
= ∫ I m sin ωtdt
C
1
=− I cos ωt
ωC m
1
= I m sin(ωt − 90 0 )
ωC
Thus the current phasor leads the voltage phasor by 90ofor a capacitor
WORKED EXAMPLE:
A 2.5hp motor operates on an efficiency of 75%. What is the power drawn from the supply in watts. If the input current is
10.8A what is the supply voltage?
1hp = 746W
Solution
20
Po 2.5 × 746
η= × 100 ⇒ 0.75 = ⇒ Pi = 2486.7
Pi Pi
P 2486.7
V= = = 230V
I 10.8
The product of the potential difference across and the current through a branch of a circuit is a measure of the rate at
which energy is exchanged between that branch and the remainder of a circuit. If the potential difference is a positive
voltage drop, the branch is passive and absorbs energy. Conversely, if the potential difference is a positive voltage rise,
the branch is active and supplies energy.
The rate at which energy is exchanged is known as power, and by convention, the power is positive when energy is being
absorbed and negative when being supplied. With ac circuits the power alternates, so, to obtain a rate at which energy is
supplied or absorbed, it is necessary to take average power over one whole cycle.
If the voltage
v = Vmcos(ωt + θv)
and the current
i = Imcos(ωt + θi),
then the instantaneous power is given by:
p = vi = Vm I m cos(ωt + θ v ) cos(ωt + θ i )
1
Using the trigonotry identity, cos A cos B = [cos( A − B ) + sin( A + B ) , results in
2
1
p = Vm I m [cos(θ v − θ i ) + cos(2ωt + θ v − θ i )]
2
1
= Vm I m {cos(θ v − θ i ) + cos[2(ωt + θ v ) − (θ v − θ i )]}
2
1
= Vm I m [cos(θ v − θ i ) + cos 2(ωt + θ v ) cos(θ v − θ i ) + sin 2(ωt + θ v ) sin(θ v − θ i )]
2
Thus the instantaneous power is
p = P[1+cos2(ωt + θv)] + Qsin2(ωt + θv) (3.15)
where:
P = VI cos θ , is the real or active power absorbed by the circuit.
Q = VI sin θ , is the reactive power borrowed and returned by the circuit.
θ =θv-θi, is the angle between voltage and current, or the impedance angle.
V =Vm/ 2 is the rms voltage and I is the rms current
From equation (3.15) it can be seen that the quantity P varies from 0 to 2P and quantity Q varies from –Q to +Q in one
cycle, and that the waveform is of twice the periodic frequency of the current voltage waveform.
The average value of the power exchanged in one cycle is a constant, equal to quantity P, and as this quantity is the
product of the voltage and the component of current which is ‘in phase’ with the voltage it is known as the ‘real’ or
‘active’ power.
The average value of quantity Q is zero when taken over a cycle, suggesting that energy is stored in one half-cycle and
returned to the circuit in the remaining half-cycle. Q is the product of voltage and quadrature component of current, and
is known as ‘reactive power’.
Expressing the rms voltage and current phasors in polar form as: V = V ∠θ v and I = I ∠θ i then the
expression VI* yields
21
VI * = V I ∠(θ v − θ i ) = V I ∠θ
= V I cos φ + j V I sin θ
(3.16)
∴ S = VI * = P + jQ
The quantity S is described as the ‘apparent power’, and is the term used in establishing the rating of a circuit or power
equipment. The unit of apparent power, S , is the volt-ampere (VA) and the larger units are kVA (103VA) or
MVA(106VA). The SI unit for real power P is the watt (W) and the larger units are kW (103W) or MW (106W). The unit
for reactive power Q is the volt-ampere reactive (VAr). Its larger versions are kVAr (103VAr) or MVAr (106VAr).
The reactive power Q is positive when the phase angle θ between voltage and current (impedance angle) is positive (i.e.,
when the load impedance is inductive and I lags V). Q is negative when θ is negative (i.e., when the load impedance is
capacitive and I leads V).
Based on eqn (3.16) it is convenient to think of P, Q, and S as forming the sides of a right triangle, referred to as the
power triangle. This is illustrated in Fig 3.5
In this case the voltage is leading the current by ϕ degrees (radians) or the current is lagging the voltage by ϕ degrees
(radians). In terms of power factor (pf) we say that:
1. pf is lagging when current is lagging behind voltage (as in inductive ccts)
2. pf is leading when current is leading voltage (as in capacitive ccts).
Apparent power, S = VI = P2 + Q2 = I 2Z
Hence, power factor
pf = cos ϕ
⎡ ⎛ Q ⎞⎤
= cos ⎢ tan −1 ⎜ ⎟⎥
⎣ ⎝ P ⎠⎦
⎡ ⎛ X ⎞⎤
= cos ⎢ tan −1 ⎜ L ⎟⎥
⎣ ⎝ R ⎠⎦
22
phase source is a source containing three alternating driving voltages that are assumed to reach a maximum in phase
sequence; red (R), yellow (Y), blue (B). The positive phase sequence is RYB, whereas the negative phase sequence is
RBY.
Phase sequence
Each phase driving voltage is associated with a phase branch of the system network as shown in figure 3.5(a). If a
polyphase system has balanced voltages, that is, equal in magnitude and reaching a maximum at equally displaced time
intervals, and the phase branch impedances are identical, it is called a ‘balanced’ system. It will become ‘unbalanced’ if
any of the above conditions are not satisfied. Calculations using a balanced polyphase system are simplified, as it is only
necessary to solve for a single phase, the solution for the remaining phases being obtained by symmetry.
The power system is normally operated as a three-phase, balanced, system. For this reason the phase voltages are equal
in magnitude and can be represented by three vectors spaced 120o (or 2π ⁄ 3 radians) apart, as shown in figure 3.5(b).
Since the voltages are symmetrical, they may be expressed in terms of one, that is:
E r = E r = E sin ωt ⎫
⎪⎪
E y = a 2 E r = E sin(ωt − 120 o )⎬ (3.17)
⎪
E b = aE r = E sin(ωt + 120 o ) ⎭⎪
where a is the vector operator ej2π ⁄ 3. Further, if the phase branch impedances are identical in a balanced system, it
follows that the resulting currents are also balanced.
23
In a Y-connected circuit the phase voltages are measured between the lines and the neutral or star point: so we have
VRN (red phase voltage), VYN (yellow phase voltage) and VBN (blue phase voltage). The line voltages are measured
between the lines R, Y, and B: so we have VRY (voltage between red and yellow lines), VYB (voltage between yellow
and blue lines) and VBR (voltage between blue and red lines). The phase currents are IR, IB and IY
Fig. Line current, phase current and phase voltage phasors in a ∆-connected circuit
Let VL denote line voltage, VP phase voltage, IL line current and IP phase current. It is easy to show from appropriate
phasor diagrams that:
For a star-connected 3-phase circuit
• The VP lags VL by 30o
• VL= 3 VP
• IL=IP
For a ∆-connected circuit
• IL lags IP by 30o
• VL=VP
• IL= 3 IP
POWER
Power in a ∆- or Y-connected system is given by
P= 3 VLIL cosφ (Real power)
Q= 3 VLIL sinφ (Reactive power)
where φ = angle between line voltage and current phasors
24
S= P 2 + Q 2 = 3 VLIL (Apparent power)
cosφ is the power factor.
Rating of 3-φ equipment such as generators, motors, transformers or transmission lines are normally given as total or 3-φ
power in MW, or as total apparent power in MVA, along with the line-line voltage in kV.
WORKED EXAMPLE
A generator supplies a load through a feeder whose impedance is Zfdr = 1 + j2Ω, the load impedance is ZL = 8 + j6Ω,
the voltage across the load is 220V. Find the real power and the reactive power supplied by the generator take the load
voltage VL as the reference phasor.
Solution
Zfdr = 1 + 2j = 2.24 ∠ 63.40 Ω
ZL = 8 + j6 = 10 ∠ 36.90 Ω
VL = 220 ∠ 00 V
VL 220∠0 0
∴ IL = = = 22∠ − 36.9 0 A
Z L 10∠36.9 0
= 264 ∠ 4.80
The complex power supplied by the generator is given by
S = Eg Ig *
= (264 ∠ 4.8) x (22 ∠ 36.90)
= 4336.5+j3863.6
= 5,808 ∠41.7 kVA
0
2. Two-wattmeter method: This is employed for both balanced and unbalanced loads.
25
The wattmeter readings are
W1= VLIL cos (30o +φ)
W2= VLIL cos (30o+φ)
P= W1+W2
P= VLIL [cos (30o+φ) + cos (30o-φ)]
P= 3 VLIL cosφ
The difference between the wattmeter readings is
W2-W1= ILVL [cos (30-φ)-cos (30+φ] = VLIL Sinφ
Which is, 1 / 3 times the total 3-φ reactive power. Thus, reactive power, is given by
Q = 3 [W2 – W1]
The power factor is given by
Q
φ = tan-1 [ ]
P
⎡ 3 ( w2 − w1 ) ⎤
-1 ⎢ ⎥
= tan
⎣⎢ w2 + w1 ) ⎦⎥
The power factor is given by
pf = cos(φ)
26
d) Verify that the current in the wire is zero
Solution
a) The phase angles are:
θ2 = -120o
θ3 = +120o or – 240o
b) EL = 3E P
= 3 x 120
= 208V
∴ ERY = EYB = EBR = 208V
c) EP = VP
∴ Vrn = ERN
Vyn = EYN
Vbn = EBN
Vrn 120∠0 o 120∠0 o
Irn = = = = 24∠ − 53.13 o ∆
Z rn 3 + j4 5∠53.13 o
d) KCL yields
IN = Irn + Iyn + Ibn
Irn = 24 ∠ − 53.13 = 14.4 – j19.20
o
9.43 + j22.07
Ibn = 24 ∠66.87 =
o
0 + j0
27
c) Find the magnitude of the line currents
150∠ − 120 o
Ib = = 15∠ − 173.13 o ∆
10∠53.13 o
150∠120 o
Ir = = 15∠66.87 o ∆
10∠53.13 o
c) IL = 3I P
= 3 × 15
= 25.95∆
Since it is a balanced load system,
IR = IY = IB = 25.95∆
WORKED EXAMPLE:
A 500KVA, 6.6kV alternator is ∆-connected. Calculate the current in each phase of the alternator when it delivers its full
output to a balanced 3-φ load at a power factor of 0.8 lagging.
Solution:
Power supplied by the alternator
P = 3V L I L cos ϕ
Power supplied, P = 500 x 0.8 = 400kW
Thus, 400,000 = 3 × 6600 I L × 0.8
28
400,000
∴ IL = = 43.8 A
3 × 6600 × 0.8
For a ∆ connection
IL 43.8
IP = = = 25.3 A
3 3
WORKED EXAMPLE:
A balanced 3-φ load is connected to 2.2 kV feeder. The load draws a line current of 60A at a pf of 0.9 lagging. Calculate
the real, reactive, and apparent power absorbed by the load.
Solution:
VL = 2200V
IL = 60A
P.F = 0.9 lag ⇒ φ = -cos-1(0.9) = -25.8o
P= 3 VLIL cosφ = 205.8kW
Φ= 3 VLIL sinφ = 99.7kVAR
S= 3 VLIL = 228kVA
WORKED EXAMPLE:
A 3-φ, 1.5, kW, unity power factor; heating unit, and a 5 hp induction motor with a full load efficiency of 80% and pf of
0.85 are served from the same 3-ф, 3-wire 208V system. Find the magnitude of the line current for rated output from the
5hp motor. Note that 1 hp = 746W.
Solution:
Motor Output = 5x746=3730W
3730 3730
Motor Input = = = 4662W
η 0.8
The motor is a balanced 3-φ load so that
P= 3 VLILmcos φ
4662 = 3 x 208 x ILm x 0.85
4662
ILm = = 15.25 A
3 × 208 × 0.85
Ф = -cos-1 (0.85) = -31.7o
Hence, the motor line current is ILm = 15.25 ∠ -31.70A
For the heater P = 3 VLILh
1500 = 3 x 208 x ILh
1500
ILh = = 4.16∠0 o A
3 × 208
Therefore, total line current is the phasor sum of motor and the heater line current.
