Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Task Mode
Task Name
Duration
Start
Finish
Tue 19 Nov 12
Fri 22 Nov 0 12 0
Mon 25 Nov 12
Scoping Identify Client and their needs Fill out Client form and get project approved Meet the client to discuss their requirements First Questionnaire Second Questionnaire Project outlined and contract created Planning Work Breakdown Structure Gantt Chart SWOT Needs Analysis Risk Assessment Design & Development Website Design Create Interface Design Create detailed storyboard of design for client Show client and get approval Graphics
39 days 1 day 1 day 1 day 1 day 1 day 2 days 9 days 3 days 1 day 2 days 1 day 2 days 38 days 35 days 5 days 3 days 2 days 1 day 33 days
Fri 22/11/13 Wed 15/01/14 Fri 22/11/13 Fri 22/11/13 Mon Mon 25/11/13 25/11/13 Wed Wed 27/11/13 27/11/13 Mon 06/01/14Mon 06/01/14 Wed 08/01/14Wed 08/01/14 Tue 14/01/14 Wed 15/01/14 Mon 20/01/14Thu 30/01/14 Mon 20/01/14Wed 22/01/14 Fri 24/01/14 Fri 24/01/14 Fri 24/01/14 Mon 27/01/14 Tue 28/01/14 Tue 28/01/14 Wed 29/01/14Thu 30/01/14 Fri 10/01/14 Tue 04/03/14 Fri 10/01/14 Thu 27/02/14 Sun 02/02/14 Sat 08/02/14 Sun 02/02/14 Tue 04/02/14 Wed Thu 06/02/14 05/02/14 Sat 08/02/14 Sat 08/02/14 Fri 10/01/14 Tue 25/02/14
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 1
ID 21 22 23
Task Mode
Task Name
Duration
Start
Finish
Tue 19 Nov 12
Fri 22 Nov 0 12 0
Mon 25 Nov 12
Create graphics for background 4 days Create animated graphics for 4 days background Create any other graphics 4 days needed (Determined by the interface design) Show client and get approval 1 day Content 2 days Source Content 1 day Proof read text 1 day Edit Images 1 day Business Cards 2 days Show client business card samples 1 day Confirm selection Create design using Adobe InDesign Show designs to client Get approval from client Send design to the printers CV Create design using InDesign Show client to get approval 1 day 2 days 1 day 1 day 1 day 2 days 2 days 1 day
Fri 10/01/14 Wed 15/01/14 Sat 15/02/14 Wed 19/02/14 Thu 20/02/14 Tue 25/02/14
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Tue 25/02/14 Tue 25/02/14 Wed 26/02/14Thu 27/02/14 Wed 26/02/14Wed 26/02/14 Wed 26/02/14Wed 26/02/14 Thu 27/02/14 Thu 27/02/14 Thu 27/02/14 Fri 28/02/14 Thu 27/02/14 Thu 27/02/14 Thu 27/02/14 Thu 27/02/14 Thu 27/02/14 Fri 28/02/14 Fri 28/02/14 Fri 28/02/14 Fri 28/02/14 Fri 28/02/14 Fri 28/02/14 Fri 28/02/14 Sat 01/03/14 Tue 04/03/14 Sat 01/03/14 Mon 03/03/14 Mon 03/03/14Mon 03/03/14
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 2
ID 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59
Task Mode
Task Name
Duration
Start
Finish
Tue 19 Nov 12
Fri 22 Nov 0 12 0
Mon 25 Nov 12
