API-653 Pre-Course Workbook and Examination Study Guide

Introduction and Workbook

API-653 - Inspection, Repair, Alteration, & Reconstruction API-650 - Welded Steel Storage Tanks API-651 - Cathodic Protection API-652 - Lining Aboveground Tanks API - 2207 - Preparing for Hot Work API-2015 - Safe Entry & Cleaning of Tanks API-575 - Inspection of Storage Tanks ASME Section IX - Welding Qualifications ASME Section V Nondestructive Examination

Presented by:

Hellier Codes & Standards Training


and

BAY Technical Associates, Inc. (610) 594-9036

Subject Introduction & Workbook

Issue Date 08/98

Revision Date 07/00

Page 1

Statement

This course manual has been prepared by BAY Technical Associates, Inc., strictly for the use of attendees to this Hellier/BAY Tech API-653 Examination Preparation Course. This manual is to be used as an aid to assist those persons wishing to take the API-653 Aboveground Storage Tank Inspector Certification Examination. This manual is not allinclusive and may not be used in place of any recognized Code or Standard. The information contained in this manual was obtained from the authors research and experience and through numerous published resources including: American Petroleum Institute Codes, Standards, and Recommended Practices: API-653, Tank Inspection, Repair, Alteration, and Reconstruction API-650, Welded Steel Tanks for Oil Storage API-575, Inspection of Atmospheric and Low Pressure Storage Tanks API-651, Cathodic Protection of Aboveground Petroleum Storage Tanks API-652, Lining of Aboveground Petroleum Storage Tank Bottoms API-2015, Cleaning Petroleum Storage Tanks API-2207, Preparing Tank Bottoms for Hoe Work American Society of Mechanical Engineers (ASME) Boiler & Pressure Vessel Codes: ASME Section V, Nondestructive Examination ASME Section IX, Welding and Brazing Qualifications The Procedure Handbook of Arc Welding, Twelfth Edition: The Lincoln Electric Co. Metals and How to Weld Them, Second Edition: The James F. Lincoln Arc Welding Foundation. This manual may not be reproduced by any means without the express written consent of BAY Technical Associates, Inc.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject Introduction & Workbook

Issue Date 08/98

Revision Date 07/00

Page 2

Preface The API-653 Aboveground Storage Tank Inspector Certification Examination consists of two parts; an Open Book part and a Closed Book part. The open book portion of the examination contains approximately forty to fifty-five (40 to 55) questions. This part of the examination requires the use of detailed information that the inspector must be able to research in the permitted documents, and is not expected to have committed to memory. Not all open book questions are mathematical in nature. The closed book portion of the examination represents the remaining questions. Some of the closed book questions require the applicant to perform basic math; remember to have your calculator available. The closed book portion tests the inspector on knowledge and tasks requiring everyday working knowledge of API Standard 653 and the applicable reference documents. This examination preparation course is designed to prepare the participant to successfully sit for the API-653 exam. Through your concentrated effort, and the material provided in this course, you should have sufficient information to pass the examination. The majority of the classroom study will focus on the Open Book portion of the exam. The goal, since this is open book, is to obtain a perfect score in this section. Study for the practical questions (Closed Book) will be included in the daily classroom activity and assigned homework. The material contained in this manual is to be thoroughly studied and practiced prior to attending the course. The math examples and practice problems are based on the types of questions given on the API-653 exam. Through the use of these examples, you will be exposed to many of the formulas used during the course. Remember, this is a very intense course. There will be eight hours of classroom study each day. The instructor will be available by phone, fax, or e-mail each evening between 7:00pm and 9:00pm to answer questions or to assist any participant having difficulty with the homework assignments or any topic discussed during class. Typically, there will be two to three hours of homework assignments each day. Daily quizzes are given and one practice API-653 examination is provided. The pace is fast and focused. The participant is responsible for making all arrangements for taking the examination including confirming your eligibility and applying to the American Petroleum Institute.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject Introduction & Workbook Introduction: Objective for this section: At the end of this section, you should be able to:

Issue Date 08/98

Revision Date 07/00

Page 3

1. List the required reference manuals you must bring to the course 2. List the reference material permitted during the exam 3. Know where you can obtain ASME and API Code books 4. List what material will be provided during the course 5. Explain the structure of the API-653 Exam How to use this Pre-Course Study Guide: 1. Review the basic math skills section and complete the practice math test. 2. Complete the reading assignments, 3. Research and answers the questions in the "Practical Questions" section of this study guide (chapters 2 through 10). 4. Compare your answers with the answer guide at the end of each section.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject Introduction & Workbook Required Reference Material

Issue Date 08/98

Revision Date 07/00

Page 4

You must bring the following API Standards, API Recommended Practices (RP), ASME Code books, and material with you to the course: 1. API Standard 650, Welded Steel Tanks for Oil Storage, 10th Edition 2. API Standard 653, Tank Inspection, Repair, Alteration, and Reconstruction, 2nd Edition, December 1995; including Addendum 1, 2, & 3 3. API Standard 2015, Safe Entry and Cleaning of Petroleum Storage Tanks, 5th Edition (May 1994) 4. API Publication 2207, Preparing Tank Bottoms for Hot Work, 5th Edition (September 1998) 5 API RP - 575, Inspection of Atmospheric & Low Pressure Storage Tanks, 1st Edition, (November, 1995) 6. API RP - 651, Cathodic Protection of Aboveground Petroleum Storage Tanks, 2nd Edition (December 1997) 7. API RP - 652, Lining of Aboveground Storage Tank Bottoms, 2nd Edition (December 1997) 8. ASME Section V, Nondestructive Examination, 1998 Edition & 1999 Addenda 9. ASME Section IX, Welding and Brazing Qualifications, 1998 Edition & 1999 Addenda 10. This Study Manual 11. Non-Programmable Calculator

To order ASME Code books, you may call the ASME at 1(800) THE-ASME (843-2763) or you can write them at: ASME Order Department 22 Law Drive Box 2300 Fairfield, NJ 07007-2300 To order API Documents, you may call them at: 1(202) 682-8375 or you can write them at: American Petroleum Institute Order desk 1220 L Street Washington, DC 20005

Hellier and BAY Technical Associates, Inc. will not provide Code books.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject Introduction & Workbook

Issue Date 08/98

Revision Date 07/00

Page 5

Hellier and BAY Technical Associates, Inc. will provide: 1. Pre-course Study Manual 2. Student Reference Manual (Provided on Day-one) 3. Certificate of Completion Hellier and BAY Technical Associates, Inc. will have available for reference: 1. Welding reference books 2. Overhead transparencies 3. Various applicable reference documents The structure of the API-653 Examination: The API-653 Examination is given on Saturday September 23,2000. The exam consists of an open book portion and a closed book portion You will have not more than five hours to complete the entire examination. The questions consist of multiple choice and true/false type questions. You are permitted and required to use the following Reference books during the open book portion of the exam: 1. API Standard 650, Welded Steel Tanks for Oil Storage, 10th Edition 2. API Standard 653, Tank Inspection, Repair, Alteration, and Reconstruction, 2nd Edition, December 1995; including Addendum 1 - 3 3. API Standard 2015, Safe Entry and Cleaning of Petroleum Storage Tanks, 5th Edition (May 1994) 4. API Publication 2207, Preparing Tank Bottoms for Hot Work, 5th Edition (September 1998) 5 API RP - 575, Inspection of Atmospheric & Low Pressure Storage Tanks, 1st Edition, (November, 1995) 6. API RP - 651, Cathodic Protection of Aboveground Petroleum Storage Tanks, 2nd Edition (December 1997) 7. API RP - 652, Lining of Aboveground Storage Tank Bottoms, 2nd Edition (December 1997) 8. ASME Section V, Nondestructive Examination, 1998 Edition & 1999 Addenda 9. ASME Section IX, Welding and Brazing Qualifications, 1998 Edition & 1999 Addenda No reference material of any kind will be permitted during the closed book portion; some examining proctors may permit language translation dictionaries. There will be some common knowledge mathematical questions on the practical portion of the exam - remember to have your calculator available for this part of the exam. During this course, we will attempt to duplicate actual examination conditions including using a separate answer sheet during the practice examination.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject Introduction & Workbook

Issue Date 08/98

Revision Date 07/00

Page 6

NOTES

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject Introduction & Workbook Reading Assignments:

Issue Date 08/98

Revision Date 07/00

Page 7

At the end of this section, you should: 1. Have completed the reading assignments 2. Be familiar with the layout and structure of each API Standards, API Recommended Practices, and ASME Code Books used in the course and on the exam. (These Standards, RPs, and Code books will be referred to as "Reference books" in this section) 3. Compile a list of questions concerning paragraphs/subjects you do not understand. The classroom portion of this American Petroleum Institute examination preparation course is focused on the "open book" portion of the exam. A thorough understanding each reference book is also essential in order to answer the closed book questions on the exam. All Reference books will be reviewed and discussed during the course. Many hours of the homework assignments will be reading selected portions of each Reference book. The course begins up-to-speed on day one and continues until the practice exam. It is essential that you complete the "pre-course" reading assignments. You are not expected understand all that you read, but the familiarity gained will assist you in keeping up and not becoming overwhelmed on the first day of class. If during the course of reading this material you have questions, do not dwell too long on the subject. Write your question down and be sure to ask for clarification during the course. Do not try to memorize Reference book paragraphs at this time, selected portions will be pointed out for highlighting and memorization during the course. Studying and researching the example questions and answers provided in the "Pre-Course Workbook and Study Guide" should be sufficient for exam purposes. The first thing one realizes, when they begin working with these Reference books, is that they are dynamic and change constantly. An inspector should never rely on memorized passages, but should instead always research the answer to a question; that is why understanding the structure of the Reference books is imperative. Reading Assignments: It is highly recommended that you obtain a set of tabs or binder index pages. The API permits tabs, indexes, highlighting, underlining, and some written notes in the margins; they do not permit any type of inserted pages in the Reference books. API Standard 650, Welded Steel Tanks for Oil Storage: Title Foreword Asbestos Information Required Ordering Information Section 1 - Scope Section 2 - Materials Section 4 - Fabrication Section 7 - Welding Section 8 - Marking Paragraph(s) All All All All All All All All Pages(s) iii iv xiii 1-1 through 1-4 2-1 through 2-8 4-1 7-1 through 7-2 8-1 through 8-2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject Introduction & Workbook

Issue Date 08/98

Revision Date 07/00

Page 8

API Standard 653, Tank Inspection, Repair, Alteration, and Reconstruction: Entire document must be read. You should be thoroughly familiar with this standard. API Standard 2015, Safe Entry and Cleaning of Petroleum Storage Tanks Read this entire document - remember this is a safety code to help ensure your ability to survive your daily work. The API takes a dim view of your answers to questions if they could result in injury to yourself or others. API Publication 2207, Preparing Tank Bottoms for Hot Work Entire document must be read. You should be thoroughly familiar with this publication API Recommended Practice 651, Cathodic Protection of Aboveground Petroleum Storage Tanks Sections 1 through 6 - Pages 1 through paragraph 6.3.5 on page 11. Recommended Practice 652, Lining of Aboveground Petroleum Storage Tank Bottoms Entire document must be read. You should be thoroughly familiar with this RP. Recommended Practice 575, Inspection Atmospheric and Low Pressure Storage Tanks Entire document must be read. You should be thoroughly familiar with this RP ASME Section V Nondestructive Examination: Title Subsection A - Article 1 Subsection A - Article 2 Subsection A - Article 5 Subsection A - Article 6 Subsection A - Article 7 Paragraph(s) All T-210 through T-292 T-510 through T-594 T-600 through T-690 T-710 through T-791

ASME Section IX, Welding and Brazing Qualifications: Title Foreword Introduction Part QW - Article I Part QW - Article II Part QW - Article III Part QW - Article IV Part QW - Article IV Paragraph(s) All All QW-100 through QW-196.2.2 QW-200 through QW-251.4 QW-300 through QW-361.2(h) QW-400 through QW-401.5 Graphics QW-460 through 461.9

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject Introduction & Workbook Pre-Course Workbook Practice Mathematics Objective:

Issue Date 08/98

Revision Date 07/00

Page 9

At the end of this section, you should: 1. 2. 3. 4. Be familiar with the basic types of mathematics used on the exam. Have taken and self graded the pre and post math tests Have reviewed the basic mathematical functions Worked the practice problems

A Pre-Test is provided on pages 15 & 16 with the answers on page 20 & 21 Practice problems are provided on pages 17 through 19 with the answers on pages 22 & 23 A Post-Test is provided on page 24 with answers on pages 25 & 26

