Sei sulla pagina 1di 2

BUILT-UP RATE FOR PLASTERING

TENDER FILE NO :

PROJECT :

LOCATION :

SUPPLIER :

SUB-CONTRACTOR :

QUOTATION DATE :

Material Cost

Cement 10.35 per bags 50kg ( Including Rm 0.25 for unloading )


White Lime 3.90 per bags 13kg
Plasterlime Lime 2.00 per bags 10kg
Sand (ex-mining) 250.00 per loads ( 14 cu. yard ) or 23.48 per m3
Sand (wash fine) 15.00 per cu. Yard 19.50 per m3

Cement & Sand ( 1:6 ) Mixed Material Cost

Cement ( 1440kg/50 ) @ 1 m3 29 bags @ 10.35 300.15


Lime ( 1 bag / 100 ft2 ) 3 bags @ 3.90 11.70
Sand (ex-mining) 6 m3 @ 23.48 140.89
Total cost For 5 m3 452.74

Net volume after shrinkage @ 33 1/3% 4.67 m3

Material cost per m3 96.97


Plant cost ( Concrete mixer @ 3.50/m3 ) 3.50
Total Cost : 100.47

Labour Cost
Internal Plastering 8.60 per m2 ( 0.80 per ft2 )
300mm String 4.92 per m ( 1.50 per ft2 )
External Plastering 8.60 per m2 ( 0.80 per ft2 )

Plastering - Internal Cost / m2


Cement & Sand (1:6) 16mm thk 20mm thk
Material cost 1.61 2.01
Wastage @ 5% 0.08 0.10
Total material cost / m2 1.69 2.11
Labour Cost 8.60 8.60
Plant Cost ( Inclusived ) - -
Tender Cost / m2 10.29 10.71
Plastering - 300mm String Cost / m
Cement & Sand (1:6) 16mm thk 20mm thk
300mm high 300mm high
Material cost 0.48 0.60
Wastage @ 5% 0.02 0.03
Total material cost / m2 0.51 0.63
Labour Cost 4.92 4.92
Plant Cost ( Inclusived ) - -
Tender Cost / m 5.43 5.55

Plastering - External Cost / m2


Cement & Sand (1:6) 20mm thk 25mm thk
Material cost 2.01 2.51
Wastage @ 5% 0.10 0.13
Total material cost / m2 2.11 2.64
Labour Cost 8.60 8.60
Plant Cost ( Inclusived ) - -
Tender Cost / m2 10.71 11.24

Potrebbero piacerti anche