GUMUSUT KAKAP DESIGN CHANGE NOTE 02 COLD PERMIT DEMOLITION (PIPING) WCR 0201 HOT PERMIT

DCN No: Location: Shutdown: Scaffolding Requirement:

0118 OFFSHORE-FPS NO YES

REMOVAL OF LINE PIPE WCR-301001 BASED ON DCN-PI-118

P5-GKT-WCR-301001-NOR-N-E SHT 14 REV. 1, P5-GKT-WCR-301001-NOR-N-E SHT 12 REV. 1, GKT-300-PX-2365-555009-011 Drawing/ REV. 06C, GKT-300-PX-2365-555003-011 REV. 06C Document Ref:

Task 1 2 3 4 5

Task Description
MATERIAL HANDLING & PREPATORY WORK SITE CHECK / WORK PREPARATION VERIFY ALL ASSOCIATED LINE AS PER ISOLATION PLAN SAFE HABITAT/ FIRE BLANKET PREPARATION + REMOVAL CUT AT JT #120, 132, #133 & #135 FIRWATCHER ASSIST ON TASK #5

Area
W-ID MODULE W-ID MODULE W-ID MODULE W-ID MODULE W-ID MODULE W-ID MODULE W-ID MODULE W-ID MODULE W-ID MODULE W-ID MODULE W-ID MODULE W-ID MODULE

Trade
RG RG RG

Est. Mhr
1.0 0.5 2.0 10.0 0.84 1.13 2.54 1.47 1.60 0.94 5.6 1.7 1.7 1.0

Bud. Mhr
1.0 0.5 2.0 10.0 1.01 1.26 2.54 1.76 1.82 0.94 5.6 1.7 1.7 1.0

Act. Mhr

Act. %

SHT WF FW RG WF FW RG RG RG RG RG

6 7

RIG DOWN SPOOL #45 & #49 CUT AT JT #124, #125, #126, #127, #128 , #129 & #131 FIRWATCHER ASSIST ON TASK #6

8 9 10 11 12

RIG DOWN SPOOL #46 & #47 UNBOLT FLANGE CONNECTION AT JT #124, #126, #127 & #131 SECURE & REMOVE BUTTERFLY VALVE VAVLE (TAG NO : 301-MV-0504)

SECURE & REMOVE GAS TURBINE FLOW METER (TAG NO : GB-FZIT-185) W-ID MODULE HOUSEKEPING W-ID MODULE

Jobcard Total: Actual Start: Actual Finish: Status: ITEM


1

32.83

PROJECT MATERIALS REFER TO MTO LIST

QUANTITY

LOCATION
ID WEST MODULE

REMARKS

PETRA: NAME: DATE: SIGNATURE: PREPARED BY : NASHAR KHUSAIRI

QA/QC PETRA NAME: DATE: SIGNATURE:

SHELL NAME: DATE: SIGNATURE: APPROVED BY :

Potrebbero piacerti anche