IL = 15.25 ∠ -31.7o + 4.16 ∠ 0o
IL = 18.9 ∠ -25.1oA
WORKED EXAMPLE:
A ∆- connected load consists of three identical impedances of 8+j6Ω each and supplied from a three phase 200V source.
Calculate (a) the power factor (b) the phase current and line current (c) the real, reactive and apparent power taken by
the load.
Solution
(a) Z∆ = 8 + j6 = 10 ∠ 36.9oΩ
29
VL = Vph. = 200 ∠ 0o
Vph 200∠0 o
Iph = =
Z∆ 10∠36.9 o
Iph = 20 ∠ - 36.9o
IL = 3 Iph ∠ (-36.9o-30o) = 34.6 ∠ -66.9oA
30
The mesh equation by inspection is
⎡10∠0 o + 15∠ − 3o − 15∠30 o ⎤ ⎡ I 1 ⎤ ⎡208∠120 o ⎤
⎢ ⎥ ⎢ ⎥ =⎢ ⎥
⎣⎢− 15∠30
o
15∠30 o + 10∠ − 30⎦⎥ ⎣ I 2 ⎦ ⎢⎣208∠0 o ⎦⎥
5210∠90 o
I1 = = 14.15 ∠ 86.1A
367.5∠3.9
3730∠56.6 o
I2 = = 10.15 ∠ 52.7A
367.5∠3.9 o
Line Currents
IR = I1 = 14.5 ∠ 86.1o A
IY = I2 – I1 = 8.0 ∠ -49.5o A
IB = - I2 = - 10.15 ∠ 52.7o or 10.15 ∠ (52.7 – 180o) A
Load Voltage
VRN = IRZR = (14.5 ∠ 86.1)(10 ∠ 0o) 141.5 ∠ 86.1o V
VYN = IYZY = (8 ∠ -49.5o)(15 ∠ 30o) = 120 ∠ -19.5o V
VBN = IBZB = (10.15)(-127.3o)(10 ∠ -30o) = 101.5 ∠ -157.3o V
EXERCISE
1. Each arm of a ∆-connected load consists of resistance of 20Ω in series with an inductive reactance of 34.6Ω.
Two wattmeters are used to measure the power supply to the load from a balanced 415V 3-Φ supply. Calculate
the magnitude of the line and phase currents and the wattmeter readings. Taking as the reference the voltage
between the supply neutral and the line without a wattmeter current coil (line B) .Give the phase angles of all
line and phase currents.
Answer IL = 18A ∠ -30 ∠ -150 ∠ -90. Iph = 10.4A, ∠ -60o ∠ -180o ∠ -60o wattmeter reading WR = 6490W,
WY = 0W
2. A 345kV, 3-φ transmission line delivers 500MVA at 0.868 pf lagging to a 3-φ load connected to the receiving
end terminals. Assume that the load is delta-connected and the voltage at the receiving end is 345kV.
(a) Find the complex load impedance per phase.
(b) Calculate the line and phase currents.
(c) Find the real and reactive power per phase.
(d) Find the total real and reactive power.
31
In the per-unit (pu) notation, any electrical quantity may be expressed in pu as the ratio of the actual quantity and the
chosen base value for the quantity expressed either in decimal form or percent. Four basic quantities must be considered,
namely, power Sb, voltage Vb, current Ib, and impedance Zb.
In single phase systems, the relationships among these quantities are:
Sb = VbIb
Vb = IbZb
With only two equations relating the four basic quantities, it is necessary to specify two base values. The power and
voltage bases are usually chosen equal to the rated value and the other two are computed from the above equations as
follows.
Sb Vb (Vb ) 2 ( KVb ) 2
Ib = Zb = = =
Vb Ib Sb MVAb
The specified power base is applicable to all parts of the power system. The voltage base varies across a transformer and
so do the current base and impedance base. The pu electrical quantities are calculated as follows:
P + jQ
Su = = Pu + jQu pu
Sb
V
Vu = pu
Vb
I
Iu = pu
Ib
Z
Zu = pu
Zb
32
MVA b2 ⎫
Z b2 = Z b1 ×
MVA b1 ⎪⎪
2⎬ (3.20)
⎛ kVb1 ⎞ ⎪
Z b2 = Z b1 × ⎜⎜ ⎟⎟
⎪
⎝ kVb2 ⎠ ⎭
where suffix b1 denotes the value to the original base
and suffix b2 denotes the value to the new base
The choice of impedance notation depends upon the complexity of the system, plant impedance notation and the nature
of the system calculations envisaged.
If the system is relatively simple and contains mainly transmission line data, given in ohms, then the ohmic method can
be adopted with advantage. However, the per-unit method of impedance notation is the most common for general system
studies since:
1. Impedances are the same referred to either side of a transformer if the ratio of base voltages on the two sides of
a transformer is equal to the transformer turns ratio
2. Confusion caused by introduction of powers of 100 in percentage calculations is avoided
3. By a suitable choice of bases, the magnitudes of the data and results are kept within a predictable range, and
hence errors in data and computations are easier to spot.
Most power system studies are carried out using software in per unit quantities. Irrespective of the method of calculation,
the choice of base voltage, and unifying system impedances to this base, should be approached with caution, as shown in
the following example (Fig. 3.6).
Right selection
141
11.8kV 141kV x 11 = 11.7kV
132
Fig 3.6 Selection of base voltages
WORKED EXAMPLE
A 500KVA, 6.6kv alternator is ∆ connected. Calculate the current in each phase of the alternator when it delivers its full
output to a balanced 3-φ load at a power factor of 0.8 lagging.
Solution.
Power supplied by the alternator
P = 3V L I L cos ϕ
Power supplied, P = 500 x 0.8 = 400kw
Thus, 400,000w = 3 × 6600 I L × 0.8
400,000
∴ IL = = 43.8 A
3 × 6600 × 0.8
For a ∆ connection
IL 43.8
IP = = = 25.3 A
3 3
WORKED EXAMPLE
A balanced 3-φ load is connected to 2.2 kV feeder, the load draws a line current of 60A at a P.f of 0.9 lagging. Calculate
the real, reactive, and apparent power absorbed by the load.
Solution
33
VL = 2200V
IL = 60A
P.F = 0.9 lag ⇒ φ = -cos-1(0.9) = -25.80
P= 3 VLIL cosφ = 205.8KW
Φ= 3 VLIL sinφ = 99.7KVAR
S= 3 VLIL = 228KVA
WORKED EXAMPLE
A 3-φ 1.5 KW, unity power factor; rating unit, and a 5 horse power induction motor with a full load efficiency of 80%
and P.f of 0.85 are served from the same 3Q, 3 wire 208v system. Find the magnitude of the line current for rated O/P
from the 5HP motor. Note that 1 HP = 746W.
Solution
Motor Output = 5x746=3730w
3730 3730
Motor Input = = = 4662W
η 0.8
The motor is a balanced 3-φ load so that
P= 3 VLIL cos φ
4662 = 3 x 208 x IL x 0.85
4662
IL = = 15.25 A
3 × 208 × 0.85
Ф = cos-1 (0.85) = 31.70
Hence, the motor line current is IL = 15.25 ∠ -31.70A
For the heater P = 3 VLIL
1500 = 3 x 208 x IL
1500
ILH = = 4.16∠0 0 A cosφ = 1
3 × 208
Therefore, total line current is the phasor sum of motor and the later line current.
IL = 15.25 ∠ -31.70 + 416 ∠ 00
IL = 18.9 ∠ -25.10A
WORKED EXAMPLE
A ∆- connected load consists of three identical impedance of 8+j6w each and supplied from a three phase 200V source.
Calculate (a) the power factor (b) phase current and line current (c) the real, reactive and apparent power taken by the
load.
Solution
Z ∆ = 8 + j6 =10 ∠ 36.90 Ω VL = Vph. = 200 ∠ 00
0
(a) pf = cos36.9 = 0.8 lagging
V ph 200∠0 0
(b) Iph = = Iph = 20 ∠ -36.90
ZA 10∠36.9 0
IL = 3 Iph ∠ -300 = 34.6 ∠ -66.90A
34
PL = 3 VLIL cosφ = 96 kW
Q = 3 VLIL sinφ = 7.2 kVAR
S = 3 VLIL = 12kVA
V ph 115.5
(b) Iph = = = 11.53∠ − 36.9 0 A
Z y 8 + j6
IL = IP = 11.53 ∠ -36.90A
(c) PL = 3 VLIL cosφ = 3 x 200 x 11.55 cos36.90 = 3.2kW
QL = 3 VLIL sinφ = 2.4 kVAR
SL = 3 VLIL = 4kVA
WORKED EXAMPLE
A generator supplied a load through a feeder whose impedance is Zf = 1+j202. the load impedance ZL = 8+j602 the
voltage across the load is 120V. find the real power and reactive power supplied by the generator using per unit
representation. Take the load voltage as the reference phasor and choose Sb = 1500VA, Vb = 120V
Solution
S b 1500
Ib = = = 12.5A
Vb 120
2
V (120) 2
Zb = b = = 9.6
Sb 1500
Per unit value (PU)
120∠0 10∠36.9 0
VL= = 1.0 ∠ 00 ZL = = 1.04 ∠ 36.90PU
120 9.6
1.0∠0 0 2.24∠63.4
= 0.96∠ − 36.9 Zfd = = 0.233 ∠ 63.40PUm
0
IL =
1.04∠36.9 0
9.6
Generator voltage
Eg = VL + IL Zfdr
= 1 ∠ 00 + (0.96 ∠ -36.90)(0.233 ∠ 63.10) = 1.204 ∠ 4.8PU V
The real voltage for generator is 1.204 ∠ 4.80 x 120-----base voltage = 144.5 ∠ 4.8v
Complex power Sg = EgIg* =Eg IL*
∴ Sg = (1.204 ∠ 4.80) (0.96 ∠ -36.90)
= 1.156 ∠ 41.70
= 0.863 + j0.969 pu
Pg = 0.863 x 1500 = 1295W
Qg = 0.769 x 1500 = 1154VAR.
35
unchanged when referred from primary to secondary and verser. Furthermore, in comparing xmer of different
ratings, comparison of P.U impedance is to half full than comparison of actual impedance i.e. if 2 xmers have the same
P.U leakage reactance and resistances, there regulation are the same for all load P.F, although their actual reactance
and resistances may be very different.
2. The need to transform from 3φ to single phase equivalent vice verser is avoided with the use of P.U quantities
hence there is less confusion in handling and in handling various parameters in 3φ system.
EXERCISE
A single phase source is connected to an electrical load, the load draws 0.6 pu current at 1.1 pu voltage while taking a
real power of 0.4 pu at a lagging pf. Choose a base voltage of 8kV and a base current of 125A. Calculate the following.
(a) Real power in kW
(b) Reactive power in kVAR
(c) pf
(d) Ohmic values of resistance and reactance of the load.
36
CHAPTER FOUR
POWER FACTOR CORRECTION
4.1 Introduction
The power factor (pf) of a given circuit is equal to the cosine of the phase angle between the circuit voltage and current
phasors. The voltage is always taken as reference. An ordinary consumer of electrical energy is not interested in the
phase angle between the voltage and the current applied to the equipment (e.g. electric motor). Concern is usually not
with the power factor but with the actual real power output (kW) of the equipment. However, for constant voltage and
output power, the current, I, through the supply feeder depends on the power factor according to the relation,
Pi n
I= (4.1)
3V L cos φ
where Pin is the power supplied by the feeder, VL is the line voltage, and cosΦ is the power factor.
Note that from eqn. (4.1), a reduction in the power factor (cosΦ) from unity to 0.8 will result in a 25% increase in current
I. Conversely, an increase (or improvement) in the pf will result in a reduction in the current, which will reduce the
following:
a) The losses in the feeder (I2R).
b) The required size of feeder conductors (conductor size depends on current carrying capacity).
c) The required rating of the transformer and other station equipment (e.g., a lower rated transformer can serve)
d) The losses in the transformer.
e) The voltage drop in the feeder. This results in improved voltage regulation.
