Bianca Jane B.

Maaliw IT-5 PERT/CPM C (2wks)


Installation & commissioning hardware

J (1day)
Core module & training

A (1wk)
High Level analysis

N (1wk) I (1wk)
Quality assurance of supporting modules Detailed training

E (2wks)
Detailed analysis of core modules

K (1wk)
Development & QA of accounting reporting

Critical path: 1. ABCJN= 4.286 weeks 2. ADFHJN= 8.143 weeks 3. ADEGIN= 10 weeks 4. ADEKN= 7 weeks 5. ADELMN= 8 weeks Therefore, the critical or longest path is ADEGIN With expected completion time of 10 weeks.