Print test CV's to experiment with 1 day paper thickness/ quality Confirm selection with client 1 day Print CV 1 day Gantt Chart Update 1 day Website Implementation 11 days Learning Software 4 days Learnt technology behind parallax 3 days scrolling site Create test site to experiment 2 days Production 7 days Create the site, using the interface 5 days design as a guide Add the graphics to the test 1 day Test 1 day Add content 1 day Test 1 day Show client to get feedback 1 day Make changes 2 days Show client and get website 1 day approved Creating the website 1 day Put website onto server 1 day Gantt Chart Update 1 day Project Delivery 1 day
Task Split
Mon Mon 03/03/14 03/03/14 Tue 04/03/14 Tue 04/03/14 Tue 04/03/14 Tue 04/03/14 Tue 04/03/14 Tue 04/03/14 Tue 04/03/14 Tue 18/03/14 Tue 04/03/14 Fri 07/03/14 Tue 04/03/14 Thu 06/03/14 Thu 06/03/14 Fri 07/03/14 Fri 07/03/14 Mon 17/03/14 Fri 07/03/14 Thu 13/03/14 Thu 13/03/14 Thu 13/03/14 Thu 13/03/14 Thu 13/03/14 Fri 14/03/14 Fri 14/03/14 Fri 14/03/14 Fri 14/03/14 Fri 14/03/14 Fri 14/03/14 Fri 14/03/14 Mon 17/03/14 Mon Mon 17/03/14 17/03/14 Tue 18/03/14 Tue 18/03/14 Tue 18/03/14 Tue 18/03/14 Tue 18/03/14 Tue 18/03/14 Tue 18/03/14 Tue 18/03/14
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 3 Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress
ID 60 61 62 63 64 65 66 67 68 69 70 71 72
Task Mode
Task Name
Duration
Start
Finish
Tue 19 Nov 12
Fri 22 Nov 0 12 0
Mon 25 Nov 12
Review project with client Ensure project is running to plan Testing Usability Testing Accessability Testing Error Catching Correct any faults Does it meet the clients needs? Sign off project Sign off project document Meet with client and show project Both sign end of project document Final Evaluation (1500 Words)
1 day 1 day 1 day 1 day 1 day 1 day 1 day 1 day 39 days 1 day 1 day 1 day 2 days
Tue 18/03/14 Tue 18/03/14 Tue 18/03/14 Tue 18/03/14 Wed 19/03/14Wed 19/03/14 Wed 19/03/14Wed 19/03/14 Wed 19/03/14Wed 19/03/14 Wed 19/03/14Wed 19/03/14 Wed 19/03/14Wed 19/03/14 Wed 19/03/14Wed 19/03/14 Fri 24/01/14 Wed 19/03/14 Fri 24/01/14 Fri 24/01/14 Wed 19/03/14Wed 19/03/14 Wed 19/03/14Wed 19/03/14 Wed 19/03/14Thu 20/03/14
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 4
Thu 28 Nov 12
Sun 01 Dec 12
Wed 04 Dec 12
Sat 07 Dec 12
Tue 10 Dec 12
Fri 13 Dec 0 12 0
Mon 16 De 1
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 5
Thu 28 Nov 12
Sun 01 Dec 12
Wed 04 Dec 12
Sat 07 Dec 12
Tue 10 Dec 12
Fri 13 Dec 0 12 0
Mon 16 De 1
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 6
Thu 28 Nov 12
Sun 01 Dec 12
Wed 04 Dec 12
Sat 07 Dec 12
Tue 10 Dec 12
Fri 13 Dec 0 12 0
Mon 16 De 1
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 7
Thu 28 Nov 12
Sun 01 Dec 12
Wed 04 Dec 12
Sat 07 Dec 12
Tue 10 Dec 12
Fri 13 Dec 0 12 0
Mon 16 De 1
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 8
Mon 16 Dec 12
Thu 19 Dec 12
Sun 22 Dec 12
Wed 25 Dec 12
Sat 28 Dec 12
Tue 31 Dec 12
Fri 03 Jan 0 12
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 9
Mon 16 Dec 12
Thu 19 Dec 12
Sun 22 Dec 12
Wed 25 Dec 12
Sat 28 Dec 12
Tue 31 Dec 12
Fri 03 Jan 0 12