In general, the efficiency of power generation, transmission and distribution equipment is improved when operating near
unity power factor. Consequently, utilities encourage consumers of electric energy to improve or correct the power factor
of their electrical load. An improved power factor implies reduced reactive power supplied by the source.
Equipment that compensate for the reactive power demand of the load are often used: e.g. static capacitors, synchronous
condensers, and phase advancers. This chapter deals with principles of power factor correction.
2300∠0 o 230 o
Ic = = =230 ∠ 90oA
− j10 10∠ − 90 o
Fig 4.1 Pure capacitive load
The current phase angle is positive indicating that the current phasor leads the voltage phasor by 90o.
The apparent power delivered to the capacitive load is
Sc = VI* = 2300 ∠ 0o x 230 ∠ -90o = 529 ∠ -90o kVAR
Hence, we observe the following:
1. The capacitor does not draw real power, i.e. Pc = 0 kVA
2. The capacitor draws energy as it is charged, but returns the same energy during the discharge part of each cycle.
A wattmeter would read zero. In this case the reactive power Qc = -529 kVAR. This can be costly to a power
company since the supply system must be sized to carry the current without unreasonable voltage drop or power
loss. For this reason power factor meters are installed to monitor large industrial consumers.
3. The power factor, pfc = cos φ = cos 90o =0
37
4.2.2. Inductive Load
Fig 4.2 shows an inductive load connected to the 2.3kV power line.
If this load is an industrial plant, PL corresponds to the “useful” power purchased from the power company to light and
heat the plant and to run power tools, etc. The reactive power QL, has only nuisance value. The apparent power dawn by
the load is:
SL = (846 2 + 635 2 ) = 1058kVA
The power triangle for this load is sketched in Fig. 4.3. The apparent power dawn by the load is SL = (846 2 + 635 2 )
= 1058 kVA
38
Fig. 4.4 Combined capacitive and inductive loads
Since the current through each of the elements remains unchanged the resulting active and reactive power drawn from
the source is:
P = 0+635 = 635 kW, Q = -529+846 = 317 kVAR.
The power factor of the combined load is given by
Q 317
pf = cos(tan −1 ) = cos(tan −1 ) = 0.89
P 635
The new phase angle is Φ=cos-1(0.89) = 27o
The total current drawn by the combined load is
I T = I c + I L = 230∠90 0 + 460∠ − 530
= j 230 + 276.2 − j 367.9
276.2 − j137.9 = 308.7∠27 0 A
The current drawn by the inductive load has been reduced from 460 A to 308 A as a result of connecting the capacitor in
parallel with the load. Moreover, the overall phase angle has reduced from 53o to 27o. The smaller the phase angle, the
better the system power factor. The addition of the capacitor, which is common practice in large power systems, reduces
the reactive power seen by the incoming feeder, and has brought the power factor much closer to unity.
Example 4.1
An industrial plant draws 250kW with pf of 0.707 lagging, a capacitor is to be added in parallel with the plant to
improve the overall pf to 0.866 lagging. Find the value of the capacitance required. The source is 2.3kV, 60Hz
Solution
Plant: pf = 0.707 lagging, Pp = 250kW
PP
Now, pf =
SP
PP 2.50
∴ SP = = = 353.6∠φ o kVA
pf 0.707
Qp = Sp sinф = Sp sin(cos-10707) = Sp sin(45o)
Qp = 250kVAR
Sp = 250 + j250 kVA
For the plant capacitor combination
Q2 = cos-1(0.866) = 30o
S2 = 250 + jQ2
Q2
Now, tan300 = and therefore, Q2 = 250 tan300 = 144KVAR
250
Thus the required capacitor rating is: Qc = 144 – 250 = -106 kVAR
V2
∴ Qc = VIc sin(-900) = -106 x 103 =
1 /(ωC )
f = 60Hz
ω = 2πf = 2π x 60 rad/S
39
106 × 10 3
∴C= = 53.1µf
(2300) 2 (2π × 60)
EXAMPLE 4.2
A three phase motor draws 20kVA at 0.707 pf lagging from a 220V source. It is desired to improve the pf to 0.9
lagging by connecting a capacitor bank across the terminals of the motor
a) Calculate the line current before and after the addition of the capacitor bank.
b) Determine the required kVA rating of the capacitor bank.
Solution
The motor real and reactive powers are
Pm = 20 x 0.707 = 14.14 kW
Qm = 20 sin [cos-1 (0.707)] = 14.14 kVAR
Sm 20,000
a) The current of the motor is Im = = = 52.5 A
3VL 3 × 220
Thus before power factor correction the line current is 52.5 A
The corrected power factor is, pfcorr = 0.90
The new line current is,
Pm 14140
Icorr = = = 41.2A
3VL × Pf corr 3 × 220 × 0.9
That is, after power factor correction the line current is 41.2A
b) The corrected value of reactive power is
Qcorr = Pm tan(cos-10.9)
= 14.14 tan(25.80)
= 6.85kVAR.
The kVAR rating of the capacitor bank required to improve the pf from 0.707 to 0.9 lagging is found as
Qcap = Qcorr - Qm = 6.85 – 14.14
= -7.29 kVAR
Thus the capacitor bank rated 7.29kVA will correct the power factor to 0.9 lagging
The least expensive way to achieve near unity pf is with the use of power-factor correction capacitors. Capacitors
provide a static source of leading reactive current and can be installed close to the load. The leading current drawn by the
capacitors may partly or completely neutralize the lagging reactive component of the load current. This raises the pf of
the load. Four of the most common capacitor connections are illustrated below.
a) 3-Φ grounded-star
b) 3-Φ ungrounded-star
c) 3-Φ delta
d) 1-Φ
Grounded or ungrounded Y-connections are usually made on high-voltage circuits (primary) while ∆ and 1-Φ
connections are usually made on low-voltage circuits (secondary) through protective fuses.
Majority of power capacitor equipment installed on primary feeders is connected grounded-Y due to the following
benefits it offers.
i) With grounded-Y connections switch tanks and frames are at ground potential. This provides for increased
personnel safety.
ii) It provides for faster operation of the series fuse in case of capacitor failure.
iii) Grounded capacitors can by-pass some line surges to ground and therefore exhibit a degree of self
protection from transient voltages and lightning surges.
iv) It provides a low impedance path for harmonics.
40
4.3.1 Advantages of static capacitors
• Low losses (almost negligible)
• Require little maintenance as there are no moving parts
• Can be easily installed as they are light and require no foundation
• Operate under ordinary atmospheric conditions
It should be noted that neither the consumer nor supply authority benefits by over-correction of power factor. An optimal
value of power factor can be computed based on economic considerations. In any case corrective appliances should be
switched on or off with the loads which they correct.
Example 4.3
A single phase source is connected to an electrical load. The load draws a 0.6 pu current at 1.10 pu voltage
while taking a real power of 0.4 pu at a lagging power factor.
Choose a base voltage of 8 kV and a base current of 125 A. Calculate the following:
a) Real power in kW
b) Reactive power in kVAR
c) Power factor
d) Ohmic values of the resistance and reactance
e) The capacitor kVA rating required to improve the power factor to 0.9 lagging.
Solution
Vb = 8kV, Ib = 125A ∴ Sb = VbIb = 8 x 125 = 1000 kVA
Iu = 0.6pu, Vu = 1.1pu and Pu = 0.4 pu pf lagging
a) Real power P = 0.4 x 1000 = 400kW
b) Apparent power Su = 1.1*0.6 = 0.66pu
Reactive power Qu = S u2 − Pu2 = 0.66 2 − 0.4 2 = 0.525pu
∴ Q = 0.525 x 1000 = 525kVAR
⎛ −1 Q ⎞
c) Power factor, pf = cosΦ = cos ⎜ tan ⎟
⎝ P⎠
41
⎡ −1 525 ⎤
= cos ⎢ tan = 0.606 lagging.
⎣ 400 ⎥⎦
8000
d) Base impedance Zb = = 64Ω
125
V 1.1
New Zu = u = = 1.833 pu ⇒ Z = Zu x Zb = 1.8 33 x 64
Iu 0.6
ф = cos-10.606 = 52.70
∴ Z = 117.33 ∠52.7 0 = 71.1+ j93.33Ω
∴ R = 71.1Ω and X = 93.33Ω
e) Φnew = cos-10.8 = 36.870
Qnew = P tanΦnew = 400 tan36.870 = 400 x 0.75 = 300kVAR
Qnew = Qold +Qc ⇒ 300 = 525 + Qc ⇒ Qc = -225kVAR
Qc = 225kVA
EXAMPLE 4.4
An over-excited synchronous motor is connected across a 250kVA inductive load of 0.6 lagging power factor. The motor
takes 20kW while running on no-load.
Calculate the kVA rating of the motor in order to raise the overall power factor of the motor plus inductive load
combination to 0.95 lagging.
Solution
SL = 250kVA, ФL = - cos-1(0.6) = -53.1o, PL=250x0.6=150 kW
QL = PL tan(cos-10.6) = 150 tan(53.1o) = 200kVAR
PM = 20kW,
PT = PL + PM = 150 + 20 = 170kW
QT = PT tan(cos-10.95) = 170 tan(18.2o) = 55.9kVAR
QM = QT - QL = 55.9 – 200 = -144.1kVAR
SM = PM2 + Q 2M = 20 2 + (−144.1) 2 = 145.5kVA
Hence a150kVA synchronous motor will do.
42
CHAPTER FIVE
STATION LOAD CHARACTERISTICS AND ECONOMICS
5.1 Introduction
The ultimate objective of any power system is to deliver electrical energy to the consumer safely, reliably, economically
and with good quality. Operation of the power system requires that proper attention be given to the safety not only of the
utility personnel but also of the general public. At the load centre, electrical energy is converted to other more desirable
and useful forms of energy. This implies that electricity supply should be available where, when and in whatever amount
the consumer requires.
The quality of the supplied electrical energy is partially dependent on energy usage by the consumers. When there is high
demand on the limited capabilities of the power system, voltage may deviate from its acceptable levels. Switching of
large machinery could cause fluctuation of the voltage as well as the frequency. Usually high and prolonged demands
may lead to overloaded equipment, which may cause tripping of protective devices to prevent further damage to the
equipment.
Finally, the power system must be operated such that the overall costs of producing electricity, including all attendant
losses in the generation and delivery systems, are minimized. The most economical conditions derive not only from
proper operating procedures but also from efficient system planning and design.
Residential loads are private homes and apartments. They include lighting, cooking, comfort heating and cooling,
refrigerators, water heaters, washers and dryers, electronic gadgets for entertainment, pressing irons and many more
different appliances.
Commercial loads include office buildings, department stores, grocery stores and shops.
Industrial loads consist of factories, manufacturing plants, steel, lumber, paper, mining, textile and other industrial
factories. In both commercial and industrial groups, loads include lighting, comfort heating and cooling, and various
types of office equipment. In addition, industrial loads contain various types and sizes of motors, fans, presses, furnaces,
etc.
Electrical load refers to the amount of electrical energy or electrical power consumed by a particular device or by a
whole community. It is also referred to as electrical demand. At the individual consumer level, the electrical demand is
quite unpredictable. However, as the demands of the various users are accumulated and added at a feeder or a substation,
they begin to exhibit a definite pattern.
43
The daily load curves for Monday through Friday are similar in shape and peak values. Weekend curves are generally
different, particularly for industrial and commercial customers because of shutdown of operations on Saturdays and
Sundays.
Load curves may be constructed for feeders, substations, generating plants, or for the whole system. Load curves are also
drawn for different periods or seasons of year. Thus, the system peak load for the hot season, or rain season, or cold
season (e.g. Harmattan), may be read as the highest ordinate from the corresponding load curve.
The daily load curves may be accumulated for the whole year and presented in another curve, the annual load duration
curve (LDC). A typical LDC is shown in Fig 5.2.
Several factors used in the electricity supply industry may be defined in terms of parameters of load and load-duration
curves:
A high load factor helps in drawing more energy from a given installation. As individual load centres have their own
characteristics, their peaks in general have a time diversity, which when utilized through transmission interconnection,
greatly aids in jacking up load factors at an individual plant - excess power of a plant during light load periods is
evacuated through long distance high voltage transmission lines, while a heavily loaded plant receives power.