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject Introduction & Workbook

Issue Date 08/98

Revision Date 07/00

Page 10

MATH Calculation questions found on the API-653 examination are oriented toward existing tanks and not new tanks. API authorized above ground storage tank inspectors are expected to be able to check and perform calculations necessary to ensure compliance with appropriate Codes and standards. For this reason, the inspector must have a thorough understanding of the formulas and procedures used to calculate the following: Corrosion Rates and Inspection Intervals Remaining Life determination Joint Efficiencies Maximum Height (Hydrostatic Testing) Determining appropriate weld sizes for shell opening Minimum spacing between existing and new hot tap nozzles Settlement evaluation including the number of survey points Minimum Thickness for Existing and Reconstructed Tank Shells Corroded areas of tank shells including evaluation of pitting Bottom plate thickness determination and evaluation Reinforcement of openings The American Petroleum Institute does not permit the use of programmable calculators while taking the exam; therefore, programmable calculators will not be permitted during the course. A recommended answer sheet layout format for use during the course is provided in this section. Using the layout will help keep your procedures straight and make it easier for you to check your work. This format is only recommended. The remainder of this section deals with the typical mathematical skill level required. It is divided into modules: Pre-Test, Basic Math Functions, and Post-Test. Typically, if a formula requires transposing, the appropriate formula is given in the examination question however, you should have a basic understanding of Algebra. Completion and understanding of this portion of the pre-course manual will increase your chances of passing the exam as well as enhancing your ability to keep up with the pace during the course. Should you have difficulty with any portion of this math section, you should obtain assistance. In any case, you should complete all the problems and practice them until you are comfortable with them.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject Introduction & Workbook

Issue Date 08/98

Revision Date 07/00

Page 11

Recommended Math Page Layout Name Answer (a) Page ____of_____ Answer (b) Answer (c) Answer (d) Drawing if Applicable Page Number

Problem Number

Given Information:

Final Formula

Formula with Variables Plugged In

Show all Work

Find:

Reference:

Formula to use:

Formula Transposition

Answer:

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject Introduction & Workbook

Issue Date 08/98

Revision Date 07/00

Page 12

Recommended Math Page Layout Name: Answer (a) Answer (b) Answer (c) Answer (d) Drawing if Applicable Page Number

Problem Number

Page ____of_____

Given Information:

Final Formula

Formula with Variables Plugged In (Note:) At this point make sure you have: a value for each variable, included the correct sign, and included the correct information within any parentheses or brackets) Show all Work

Find: (what does the question ask)

Reference: (Code book and paragraph)

Formula to use:

Formula Transposition

Answer:

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject Introduction & Workbook Mathematics Fundamentals:

Issue Date 08/98

Revision Date 07/00

Page 13

As we all know, mathematics has a language of its own, made up of signs, symbols, and characters. During this course of study many common mathematical signs, symbols, and characters, which you must be familiar with, will be used. Some of these are listed below. + Addition Subtraction Multiplication Division Pi Expressed as 3.14 Less than Greater than Therefore Less than or equal to Greater than or equal to Equal Number squared Square root

< > = X2

()

In addition to the symbols, we will use the common Arabic numerals 1,2,3,4, (etc) and the letters of the alphabet to develop our mathematical problems and solutions. How we use this language is determined by the structure of the question. In our use of the language of math, all equations must be complete and retain their equality throughout in order to be useful. One of the first things that must be clear is the order in which operations must be performed. An operation is a function caused by the sign in the equation. For instance, the + sign tells us to add two or more characters together. In the following statement 12+87 doesnt tell us anything; just two numbers separated by an addition sign. If we add the = sign, now the statement asks a question: 12+87=X, when we replace the X with the correct answer we have completed the equation 12+87=99 is a true statement and meets all the requirements of an equation for our purposes. Order of Operations and Grouping: Operation 1. Addition 2. Subtraction 3. Multiplication 4. Division Grouping 1. Parentheses ( ) 2. Brackets [ ] 3. Braces { }

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject Introduction & Workbook

Issue Date 08/98

Revision Date 07/00

Page 14

Clarification: At this point, it is assumed that the participant is already familiar with the basics of addition, subtraction, multiplication, and division. Finding areas of shapes will follow customary rules. The area of a circle can be found using A = R2 or A = (.7854)(d2). Algebra The first rule in algebraic statements is the equality of the equation must remain throughout the steps leading to the final solution. In other words, the left side of the equal sign must always equal the right side of the equal sign. In order to ensure this, always remember: whatever you do to one side of the equal sign, you must also do to the other side of the equal sign. Lets look at the following equation: tm = t + c If we know all the variables except the minimum required design thickness, we can transpose the formula to solve for the thickness. tm c = t t = tm c
t = .3165 .0625 t = .254"

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject Introduction & Workbook Pre-Test:

Issue Date 08/98

Revision Date 07/00

Page 15

1. Find the minimum acceptable shell plate thickness of the first course of an existing AST. t min D H G S E
t min = 2.6 DHG SE

= Minimum acceptable thickness = Nominal diameter of tank, in feet = Height of tank in feet = Specific gravity of contents = Maximum allowable stress = Joint efficiency of tank

? 120 48 1 21000 .85

2. Find the corrosion rate of an AST given the following information. Original thickness = .875 Measured thickness = .625 Years since last thickness measurement = 11 CR = t original t last Time

3. Using the corrosion rate determined in problem number 2, what would the remaining life expectancy of this tank be if the minimum required thickness is 0.436?
RL = t actual t min imum CR

4. Shell settlement evaluation measurements are to be taken on a 146 feet diameter AST. Given the following formula, how many elevation measurements would be required? N= D 10

5. Using the information in number four, does this number meet the requirements of API653, which does not permit the measurement points to exceed 32 feet?
Dis tan ce =

D
N

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject Introduction & Workbook Pre-Test continued:

Issue Date 08/98

Revision Date 07/00

Page 16

6. Find the throat of a right angle fillet weld with a weld leg length of .4375 inches.

7. Using the following information, what is the maximum vertical length (also known as critical length), in inches, over which hoop stresses are assumed to average out around local discontinuities? Diameter of the tank is 136 feet, the least thickness in an area of corrosion, exclusive of pits, is determined to be .563 L = 3.7 Dt 2

8. A 6 inch nozzle is to be placed in the tank shell of an AST. The shell course where the nozzle will be installed is .875 thick. What is the required area of reinforcement? A = ODnozzle t shell

9. The maximum ultrasonic thickness measurement interval shall be five years when the corrosion rate is not known. What is the interval based on a known corrosion rate? The tank information is as follows: Initial thickness of the tank was 1.0625, the actual thickness is .815, the calculated required thickness is .473, the tank has been in service for 16 years with no measurements taken since it was installed. RCA = .342 N = .015
Interval = RCA 2N

10. What is the circumference of an AST that is 96 feet in diameter?

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject Introduction & Workbook

Issue Date 08/98

Revision Date 07/00

Page 17

Practice problems #1: Problem #1 Find S when t min , D, H, G, and E are known where: D=78, H=29, G = 1, E=.85, and t min =.602
t min = 2.6 DHG SE

Problem #2 Find E when D, H, G, S, G, and t min are known where: D =128, H=60, S = 22,300 G = .87, and t min = 1.125
t min = 2.6 DHG SE

Problem #3 Find D when H, E, S, G, and t min are known where: H=45, E=.90, S=22500, G= .7 and t min = .9375 t min = 2.6 DHG SE

Problem #4 Find S t when E, H t , D, G, and t min are know where: E = .80, H t = 54, D= 70, G = 1 and t min =.4325
Ht = S t Et min 2.6 D

Problem #5 Find C when D and H are know where D = 60, H = 54 C = 014 . D2 H

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject Introduction & Workbook

Issue Date 08/98

Revision Date 07/00

Page 18

Lets go a step farther: What do we do when our Unknown is inside a radical (square root symbol)? We know all the values except for the d .7854 a= d .7854 a2 = d 2 da = .7854 .7854 d= a2 Step 1 -To eliminate the radical, we must do the opposite of its function. The opposite function of extracting a square root is to square the variable. We square both sides of the equation. Step 2 - .7854 is divided by d. The opposite of division is multiplication; therefore we multiply both sides by the d Step 3 - a2 is multiplied by d. We perform the opposite function and divide both sides by a2

Practice Problems #2 Problem # 1 Find d when a=1.0755 a = .7854d 2

Problem # 2 Find D when t=.875, L=32.5 L = 3.7 Dt 2

Problem # 3 Find t initial when L longterm CR=.015, T years = 19 and t last = 1.134

CR =

t initial t last Tyears

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject Introduction & Workbook Practice Problems # 3 Problem # 1 Exponents: (a) 43 = ? (b) (23)(24) = ?

Issue Date 08/98

Revision Date 07/00

Page 19

(c) Calculator display 1.0137-3 would be written as ?

Problem # 2 Square Root: (a) X = 3 + 9 (b) X = 196 . .0013 (c) Find t L = 3.7 Dt 2

Problem # 3 Fractions: (a) 3 5 1 1 5 + + = (b) + = 3 6 7 7 7


4 1 = 7 2 3 2 (f) 1 = 4 5

3 1 (c) 2 + 3 = 8 6 (g)
3 7 = 8 9

(d)

5 3 = 6 6
3 2 3 = 10 3 4

(e)

(h)

3 2 5 5 (i) 1 2 = (j) = 8 3 8 11

3 1 (k) 1 2 = 4 2

1 1 (l) 3 1 = 3 6

Problem # 4 Ratios and Proportions: (a)


N 2 = N = 9 3

(b)

3 N = N = 4 12

(c)

2 3 = K = K 15

Problem # 5 Area: A 24-inch nozzle is to be installed in a 1.0625 thick shell course. What is the required area of reinforcement?

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject Introduction & Workbook Pre-Test: ANSWERS

Issue Date 08/98

Revision Date 07/00

Page 20

1. Find the minimum acceptable shell plate thickness of the first course of an AST. Tmin D H G S E
t min = 2.6 DHG SE

= Minimum acceptable thickness = Nominal diameter of tank, in feet = Height of tank in feet = Specific gravity of contents = Maximum allowable stress = Joint efficiency of tank
14976 (2.6)(120)(48)(1) t min = = .839" 17850 (21000)(.85)

? 120 48 1 21000 .85

t min =

2. Find the corrosion rate of an AST given the following information. Original thickness = .875 Measured thickness = .625 Years since last thickness measurement = 11 CR = t original t last Time CR = .875.625 CR =.023 11

3. Using the corrosion rate determined in problem number 2, what would the remaining life expectancy of this tank be if the minimum required thickness is 0.436?
RL = t actual t min imum CR RL = .625.436 RL = 8.2 years .023

4. Shell settlement evaluation measurements are to be taken on a 146 feet diameter AST. Given the following formula, how many elevation measurements would be required?
N= D 146 N = 14.6 = 15 N= 10 10

5. Using the information in number four, does this number meet the requirements of API653, which does not permit the measurement points to exceed 32 feet?
(314 . )(146) Distance = 30.5ft. yes meet requirements N 15 Reference: API-653 Paragraph 10.5.1.2 definition of N Dis tan ce = Dis tan ce =

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject Introduction & Workbook Pre-Test continued: ANSWERS

Issue Date 08/98

Revision Date 07/00

Page 21

6. Find the throat of a right angle fillet weld with a weld leg length of .4375 inches. Throat =.707Wleg Throat = (.707)(.4375) Throat = .309

7. Using the following information, what is the maximum vertical length (also known as critical length), in inches, over which hoop stresses are assumed to average out around local discontinuities? Diameter of the tank is 136 feet, the least thickness in an area of corrosion, exclusive of pits, is determined to be .563

L = 3.7 Dt 2

L = 3.7 (136)(.563) L = 3.7 76.568 L = (3.7)(8.75) L = 32.375"

8. A 6 inch nozzle is to be placed in the tank shell of an AST. The shell course where the nozzle will be installed is .875 thick. What is the required area of reinforcement?
A = ODnozzle t shell A = (6.75)(.875) = 5.906 square inches API-650 3.7.2.1 & 3.7.2.2

9. The maximum ultrasonic thickness measurement interval shall be five years when the corrosion rate is not known. What is the interval based on a known corrosion rate? The tank information is as follows: Initial thickness of the tank was 1.0625, the actual thickness is .815, the calculated required thickness is .473, the tank has been in service for 16 years with no measurements taken since it was installed. RCA = .342 N = .015 .342 RCA . years API-653 4.3.3.2 b. = 114 Interval = Interval = (2)(.015) 2N

