ELEVATED SUBSTATION IN SEK Doc Title: Fabrication and Installation Procedure for U/G Piping

Doc. No.: 50614-000-FA5-PRO-0008 Date: 19-Jan.-2014 Rev.C

Attachment # 5: FLOW CHART FOR PIPING WORK PROCEDURE

TRANSPORTATION OF PLAIN END PIPE TO IMCO BY SKEC

UNLOADING IN IMCO WORKSHOP BY IMCO

ALL SPOOLS WILL BE FABRICATED IN IMCO WORKSHOP

FIT-UP & WELDING OF SPOOLS WILL BE CARRIED OUT IN IMCO WORKSHOP

ALL WELDING JOINTS ARE 100% SHOP JOINTS

THE SPOOLS WILL BE UNLOADED BY NCC. INTERNAL & EXTERNAL COATING WILL BE DONE IN NCC YARD. AFTER FINAL INSPECTION FOR COATING, IT WILL BE LOADED BY NCC

AFTER HYDROTEST, THE SPOOLS WILL BE TRANSPORTED TO NCC COATING WORKSHOP BY IMCO

AFTER NDT IS CLEARED, HYDROTEST WILL BE CARRIED OUT ON ALL SPOOLS (100% HYDROTEST) IN IMCO WORKSHOP

ONCE THE FABRICATION OF SPOOLS ARE COMPLETED, NDT WILL BE CARRIED OUT ON SPOOLS

THERE ARE NO WELDING JOINTS IN FIELD & ONLY BOLTING JOINTS ARE ALLOWED IN FIELD

AFTER COATING IS COMPLETED, THE SPOOLS WILL BE TRANSPORTED TO RESPECTIVE GC BY IMCO

ONCE THE CIVIL EXCAVATION ARE COMPLETED AND INSPECTIONS DONE, THE PIPE WILL BE LAID IN THE EXCAVATED AREA & BOLTING OF FLANGE JOINTS WILL BE DONE. AFTER, BOLT TORQUE TIGHTENING WILL BE DONE ON BOLTED JOINTS

INSPECTION NOTIFICATION WILL BE SUBMITTED TO PMC BEFORE 24 HOURS PRIOR FOR HYDROTEST

AFTER ALL BOLTING JOINTS ARE DONE IN FIELD, FIELD HYDROTEST WILL BE CARRIED OUT TO CHECK FOR ANY LEAKS

AFTER HYDROTEST ARE DONE , HOLIDAY TEST FOR COATED PIPE WILL BE INSPECTED

AFTER SUCCESSFULLY COMPLETING THE INSPECTION, THE BACKFILLING WILL BE CARRIED OUT

SUBMIT INSPECTION NOTIFICATION FOR SURVEY REPORT PRIOR TO BACKFILLING