Thus, if a plant’s peak load is 1000MW but the average annual load is 350MW, its annual load factor would be only
0.35. Most of its capacity remains un-utilized for the major part of the year and so the cost would be high. The average
load is estimated by dividing the area under the daily load curve by the time period considered.
Area under load curve (kWh)
Average load = (5.2)
24 (h)
5.3.2 Diversity Factor
This is defined as the sum of individual maximum demands by the consumers, divided by the maximum load on the
system, i.e.,
Sum of individual consumer groups maximum demand
Diversity factor = (5.3)
Actual peak load of the system
44
This factor gives the time diversification of the load and is used to decide the installation of sufficient generating and
transmission plant. If all the demands came at the same time, i.e. unity diversity factor, the total installed capacity
required would be much more. Luckily, the factor is much higher than unity, especially for domestic loads.
Diversity helps to improve the load factor and the economic operation of the power plant. A high load factor is, in
general, an indication of balanced load curve with relatively small load changes. High values of demand factor, load
factor, diversity factor and capacity factor (define below) are desired for economic operation of the plant and to produce
electricity at less cost.
Each consumer has a “connected load” which is the sum of the continuous ratings of all the equipment and outlets on the
consumer’s circuits. The maximum demand is the maximum load which a consumer uses at any time. It is always less
than or equal to the connected load.
It is the ratio of the energy produced in a given time to the maximum possible energy that could have been produced
during the same time of operation. If the operating time is one year (or 8760) hours, the plant use factor is equal to the
capacity factor.
If the rated capacity of the plant is equal to the peak load, then the load factor and capacity factor will be numerically
equal. The difference between load factor and capacity factor is an indication of the reserve capacity.
kWinstal load factor
Reserve factor = = (5.6)
kWmax capacity factor
If the daily load curve of a power station shows a peak demand that is greater than the installed capacity of the station,
then the peak load is shared by other stations interconnected with it.
45
The base load is the load below which the demand never falls and is supplied 100% of the time. The peaking load occurs
for about 15% of the time. The intermediate load represents the remaining region of the LDC.
EXAMPLE 2
A substation supplies power via four feeders to its consumers. Feeder No 1 supplies six consumers, whose individual
daily maximum demands are 70kW, 90kW, 20kW, 50kW, 10kW and 20kW, while the maximum demand on the feeder is
200kW. Feeder No 2 supplies four consumers, whose daily maximum demands are 60kW, 40kW, 70kW and 30kW, while
the maximum demand on the feeder 2 is 160kW. Feeders number 3 and 4 have daily maximum demand of 150kW and
200kW respectively, while the maximum demand on the station is 600kW.
Determine the diversity factors for the consumers of feeder No 1, feeder No 2 and for the four feeders.
SOLUTION:
−1
⎡ Maximum demand of the Group ⎤
Diversity = ⎢ ⎥
⎣ Sum of individual Maximum demands ⎦
46
70 + 90 + 20 + 50 + 10 + 20 1
Diversity factor for feeder 1: Div = = = 1.3
200 0.77
60 + 40 + 70 + 30
Diversity factor for feeder 2: Div = = 1.25
160
200 + 160 + 150 + 200 1
Diversity factor for the feeders: Div = = = 1.183
600 0.845
EXAMPLE 3
The peak load on a power station is 60MW. The loads having max demands of 30MW, 20MW, 10MW and 14MW are
connected to the station. The station capacity is 80MW and the annual load factor is 0.50. Estimate;
(a) the average station load,
(b) the energy supplied per year,
(c) the demand factor, and
(d) the diversity factor.
SOLUTION :
Average load
a) Load factor =
peak load
Average load
0.5 =
60MW
∴ Average load = 30MW
Energy supplied per year
= average load x 8760
= 30 x 8760MWh
= 262.8 x 106kWh
Max Demand 60 60
c) Demand factor = = = = 0.811
Connected load 30 + 20 + 10 + 14 74
Sum of individual Max demand 30 + 20 + 10 + 14 74
d) Diversity factor = = = = 1.233
Simultaneous Max demand 60 60
EXAMPLE 4
A power plant has the following annual factors: load factor = 0.75, capacity factor = 0.60, use factor = 0.65. Maximum
demand is 60MW.
Estimate:
a) The annual energy production
b) The reserve capacity over and above the peak load, and
c) The hours during which the plant is not in service per year.
SOLUTION:
Average load
Load factor =
Peak load
∴ Average load = 0.75 x 60 = 45MW
Annual energy production = 45000 x 8760 = 394,200,000kWh
= 394.2 x 106kWh
Average load
Capacity factor =
Plant capacity
45
Plant capacity = = 75MW
0.6
Reserve capacity over and above the peak load = 75 – 60 = 15MW
Energy generated per year
Use factor =
Plant capacity × hours in operation
47
394.2 × 10 6 kWh
∴ Hours in operation = = 8086 hours
75 × 10 3 kW × 0.65
Hours not in service in service in a year = 8760 – 8086 = 674 hours
EXAMPLE 5
A power station has to supply load as follows
Time (h) 0-6 6-12 12-14 14-18 18-24
Load (MW) 30 90 60 100 50
a) Draw the load curve
b) Draw the load duration curve
c) Select suitable generating units to supply the load
d) Calculate the load factor
e) Calculate the capacity of the plant and the plant capacity factor
SOLUTION:
a) Draw the load curve
b) Draw the load duration curve
c) Energy generated = 30 x 6 + 90 x 6 + 60 x 2 + 100 x 4 + 50 x 6
= 1540MWh = 1540 x 103kWh.
1540 × 10 3
Average load = kW = 64.17MW
24
3
Max demand = 100 x 10 Kw
1540 × 10 3
Load factor = = 0.64
24 × 100 × 10 3
To supply the load, three generating units, each of 30MW capacity and one generating unit of 10MW capacity will be
selected. One additional unit will be kept standby. Its capacity will be equal to that of the largest unit, i.e. 30MW.
Load duration curve will indicate the operational schedule of different generating units, which will be as follows
i) One 30MW unit will run for 24 hours
ii) Second 30MW unit will run for 18 hours
iii) Third 30MW unit to run for 10 hours
iv) Fourth 30MW unit to run for 4 hours
Plant capacity = 30 x 4 + 10 x 1 = 130Kw
Energy generated 1540 × 10 3 kWh
Capacity factor = = = 0.494
Capacity × operating time 130 × 10 3 × 24kWh
Of all the information, which, collectively, defines the task of supplying electric power to the consumer, none is more
important than the estimate of the load. Indeed, the electric load is the most important input in the utility's budget and the
most vital for the study of transmission and distribution system, as rates.
Load or demand estimation is the starting point for planning the future electric power supply. The consistency of demand
growth over the years has lead to numerous attempts to fit mathematical curves to this trend. One of the simplest curves
is
P = P0 e α( t − t 0 ) (5.7)
where α is the average per unit growth rate, P is the demand in year t, and P0 is the given demand at year t0.
Example
In a certain country, the energy consumption is expected to double in ten years. Assuming a simple exponential growth
given by P = P0 e αt calculate the growth α.
Solution
Let the starting demand be P0 in year 1. After 10 years the demand double, i.e P=2P0. Thus the demand growth equation
yields
2P0 = P0 e10α Or 2 = e10α
48
Taking natural logarithms on both sides gives
λn( 2 )
λn( 2 ) = 10α and ∴ α= = 0.0693
10
The tool often used by engineers in making long-term forecasts is termed the method of least squares. The method can
be used to establish the trend of random or scattered data accurately. Although the method of least squares is
mathematically correct, the accuracy of predictions based on its use is less reliable, as the trend is projected continually
further into the future. In practice, a line might be extended into the future with reasonable accuracy for a period of time
equal to that of the data used to calculate the trend.
In the electric utility industry, two variations of the method are used. These are the straight line and the compound-
growth methods. The, compound-growth method is more popular, but the choice of the straight-line method is a matter
of individual judgement in any particular situation.
Based on the above historical data, the load can be predicted five years ahead using the least-squares method. The
principle is as follows.
Suppose we are given a set of m data points: (x1, y1), (x2, y2),….(xm, ym).
We would like to determine a function F(x) such that
yi = F(xi) + µi (5.8)
For i = 1, 2, ….., m, where the approximation errors µi are small.
The form of the function F(x) depends on the problem at hand. Here we assume that it has the form of a linearly
weighted sum:
n
F(x) = ∑c f ( x )
j=1
j j (5.9)
where the number of summands n and the specific basis functions fi are chosen based on knowledge of the problem at
hand. A common choice is
fj = xj-1
Let
49
⎡ f1 ( x1 ) f 2 ( x1 ) . f n ( x1 ) ⎤
⎢ f (x ) f (x ) . f n ( x 2 ) ⎥⎥
A=⎢ 1 2 2 2
= [aij ]
⎢ . . . . ⎥
⎢ ⎥
⎣ f1 ( x m ) f 2 ( x m ) . f n ( x m )⎦
⎡ f1 ( x1 ) . f 2 ( x1 ) . f n ( x1 ) ⎤ ⎡c1 ⎤
⎢ f (x ) f (x ) . f n ( x 2 ) ⎥⎥ ⎢⎢c 2 ⎥⎥
Ac = ⎢ 1 2 2 2
⎢ . . . . ⎥⎢ . ⎥
⎢ ⎥⎢ ⎥
⎣ f1 ( xm ) f 2 ( x m ) . f n ( x m ) ⎦ ⎣c n ⎦
⎡ F ( x1 ) ⎤
⎢F (x ) ⎥
=⎢ 2 ⎥
⎢ . ⎥
⎢ ⎥
⎣ F ( x m )⎦
µ = Ac – y
is the m-vector of approximation errors. The least squares solution that minimizes µ is given by
c = [(ATA)-1AT]y
= A+y
Worked Example
Based on the annual peak load data given in table 1
(a) Find the function of the form
y = c1 + c 2 x
that is the best least-squares fit to the data points.
(b) Hence estimate the annual peak load and growth for five more years.
Solution:
(a) From the given data we form matrix A as follows
⎡1 x1 ⎤ ⎡1 1⎤
⎢1 x2 ⎥⎥ ⎢1
⎢ ⎢ 2⎥⎥
A = ⎢1 x3 ⎥ = ⎢1 3⎥
⎢ ⎥ ⎢ ⎥
⎢1 x4 ⎥ ⎢1 4⎥
⎢1 x5 ⎥⎦ ⎢⎣1 5 ⎥⎦
⎣
50
⎡1 1⎤
⎢1 2⎥⎥
⎡1 1 1 1 1⎤ ⎢ ⎡5 15 ⎤
A A=⎢ ⎥ ⎢1 3⎥ = ⎢
T
⎥
⎣1 2 3 4 5⎦ ⎢1 ⎥ 15 55⎦
4⎥ ⎣
⎢
⎢⎣1 5 ⎥⎦
(ATA)-1 = 1 ⎡ 55 − 15⎤
50 ⎢⎣− 15 5 ⎥⎦
A+ = (ATA)-1AT =
1 ⎡ 55 − 15⎤ ⎡1 1 1 1 1⎤ 1 ⎡ 40 25 10 − 5 − 20⎤
=
50 ⎢⎣− 15 5 ⎥⎦ ⎢⎣1 2 3 4 5⎥⎦ 50 ⎢⎣− 10 − 5 0 5 10 ⎥⎦
c= A+y
⎡22200⎤
⎢26000⎥
1 ⎡ 40 25 10 − 5 − 20⎤ ⎢ ⎥ 1 ⎡896000⎤ ⎡17920⎤
= ⎢ ⎥ ⎢32000⎥ = ⎢ ⎥=⎢ ⎥
50 ⎣− 10 − 5 0 5 10 ⎦ ⎢ ⎥ 50 ⎣226000⎦ ⎣ 4520 ⎦
⎢ 38800 ⎥
⎢⎣38400⎥⎦
Thus the mathematical model for the annual peak load for the station is:
y= 17920 + 4500x kW
(b) Based on this model we can estimate the annual peak load for the subsequent five years. The results are shown
in Table 3.