10. What is the circumference of an AST that is 96 feet in diameter? Circumference = D Circumference = (3.14)(96) = 301.44 feet.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject Introduction & Workbook Practice problems #1: Problem #1

Issue Date 08/98

Revision Date 07/00

Page 22

Find S when t min , D, H, G, and E are known where: D=78, H=29, G = 1, E=.85, and t min =.602
t min =

(2.6)(78)(29)(1) 58812 2.6 DHG . 2.6 DHG S = 11493.4 S= S= S= (.85)(.602) SE .5117 Et min

Problem #2 Find E when D, H, G, S, G, and t min are known where: D =128, H=60, S = 22,300 G = .87, and t min = 1.125
t min =

(2.6)(128)(60)(.87) 17372.16 2.6 DHG 2.6 DHG E= E = .692 E= E= (22300)(1125 . ) 25087.5 SE St min

Problem #3 Find D when H, E, S, G, and t min are known where: H=45, E=.90, S=22500, G= .7 and t min = .9375 t min = t SE 2.6 DHG D = min SE 2.6 HG

Problem #4 Find S t when E, H t , D, G, and t min are know where: E = .80, H t = 54, D= 70, G = 1 and t min =.4325
Ht = S t Et min 2.6 D

Problem #5 Find C when D and H are know where D = 60, H = 54

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject Introduction & Workbook

Issue Date 08/98

Revision Date 07/00

Page 23

Practice Problems #2 Problem # 1 Find d when a=1.0755 a = .7854d 2 Problem # 2 Find D when t=.875, L=32.5 L = 3.7 Dt 2 Problem # 3 Find t initial when L longterm CR=.015, T years = 19 and t last = 1.134 t t CR = initial last Tyears Practice Problems # 3 Problem # 1 Exponents: (a) 43 = 64 (b) (23)(24) = 27 or 128 (c) Calculator display 1.0137-3 is written as .0010137 Problem # 2 Square Root: (a) X = 3 + 9 = 3.4641 (b) X = 196 . .0013 =1.3993 2 L L2 3.7 (c) Find t 2 L = 3.7 Dt 2 t 2 = or t 2 = D D(3.7) 2 Problem # 3 Fractions: (a)
1 5 5 3 1 1 3 5 1 3 2 1 13 (b) + = 1 (c) 2 + 3 = 5 (d) = + + =1 3 6 6 6 3 6 7 7 7 8 7 6 24 4 1 1 = 7 2 14 3 2 3 7 7 7 (f) 1 = 1 (g) = 4 5 8 9 24 20

(e)

(h)

3 2 3 3 = 10 3 4 20

3 2 5 3 1 5 1 7 1 6 1 1 (i) 1 2 = 1 (j) = 1 (k) 1 2 = (l) 3 1 = 2 8 3 8 4 3 6 11 2 10 7 4 15

Problem # 4 Ratios and Proportions: N 2 3 N (a) (b) = = N =6 N =9 9 3 4 12 Problem # 5 Area:

(c)

2 3 = K = 10 K 15

A 24-inch nozzle is to be installed in a 1.0625 thick shell course. What is the required area of reinforcement? API-650 Para. 3.7.2.1 & 3.7.2.2 (24)(1.0625) = 25.5 sq in
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject Introduction & Workbook Post Test:

Issue Date 08/98

Revision Date 07/00

Page 24

1. What is the required hydrostatic test height (H t ) of an AST given the following data? Maximum allowable hydrostatic stress (S t )= 21350 Diameter of the tank = 110 feet Hydrostatic test shell thickness (t min ) is .625 Shell joint efficiency = 70% Use API-653 2.3.3.1 formula for tanks to be hydrostatically tested. 2. What is the area of a tank bottom that is 121 feet in diameter? 3. A reinforcing plate is installed around a nozzle in the first course of an AST. What is the throat dimension of the leg fillet weld around the periphery of the reinforcing plate. 4. What is the minimum acceptable thickness of the bottom course of an existing AST that is 135 feet in diameter, maximum fill height is 56.5 feet? The product stored in the tank has a specific gravity of .87 and all shell butt-welds were 100% radiographically examined. The yield strength of the material is 28,000 and the tensile strength is 60,000. Use API-653 paragraph 2.3.3.1.
t min = 2.6 DHG SE

5. What is the required area of reinforcement for a 14 NPS nozzle installed in a shell course that is 1.0625 thick. Use API 650 Paragraph 3.7.2.1 6. A bulge is noted in a tank bottom, what is the maximum height of the bulge permitted if the radius of the inscribed circle is 10.8 feet? Use API-653 Appendix B 3.3 7. If the throat of a fillet weld is .309, what is the leg length of the weld? 8. An AST is 175 feet in diameter. How many tank settlement survey points are required? Use API-653 paragraph 10.5.1.2.

9. Do the number of settlement measurement locations and maximum spacing, calculated in problem 8, comply with API 653? Use API 653 Paragraph 10.5.1.2 10. What is the design liquid level of an AST that is 140 feet in diameter, thickness of the bottom or first course is .765, stress of the material is 21300. The specific gravity of the product to be stored is 1 and no corrosion allowance is needed nor provided.
td = 2.6 D( H 1)G t d Sd + CA H = +1 2.6 DG Sd

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject Introduction & Workbook Post Test Answers

Issue Date 08/98

Revision Date 07/00

Page 25

1. What is the required hydrostatic test height (H t ) of an AST given the following data? Maximum allowable hydrostatic stress (S t )= 21350 Diameter of the tank = 110 feet Hydrostatic test shell thickness (t min ) is .625 Shell joint efficiency = 70% Use API-653 2.3.3.1 formula for tanks to be hydrostatically tested.
Ht = S t Et min (21350)(.7)(.625) 9340.625 Ht = = = 32.6 ft 286 (2.6)(110) 2.6 D

2. What is the area of a tank bottom that is 121 feet in diameter?


A = R 2 A = (3.14)(60.5)2 A = (3.14)(3660.25) A = 11493 sqft

3. A reinforcing plate is installed around a nozzle in the first course of an AST. What is the throat dimension of the leg fillet weld around the periphery of the reinforcing plate. Throat = .707W leg Throat = (.707)(.5) = .3535 4. What is the minimum acceptable thickness of the bottom course of an existing AST that is 135 feet in diameter, maximum fill height is 56.5 feet? The product stored in the tank has a specific gravity of .87 and all shell butt-welds were 100% radiographically examined. The yield strength of the material is 28,000 and the tensile strength is 60,000. Use API-653 paragraph 2.3.3.1.
t min =

(2.6)(135)(56.5)(.87) 2.6 DHG 17253.405 t min = t min = =.7" (24640)(1) SE 24640 S = (.429)(60000) = 25740

S = (.8)(28000) = 24640

5. What is the required area of reinforcement for a 14 NPS nozzle installed in a shell course that is 1.0625 thick. Area = (14)(1.0625) = 14.875 square inches

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject Introduction & Workbook Post Test Answers

Issue Date 08/98

Revision Date 07/00

Page 26

6. A bulge is noted in a tank bottom, what is the maximum height of the bulge permitted if the radius of the inscribed circle is 10.8 feet? B B = .37R B B = (.37)(10.8) = 3.996 inches or 4 inches 7. If the throat of a fillet weld is .309, what is the leg length of the weld?
Throat .309 Wleg = =.437" .707 .707 8. An AST is 175 feet in diameter. How many tank settlement survey points are required? Use API-653 paragraph 10.5.1.2.

Throat =.707Wleg Wleg =

N=

D 175 N= = 17.5 10 10

9. Do the number of settlement measurement locations and maximum spacing, calculated in problem 8, comply with API 653? Yes (175)(3.14) = 549.3 549.3 18 = 30.5 feet spacing

10. What is the design liquid level of an AST that is 140 feet in diameter, thickness of the bottom or first course is .765, stress of the material is 21300. The specific gravity of the product to be stored is 1 and no corrosion allowance is needed nor provided.
td = 2.6 D( H 1)G (.765)(21300) t d Sd + CA H = +1 H = +1 2.6 DG (2.6)(140)(1) Sd

16294.5 H= + 1 H = 44.76 + 1 H = 45.76 feet 364

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 1

Section 1 - Introduction 1. API-653 covers which of the following types of tanks? a) Carbon and low alloy steel tanks built to ASME Section VIII, Div.1 b) Carbon and low alloy steel tanks built to ASME Section X c) Carbon and low alloy steel tanks built to API - 650 and 12C d) Carbon and low alloy steel tanks built to API - 510 Reference: API-653 Paragraph 1.1.1 2. API-653 provides the requirements for construction of which of the following? a) Process pressure vessels b) Aboveground petroleum storage tanks c) LNG Storage spheres d) This standard does not provide construction requirements Reference: API-653 Paragraph 1.1.1 3. API-653 provides for all but which of the following with regard to aboveground storage tanks? a) Repair b) Operation c) Relocation d) Alteration Reference: API-653 Paragraph 1.1.1

4. The scope of API-653 is limited to all of the following except? a) Tank foundation b) Tank Bottom c) Tank roof d) Tank mixing motor Reference: API-653 Paragraph 1.1.2

5. The API-653 standards states that many of the requirements for design, welding, and materials of API-650 and API-12C can be applied with regard to _____. a) Repair, inspection, rating, and alteration. b) Repair, personnel assignment, maintenance, and inspection. c) Inspection, product in storage, rating, and alteration. d) Alteration, refinery equipment, electrical controls, and repair. Reference: API-653 Paragraph 1.1.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 2

6.

In the application of the requirements for welding, design, and materials of API-650 or API-12C to in-service aboveground storage tanks (AST), which of the following code or standard takes precedence? a) ASME Section VIII, Pressure Vessels b) API-12C c) API-653 d) API-650

Reference: API-653 Paragraph 1.1.2 7. The API-653 Standard may only be applied to aboveground storage tanks (AST) that have been constructed to and meet the requirements of API-650. a) True b) False Reference: API-653 Paragraph 1.1.3 8. The use of API-653 is intended for organizations that have personnel who are technically trained and experienced in which of the following? a) All ASME, AWS, ASNT, and API Codes and Standards b) Tank design, fabrication, repair, construction, and inspection c) Refinery operations, safety requirements, personnel management, and refinery design d) Mechanical integrity program, OSHA regulations compliance program, and Process Safety Management Reference: API-653 Paragraph 1.1.4 9. When design and construction details are not given and not available in the original construction standard, then details that will provide a level of integrity equal to the current edition of what Code or Standard must be used? a) ASME Section VIII, Division 1, Pressure Vessels b) ASME Section VIII Division 2, Alternative Rules for Pressure Vessels c) API- 650, Welded Steel Tanks for Oil Storage d) API-12C Steel Storage Tanks for Oil Storage Reference: API-653 Paragraph 1.1.5 10. Ultimate responsibility for compliance with this standard rests with ____? a) The Owner/Operator b) The Owner/Operators Inspector c) The repair organization of the Owner/Operator d) The manufacturer of the AST Reference: API-653 Paragraph 1.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 3

11. According to API-653, if any provision presents a direct or implied conflict with any statutory regulation, the regulation governs. What governs if API-653 requirements are more stringent than the statutory regulation? a) The statutory regulation applies in all cases b) The conflict must be submitted to the American Petroleum Institute for resolution c) The owner/operator has the option of applying the requirement best suited to the situation d) The API-653 requirements shall govern Reference: API-653 Paragraph 1.3 12. Safe working practices shall comply with what requirements concerning confined space entry? a) Procedures must comply with any trade developed safety precautions b) Procedures must comply with any federal or state regulations c) Procedures need only comply with owner/operator/s requirements d) Procedures need only comply with NFPA requirements Reference: API-653 Paragraph 1.4