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 10
Mon 16 Dec 12
Thu 19 Dec 12
Sun 22 Dec 12
Wed 25 Dec 12
Sat 28 Dec 12
Tue 31 Dec 12
Fri 03 Jan 0 12
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 11
Mon 16 Dec 12
Thu 19 Dec 12
Sun 22 Dec 12
Wed 25 Dec 12
Sat 28 Dec 12
Tue 31 Dec 12
Fri 03 Jan 0 12
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 12
Mon 06 Jan 12
Thu 09 Jan 12
Sun 12 Jan 12
Wed 15 Jan 12
Sat 18 Jan 0 12 0
Tue 21 Jan 12
Fri 24 Jan 0
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 13
Mon 06 Jan 12
Thu 09 Jan 12
Sun 12 Jan 12
Wed 15 Jan 12
Sat 18 Jan 0 12 0
Tue 21 Jan 12
Fri 24 Jan 0
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 14
Mon 06 Jan 12
Thu 09 Jan 12
Sun 12 Jan 12
Wed 15 Jan 12
Sat 18 Jan 0 12 0
Tue 21 Jan 12
Fri 24 Jan 0
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 15
Mon 06 Jan 12
Thu 09 Jan 12
Sun 12 Jan 12
Wed 15 Jan 12
Sat 18 Jan 0 12 0
Tue 21 Jan 12
Fri 24 Jan 0
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 16
Fri 24 Jan 12 0
Mon 27 Jan 12
Thu 30 Jan 12
Sun 02 Feb 12
Wed 05 Feb 12
Sat 08 Feb 12
Tue 11 Feb 12
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 17
Fri 24 Jan 12 0
Mon 27 Jan 12
Thu 30 Jan 12
Sun 02 Feb 12
Wed 05 Feb 12
Sat 08 Feb 12
Tue 11 Feb 12
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 18
Fri 24 Jan 12 0
Mon 27 Jan 12
Thu 30 Jan 12
Sun 02 Feb 12
Wed 05 Feb 12
Sat 08 Feb 12
Tue 11 Feb 12
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 19
Fri 24 Jan 12 0
Mon 27 Jan 12
Thu 30 Jan 12
Sun 02 Feb 12
Wed 05 Feb 12
Sat 08 Feb 12
Tue 11 Feb 12
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 20
Fri 14 Feb 0 12 0
Mon 17 Feb 12
Thu 20 Feb 12
Sun 23 Feb 12
Wed 26 Feb 12
Sat 01 Mar 12
Tue 04 Ma 1
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 21
Fri 14 Feb 0 12 0
Mon 17 Feb 12
Thu 20 Feb 12
Sun 23 Feb 12
Wed 26 Feb 12
Sat 01 Mar 12
Tue 04 Ma 1
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 22
Fri 14 Feb 0 12 0
Mon 17 Feb 12
Thu 20 Feb 12
Sun 23 Feb 12
Wed 26 Feb 12
Sat 01 Mar 12
Tue 04 Ma 1
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 23
Fri 14 Feb 0 12 0
Mon 17 Feb 12
Thu 20 Feb 12
Sun 23 Feb 12
Wed 26 Feb 12
Sat 01 Mar 12
Tue 04 Ma 1
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 24
Tue 04 Mar 12
Fri 07 Mar 12
Mon 10 Mar 12
Thu 13 Mar 12
Sun 16 Mar 12
Wed 19 Mar 12
Sat 22 Mar 12
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 25
Tue 04 Mar 12
Fri 07 Mar 12
Mon 10 Mar 12
Thu 13 Mar 12
Sun 16 Mar 12
Wed 19 Mar 12
Sat 22 Mar 12
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 26
Tue 04 Mar 12
Fri 07 Mar 12
Mon 10 Mar 12
Thu 13 Mar 12
Sun 16 Mar 12
Wed 19 Mar 12
Sat 22 Mar 12
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 27
Tue 04 Mar 12
Fri 07 Mar 12
Mon 10 Mar 12
Thu 13 Mar 12
Sun 16 Mar 12
Wed 19 Mar 12
Sat 22 Mar 12
Task Split Project: Project Plan Date: Fri 24/01/14 Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Page 28