51
CHAPTER SIX
TARIFFS
6.1 Introduction
Tariffs are prices charged by a utility for supplying the energy needs of consumers. The costs involved in the generation,
transmission and distribution of electrical energy fall into two major categories.
i) The cost incurred due to maximum demand on the power system (i.e. the capital expenditure of providing
sufficient generating plant to supply the maximum needs of all consumers).
ii) The cost incurred in operating the power system (i.e. fuel costs for generation of power, maintenance costs,
personnel emoluments, etc).
Tariffs may be structured such as to influence the load curve and improve the load factor. Some of the tariff structures
are:
a) Two-part tariff
b) Block rate tariff
c) Power factor tariff
6.2 Two-Part Tariff
In this tariff structure electrical energy charges are divided in two parts:
a) A fixed charge on the basis of the maximum demand in kVA
b) A running charge based on energy consumed in kWh.
For the fixed charge either a maximum demand (MD) meter is installed in the consumer premises to indicate the
maximum kVA demanded in a prescribed period of time (e.g. a month) or it is assessed based on installed capacity.
Whether or not an MD meter is installed usually depends on the size of demand. When maximum demand is not likely to
exceed 50kVA an assessment is made. The cost of metering is of necessity quite high because of the accuracy required to
avoid errors which can amount to large cost to the consumer.
Consumers of electrical energy may be divided into classes depending on their load characteristics. Typical classes
include the following:
• Residential
• Commercial (shops, offices, etc)
• Industrial
• Street lighting
• Special Class (e.g. Agro-allied enterprises involved in farming; crop cultivation; religious houses; Government
and Teaching Hospitals; Government Research Institutes; Education and Secondary Schools; Water Boards).
Table 1.1 shows hypothetical two-part tariff codes for the above categories of consumers.
Disadvantages
• Fixed charges have to be paid whether energy is consumed or not
• Requires additional MD meter cost or else there is always error in assessing the maximum demand.
52
Levels Charge Charge per per Month per kWh
(N) kVA (N) (N)
(N)
1.0 Residential
1.1 R1 < 5kVa 20 100 - 20 1.20
1.2 R2 5-15kVA 30 100 - 30 4.00
1.3 R3 15-45kVA 120 500 - 120 6.00
1.4 R4 45-500kVA 120 1500 - 5000 8.50
2.0 Commercial
2.1 C1 5-15kVA 90 100 - 90 6.50
2.2 C2 15-45kVA 120 500 - 120 8.50
2.3 C3 45-500kVA 240 1500 230 5000 8.50
2.4 C4 0.5-2MVA - 2200 250 31250 8.50
3.0 Industrial
3.1 D1 5-15kVA 90 100 - 90 6.50
3.2 D2 15-45kVA 120 500 - 120 8.50
3.3 D3 45-500kVA 240 1500 230 5000 8.50
3.4 D4 0.5-2MVA - 2200 250 31250 8.50
3.5 D5 >2MVA - 2200 270 1500000 8.50
4.0 Street lighting
4.1 S1 1-φ, 3-φ - 5.00 - 240 6.50
5.0 Special tariff
5.1 A1 15-45kVA 120 500 - 120 5.80
5.2 A2 45-500kVA 240 1500 - 5000 5.80
5.3 A3 0.5-2MVA - 2200 - 31250 5.80
5.4 A4 >2MVA - 2200 - 31250 5.80
Example 6.1
A factory to be set up is to have a fixed load of 760 kW at 0.8 pf. The electricity board offers to supply energy at the
following alternate rates:
a) LV supply at N 32/kVA max demand/annum + 10 kobo/kWh
b) HV supply at N 30/kVA max demand/annum + 10kobo/kWh.
The HV switchgear costs N 60/kVA and switchgear losses at full load amount to 5%. Interest, depreciation charges
for the switchgear are 12% of the capital cost. If the factory is to work for 48 hours/week, determine the more
economical tariff.
Solution
760
Maximum demand = = 950kVA
0. 8
Loss in switchgear = 5%
950
∴ Input demand = = 1000kVA
0.95
Cost of switchgear = 60 x 1000 = N 60,000
Annual charges on depreciation = 0.12 x 60,000 = N 7,200
Annual fixed charges due to maximum demand corresponding to tariff (b)
53
= 30 x 1,000 = N 30,000
Annual running charges due to kWh consumed
= 1000 x 0.8 x 48 x 52 x 0.10
= N 199,680
Total charges/annum = N 236,880
Maximum demand corresponding to tariff (a) = 950kVA
Annual fixed charges = 32 x 950 = N 30,400
Annual running charges for kWh consumed
= 950 x 0.8 x 48 x 52 x 0.10
= N 189,696
Total charges/annum = N 220,096
Therefore, tariff (a) is economical.
54
CHAPTER SEVEN
POWER FLOW STUDIES
7.1 INTRODUCTION
Successful operation of power system under normal balanced three-phase steady-state conditions requires that:
• Generation supplies the demand (load) plus losses.
• Bus voltage magnitudes remain close to rated values.
• Generators operate with specified real and reactive power limits.
• Transmission lines and transformers are not overloaded
Power flow (also commonly called load flow) studies routinely investigate these requirements with the aid of a power
flow computer program. Such a program computes:
¾ The voltage magnitude and angle at each bus in a power system under balanced 3-Φ
steady-state conditions,
¾ Real and reactive power flow for all equipment interconnecting the buses, and the
¾ Technical losses in the power system
Power flow studies investigate both existing power systems and proposed changes including new generation and
transmission to meet projected load growth. Power flow studies also allow determination of:
o The best size and the most favourable locations for power capacitors both for power factor improvement or
raising bus voltages.
o The best location as well as the optimal capacity of proposed generating stations, substations or new power
lines.
o The state of the power system under a given operational condition so that operators detect overloads and
evaluate transfer limits.
The voltage angle of the slack bus generator is set to zero or any arbitrary value, so its voltage becomes the reference
voltage for other bus voltages in the system.
Table 7.1 summarizes the status of the variables at each bus type. It is assumed that the system has N buses out of which
G are generator buses.
55
Table 7.1 Typical power flow bus specifications
Bus type Known Unknown Number of
quantities quantities Unknowns
Slack (swing) bus V, Φ = 0 P, Q 2
Generator bus P, V Q, Φ 2(G-1)
56
N
Or Pi − jQ i = Vi* ∑Y V
k =1
ik k i = 1,2, …., N (7.5)
It should be noted that the N equations in eqn (7.5) are complex. These equations represent 2N real equations which may
be expressed in rectangular, polar or hybrid form (a combination of rectangular and polar).
For the rectangular form the voltages Vi = ei + jfi and the bus admittance matrix elements Yik = Gik + jBik are substituted
into eqn. (7.5). After simplification we obtain the rectangular form:
⎡N ⎤ ⎡ N ⎤
∑
⎣⎢ k =1 ⎦⎥ ⎣⎢ k =1
∑
Pi = ei ⎢ ( G ik e i − B ik f i )⎥ + fi ⎢ ( G ik f k + B ik e i )⎥
⎦⎥
(7.6a)
⎡ N ⎤ ⎡ N ⎤
Qi = fi ⎢∑ ( G ik e k − B ik f k )⎥ - ei ⎢∑ ( G ik f k + B ik e k )⎥ (7.6b)
⎣⎢ k =1 ⎦⎥ ⎣⎢ k =1 ⎦⎥
For the polar form the voltages Vi = Vi ∠σ i or Vi = Vi e jσ i and the bus admittance elements Yjk = Y jk ∠Ψik are
substituted into eqn (7.5). After simplification the equations in polar form are:
N
Pi = Vi ∑Y
k =1
ik Vk cos( σ i − σ k − ψ ik ) (7.7a)
N
Q i = Vi ∑Y
k =1
ik Vk sin( σ i − σ k − ψ ik ) (7.7b)
Example 7.1
Write the power flow equations for the 3-bus network in Fig. 7.1 in polar form.
57
Y33 = 17.00 ∠ − 61.9
0
Y31=Y13
Converting the bus voltages into polar form yields:
V1 = 1 ∠0 pu, V2 = 1.124 ∠σ 2 , and V3 = V3 ∠σ 3
0
For bus 1
P1 – jQ1 = V1* [ Y11V1 + Y12 V2 + Y13V3 ]
= ( 1∠0 0 )* [( 6.4031∠ − 51.3 0 )( 1∠0 0 ) + ( 0 )( 1.124∠σ 2 ) +
+ ( 6.4031∠128.7 0 )( V3 ∠σ 3 )]
∴ P1 − jQ1 = 6.4031 ∠ − 51.3 0 + 0 + 6.4031 V3 ∠( 128.7 0 + σ 3 ) (7.9)
For bus 2
P2 – jQ2 = V2* [ Y21V1 + Y22V2 + Y23V3 ]
= ( 1.124∠ − σ 2 )[( 0 )( 1∠0 0 ) + ( 10.77∠ − 68.2 0 )( 1.124∠σ 2 ) +
+ ( 10.77∠111.8 0 )( V3 ∠σ 3 )]
Thus the nodal equation at bus 2 is:
1.7 - jQ2 = 0 + 13.606 ∠ − 68.2 0 + 12.105 V3 ∠( 111.8 0 + σ 3 − σ 2 ) (7.10)
For bus 3
P3 – jQ3 = V3* [ Y31V1 + Y32V2 + Y33V3 ]
= ( V3 ∠ − σ 3 )[( 6.4031∠128.7 0 )( 1∠0 0 ) + ( 10.77∠111.8 0 )( 1.124∠σ 2 ) +
+ ( 17∠ − 61.9 0 )( V3 ∠σ 3 )]
Thus the nodal equation for bus 3 is:
− 2 + j1 = 6.4031 V3 ∠( 128 .7 0 − σ 3 ) + 12 .105 V3 ∠( 111 .8 0 + σ 2 − σ 3 ) +
2
(7.11)
+ 17 V3 ∠ − 61 .9 0
Simultaneous equations (7.9)-(7.10) relate the powers in the network to the bus voltages. These equations are typically
complex and nonlinear. In a power flow study the equations are solved for the unknown quantities using a numerical
iterative technique such as the Gauss method, the Gauss-Siedel method, the Newton-Raphson method, etc. The Gauss
and Gauss-Siedel iterative methods are outlined in the next section.
The solution vector to eqn. (7.12) can be obtained by iterative techniques to estimate the numerical solution as accurately
as desired.
The steps in solving the problem by iteration methods are:
(i) Guess the initial solution approximately.
(ii) This solution is used in conjunction with the original equation to compute a new and more accurate
estimate.
(iii) The second estimate is used in finding out the third estimate and so on.
Any process of successive approximations used to obtain a numerical solution of algebraic equations, differential
equations, etc. is known as iterative method. Digital computers are used for obtaining the solution quickly. The list of
computer instructions stating the sequence of operations is an algorithm. The quality of an algorithm is decided by the
speed of convergence to the acceptable solution. The solution is said to have converged if the largest change between
successive iterates is less than a given tolerance value.
The Gauss and Gauss-Siedel methods of iterative solution of linear and nonlinear algebraic equations are illustrated by
the following examples.
58
Example 7.2
Solve the following set of linear simultaneous equations using the:
(a) Gauss iterative method
(b) Gauss-Siedel iterative method
4 x1 − x 2 − x3 − 7 = 0
4 x1 − 8 x2 + x3 + 21 = 0
− 2 x1 + x 2 + 5 x3 − 15 = 0
Solution
7 + x 2( k ) − x3( k )
x1( k +1) =
4
21 + 2 x1( k ) + x3( k ) (7.13)
x 2( k +1) =
8
15 + 2 x1( k ) − x 2( k )
x3( k +1) =
5
x1(1) = 7+2−2
= 1.75
4
x 2(1) = 21 + 4 + 2
= 3.375
8
x3(1) = 15 + 2 − 2
=3
5
k x1( k ) x 2( k ) x3( k )
0 1 2 2
1 1.75 3.375 3
2 1.84375 3.875 3.025
3 1.9625 3.925 2.9625
4 1.99062500 3.97656250 3.000000
5 1.99414063 3.99531250 3.00093750
Μ Μ Μ Μ
15 1.99999993 3.99999985 2.99999993
Μ Μ Μ Μ
19 2.00000000 4.00000000 3.00000000
59
After 19 steps the iteration has converged to the nine-digit machine approximation. The solution to the above system of
linear equations is actually P = (2, 4, 3).