Answers to API-653 Section 1, Introduction


Question Number 1 2 3 4 5 6 7 8 9 10 11 12 Answer C D B D A C B B C A D B

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 4

Section 2 Suitability for Service 1. When must an evaluation, to determine the suitability for continued use, be conducted? a) Evaluations shall be conducted when a tank inspection reveals a change has occurred from the original physical condition of the tank. b) Evaluations shall be conducted at least annually c) Evaluations shall be conducted at an interval not to exceed the calculated tank inspection frequency. d) Evaluations shall be conducted once each ten years of service Reference: API-653 Paragraph 2.1.1 2. What factors are required for consideration when performing an evaluation for continued use of an AST? a) Only those listed in API-653 b) The recommended list of considerations provided in API-510 can be modified to suit this purpose c) Engineering analysis and judgement required for each situation d) Only those items requested by the Certified Aboveground Storage Tank Inspector Reference: API-653 Paragraph 2.1.3 3. Roof plates corroded to an average thickness of less that ____ inch in any ___ square inch area shall be repaired of replaced. a) 0.9 inch in any 100 square inch area b) 0.09 inch in any 10 square inch area c) 0.09 inch in any 144 square inch area (1 square foot) d) 0.09 inch in any 100 square inch area Reference: API-653 Paragraph 2.2.1.2 4. The method of inspecting roof support members shall be acceptable to whom? a) The manufacturer of the AST b) The responsible inspector c) The Owner/Operators design engineering department d) The operations manager Reference: API-653 Paragraph 2.2.2 5. During the inspection of fixed roof support members, particular attention must be given to . a) Severe external corrosion of the roof plate where support structures are attached b) Severe internal corrosion of pipe columns c) Severe internal corrosion of the roof plate where support structures are attached d) Deterioration of wind girders at the point of attachment Reference: API-653 Paragraph 2.2.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 5

6. Inspection of floating roofs is limited to roof plates and pontoons. a) True b) False Reference: API-653 Paragraph 2.2.3.3 7. Evaluation of existing floating roofs shall be based on the criteria of a) API-650, Appendix C for external floating roofs and Appendix H for internal floating roofs b) API-510 Paragraph 6.4.3 for external floating roofs and 6.5.3 for internal c) ASME Section VIII, Div 1 Appendix C for external floating roofs and Appendix H for internal d) ASME Section VIII, Div. 2 Alternative Rules Reference: API-653 Paragraph 2.2.3.4 8. What API Standard or Recommended Practice must be used for evaluating the effects of design partial vacuum on tank roofs? a) API Standard 620 b) API Standard 650 c) API Recommended Practice 651 d) API Recommended Practice 652 Reference: API-653 Paragraph 2.2.4.2 9. Above what operating temperature shall API Standard 650, Appendix M, be considered before changing the service of a tank? a) 500F b) 400F c) 300F d) 200F Reference: API-653 Paragraph 2.2.4.3 10. Under what conditions may a tank be operated at a temperature lower than the original design? a) When the requirements for impact testing of ASME Section VIII, Division 1 have been met b) When the requirements of the applicable standard or API Standard 650 have been met c) When the requirements of ASTM Specification A-370 have been met d) When the requirements of ASTM Specification A-20 have been met Reference: API-653 Paragraph 2.2.4.4

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 6

11. Flaws, deterioration, or other conditions that might adversely affect the performance or structural integrity of the shell of an existing tank must be evaluated. Personnel experienced in tank design shall conduct the evaluation. This analysis shall take into account any of the following except a) Fluid static head b) Internal and external pressure c) Organization that manufactured the tank d) Seismic loads Reference: API-653 Paragraph 2.3.1.2 12. Of the following, which is not an option available to the owner/operator if it is not possible to satisfy the requirements for minimum thickness calculations for a welded tank? a) Repair damaged areas b) Reduce allowable liquid level c) Retire the tank d) Reduce the fill rate so the tank fills slower and applies pressure gradually Reference: API-653 Paragraph 2.3.1.5 13. Out-of-roundness, buckled areas, flat spots, and peaking and banding of welded joints are all examples of _____. a) Shell Distortions b) Flaws c) Discontinuities d) Severe damage Reference: API-653 Paragraph 2.3.5.1 14. Shell distortions require the tank to be immediately removed from service and inspected. a) True b) False Reference: API-653 Paragraph 2.3.5.3 15. Flaws such as cracks or laminations shall be thoroughly examined to determine their nature and extent and the need for repairs. a) True b) False Reference: API-653 Paragraph 2.3.6

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 7

16. What if anything should be done with cracks in the shell-to-bottom weld? a) These cracks can be sealed with caulking and the tank returned to service b) The welds can have a cover weld pass applied over them to prevent leakage c) Cracks of this type are critical and the tank must be retired from service since repairs are prohibited. d) Cracks in the shell-to-bottom weld are critical and shall be removed and the weld repaired Reference: API-653 Paragraph 2.3.6 17. Internal pitting and pitting rates in the anticipated service, corrosion of weld joints (weld and heat affected zone), weld joint cracking history, and stresses placed on the bottom plates by roof support loads and shell settlement are all examples of causes of what type of failure? a) Annular ring failure b) Shell plate failure at first shell course c) Bottom failure d) Fatigue failure due to repeated jacking of floor plates Reference: API-653 Paragraph 2.4.2 18. Underside corrosion (normally in the form of pitting), inadequate drainage resulting in surface water flowing under the tank bottom, lack of an annular plate ring when required, uneven settlement that results in high localized stresses in the bottom plates, and inadequate provision for movement of roof support columns and other supports are all examples of causes of what type of failure? a) Shell plate failure at first course b) Bottom failure c) Failure of support columns due to hydraulic compression d) Creep cracking failure Reference: API-653 Paragraph 2.4.2 19. Of the following what has historically not been a cause of bottom failures? a) Non-homogeneous fill under the tank bottom b) Rock or gravel foundation pads with inadequately filled-in surface voids c) Inadequate inspection frequency d) Inadequately supported sumps Reference: API-653 Paragraph 2.4.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 8

20. Where would you look to find the basis for cathodic protection systems for the underside of tank bottoms? a) API Recommended Practice 651 b) API Recommended Practice 652 c) API Standard 2015 d) API Standard 2207 Reference: API-653 Paragraph 2.4.3 21. Where would you look to find procedures and practices for protecting tank bottoms with internal lining? a) API Recommended Practice 651 b) API Recommended Practice 652 c) API Standard 2015 d) API Standard 2207 Reference: API-653 Paragraph 2.4.4 22. What two methods may be used in quantifying the remaining thickness of tank bottoms? a) Drilling and actual measurement b) Ultrasonic and radiography c) Deterministic and probabilistic d) Detailed stress analysis and plate deformation measurement Reference: API-653 Paragraph 2.4.7 23. Unless a stress analysis is performed, what is the minimum thickness of bottom plates in the critical zone? a) Smaller of the original bottom plate thickness or 50% of t min of the lower shell course but not less than 0.1 inch. b) Smaller of the original bottom plate thickness or 25% of t min of the lower shell course but not less than 0.1 inch. c) Smaller of the original bottom plate thickness or 75% of t min of the lower shell course but not less than 0.1 inch. d) Smaller of the original bottom plate thickness or 50% of t min of the lower shell course but not less than 0.01 inch. Reference: API-653 Paragraph 2.4.7.4 24. When repairing internal pitting for the extension of in-service operating period, the repair shall be by any of the following methods except. a) Pit welding b) Brazing c) Overlay welding d) Lap Patching Reference: API-653 Paragraph 2.4.7.5

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 9

25. The thickness of the bottom plate projection beyond the shell, measured at the toe of the weld of the outside bottom-to-shell fillet weld shall be not less than? a) 0.25 inch b) 0.01 inch c) 0.50 inch d) 0.10 inch Reference: API-653 Paragraph 2.4.7.7 26. The projection of the bottom plate beyond the toe of the shell-to-bottom weld shall be at least? a) 0.125 inch b) 0.250 inch c) 0.375 inch d) 0.500 inch Reference: API-653 Paragraph 2.4.7.7 27. An aboveground storage tank contains a fluid with a specific gravity of less than one. The thickness of the plate in the first course is 7/8. What is the minimum thickness of the annular plate ring, seismic loading is not a consideration, and the stress in the first course is 27,850 pound per square inch? a) 0.22 inch b) 0.31 inch c) 0.20 inch d) 0.23 inch Reference: API-653 Paragraph 2.4.8.2 and Table 2-3 28. An aboveground storage tank contains a fluid with a specific gravity of greater than one. The thickness of the plate in the first course is 7/8. What is the minimum thickness of the annular plate ring, seismic loading is not a consideration, and the hydrostatic test stress in the first shell course is 27,850 pound per square inch?
a) b) c) d) 1 / 4 inch 3 / 8 inch 9 / 32 inch 11 / 32 inch

Reference: API-653 Paragraph 2.4.8.3 and Table 3-1 API-650 29. Settlement, erosion, cracking, and deterioration of concrete are all examples of which of the following principle modes of failure or deterioration? a) Annular plate ring failure b) Shell-to-bottom weld failure c) Deterioration of walkways and roadways d) Deterioration of foundations Reference: API-653 Paragraph 2.5.1.1

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 10

30. To ensure suitability for service, what is the minimum permitted frequency of tank foundation inspection? a) Annually b) Every five years c) Monthly d) Periodically Reference: API-653 Paragraphs 2.5.1.1 & 4.3.1.2 31. Distortion of anchor bolts and excessive cracking of concrete structures may be indications of what two conditions? a) Serious foundation settlement of a tank overpressure uplift condition b) Inferior material used in the anchor bolts and the concrete structure c) Over tightening of the anchor bolts and improper mixing of the concrete d) The tank was struck by lightning and wind caused movement of the tank Reference: API-653 Paragraph 2.5.3 Message to the student: API-653 Paragraph 2.5.1.2 contains descriptions of some mechanisms of concrete deterioration. It would be in your best interest to read these descriptions carefully and understand them. The examination may contain questions that would require you to know the definition of one or more of these modes of deterioration.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 11

Answers to API-653 Section 2, Suitability for Service


Question Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Answer A C D B B B A A D B C D A B A D C B C A B C A B D C B C D C A

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 12

Section 3 Brittle Fracture Considerations 1. Incidents of tank failure due to brittle fracture have occurred shortly after erection during hydrostatic testing or in all but which of the following incidents? a) On the first filling in cold weather b) After a change to a higher temperature service c) After a change to a lower temperature service d) After a repair or alteration Reference: API-653 Paragraph 3.2.1 2. The risk of tank failure due to brittle fracture is considered minimal after what condition(s)? a) The tank has demonstrated its ability to withstand the combined effects of maximum liquid level (highest stresses) and highest operating temperature b) The tank has demonstrated its ability to withstand the combined effects of intermediate liquid level (highest stresses) and lowest operating temperature c) The tank has demonstrated its ability to withstand the combined effects of maximum liquid level (highest stresses) and lowest operating temperature d) The tank has demonstrated its ability to withstand the combined effects of maximum liquid level (highest stresses) and intermediate operating temperature

Reference: API-653 Paragraph 3.2.1 3. If it is decided to change the service to a more severe service, it is necessary to a) Consider the need for pneumatically testing the entire tank b) Consider the need to recalculate the effectiveness of all reinforcement of openings c) Consider the need for hydrostatic testing d) Consider removing all previous welded repairs and have them redone Reference: API-653 Paragraph 3.2.2 4. If a tank shell thickness is less than _____ inch, and an evaluation in accordance with Section 2 of API-653 has been performed, the risk of brittle fracture is considered to be minimal. a) 0.01 b) 0.10 c) 0.05 d) 0.50 Reference: API-653 Paragraph 3.3.4 5. No known tank failures attributed to brittle fracture have occurred at shell metal temperatures of _____F and above. a) -20 b) 20 c) 40 d) 60 Reference: API-653 Paragraph 3.3.5
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 13

6.