(b) In the Gauss-Siedel iteration method new values of each variable are used as soon as they are available. Hence the
iteration equations become
7 + x 2( k ) − x3( k )
x1( k +1) =
4
21 + 2 x1( k +1) + x3( k )
x 2( k +1) =
8
15 + 2 x1( k +1) − x 2( k +1)
x3( k +1) =
5
x1(1) = 7+2−2
= 1.75
4
x 2(1) = 21 + 4 x1.75 + 2
= 3.75
8
k x1( k ) x 2( k ) x3( k )
0 1 2 2
1 1.75 3.75 2.95
2 1.95 3.96875 2.98625
3 1.995625 3.99609375 2.99903125
. . . .
. . . .
. . . .
8 1.99999983 3.99999988 2.99999996
9 1.99999998 3.99999999 3.00000000
10 2.00000000 4.00000000 3.00000000
It has converged to the solution in 10 iterations only which is a considerable improvement on the Gauss method.
Example 7.3
Consider the nonlinear equations
3x1 + x1 x 2 − 2 = 0
3x 2 − x1 x 2 + 2 = 0
Solution:
Using the usual method, it is seen that the solution to the equations is x1 = 1, x2 = -1. Let the equations be re-arranged as:
60
x1 = 2 - x 1 x 2 and x2 = - 2 + x 1 x 2
3 3
(Note that there are other possible re-arrangements for the two equations. Some of them may not necessarily result in
solutions that converge to the actual solution. This is a subject of numerical analysis which is beyond the scope of this
course.)
2 − (0.6666) × ( −0.6666)
x1( 2 ) = = 0.8147
3
− 2 + (0.6666) × ( −0.6666)
x 2( 2 ) = = −0.8147
3
2 − (0.8147 ) × (−0.8147)
x1(3) = = −0.8878
3
− 2 − (0.8147 ) × ( −0.8147 )
x1( 3) = = −0.8878
3
( 4) ( 4) ( 5) ( 5)
Substitute the values obtained of x1 and x2 and continue steps for x1 , x 2 , x1 , x 2 , etc. till the final results obtained
are steady.
b) Gauss-Siedel method.
In the Gauss-Siedel method, the convergence is obtained faster by making use of the upgraded iterates as soon as they
are available, i.e. use x(k+1) and not x(k), as soon as it is available.
So the algorithm becomes: x1( k +1) = 2 − x1 x 2
(k ) (k )
− 2 + x1( k +1) x 2( k )
and x 2( k +1) =
3 3
Let for k=0, x1
( 0)
= 0 and x 2( 0) = 0
(1)
Iteration k=1: x1 = 0.6666 – 0 = 0.6666
x 2(1) ) = - 0.6666 + 0 = - 0.6666
Iteration k=2:
2 − (0.6666) × (−0.6666)
x1( 2 ) = = 0.8147
3
− 2 + (0.8147 ) × (−0.6666)
x 2( 2 ) = = −0.8476
3
61
Iteration k=3:
2 − (0.8147 ) × (−0.8476)
x1(3) = = 0.8476
3
− 2 + (0.8476) × (−0.8476)
x 2( 3) = = −0.9200
3
( 4) ( 4) ( 5) ( 5)
Substitute the values obtained of x1 and x2 and continue steps for x1 , x 2 , x1 , x 2 , etc. till the final results obtained
are steady. It will be observed that the speed of convergence in this method is increased or the number of iterations
needed is less.
Each difference is multiplied by the acceleration factor, α. The accelerated iterates are obtained as follows:
x1(acc
k) k −1)
= x1(acc + α∆x1( k )
x 2( kacc
) −1)
= x 2( kacc + α∆x 2( k )
These accelerated values, x1acc and x2acc, are used in the iteration process instead of x1 and x2.
The value of α is taken between 1.5 and 1.7 for the solution of load-flow equations.
At a generator bus Q is solved for iteratively using current estimates of phasor voltages at the other buses. The real
power equation is then used to compute the bus voltage V and its phase angle σ. however, since the magnitude of voltage
is specified, we reset the magnitude to this value and retain the phase angle σ for other computations.
Solution Convergence
The solution has converged when changes in the computed values from previous to current iteration are within specified
tolerance (e.g. 0.01 pu).
i.e. ∆Vki +1 = Vki +1 − Vki ≤ 0.01 pu
∆Q ki +1 = Qki +1 − Qki ≤ 0.01 pu
∆σ ki +1 = σ k − σ k ≤ 0.01 pu
i +1 i
After the solution has converged, the phasor voltages at all buses are known and may be used to find other information
about the steady-state operating point characteristics of the power system such as: Real and reactive power generation at
62
slack bus; Reactive power generation at PV buses; Real and reactive power flows in the lines; Real and reactive power
losses between buses.
The slack bus power is found using,
*
S1 =P1 + jQ1 = V1 ⎡ ⎤
N
⎢∑ Y1k Vk ⎥
⎣ k =1 ⎦
The real and reactive power flowing between bus k and m may be computed using
[
Skm = Pkm + jQkm = Vk (Vk − Vm )Ykm + Yshk Vk *]
where Yshk is the shunt admittance in the π model of the transmission line.
Specifically, the line power Skm measured at bus k and defined positive in direction k to m is given by,
*
Skm = Pkm + jQkm = VkI km = Vk [Vk* − Vm* ]Ykm
*
+ Vk Vk*Yshk
Real and reactive power losses are computed using the line flows as follows
loss
S km = Skm + Smk
P km + jQ km = [Pkm + Pmk ] + j (Qkm + Qmk )
loss loss
Example 7.4
For the 3-bus system in Fig 7.2, the line per-unit reactances are: x12=0.75, x13=0.25, and x23=0.50.
Bus 1 is selected as the swing bus, and its voltage set at V1 = 1.0∠0 pu.
0
Bus 2 is a generator bus with voltage magnitude V2 = 1.02 pu and real injected power, P2=0.6 pu.
Bus 3 is a load bus with injected power: P3=-0.8 pu and Q3=-0.6 pu.
a) Use the Gauss-Seidel method to determine the power flow solution for power system within a tolerance of 0.01
pu.
b) Calculate the power flow through line 1-3 at both ends
c) Calculate the power loss on line 1-3.
63
1 1 ⎡ 1 1 ⎤
Y33 = + = + = − j 6.0
jx13 jx 23 ⎢⎣ j 0.25 j 0.5 ⎥⎦
Known quantities:
Bus 1: Slack bus: V1 = 1 ∠ 0opu
Bus 2: PV bus: V2 = 1.02pu, P2 = 0.6pu
Bus 3: PQ bus: P3 = -0.8pu, Q3 = -0.6pu
Unknown quantities to be determined
Bus 2: σ 2 and Q 2
Bus 3: V3 and σ 3
Gauss-Siedel equations:
Q (i)
2 =-
Im (V2(i)* (Y21 V1 + Y22 V2(i) + Y23 V3(i) ) )
⎡ ⎤
V2(i) = 1 ⎢ P2 − jQ 2 − Y21V1 − Y23 V3(i−1) ⎥
Y22 ⎢ V2
⎣
(i) *
[ ] ⎥
⎦
⎡ ⎤
V3(i) = 1 ⎢ P3 − jQ 3 − Y31 V1 − Y32 V2(i −1) ⎥
Y33 ⎢ V3(i) *
⎣ [ ] ⎥
⎦
Constant terms: Y21 V1 = j1.333(1∠0 0 ) and Y31 V1 = j4.0
(0) (0)
Using a flat start: V 2
= V3 = 1∠0 0
Thus at iteration i=0, the reactive power injected by bus 2 is given by:
[ {
Q2( 0 ) = − Im (1.02∠0 0 ) * j1.333 + (− j 3.333)(1.02∠0 0 ) + ( j 2)(1∠0 0 ) = 0.07 }]
Iteration 1
1 ⎡ 0.6 − j 0.07 ⎤
V2(1) = − j1.333 − ( j 2)(1∠0 0 )⎥ = 1.04∠9.8 0
− j 3.333 ⎢⎣ (1.02∠0 0 ) * ⎦
Now the magnitude of V2 is fixed to be 1.02 hence the above calculated value of 1.04 is reset to 1.02 while the phase
angle is retained. Hence V2(1) = 1.02∠9.8 0
1 ⎡ − 0.8 + j0.6 ⎤
V31 = ⎢ − j4 − (j2)(1.02∠9.8 o )⎥ = 0.91∠ − 4.8 o
− j6 ⎣ (1∠0 o ) * ⎦
Test for convergence:
∆V3(1) = V3(1) − V3( 0 ) = 0.09
[
Q2(1) = −Im (1.02∠9.8 o ) * {j1.333 + (− j3.333)(1.02∠9.8 o ) + (j2)(0.91∠ − 4.8 o )} = 0.33 ]
Iteration 2
1 ⎡ 0.6 − j0.33 ⎤
V2( 2 ) = ⎢ − j1.333 − (j2)(0.91∠ − 4.8 o )⎥ = 1.02∠8.2 o
− j3.333 ⎣ (1.02∠9.8 ) *
o
⎦
1 ⎡ − 0.8 + j0.6 ⎤
V3( 2) = ⎢ − j4 − (j2)(1.02∠8.2 o )⎥ = 0.89∠ − 5.7 o
− j6 ⎣ (0.91∠ − 4.8 ) *
o
⎦
∆V3(2) = V3( 2 ) − V3(1) = 0.02
[ ]
Q2( 2) = − Im (1.02∠8.2 0 ) * { j1.333 + (− j 3.333)(1.02∠8.2 0 ) + ( j 2)(0.89∠ − 5.7 0 ) = 0.36
Iteration 3
1 ⎡ 0.6 − j0.36 ⎤
V2( 3) = ⎢ − j1.333 − (j2)(0.89∠ − 5.7 o )⎥ = 1.02∠7.7 o
− j3.333 ⎣ (1.02∠8.2 o ) * ⎦
64
1 ⎡ − 0.8 + j 0.6 ⎤
V3(3) = ⎢ − j 4 − ( j 2)(1.02∠7.7 0 )⎥ = 0.88∠ − 6 0
− j 6 ⎣ (0.89∠ − 5.7 )
0 *
⎦
∆V2(3) = V3( 3) − V3( 2 ) = 0.01
[ ]
Q (23) = − Im (1.02∠7.7 o ) * {j1.333 + (− j3.333)(1.02∠7.7 o ) + (j2)(0.88∠ − 6 o )} = 0.38
The solution has converged and the system bus voltages are
V1 = 1 ∠ 0o V2 = 1.02 ∠ 7.7o and V3 = 0.88 ∠ -6o pu
(ii) Power flows on line 1-3
* *
S13 = V1 ⎛⎜ V1 − V3 ⎞⎟ o ⎡1∠0 − 0.88∠ − 6 ⎤
o o
pu
⎜ ⎟ = 1∠ 0 ⎢ ⎥ = 0.62∠53.5
o
⎝ jx 13 ⎠ ⎣ j0.25 ⎦
* *
S31 = V3 ⎛⎜ V3 − V1 ⎞⎟ ⎡ 0.88∠ − 6 o − 1∠0 o ⎤ pu
⎟ = 0.88∠ − 6 ⎢ ⎥ = 0.62∠ − 126
o
⎜ jx 13 j0.25
⎝ ⎠ ⎣ ⎦
Power loss on line 1-3 = S13 + S31 = 4.4 x 10-3 ∠ -0.0032 o pu
EXERCISES
7.1 The one-line diagram of an unloaded power system is shown in fig. 7.3. The reactance of the transmission line is X=
30Ω. The generators and transformers are rated as follows:
G1: 20 MVA, 12kV, X = 1.20 pu
G2: 60 MVA, 13.8kV, X = 1.40 pu
G3: 20 MVA, 13.2kV, X = 1.20 pu
T1: 25 MVA, 12/69kV, X = 0.08 PU
T2: 60 MVA, 69/13.8kV, X = 0.14 pu
T3: 75 MVA, 13.2/69kV, X = 0.16 pu
Fig 7.3
Choose a power base of 50 MVA and a voltage base of 12kV in the circuit of generator
1. Form the bus admittance matrix.
7.2 The power system shown in fig. 7.4 has the following generator and transformer data.
G1: 50 MVA, 13.2kV, X = 1.20 pu
G2: 20 MVA, 13.2kV, X = 1.10 pu
T1: 60 MVA, 13.2/115kV, X = 0.16 pu
T2: 25 MVA, 34.5/13.2kV, X = 0.10 pu
T3: 60 MVA, 115/34.5kV, X = 0.16 pu
T4: 10 MVA, 4.16/34.5kV, X = 0.05 pu
65
Fig. 7.4
The 115-kV transmission line is 50 km long, and it has a reactance of 0.8 Ω/km. The 34.5-kV line is 10 km long, and it
has a reactance of 1.2 Ω/km. Choose a power base of 50 MVA and a voltage base of 115kV for the high-voltage
transmission line.
a. Choose the voltage bases in the other parts of the system in order that per-unit turns ratios of all transformers
are 1:1.
b. Draw the one-line impedance diagram showing all impedance values in per unit.
c. Form the bus admittance matrix.
7.3 For the power system shown in fig. 7.5, bus 1 is selected as the slack or swing bus and its voltage is set to V1 =
1.0 ∠ 0o pu. The chosen power base is 100 MVA. Generator 2 delivers a real power of 0.75 pu at a voltage of 1.02 pu.
The loads on buses 3 and 4 are SD3 = (0.40 +j0.30) pu and SD4 = (0.80 + j0.60) pu, respectively. The impedance
parameters for the transmission lines referred to the given power base and a voltage base of 115kV are
Line 1-2: Z = (0.01 + j0.05) pu; Y = j0.30 pu
Line 2-3: Z = (0.03 + j0.15) pu; Y = j0.90 pu
Fig 7.5
The transformer is connected between buses 3 and 4, and its reactance is 0.10 pu.
From a flat start, perform one iterate of the Gauss-Siedel iterative technique to find the voltages at buses 2, 3, and 4.
66
CHAPTER EIGHT
POWER SYSTEM PROTECTION
8.1 Introduction
The operation of a power system is affected by disturbances that could be due to natural occurrences such as lightning,
wind, trees, animals, and human errors or accidents. These disturbances could lead to abnormal system conditions such
as short circuits, overloads, and open circuits.
Short circuits, which are also referred to as faults, are of the greatest concern because they could lead to damage to
equipment or system elements and other operating problems including voltage drops, decrease in frequency, loss of
synchronism, and complete system collapse. There is, therefore, a need for a device or a group of devices that is capable
of recognizing a disturbance and acting automatically to alleviate any ill effects on the system element or on the operator.
Such capability is provided by the protection system.
The protection system is designed to disconnect the faulted system element automatically when the short circuit currents
are high enough to present a direct danger to the element or to the system as a whole. When the fault results in overloads
or short-circuit currents that do not present any immediate danger, the protection system will initiate an alarm so that
measures can be implemented to remedy the situation.
8.2.1 Transducers.
The transducer serves as a sensor to detect abnormal system conditions and to transform the high values of short-circuit
current and voltage to lower levels. The main sensors used are the current transformer (CT) and the potential transformer
(PT).
The current transformer is designed to provide a standard continuous secondary current of 5 A. Standard CT ratios
available include 50/5, 100/5, 150/5, 200/5, 250/5, 300/5, 400/5, 600/5, 800/5, 900/5, 1000/5, 1200/5, 1500/5, 1500/5,
and 2000/5. During fault conditions, the short-circuit currents could reach over 10 times normal for short periods of time
without damaging the CT windings.
The current transformer has a primary winding that usually consists of one turn and a secondary winding of several turns.
It is, therefore, unsafe to open-circuit the secondary of a CT whose primary is energized.
The potential transformer is designed to operate at a constant standard secondary voltage of 120 V. For low-voltage
applications, the VT is just like any other two-winding voltage transformer. For primary voltages in the HV and EHV
levels, a capacitor voltage-divider circuit is used together with the VT, forming the capacitor voltage transformer (CVT).
The primary voltage is impressed across the series-connected capacitors. The VT is used to measure the voltage of a few
kilovolts across the capacitor of the smaller capacitance value.
The electromechanical relay develops an electromagnetic force or torque from the signal provided by the transducer; this
force or torque is used to physically open, or close a set of contacts to permit or initiate the tripping of circuit breakers or
actuate an alarm.
67
The solid-state, or static, relay is energized by the same signals as in an electromechanical relay. However, there is no
physical opening, or closing, of the relay contacts. Instead, the switching of the relay contacts is simulated by causing a
solid state device to change its status from conducting (closed position) to non-conducting (open position).
Electromechanical relays predate the solid-state relays. A majority of power system installations still use
electromechanical relays. The improved reliability, versatility, and faster response (as low as one-quarter cycle) of solid-
state relays have made them more attractive. Some electromechanical relays have been replaced by solid-state relays, and
in newer installations a mixture of both types would usually be found.
When the current-carrying contacts of the circuit breaker are opened, an electric field appears across the contacts that
ionizes the medium between them, and an arc is established between the contacts. The circuit breaker must be able to
extinguish, or interrupt, this arc as quickly as possible. The arc is made to take an elongated path, cooled, and finally
extinguished when the AC current feeding the arc passes through its zero value. Sometimes, the arc is extinguished in
air, oil, sulphur hexafluoride (SF6), or a vacuum.
A separate zone of protection is established around each system element as in Fig. 8.1. There is overlapping of adjacent
zones of protection around the circuit breakers. Thus, if a fault occurs within the overlap region, more breakers are
tripped than is actually necessary. On the other hand, if there is no overlap, a fault that occurs in the region between two
zones of protection will not be in either zone, and no protective relay will operate and no circuit breaker will be tripped.
Although each major piece of equipment and transmission line segment is provided with primary protection and the
primary zones of protection are made to overlap, it is still possible for the protection to fail. Hence, there is a need for
backup protection.
68
Fig 8.1 Zones of primary protection in a power system
The backup protection should be designed in such a way that the cause of failure of the primary protection is not going to
cause the same failure in the backup protection. Therefore, the backup protection should be located at a different station
from the primary protection.
Consider a fault on line segment 3-4 of the power system shown in Fig. 8.2. If circuit breaker 3 fails to trip, the backup
relay would trip circuit breaker 1; or, if the circuit breaker 4 fails to trip, the backup relays would trip circuit breakers 7
and 8. Because circuit breaker 1 is located differently from 3 and circuit breakers 7 and 8 are located differently from 4,
the cause of failure of the primary protection would probably not cause failure of the backup protection, which might
happen if the backup protection were provided at 2 or 5 and 6 instead.
If a fault occurred at station C, primary protection would be provided by circuit breakers at 4, 5 and 6. Backup protection
would be located at 3, 7 and 8.
8.4.1 Speed.
The speed of the protection system refers to the operating times of the protective relays. The potential damage to the
faulted element depends on the length of time the short-circuit currents are allowed to flow. The speed of clearing, or
isolating, the faulted system component also affects the stability of the whole system.
Protective relays may be characterized as instantaneous with an operating time of about 0.10s, or as high speed with an
operating time of less than 0.05s. Solid-state, or static, relays can have operating times as low as one quarter of a cycle.
8.4.2 Selectivity.
Selectivity is the ability of the protection system to detect a fault, identify the point at which the fault occurred, and
isolate the faulted circuit element by tripping the minimum number of circuit breakers. Selectivity of the protection
system is obtained by proper coordination of the operating currents and time delays of the protective relays.
8.4.3 Reliability.
The reliability of the protection system is its ability to operate upon the occurrence of any fault for which it was designed
to protect. In other words, the protection system should operate when it is supposed to and not operate when it is not
supposed to.
8.4.4 Sensitivity.
69
Sensitivity refers to the characteristic of a protective relay that it operates reliably, when required, in response to a fault
that produces the minimum short-circuit current flowing through the relay.
A relay is said to pick up when it operates to open its normally closed (NC) contact or to close its normally open (NO)
contact in response to a disturbance to produce a desired control action. The smallest value of the actuating quantity for
the relay to operate is called its pickup value.
A relay is said to reset when it operates to close an open contact that is normally closed (NC) or to open a closed contact
that is normally open (NO). The largest value of the actuating quantity for this to happen is called the reset value.
The instantaneous relay element has no intentional time delay, and it operates quickly from ½ to 3 cycles depending on
the value of the fault current. A typical operating characteristic of this relay type is shown in Fig. 8.3.
The time-delay relay element is characterized by having an operating time that varies inversely as the fault current
flowing through the relay. A typical inverse time characteristic is shown in Fig. 8.3. The time-delay characteristic may be
shifted up or down by adjusting the time-dial setting so that the relay operates with a different time delay for the same
value of fault currents.
The difficulty in using over-current relays is that they are inherently non-selective. They detect over-current (faults) not
only in their own zones of protection but also in adjacent zones. The selectivity can be improved by proper coordination
of the relay pickup values and time-delay settings. As the electric load grows and the power system configuration
changes, operating conditions and magnitudes of short-circuit currents will vary. The pickup values of the over-current
relays have to be readjusted continually in response to these changes.
Over-current relays are popular especially on low-voltage circuits because of their low cost. They are also used in
specific applications on high-voltage systems.
70
Directional relaying is typically used in conjunction with some other relay, usually the over-current relay to improve its
selectivity.
Typical differential relaying employing an over-current relay is shown in Fig. 8.4. Identical current transformers are
placed at both ends of the protected element, and the CT secondaries are connected in parallel with an over-current relay.
The directions of current flows shown in Fig. 8.4 are those corresponding to normal load conditions or to a fault external
to the protected element. Thus, it is seen that the CT secondary currents merely circulate between the CTs, and no
current flows in the over-current relay.
Suppose a fault occurs on the protected element as shown in Fig 8.5. The short-circuit currents flow into the fault, and
the CT secondary currents no longer circulate. The vectorial sum of the CT secondary currents flows through the over-
current relay and causes the relay to disconnect the element from the system.
Even though the current transformers used for the differential relay are identical, the secondary currents may not be
identical because of CT transformation inaccuracies. Thus, the secondary currents will no longer merely circulate for
normal load conditions or for external faults. The differential current that will flow through the over-current relay may be
sufficient for the relay to pick up and cause false tripping of the circuit breakers.
71
The difficulty encountered in differential relaying due to CT errors is eased by the use of a percentage-differential relay.
This type of relay has an operating coil and two restraining coils. The operating current is proportional to (IA-IB) and
must exceed a certain percentage of the restraining current, which is proportional to ½(IA+IB), before the relay will
operate.
This distance relay is useful because it is able to differentiate between a fault and normal operating conditions and to
differentiate between faults in a specific area and a fault in a different part of the system. The operation of the distance
relay is limited to a certain range of pick up values of impedance. The distance relay picks up whenever the measured
impedance is less than or equal to the selected pickup value of impedance.
There are several types of distance relays, including impedance, reactance and mho relays. The mho relay has an
inherent directional characteristic; that is, it responds to or “sees” faults in only one direction. On the other hand, the
impedance and the reactance relays see faults in all directions. Thus, a directional relay is commonly used together with
impedance relay, and a mho relay is used as a starting unit for the reactance relay.
A wire pilot consists of a twisted pair of copper wires of the telephone line type. It may be leased from the telephone
company, or it may be owned by the electric utility.
The power line carrier is the most commonly used pilot for protective relaying. In this type of pilot, a low-voltage, high-
frequency current (30 to 300 kHz) is transmitted along one phase of the high-voltage power line to a receiver at the other
end of the protective line. Line traps, located at both line terminals, serve to contain a carrier signal inside the zone of the
protected line.
The microwave pilot is an ultra-high-frequency radio system operating above 900 MHz. In this pilot, transmitters and
receivers operate the same way as in power line carrier pilot; however, line traps are replaced by a line-of-sight antenna.
When a short circuit occurs between stator windings of a synchronous generator, or between a stator winding and
ground, the protection system should quickly trip the main circuit breaker to disconnect the machine from the rest of the
system and at the same time disconnect the field winding from the exciter.