According to industry experience and laboratory tests, what membrane stress is required to caused failure due to brittle fracture? a) 6 ksi b) 7 ksi c) 10 ksi d) 12 ksi

Reference: API-653 Paragraph 3.3.6 7. What is the lowest temperature that a tank, constructed of carbon steel of unknown toughness, may be used? The maximum thickness of the shell is .625 a) 40F b) 45F c) 50F d) 55F Reference: API-653 Paragraph 3.3.7 and Figure 3-2 8. What is the purpose of Figure 3-1 of API-653? a) Provides a procedure to be used in the evaluation of the remaining life of tank bottom plates b) Provides a procedure to be used in the evaluation of the likelihood of floating roof pontoon failure c) Provides an assessment procedure for evaluating aboveground storage tanks operating at 15 psi d) Provides an assessment procedure for evaluating atmospheric aboveground storage tanks Reference: API-653 Paragraph 3.3 and Figure 3-1 Answers to API-653 Section 3, Brittle Fracture Considerations Question Number Answer 1 B 2 C 3 C 4 D 5 D 6 B 7 A 8 D Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 14

Section 4 Inspection 1. What is the purpose of periodic in-service inspection? a) The purpose of periodic in-service inspection, assure job security for inspectors b) The purpose of periodic in-service inspection, assure proper operation of AST c) The purpose of periodic in-service inspection is to assure continued tank integrity d) The purpose of periodic in-service inspection is to assure OSHA compliance Reference: API-653 Paragraph 4.1 2. Of the following, which is not a consideration that must be addressed in determining inspection intervals for ASTs? a) Corrosion prevention systems b) Inspection interval of other equipment located near the tank under consideration c) Changes in service (including changes in water bottoms) d) Previous inspection results Reference: API-653 Paragraph 4.2.1 3. What methods of inspection must be considered when establishing inspection frequencies? a) On-stream core sample inspection b) On-stream nondestructive inspection c) In-service aerial inspection d) In-service groundwater inspection Reference: API-653 Paragraph 4.2.2 4. Close visual inspections of aboveground storage tanks, from the ground, are required. Owner/operator personnel who may be other than the Authorized Inspector may perform this inspection. The interval of such inspections shall not exceed: a) At least every five years or 1/4 the corrosion rate life of the shell whichever is less b) 12 months c) 6 months d) 1 month Reference: API-653 Paragraph 4.3.1.2 5. All tanks shall be given a visual external inspection, by an Authorized Inspector, at what frequency? a) Inspection conducted at least every 20 years or at the quarter corrosion rate of the bottom whichever is less b) Inspection conducted at least every 5 years or at the quarter corrosion rate of the bottom whichever is less c) Inspection conducted at least every 5 years or at the quarter corrosion rate of the shell whichever is less d) Inspection conducted at least every 20 years or at the quarter corrosion rate of the shell whichever is less Reference: API-653 Paragraph 4.3.2.1
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 15

6. External ultrasonic thickness measurements of the shell, while the tank is in service, can be a means of determining rate of uniform corrosion. The extent of UT measurements shall be determined by the owner/operator. What is maximum interval of such thickness measurements when the corrosion rate is not known? a) Five years b) Three years c) One year d) Every three months until the corrosion rate is established
Reference: API-653 Paragraph 4.3.3.2a.

7. The minimum thickness of a tank was established at 0.585 inch. The shell was fabricated from 3/4 inch plate and included a 0.125 inch corrosion allowance. The tank has been in service for eight years and current ultrasonic thickness measurements reveal an average thickness of 0.712 inch. Based on this information determine when the next ultrasonic thickness measurements will be required. a) Fifteen years b) Thirteen years c) Eleven years d) Nine years
Reference: API-653 Paragraph 4.3.3.2b.

8. Internal inspections are primarily required to do all but which of the following? a) Ensure the internal surfaces of the tank are thoroughly cleaned periodically b) Identify and evaluate any tank bottom settlement c) Ensure that the bottom is not severely corroded and leaking d) Gather data necessary for the minimum bottom and shell thickness assessments
Reference: API-653 Paragraph 4.4.1.1 9. When can the required internal inspection be performed by some method other than visual inspection? a) Substitution of the visual inspection is never permitted b) If the internal inspection is required solely for determining the condition and integrity of the tank bottom c) If the internal inspection is required solely for determining the condition and integrity of the tank critical zone d) If the internal inspection is required solely for determining the condition and integrity of the tank roof support structure

Reference: API-653 Paragraph 4.4.1.2


10. According to API-653, all tanks shall have a formal internal inspection conducted at intervals defined by this standard. Who is required to conduct the visual inspection? a) The corrosion engineer b) The person designated by the Authorized Inspector c) The authorized Inspector d) The person designated by the owner user Reference: API-653 Paragraph 4.4.1.2
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 16

11. Intervals between internal inspections shall be determined by the corrosion rates measured during previous inspections or anticipated based on experience with tanks in similar service. The internal inspection interval shall not exceed how many years? a) Ten years b) Fifteen years c) Twenty years d) Twenty-five years Reference: API-653 Paragraph 4.4.2.1 12. What is the minimum thickness permitted at the next inspection for a tank bottom designed with a means to provide detection and containment of a bottom leak? a) 0.01 inch b) 0.10 inch c) 0.50 inch d) 0.05 inch Reference: API-653 Paragraph 4.4.2.1 & 2.4.7.4 13. In cases where corrosion rates are not known and similar service experience is not available, the bottom plate actual thickness shall be determined by inspection(s) within how many years? a) 25 years b) 20 years c) 15 years d) 10 years Reference: API-653 Paragraph 4.4.2.2 14. Which of the following is a recognized alternative to internal inspection interval described in API-653? a) Risk-based Inspection procedures (RBI) b) Hydrostatically testing the tank every five years c) Performing complete calculations for minimum required thickness of the tank shell and bottom d) API-653 does not permit any alternatives to the internal inspection intervals Reference: API-653 Paragraph 4.4.3 15. Of the following, which would not be a factor to be considered in a Risk-based assessment of a tank? a) Availability and effectiveness of inspection methods and quality of data collected b) The methods used for determining the thickness of the shell and bottom plates c) Effectiveness of corrosion mitigation methods d) Names of all operators since the initial start-up of the tank Reference: API-653 Paragraph 4.4.3
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 17

16. The owner/operator is required to maintain complete record file consisting of three types of records. Which of the following is not one of the three types of records. a) Repair/alteration history b) Fill cycles c) Construction d) Inspection Reference: API-653 Paragraph 4.8.1 17. General inspection reports shall include which of the following? a) Metal thickness measurement, repairs, conditions found, settlement measurements, and recommendations b) Metal thickness measurement, repairs, operational upsets, settlement measurements, and recommendations c) Metal thickness measurement, repairs, conditions found, name of organization performing environmental impact study, and recommendations d) Metal thickness measurement, list of all personnel who have worked on the tank since the last inspection, conditions found, settlement measurements, and recommendations Reference: API-653 Paragraph 4.9.2 Note to Student: Be sure to know all the requirements for Inspector Qualifications. Questions can appear on the exam requiring you to know one, two, or all of these qualification requirements. You will find these requirements are similar to those found in Inspector Certification programs for API-510 and API-570. Answers to API-653 Section 4, Inspection Question Number 1 2 3 4 5 6 7 8 9 Answer c b b d c a b a b Question Number 10 11 12 13 14 15 16 17 Answer c c d d a d b a

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 18

Section 5 Materials 1. All new materials used for repair, alteration, and reconstruction shall conform to which of the following? a) The existing material code at the time of original construction b) The latest NFPA Code c) The current applicable tank standards d) Any ASME Code specification for P-1 material Reference: API-653, Paragraph 5.2 2. All shell plates and bottom plates welded to the shell shall be identified. Material identified by any of the following except _____ does not require further identification? a) Original contract drawings b) API name plates c) Suitable documentation d) Owner/operator's experience with similar tanks in similar service constructed of similar material Reference: API-653, Paragraph 5.3.1.1 3. Each individual plate for which adequate identification can not be made; the plate shall be _______. a) Subjected to chemical analysis and mechanical tests as required in ASTM A6 and A370 including Charpy V-Notch b) Subjected to chemical analysis and mechanical tests as required in ASTM A20 and A333 including Charpy V-Notch c) Subjected to Brinell hardness analysis and mechanical tests as required in ASTM A6 and A370 including Charpy V-Notch d) Subjected to Brinell hardness analysis and mechanical tests as required in ASTM A20 and A333 including Charpy V-Notch Reference: API-653, Paragraph 5.3.1.2

4. Under what condition does API-653 require two tension specimens shall be taken at right angles to each other from a corner of each plate? One of those specimens must meet the specification requirements. a) When the direction of rolling is not definitely known b) When the welding will be conducted at a temperature less than 32F c) When the plate is not a full size plate and may be installed with the grain running vertical d) When the material is not a P-1 material Reference: API-653, Paragraph 5.3.1.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 19

5. Even when a material is identified, all shell plates and bottom plates welded to the shell shall meet what minimum requirements? a) The chemistry and mechanical properties of material specified for the application with regard to thickness and design temperature given in ASME Section II, Part A b) The chemistry and mechanical properties of material specified for the application with regard to thickness and design temperature given in API Standard 650 c) The chemistry and mechanical properties of material specified for the application with regard to thickness and design temperature given in the owner/operator's engineering design d) The chemistry and mechanical properties of material specified for the application with regard to thickness and design temperature given in the contract for the tank repair, alteration, or reconstruction Reference: API-653, Paragraph 5.3.1.3 6. Is it permissible to reuse existing rolled structural shapes? If so what specification applies? a) Yes, existing rolled structural shapes shall meet the requirement of ASTM A-20 as a minimum b) Yes, existing rolled structural shapes shall meet the requirement of ASTM A-370 as a minimum c) Yes, existing rolled structural shapes shall meet the requirement of ASTM A-6 as a minimum d) Yes, existing rolled structural shapes shall meet the requirement of ASTM A-7 as a minimum Reference: API-653, Paragraph 5.3.2 7. Flange material must meet the minimum requirements of the material specifications of the current applicable standard. a) True b) False Reference: API-653, Paragraph 5.3.3.1 8. Fasteners shall meet the material specifications of the current applicable standard. a) True b) False Reference: API-653, Paragraph 5.3.3.2 9. If existing plates are to be used to reconstruct the tank, they shall be checked for which of the following? a) Chemical compatibility with other plates used in the reconstruction b) Excessive corrosion and pitting c) Mechanical strength including impact properties d) Inadequately reinforced openings Reference: API-653, Paragraph 5.3.4
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 20

Answers to API-653 Section 5, Materials


Question Number 1 2 3 4 5 6 7 8 9 Answer C D A A B D B A B

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 21

Section 6 Design Considerations for Reconstructed Tanks 1. Design considerations other than normal product loading shall be specified by the _____. a) Organization performing the reconstruction b) Authorized Inspector c) Owner/operator d) Registered professional engineer contracted by the repair organization Reference API 653 Paragraph 6.1 2. Weld joint details shall meet the requirements of which of the following? a) API Standard 650 b) ASME Section IX only c) The applicable standard d) AWS D1.1 Structural Welding Code Reference API 653 Paragraph 6.2.1 3. The thickness to be used for each shell course when checking tank design shall be based on: a) Measurements taken within 30 days prior to relocation b) Measurements taken within 60 days prior to relocation c) Measurements taken within 120 days prior to relocation d) Measurements taken within 180 days prior to relocation Reference API 653 Paragraph 6.4.1 4. The maximum liquid level for hydrostatic test shall be determined by using which of the following? a) The nominal thickness of each shell course at the time of original construction b) The actual thickness measured for each shell course c) The anticipated thickness for each shell course at the time of next thickness measurements d) Twice the anticipated thickness for each shell course at the time of next thickness measurements Reference API 653 Paragraph 6.4.3 5. The joint efficiency and allowable stress levels for existing welded joints that are not to be removed and replaced shall be based on which of the following? a) Original construction standard b) Original degree and type of inspection c) Current construction standard d) Current degree and type of inspection Reference API 653 Paragraph 6.4.5

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 22

6. Replacement and new penetrations shall be designed, detailed, welded, and examined to meet what requirements? a) The current applicable standard b) The original standard of construction c) The requirements of the Authorized Inspector d) The requirements of the owner/operator Reference API 653 Paragraph 6.5.1 7. Existing penetrations shall be evaluated for compliance with what requirements? a) The current applicable standard b) The original standard of construction c) The requirements of the Authorized Inspector d) The requirements of the owner/operator Reference API 653 Paragraph 6.5.2 8. With regard to seismic design, reconstructed tanks shall be built to meet the stability requirements of: a) The requirements of the owner/operator b) The requirements of the Authorized Inspector c) The original standard of construction d) The applicable standard Reference API 653 Paragraph 6.8

Answers to API-653 Section 6, Design


Question Number 1 2 3 4 5 6 7 8 Answer C C D B B A B D

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 23

Section 7 Tank Repair and Alteration 1. The basis for repairs and alterations shall be equivalent to which of the following? a) API-653 b) API-650 c) API-510 d) API-570 Reference API-653, Paragraph 7.1.1 2. The minimum dimension for a replacement shall plate shall be _____ inches or ____ times the thickness of the replacement plate whichever is ______. a) 12, 12, greater b) 12, 12, lesser c) 18, 18, greater d) 18, 18, lesser Reference API-653, Paragraph 7.2.2.1 3. Unless an entire shell plate is replaced, the replacement plate may be circular, oblong, square or rectangular provide the corners are a) Provided with a radius of at least 1 inch b) Provided with a radius of at least 3% of the short dimension of the plate c) Provided with a radius of at least 3 inches d) Provided with rounded corners Reference API-653, Paragraph 7.2.2.1 4. Prior to welding the new vertical joints, the existing horizontal joints shall be cut for a minimum distance of _____ inches beyond the new vertical joints. a) Six b) Eight c) Twelve d) Sixteen Reference API-653, Paragraph 7.2.2.2 5. Vertical joints shall be welded before the horizontal joints. a) True b) False Reference API-653, Paragraph 7.2.2.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 24

6. For existing shell plates over thick, the outer edge of the butt weld, attaching the replacement shell plate shall be at least _____ times the weld thickness or _____ inches whichever is greater from the outer edge of any existing butt-welded shell joints. a) 12, 10 b) 10, 12 c) 8, 10 d) 10, 8 Reference API-653, Paragraph 7.2.3.3 7. For existing shell plates thick and less, the outer edge of the butt weld, attaching the replacement shell plate may be reduced to _____ inches from the outer edge of vertical joints or _____ inches from the outer edge of horizontal joints. a) 10, 8 b) 9, 6 c) 6, 9 d) 6, 3 Reference API-653, Paragraph 7.2.3.3 8. For existing shell plates over thick, the outer edge of the butt weld, attaching the replacement shell plate shall be at least _____ times the weld size or _____ inches, whichever is greater, from the edge (toe) of the fillet weld attaching the bottom shell course to the bottom. This rule does not apply if the replacement shell plate extends to and intersects with the bottom-to-shell joint at approximately _____ degrees. a) 8, 10, 45 b) 8, 10, 90 c) 8, 10, 60 d) There are no exceptions Reference API-653, Paragraph 7.2.3.3 9. The edge of any vertical weld joint attaching a replacement plate shall be at least how far from the edge of the weld joint in the annular plate ring or sketch plate? a) Eight inches b) Ten inches c) Twelve inches d) Six inches Reference API-653, Paragraph 7.2.3.3 10. Lapped patch shell repairs are an acceptable form of repair for butt-welded, lap-welded, and riveted tank shell only when specified by: a) The Authorized Inspector b) Repair organization c) The insurance company d) The owner/operator Reference API-653, Paragraph 7.3.1
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 25

11. Lapped patch shell repairs are not permitted on shell courses exceeding what thickness? a) inch b) inch c) 1 inch d) 1 inch Reference API-653, Paragraph 7.3.1.2 12. When a lapped patch shell repair is used, what is the minimum thickness permitted for the repair plate? a) Not less than .25 inch b) Not less than .1875 inch c) Not less than .50 inch d) Not less than .375 inch Reference API-653, Paragraph 7.3.1.3 13. Repair plates for lapped patch repairs may square or rectangular in shape. These plates must be provided with a corner radius of at least what dimension? a) They shall be rounded to a minimum radius of 1 inch b) They shall be rounded to a minimum radius of 2 inches c) They shall be rounded to a minimum radius of 3 inches d) They shall be rounded to a minimum radius of 4 inches Reference API-653, Paragraph 7.3.1.4 14. The maximum dimension of the lapped patch repair plate vertically and horizontally shall not exceed: a) 24 inches vertically and 36 inches horizontally b) 36 inches vertically and 48 inches horizontally c) 48 inches vertically and 72 inches horizontally d) There are no maximum dimensions Reference API-653, Paragraph 7.3.1.7 15. The minimum lapped patch repair plate dimension is what length? a) 6 inches b) 8 inches c) 10 inches d) 12 inches Reference API-653, Paragraph 7.3.1.7 16. Is it permissible to install a shell opening and its reinforcement within a properly designed lapped patch shell repair? a) Yes b) No Reference API-653, Paragraph 7.3.1.8
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 26

17. When a lapped patch repair plate is used to reinforce the thickness of a shell, which of the following is correct? a) The repair plate thickness shall be based on the latest edition of API-650 and 653 using a joint efficiency not exceeding 0.35 b) The repair plate thickness shall be based on the applicable standard of construction and API Standard 653 using a joint efficiency not exceeding 0.35 c) The repair plate thickness shall be based on the latest edition of API-650 and 653 using a joint efficiency not exceeding 0.70 d) The repair plate thickness shall be based on the applicable standard of construction and API Standard 650 using a joint efficiency not exceeding 0.70 Reference API-653, Paragraph 7.3.3.1 18. With regard to the thickness of the repair plate at the perimeter of the repair plate, when a lapped patch repair plate is used to reinforce the thickness of a shell, which of the following is correct? a) The repair plate shall not exceed the thickness of the shell plate by more than 1/4th but no more than 1/8th inch. The maximum repair plate thickness is 1/2inch. b) The repair plate shall not exceed the thickness of the shell plate by more than 1/3rd but no more than 1/4th inch. The maximum repair plate thickness is 1/2inch. c) The repair plate shall not exceed the thickness of the shell plate by more than 1/3rd but no more than 1/8th inch. The maximum repair plate thickness is 1/2inch. d) The repair plate shall not exceed the thickness of the shell plate by more than 1/4th but no more than 1/3rd inch. The maximum repair plate thickness is 1/2inch. Reference API-653, Paragraph 7.3.3.1 19. Lapped patch repair plates may be used to repair small leaks or minimize the potential of leaks from isolated pitting. The requirements for thickness and design are the same as for reinforcement of shell thickness. This type of repair may not be used to repair small leaks if what condition(s) exists? a) The leak is located anywhere in the first shell course within 12 inches of a vertical joint b) The leak of pit is in an area of the shell where there is a product to atmosphere interface c) There is a possibility of severe environmental impact should the repair fail d) If exposure of the fillet weld to the product would produce crevice corrosion or if a corrosion cell is likely to occur between the shell plate and the repair plate Reference API-653, Paragraph 7.3.4.4 20. An alteration to a tank shell by the addition of new plate material shall be performed in accordance with what standard? a) Current API 650 and latest addenda b) API 650 edition and addenda applicable at the time of original tank construction c) Applicable standard d) Tanks may not be altered by increasing height Reference API-653, Paragraph 7.5
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 27

21. Repairs to existing shell penetrations shall be in accordance with a) API Standard 650 b) API Standard 653 c) API Standard 510 d) National Board Inspection Code Reference API-653, Paragraph 7.7.1 22. API 653 permits the addition of reinforcing plates to existing un-reinforced nozzles. What requirement is necessary to add this reinforcement to the inside of the tank? a) The reinforcement plate may not be added to the inside of the plate b) A telltale hole shall be drilled through the shell opposite the reinforcement plate c) The reinforcement plate is the same material as the nozzle and is attached to the nozzle by full penetration weld d) Sufficient nozzle projection exists Reference API-653, Paragraph 7.7.3 23. The addition or replacement of shell penetrations shall be in accordance with a) API-650 b) API-650 and API 653 c) API-650 and API 510 d) API-650 and AMSE Section VIII, Division 2 Reference API-653, Paragraph 7.8.1 24. Installation or replacement of shell penetrations greater than 2 inches shall be installed with the use of an insert plate if what condition(s) exists? a) The penetration is no closer than 12 inches to an existing penetration b) The shell plate is greater than thickness and the shell plate material does not meet current metal temperature criteria c) The penetration is no closer than 10 inches to an existing penetration d) The shell plate is greater than 3/16 thickness and the shell plate material does not meet current metal temperature criteria Reference API-653, Paragraph 7.8.2

25. An 8 inch diameter penetration is to be installed in a shell which requires an insert plate. What is the minimum permitted diameter of the insert plate? a) Eight inches b) Twelve inches c) Sixteen inches d) Twenty inches Reference API-653, Paragraph 7.8.2(a)

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 28

26. An insert plate containing an opening with a reinforcing plate is to be installed in a tank. The reinforcing plate diameter is thirty-two inches. What is the minimum diameter of the insert plate? a) The insert plate must be 32 inches in diameter b) The insert plate must be 44 inches in diameter c) The insert plate must be 32 inches in diameter plus the diameter of the opening d) The insert plate must be 32 inches in diameter plus twice the diameter of the opening Reference API-653, Paragraph 7.8.2(b) 27. If an integral reinforcement design is used, the thickness of the insert plate, at its periphery and for a distance of 2t from the edge of the weld, shall be the same thickness as the shell. If it is not, the insert plate shall have a ______ taper to match the shell plate thickness. a) 1:2 b) 1:3 c) 1:4 d) 1:5 Reference API-653, Paragraph 7.8.2(c) 28. When it is necessary to install a new tank bottom above an existing bottom, it may be necessary to alter existing shell penetrations. This procedure may require the existing reinforcing plate to be removed and a new reinforcement plate added. This is not permitted when what condition exists? a) The assembly was originally hardness tested b) The existing assembly was not impact tested c) The existing assembly was fabricated from re-claimed material d) The existing assembly was stress relieved Reference API-653, Paragraph 7.9.2.2 29. New reinforcing plates shall be installed in accordance with Fig. 7-2a of API-653. In order to maintain weld spacing, what shape reinforcing plate is permitted? a) Oval b) Diamond c) Tombstone d) Circular is the only permitted shape Reference API-653, Paragraph 7.9.2.2 30. No welding or weld overlays are permitted within the Critical Zone except for welding of widely scattered pits, cracks in the bottom plates, the shell-to-bottom weld, or where the bottom or annular plate is being replaced. a) True b) False Reference API-653, Paragraph 7.10.1.2.1
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 29

31. API Standard 653 defines the Critical Zone for repairs to tank bottoms as what? a) That portion of the bottom or annular plate within 3" from the inside edge of the shell, measured radially inward b) Within the annular plate ring, within 12 inches of the shell, or within 12 inches of the inside edge of the annular plate ring c) That portion of the bottom or annular plate within 6" from the inside edge of the shell, measured radially inward d) Within the annular plate ring, within 3" of the shell, or within 12 inches of the inside edge of the annular plate ring Reference API-653, Paragraph 7.10.1.1 32. If more extensive repairs are required within the Critical Zone than those listed in 7.10.1.2, what must be done with the bottom plate? a) As long as the repairs do not involve the bottom plate, nothing needs to be done b) The bottom plate welded to the shell shall be cut out and a new plate installed c) The bottom plate shall be subjected to suitable nondestructive examination to ensure it has not be adversely affected by the repair d) The bottom plate and the bottom shell course shall be replaced as an assembly Reference API-653, Paragraph 7.10.1.2.4 33. When it is necessary to install a new bottom plate over an existing bottom plate, a suitable ______ material cushion such as sand, gravel or concrete shall be used between the old bottom and the new bottom. a) Drainage b) Compacted c) Non-corrosive d) Non-conductive Reference API-653, Paragraph 7.10.2.1.1 34. When a new tank bottom has been installed in a floating roof tank, what consideration must given to the floating roof level? a) The floating roof will find its own level b) The support legs can be jacked up or shortened by the same amount as the thickness of the cushion and new bottom plate c) The support legs can be jacked up or shortened by the same amount as the thickness of the cushion d) The support legs can be jacked up or shortened by the same amount as the thickness of the new bottom plate Reference API-653, Paragraph 7.10.2.1.5

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 30

35. Which of the following is not acceptable when removing an existing tank bottom, with regard to the separation of the shell from the tank bottom? a) Cutting the shell parallel to the tank bottom a minimum of above the bottom to shell weld b) Removing the entire shell to bottom attachment weld including penetration and heat affect zone c) Removing the entire shell to bottom attachment weld by arc gouging and/or grinding d) Cutting the shell parallel to the tank bottom a minimum of above the bottom to shell weld Reference API-653, Paragraph 7.10.2.2(a) and (b) 36. For installation of a new tank bottom in a tank with shell plates of unknown toughness, not exempted in Table 10-1 of API-653, new welds in the bottom or annular ring shall be spaced at least the greater of _____ inches or ____t from existing vertical weld joints in the bottom shell course. (t is the thickness of the bottom shell course) a) three, five b) six, five c) five, three d) five, six Reference API-653, Paragraph 7.10.2.3 37.What is the minimum thickness of new roof plates for supported cone roofs? a) 7/16 b) 5/16 c) 3/16 d) 1/16 Reference API-653, Paragraph 7.11.1.1 38. The nominal thickness of new roof plates for self-supporting roofs shall be equal to or greater than _____ inch not to exceed _____ inch. a) 1/4th, 5/8th b) 5/16th, 1/2 c) 3/16th, 5/16th d) 3/16th, 1/2 Reference API-653, Paragraph 7.11.2.1 and API-650 3.10.5 or 3.10.6 39. Repairs to internal floating roofs shall be made in accordance with the original construction drawings. To what requirements shall repairs be made if the original construction drawings are not available? a) The original construction standard b) Appendix H of API Standard 650 c) Appendix G of API Standard 650 d) Appendix C of API Standard 650 Reference API-653, Paragraph 7.12.2
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 31