The best stator winding short-circuit protection is provided by a percentage-differential relay, which is shown in Fig 8.6.
It may be noted that the relaying protect against a two-phase fault, or line-to-line fault, in the stator windings.
72
When the synchronous generator neutral is grounded through a high resistance, the short-circuit current for a single line-
to-ground fault is much less than the short-circuit current for a fault involving the phase windings. Thus, the ground fault
current may not be detected by the differential protection. An over voltage connected across the grounding resistor would
be able to detect the increased voltage across the resistor in the presence of a ground fault, and the over-voltage relay will
operate.
73
in Y-∆ or ∆-Y connections. The current transformers must, therefore, be connected in such a manner that the CT
secondary line currents as seen by the protective relays are equal under normal operating conditions or for external
faults. The correct magnitude relationship is obtained by proper choice of CT ratios and, if necessary, the use of an
autotransformer in the CT secondary circuit. The correct phase-angle relationship is obtained by connecting the CTs on
the Y-connected side of the transformer in delta ∆ and the CTs on the ∆-connected side in Y. In this way, the CT
conditions are able to compensate for the phase shift introduced by the Y-∆ or ∆-Y connection. The design of the
protection for a ∆-Y transformer using percentage-differential relays is illustrated in Fig. 8.8 and the following example.
Example 8.1
Design the protection of a three-phase, 50-MVA, 230/34.5 kV power transformer using available standard CT ratios.
The high-voltage side is Y-connected and the low-voltage side is ∆-connected. Specify the CT ratios, and show the three-
phase wiring diagram indicating the CT polarities. Determine the currents in the transformer and the CTs. Specify the
rating of an autotransformer, if one is needed.
Solution: When the transformer is carrying rated load, the line currents on the high-voltage side and low-voltage side are
50,000
IHV = = 125.5 A
3 (230)
50,000
ILV = = 836.7 A
3 (34.5)
The CTs on the low-voltage side are Y-connected, and the CT ratio selected for this side is 900/5. The current in the
leads flowing to the percentage-differential relay on this side is equal to the CT secondary current and is given by
⎛ 5 ⎞
ILV lead = 836.7 ⎜ ⎟ = 4.65 A
⎝ 900 ⎠
The current in the leads to the relay from the low-voltage side must be balanced by an equal current in the leads
connected to the ∆-connected CTs on the high-voltage side. This requires a CT secondary current equal to
4.65
ICT sec = = 2.68 A
3
To obtain a CT secondary current of 2.68 A, the CT ratio of the high-voltage CTs is chosen as
125.5
CT ratio = = 46.8
2.68
The nearest available standard CT ratio is 250/5. If this CT ratio is selected, the CT secondary currents will actually be
⎛ 5 ⎞
ICT sec = 125.5 ⎜ ⎟ =2.51 A
⎝ 250 ⎠
Therefore, the currents in the leads to the ∆-connected CTs from the percentage-differential relays will be
IHV lead = 3 (2.51) = 4.35 A
74
It is seen that the currents in the leads on both sides of the percentage-differential relay are not balanced. This condition
cannot just be ignored because it could lead to improper tripping of the circuit breaker for an external fault. This problem
can be solved by using an autotransformer as shown in Fig. 8.9. The autotransformer should have a turns ratio of
4.65
Nautotransformer = = 1.07
4.35
In the design of the transformer protection of Example 8.1, the magnetizing current of the transformer has been assumed
to be negligible. This is a reasonable assumption during normal operating conditions because the magnetizing current is a
small percentage of the rated load current. However, when a transformer is being energized, it may draw a large
magnetizing inrush current that soon decays with time to its normal value. The inrush current flows only in the primary,
causing an unbalance in current, and the differential relay will interpret this an internal fault and will pick up to trip the
circuit breakers.
To prevent the protection system from operating and tripping the transformer during its energization, percentage-
differential relaying with harmonic restraint is recommended. This is based on the fact that the magnetizing inrush
current has high harmonic content, whereas the fault current consists mainly of fundamental frequency sinusoid. Thus,
the current supplied to the restraining coil consists of the fundamental and harmonic components of the normal
restraining current of (IA + IB)/2, plus another signal proportional to the harmonic content of the differential current (IA –
IB)/2. Only the fundamental frequency of the differential current is supplied to the operating coil of the relay.
75
Fig 8.10 Bus protection using an over-current relay
All of the CTs are connected in parallel and an over-current relay is connected across their output. When there is no fault
on the bus, the line currents are indicated by the solid arrows, and the current through the over-current relay is given by
1
IR = (I1 + I2 – I3 – I4) = 0
CT ratio
Therefore, no current flows through the relay. On the other hand, when there is a fault at the bus, currents I3 and I4
reverse directions as shown by the broken arrows; thus, the current through the relay is now given by
1
IR = (I1 + I2 + I3 + I4) > 0
CT ratio
Hence, the over-current relay picks up to trip all circuit breakers.
For the low-voltage distribution circuits, the protection system usually provided consists of circuit reclosers and power
fuses that acts as relays and circuit breakers combined. For the protection of medium-voltage and high-voltage
transmission lines, separate relays and circuit breakers are employed. Since HV and EHV transmission lines are the
major means of bulk-power transmission, the protection of these transmission lines is designed to be more reliable and
more selective, and it is also more expensive.
76
The generator connected to bus 1 represents the rest of the power system, and it supplies loads at buses 1, 2, 3, 4 and 5
through four transmission lines. Since the short-circuit current comes from the left side of each line, it is sufficient to
provide only one circuit breaker at the sending end for each line. So that service disruption is minimized, for a fault on
line 4-5, only circuit breaker CB4 should be tripped; for a fault on the line 3-4, only breaker CB3 should be opened; for a
fault on the line2-3, only CB2 should be tripped; and so on.
The short-circuit current due to a fault on any of the lines depends on the fault location and the type of fault. Since the
total impedance increases with the distance from the generator to the fault, the short-circuit current is inversely
proportional to this distance.
Over-current relays are used mainly to provide protection for subtransmission and distribution lines. Two forms of
overcurrent protection are provided: primary protection for the line itself and backup protection for an adjacent line.
Two types of overcurrent relay units are used: time overcurrent relay and instantaneous relay.
The time overcurrent relays at each of the four buses 1, 2, 3 and 4 provide primary protection for their own line segment
and provide remote backup protection to adjacent line downstream from the relay location. Thus, the relay at bus 1
provides primary protection for line 1-2 and also provides backup protection for line 2-3; the relay at bus 2 provides
primary protection for line 2-3 and backup protection for line 3-4; and so forth.
When the relay at bus 1 provides backup protection for line 2-3, it must be adjusted to be selective with the primary
relaying at bus 2. The relay at bus 2 is expected to operate first for a fault on line 2-3 before the relay at bus1 operates.
The operating times of the relays at the different buses are shown in Fig. 8.12.
Thus, for the indicated fault, the relay at bus 4 picks up to trip circuit breaker CB4. If CB4 fails to open for any reason the
fault current persists, and after a certain time delay the relay at bus 3 picks up to trip CB3. The relay at bus 2 is selective
with the relay at bus 3; thus, if both CB3 and CB4 failed to open, the relay at bus 2 would pick up and trip CB2 after a
longer time delay.
For setting the pickup values and the selectivity clearances between the time-delay overcurrent relays for backup
protection, there are four criteria to consider:
1. The relay must be able to pick up for the minimum short-circuit currents for which the relay is designed to
protect.
2. The relay should not pick up for normal load conditions. A common practice is to set the minimum pickup
value equal to twice the peak load current in order to carry emergency peak loads and pick up cold load.
3. The relay nearer the source providing backup protection for the downstream relay must pick up for one third of
the minimum current seen by the latter.
4. The relay nearer the source providing backup protection for the downstream relay should pick up for the
maximum current seen by the latter but no sooner than (a selectivity clearance of) at least 0.3 s.
The instantaneous overcurrent relay unit provides primary protection for its own protected line segment to supplement
the time-delay overcurrent relay unit. The instantaneous unit operates quickly with no intentional time delay, so it should
77
be adjusted such that it does not operate for a fault on neighbouring lines. The pickup value is usually adjusted so that the
instantaneous relay is able to detect a fault occurring at a distance of up to 80% of the line segment. The operating times
of the instantaneous relay and the time-delay units are shown in Fig. 8.13.
The complete protection system for a line consists of three overcurrent relays for phase fault protection and one
overcurrent relay for ground fault protection. This protection system is shown in Fig. 8.14.
Protection of transmission lines connected as a network can be provided by distance relays. These distance relays
provide phase fault protection for the line, while an overcurrent relay provides ground fault protection.
Distance relays provide primary protection for a line section and backup protection for an adjacent line. The value of
impedance at the farthest fault location for which a distance relay picks up is called its “reach.” One distance relay
contains three distance relay units responding to three independently adjustable pickup impedance values (or zones of
protection) with three independently adjustable time delays.
78
The primary impedance corresponding to a particular fault location, or relay unit reach, is converted to a secondary value
that is used to adjust the phase or ground distance relay. This secondary impedance value is given by
⎛ CT ratio ⎞
Zsec = Zpri ⎜
⎜ VT ratio ⎟⎟
⎝ ⎠
The first-zone, or high-speed zone, unit of the distance relay has a reach of up to 80% to 90% of the length of the
transmission line. This relay unit operates with no time delay.
The second-zone unit of the distance relay provides protection for the rest of the line beyond the reach of at least 20% of
the adjoining line section. Because this unit “sees” faults in the adjoining line, it must be selective with the first-zone unit
of the adjacent line. Therefore, this second-zone unit is provided with a time delay of about 0.2s to 0.5s.
The third-zone unit of the distance relay provides backup protection for the rest of the adjoining line section. This unit is
adjusted to reach beyond the end of the adjoining line to ensure that backup protection is provided for the full line
section. The time delay provided for this unit is usually about 0.4s to 1.0s. The protection of a portion of a power system
by using distance relays is illustrated in Fig. 8.15.
EXERCISES
8.1 For the power system of Fig. 8.2, specify the location of the backup protection so that the cause of failure in the
primary protection of the following system components will not cause the same failure in the backup.
a. Line 5-7
b. Line 6-8
c. Station B.
8.2 Consider the power system of Fig. 8.2. In response to a fault, the protection system tripped breakers 3, 7, and 8.
Determine all possible locations of the fault. Determine what single failure had occurred, if any.
8.3 Repeat Problem 8.2 if the breakers tripped are 4, 6, and 7.
8.4 Repeat Problem 8.2 if the breakers tripped are 4, 6, and 8.
8.5 For the three-phase high-voltage bus shown in Fig. 8.16, sketch the developed three-phase wiring diagram for the
bus differential protection using overcurrent relays.
79
Fig 8.16 High-voltage bus of Problem 8.5
8.6 A three-phase step-down transformer bank is rated 10 MVA and 69/13.8kV. The high-voltage side is Y-connected,
and the low-voltage side is ∆-connected. Sketch the developed three-phase wiring diagram for the protection of the
transformer bank using percentage-differential relays. Show all CT ratings, connections, and polarities. Also show
the values of the current in the lines, leads, relay windings, and transformer windings. Indicate the connections and
ratings of any autotransformer that may be needed.
8.7 Repeat Problem 8.6 for the protection of a three-phase power transformer rated 100 MVA and 230/69kV. Assume
that the transformer windings are Y-connected in both the primary and secondary sides.
8.8 Repeat Problem 8.6 when the transformer windings are connected in Y at the primary and in ∆ at the secondary.
8.9 A portion of a power system is shown in Fig. 8.17. Stations A and B have distance relays that are each adjusted for a
first-zone reach of 100 ohms and a third-zone reach of 125 ohms. A fault occurs at F.
a. What is the impedance seen by the relay at A and by the relay at B?
b. Can the relay at A see the fault before the breaker at B has tripped?
c. Can the relay at A see the fault after the breaker at B has tripped?
8.10 Repeat Problem 8.9 if the fault occurs at G and the breaker D2 fails to open. Assume
that the fault current magnitudes are the same as those shown in Fig. 8.17.