40. To minimize evaporation losses and reduce potential hazard to workers, no more than ____ of the roof seal system should be out of an in-service tank at one time. a) One-eighth b) One-fourth c) One-half d) Three-quarters Reference API-653, Paragraph 7.13.1 41. Mechanical damage to floating roof perimeter seals shall be repaired or replaced. How are buckled parts handled? a) They shall be replaced b) They may be straightened in place c) They may be heated and bent back into position d) They may be removed straightened and re-installed Reference API-653, Paragraph 7.13.4 42. With regard to installation of primary and secondary seals, what must be done if the roof rim thickness is less than 0.10 inch. a) The roof rim shall be thoroughly inspected for damage and corrosion, if it is satisfactory then nothing further needs to be done b) It shall be replaced. The new roof rim shall be 3/16 inch thickness minimum c) It shall be replaced. The new roof rim shall be 1/4 inch thickness minimum d) The tank must be condemned and dismantled Reference API-653, Paragraph 7.13.6.2 43. What is the maximum hot tap connection permitted in an in-service tank with a minimum shell thickness of 3/8 inch? The material is of recognized toughness. a) NPS 6 b) NPS 8 c) NPS 14 d) NPS 18 Reference API-653, Paragraph 7.14.1.1(a) and Table 7-1 44. The owner/operator requires a connection to be made in an in-service tank. The shell material is of unknown toughness and the thickness is 1.25. The minimum design metal temperature is 45F. What is the maximum diameter hot tap connection that may be installed in this tank? a) NPS 18 b) NPS 14 c) NPS 8 d) NPS 4 Reference API-653, Paragraph 7.14.1.1(b)(1) and Fig. 7-6
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 32

45. The minimum height of tank liquid relative to the hot tap location shall be at least ______ during the hot tapping operation. a) The tank liquid shall be at least 3 feet below the hot tap location b) The tank liquid shall be at least 1 foot above the hot tap location c) The tank liquid shall be at least 3 feet above the hot tap location d) The tank liquid shall be at least 1 foot below the hot tap location Reference API-653, Paragraph 7.14.1.2 46. It is permissible to perform hot taps on the roof of a tank or within the gas/vapor space. a) True b) False Reference API-653, Paragraph 7.14.1.4 47. The owner/operator requires an NPS 3 nozzle to be installed in an in-service tank. The tank is 110 feet in diameter, 60 feet maximum fill height, shell thickness at the point of hot tap is .75, and the material is of unknown toughness with a minimum design metal temperature of 38F. This nozzle is to be installed adjacent to an existing nozzle. What is the minimum spacing between these nozzles? a) Minimum distance is 22.24 b) Minimum distance is 9.08 c) Minimum distance is 19.08 d) Minimum distance is 2.24 Reference API-653, Paragraph 7.14.3.1 48. When installing a pipe nozzle into an in-service tank, how shall the pipe nozzle be prepared? a) The pipe nozzle must be cut to the contour of the tank and prepared for full fillet welding b) The pipe nozzle shall be cut to the contour of the tank and beveled to a depth of not more than 1/3 the nozzle thickness to ensure partial penetration groove welding c) The pipe nozzle shall be cut to the contour of the tank and beveled to a depth of not less than 1/3 the nozzle thickness to ensure partial penetration groove welding d) The pipe nozzle shall be cut to the contour of the tank and beveled from the outside for a full penetration weld Reference API-653, Paragraph 7.14.5.1 49. After the reinforcing pad is installed, the pad shall be subjected to a pneumatic test. a) True b) False Reference API-653, Paragraph 7.14.5.3

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 33

50. After the valve has been installed on the flange, a pressure test of at least ______ shall be performed on the nozzle prior to mounting the hot tap machine. a) The same pressure as the pneumatic test of the reinforcing pad b) 1.25 times the hydrostatic head c) 1.5 times the hydrostatic head d) 2.0 times the hydrostatic head (to account for the added stress of the machine) Reference API-653, Paragraph 7.14.5.3

Answers to API-653 Section 7, Repair/Alteration


Question Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Answer B A D C A C D B C D A B B C A B B C D C A D B B D

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 34

Answers to API-653 Section 7, Repair and Alteration Continued:

Question Number 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

Answer B C D C A A B C B D A C D B B A B C D C B A D A C

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 35

Section 8 Dismantling and Reconstruction 1. Bottom plates that will be reused shall be cut by de-seaming of lap-welds or by cutting alongside of the remaining welds at a minimum of _______ away from existing welds. a) One inch b) Two inches c) Four inches d) Six inches Reference API-653, Paragraph 8.3.2.1 2. Shell plates may be cut by any of the following methods except a) Shell rings thick or thinner can be dismantled by cutting through the weld without removing the heat affected zone b) Cuts made a minimum of 6 away from existing welds except where cuts cross existing welds c) Cuts made a minimum of 2 away from existing welds except where cuts cross existing welds d) Any shell ring may be dismantled by cutting out existing weld seams and the heat affected zone of the weld Reference API-653, Paragraph 8.3.3.1 3. API-653 requires that new vertical joints in adjacent shell courses not be in alignment. What is the minimum offset dimension of these joints? a) Vertical joints shall be offset a minimum of 5 inches or 5t which ever is greater b) Vertical joints shall be offset a minimum of 5t where t is the plate thickness of the thicker course at the point of offset c) Vertical joints shall be offset a minimum of 5t where t is the plate thickness of the thinner course at the point of offset d) Vertical joints shall be offset a minimum of 5 inches or 5t which ever is less Reference: API-653, Paragraph 8.4.2.1 4. Roof plates shall be cut by de-seaming of lap-welds or by cutting alongside of the remaining welds at a minimum of _______ away from existing welds. a) One inch b) Two inches c) Four inches d) Six inches Reference API-653, Paragraph 8.3.4.1

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 36

5. In the reconstruction of aboveground storage tanks, welding shall be by any of the following welding processes except. a) Submerged arc welding b) Oxyfuel c) Gas metal-arc d) Forging Reference API-653, Paragraph 8.4.2.2 and API-650 5.2.1 6. No welding of any kind may be performed when the surfaces to be welded are wet from rain, snow, or ice. When rain or snow is falling or during high wind conditions, welding is permitted provided: a) The welder is secured to an anti-fall device and the work is properly grounded b) The welder has agreed to work in such conditions c) The welder and the work are properly shielded d) The owner/operator takes full responsibility for the safety of the welder and the quality of the welds Reference API-653, Paragraph 8.4.2.3 7. According to API-653, no welding is permitted when the temperature of the base metal is below what value? a) Base metal temperature below -20F b) Base metal temperature below 0F c) Base metal temperature below 20F d) Base metal temperature below 30F Reference API-653, Paragraph 8.4.2.3 8. If the base metal is greater than 1 thickness or the temperature of the base metal is between 0F and 32F what requirement does API-653 stipulate? a) The base metal within 3 inches of the weld area shall be heated to a temperature that is warm to the hand (approximately 180F) b) The base metal within 8 inches of the weld area shall be heated to a temperature that is warm to the hand (approximately 140F) c) The base metal within 3 inches of the weld area shall be heated to a temperature that is warm to the hand (approximately 140F) d) The base metal within 8 inches of the weld area shall be heated to a temperature that is warm to the hand (approximately 180F) Reference API-653, Paragraph 8.4.2.3 9. What is the maximum permissible undercut of the base metal for vertical joints? a) 1/64 b) 1/32 c) 1/19 d) 1/16 Reference API-653, Paragraph 8.4.2.5

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 37

10. What is the maximum permissible undercut of the base metal for horizontal joints? a) 1/64 b) 1/32 c) 1/19 d) 1/16 Reference API-653, Paragraph 8.4.2.5 11. What is the maximum weld reinforcement thickness permitted on each side of the plate for a plate, which is 7/8 thick? Vertical joints Horizontal joints a) 3/32 1/8 b) 1/8 3/16 c) 3/16 1/4 d) 1/4 5/16 Reference API-653, Paragraph 8.4.2.6 & Table 8-1 12. Tack welds used in the assembly of vertical joints in tank shells may remain in place when the joints are welded manually provided: a) They are properly cleaned of all weld slag b) They are sound c) Liquid Penetrant or Magnetic Particle examination is performed d) They shall not remain Reference API-653, Paragraph 8.4.2.7 13. What are the requirements for making tack welds according API-653? a) If the tack weld is to be removed, it must be made using qualified weld procedure and qualified welder b) If the tack weld is to remain in place, it must be made using qualified weld procedure and qualified welder c) If the tack weld is to remain in place, it may be made using any weld procedure acceptable to the owner/operator d) If the tack weld is to be removed, it may be made by any welder wishing to gain experience provided the process is the SMAW process Reference API-653, Paragraph 8.4.2.7 14. All coatings must be removed from the weld area prior to welding except weldable primer coatings. What must done if these primer coatings are used? a) Weldable primer coatings must also be removed b) If the coating is applied by brush it may remain provided the application is performed to a written procedure c) They shall be included in welding procedure qualification tests for brand, formulation, and maximum thickness of primer applied d) They shall be included in welding procedure qualification tests for the method of application either by brushing or by spraying or a combination of the two. Reference API-653, Paragraph 8.4.2.8

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 38

15. When welding tank bottoms, when should the shell-to-bottom weld be completed? a) This joint (except for door sheets) can be welded as soon as the bottom plates are laid out and welded b) This joint (except for door sheets) shall be welded as soon as the first bottom weld joint is completed to prevent distortion c) This joint (except for door sheets) shall be welded as work progresses around the tank bottom d) This joint (except for door sheets) shall be completed before the welding of bottom joints Reference API-653, Paragraph 8.4.3.2 16. What is the maximum permissible misalignment of vertical joints in shell plates that are .9375 thick? a) .125 b) .09375 c) .009375 d) .0125 Reference API-653, Paragraph 8.4.4.1 17 What is the maximum permissible misalignment of vertical joints in shell plates that are .625 thick? a) .0625 b) .00625 c) .125 d) .0125 Reference API-653, Paragraph 8.4.4.1 18. Vertical joints shall be completed before the lower horizontal weld is made. a) True b) False Reference API-653, Paragraph 8.4.4.1 19. In completing horizontal joints, what is the maximum projection of the upper plate, beyond the face of the lower plate, at any point for plate thickness of 1.125 a) .25 b) .225 c) .125 d) .0125 Reference API-653, Paragraph 8.4.4.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 39

20. When welding horizontal and vertical joints constructed of material that is over 1.5 thick, based on the thickness of the thicker part, what is the required preheat temperature? a) Preheating is not required b) 140F c) 200F d) 300F Reference API-653, Paragraph 8.4.4.3 21. When shall measurements be taken to verify tolerances of reconstructed tanks? a) After hydrostatic testing b) Before hydrostatic testing c) After lay out of all plates d) After fit-up and tack welding used for alignment purposes Reference API-653, Paragraph 8.5.1.2 22. What is the maximum out-of-plumbness of the top of the shell relative to the bottom of the shell of a tank with a total height of 62.25 feet? a) 7.47 b) .6225 c) 6.25 d) 5 Reference API-653, Paragraph 8.5.2.1 23. An aboveground storage tank is 115 feet in diameter. What is the maximum or minimum radius permitted measured at one foot above the shell-to-bottom weld? Maximum Minimum a) 115.75 114.25 b) 690.75 689.25 c) 1380.75 1379.25 d) 115.5 114.5 Reference API-653, Paragraph 8.5.3 24. An aboveground reconstructed tank is 126.5 feet in diameter. What is the maximum or minimum radius permitted measured at the second shell course up from the bottom? Maximum Minimum a) 759.75 758.25 b) 761.25 756.75 c) 1520.25 1515.75 d) 128.75 124.25 Reference API-653, Paragraph 8.5.3

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 40

25. Peaking shall not exceed . This is measured using a horizontal sweep board of what dimensions? a) The sweep board shall be 48 long and made to the true outside radius of the tank b) The sweep board shall be 48 long and made to the true inside radius of the tank c) The sweep board shall be 36 long and made to the true outside radius of the tank d) The sweep board shall be 36 long and made to the true inside radius of the tank Reference API-653, Paragraph 8.5.4 26. Banding shall not exceed ____ with a vertical 36 long sweep board. a) One half inch b) Three quarter inch c) One inch d) One and one eighth inch Reference API-653, Paragraph 8.5.5 27. The top of the concrete ringwall of a reconstructed tank, that is 115 feet in diameter, must be level within 1/8 in any 30 feet of circumference. What is the tolerance measured from the average elevation? a) 1/8 b) 3/16 c) 1/2 d) 1/4 Reference API-653, Paragraph 8.5.6.2(a) 28. Where concrete ringwalls are not provided, the foundation under the shell shall be level to within what tolerances? a) 1/8 in any 30 of the circumference and 1/2 in the total circumference measured from the average elevation b) 1/8 in any 10 of the circumference and 1/2 in the total circumference measured from the average elevation c) 1/8 in any 10 of the circumference and 1/4 in the total circumference measured from the average elevation d) 1/8 in any 30 of the circumference and 1/4 in the total circumference measured from the average elevation Reference API-653, Paragraph 8.5.6.2(b) 29. For foundations specified to be sloped from a horizontal plane, the actual elevation shall not deviate from the calculated differences by more than which of the following where concrete ringwalls are provided? a) 1/8 in any 30 of the circumference and 1/4 in the total circumference measured from the average elevation b) 1/8 in any 10 of the circumference and 1/2 in the total circumference c) 1/8 in any 10 of the circumference and 1/2 in the total circumference measured from the average elevation d) 1/8 in any 30 of the circumference and 1/4 in the total circumference Reference API-653, Paragraph 8.5.6.3(a)
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 41

30. For foundations specified to be sloped from a horizontal plane, the actual elevation shall not deviate from the calculated differences by more than which of the following where concrete ringwalls are not provided? a) 1/8 in any 30 of the circumference and 1/2 in the total circumference measured from the average elevation b) 1/8 in any 10 of the circumference and 1/2 in the total circumference c) 1/8 in any 10 of the circumference and 1/2 in the total circumference measured from the average elevation d) 1/8 in any 30 of the circumference and 1/4 in the total circumference Reference API-653, Paragraph 8.5.6.3(b) Answers to API-653 Section 8, Dismantling & Reconstruction Question Number Answer 1 b 2 c 3 b 4 b 5 d 6 c 7 b 8 c 9 a 10 b 11 b 12 d 13 b 14 c 15 d 16 b 17 a 18 a 19 c 20 c 21 b 22 d 23 b 24 b 25 c 26 c 27 d 28 b 29 d 30 b
Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 42

Section 9 - Welding 1. Welding procedure specifications and welders and welding operators shall be qualified in accordance with __________. a) Original code of construction b) Owner/operators specification c) Section IX of the ASME Code d) Repair organizations specifications Reference API-653, Paragraph 9.1.1 2. According to API Standard 653, if the material specification for the steel from an existing tank is unknown or obsolete what must be done? a) The material can not be used for tank reconstruction b) Test coupons for the WPS shall be taken from the actual plate to be used c) Test coupons for the WPS may be taken from a similar material of known specification d) Test coupons for the WPS shall only be taken from weld filler metal and not from the base metal Reference API-653, Paragraph 9.1.2 3. Each welder and welding operator shall be assigned ________. a) Only one joint to ensure traceabilitiy b) A specific welding machine c) An identifying number, letter, or symbol d) Weld joints on only one side of the tank Reference API-653, Paragraph 9.2.1 4. How does each welder and welding operator identify the welds produced by them? a) Each welder and welding operators identification mark shall be hand or machine stamped adjacent to each completed weld. b) Each welder and welding operator shall inform the owner/operator which welds he or she completed c) Each welder and welding operator shall show the inspector exactly which welds they completed d) Each welder and welding operator shall inform the owner/operator which welds they will be making prior to the start of such welding Reference API-653, Paragraph 9.2.2 5. At what intervals must the welder and welding operators identification be stamped adjacent to the completed welds? a) Identification shall be at intervals not to exceed 9 feet b) Identification shall be at intervals not to exceed 7.5 feet c) Identification shall be at intervals not to exceed 6 feet d) Identification shall be at intervals not to exceed 3 feet Reference API-653, Paragraph 9.2.2
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 43

6. In lieu of stamping, a record may be kept that identifies the welder or welding operator for each welded joint. a) True b) False Reference API-653, Paragraph 9.2.2 7. What welds do not require welders identification? a) All welds require identification b) Vertical welded joints which are located within the final shell course since this course will be subjected to relatively low stresses c) Roof plate welds and flange-to-nozzle-neck welds d) Roof plate welds and bottom plate welds Reference API-653, Paragraph 9.2.2

Answers to API-653 Section 9, Welding


Question Number 1 2 3 4 5 6 7 Answer C B C A D A C

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 44

Section 10 Examination and Testing 1. Nondestructive examination procedures, qualifications, and acceptance criteria is required for VT, MT, UT, PT, and RT methods and must be in accordance with what Code or Standard? a) ASME Code Section V, Nondestructive examination b) API Standard 650 only c) API Standard 650 and the supplements given in API-653 d) Owner/operators specifications Reference: API-653, Paragraph 10.1.1.1 2. Personnel performing nondestructive examination shall be qualified in accordance with _____. a) API Standard 650 and the supplemental requirements of API-653 b) ASME Code Section V, Nondestructive Examination c) SNT-TC-1A d) The owner/operators specifications Reference: API-653, Paragraph 10.1.1.2 3. When it is necessary to install a hot tap connection or add a reinforcing plate to an existing un-reinforced penetration, API 653 requires what type, extent, and purpose of examination. a) Magnetic particle examination for slight sub-surface discontinuities shall be performed in an area equal to twice the diameter of the opening b) Radiographic examination for cracking shall be performed in the immediate area c) Ultrasonic examination for cracking shall be performed in the immediate area d) Ultrasonic examination for lamination shall be performed in the immediate area Reference: API-653, Paragraph 10.1.2.1 4. Completed welds attaching nozzle neck to shell, and reinforcing plate to shell and nozzle neck, shall be examined by _______. a) Ultrasonic or Radiography b) Magnetic Particle or Liquid Penetrant c) Visual examination or Liquid Penetrant d) Ultrasonic or Magnetic Particle Reference: API-653, Paragraph 10.1.2.3

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 45

5. How and when does API Standard 653 require the examination of welds of completed stress relieved assemblies? a) Completed welds of stress relieved assemblies shall be examined visually only after stress relief and hydrostatic test b) Completed welds of stress relieved assemblies shall be examined visually as well as by ultrasonic methods after stress relief but before hydrostatic test c) Completed welds of stress relieved assemblies shall be examined visually as well as by magnetic particle or liquid penetrant methods after stress relief but before hydrostatic test d) Completed welds of stress relieved assemblies shall be examined visually or by radiography after stress relief but before hydrostatic test Reference: API-653, Paragraph 10.1.2.4 6. Completed butt welds between insert plates and the shell require what type and extent of examination? a) Complete radiography b) Spot Radiography c) Random Radiography d) Random Spot Radiography Reference: API-653, Paragraph 10.1.2.5 7. In repairing butt weld flaws, what type and extent of examination is required by API-653? a) Random examination by radiography or ultrasonic methods of the full length of repair b) Examined full length of the repair by liquid penetrant or magnetic particle methods c) Examined at three foot intervals by radiography or ultrasonic methods d) Examined full length of the repair by radiography or ultrasonic methods Reference: API-653, Paragraph 10.1.3.2 8. Completed repairs of fillet welds shall be examined over their full length by the appropriate nondestructive method listed in API-653. a) True b) False Reference: API-653, Paragraph 10.1.3.3 9. With regards to new welds attaching shell plate to shell plate, what method(s) of examination is/are required on the completed weld? a) Visual b) Visual and Radiography c) Visual and magnetic particle or liquid penetrant d) Visual and ultrasonic Reference: API-653, Paragraph 10.1.5

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 46

10. With regards to new welds attaching shell plate to shell plate for plate thickness greater than one inch, what additional extent and method of examination is required by API-653? a) The back gouged surface of the root and final pass (each side) shall be examined for its complete length by the Inspector b) The back gouged surface of the root and final pass (each side) shall be examined for its complete length visually c) The back gouged surface of the root and final pass (each side) shall be examined for its complete length by magnetic particle or liquid penetrant d) The back gouged surface of the root and final pass (each side) shall be examined for its complete length by ultrasonic Reference: API-653, Paragraph 10.1.5 11. New welding on the shell-to-bottom joint shall be inspected for its entire length by _____ and _______ or ________. a) Visual examination, liquid penetrant , magnetic particle b) Right-angle vacuum box and solution film, light diesel oil c) Visual examination, ultrasonic, eddy current d) Visual examination, wet fluorescent magnetic particle, helium tracer gas Reference: API-653, Paragraph 10.1.6.1 12. In applying light diesel oil to the opposite side of the first pass of new shell-to-bottom joints, how long must the oil remain on the weld and what is the weld inspected for? a) The oil shall be allowed to stand at least four hours and the weld inspected for wicking action b) The oil shall be allowed to stand at least three hours and the weld inspected for wicking action c) The oil shall be allowed to stand at least two hours and the weld inspected for wicking action d) The oil shall be allowed to stand at least one hour and the weld inspected for wicking action Reference: API-653, Paragraph 10.1.6.2 13. The existing weld at the shell-to-bottom joint shall be examined visually and magnetic particle or liquid penetrant methods, for the full length under a welded-on patch plate. How much additional shell-to-bottom joint must be examined? a) Three inches on each side of the patch plate b) Six inches on each side of the patch plate c) nine inches on each side of the patch plate d) twelve inches on each side of the patch plate Reference: API-653, Paragraph 10.1.6.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 47

14. How and to what extent are newly welded bottom joints tested? a) Newly welded bottom joints shall be tested their entire length using liquid penetrant b) Newly welded bottom joints shall be tested their entire length using a vacuum box and a solution film, or a tracer gas and detector c) Newly welded bottom joints shall be tested their entire length using visual and ultrasonic examination d) Newly welded bottom joints shall be tested their entire length using wet fluorescent magnetic particle examination Reference: API-653, Paragraph 10.1.7.1 15. What are the requirements, regarding examination, of a welded-on patch plate in the critical zone? a) The final weld shall be examined by radiography over its entire length b) Root and final pass shall be examined by radiography over its entire length c) The root and final pass shall be examined visually over its entire length d) The root and final pass shall be examined visually and by magnetic particle of liquid penetrant method over its entire length Reference: API-653, Paragraph 10.1.7.3 16. API-653 requires the number and location of radiographs to in accordance with API-650. In addition, API-653 requires how many and what location for new or repaired shell vertical joints? a) For new or repaired shell vertical joints one radiograph shall be taken in each fifty foot length b) For new or repaired shell vertical joints one radiograph shall be taken in each twenty-five foot length c) For new or repaired shell vertical joints one radiograph shall be taken in every joint d) For new or repaired shell vertical joints one radiograph shall be taken in every other joint Reference: API-653, Paragraph 10.2.1.1

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 48

17. API-653 requires the number and location of radiographs to in accordance with API-650. In addition, API-653 requires how many and what location for new or repaired shell horizontal joints? a) For new or repaired shell horizontal joints one radiograph shall be taken in each twenty-five feet of horizontal joint including those required at intersections of vertical and horizontal joints b) For new or repaired shell horizontal joints one radiograph shall be taken in each twenty-five feet of horizontal joint not including those required at intersections of vertical and horizontal joints c) For new or repaired shell horizontal joints one radiograph shall be taken in each fifty feet of horizontal joint including those required at intersections of vertical and horizontal joints d) For new or repaired shell horizontal joints one radiograph shall be taken in each fifty feet of horizontal joint not including those required at intersections of vertical and horizontal joints Reference: API-653, Paragraph 10.2.1.2 18. API-653 requires two radiographs to be taken at each new or replacement intersection between vertical and horizontal joints. One to comply with the requirement for vertical joints and one to comply with the requirements for horizontal joints. a) True b) False Reference: API-653, Paragraph 10.2.1.3 19. For reconstructed tanks, each butt-welded annular plate joint shall be radiographed in accordance with which of the following? a) API-650 b) ASME - Section V c) API-653 and API-575 d) Owner/operator's specifications Reference: API-653, Paragraph 10.2.1.4 20. For reconstructed tanks, radiographic examination is required for what percentage of all junctions of new welds over existing seams? a) 100% b) 75% c) 50% d) 25% Reference: API-653, Paragraph 10.2.1.5

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 49

21. Radiographic examination is required for new and replaced shell insert plate and door shell welds. What are the minimum number and location of such radiographs? a) Circular plates - four radiographs are required, one at each quadrant b) Square or rectangular - two radiographs are required in each vertical joint and one in a horizontal joint c) Circular plates - one radiograph and for square or rectangular - one in a vertical joint, one in a horizontal joint, and one in each corner d) Circular and square of rectangular new or replaced insert plates require 100% examination Reference: API-653, Paragraph 10.2.1.6 22. What is the minimum diagnostic length of each radiograph? a) The minimum diagnostic length of each radiograph shall be six inches b) The minimum diagnostic length of each radiograph shall be three inches c) The minimum diagnostic length of each radiograph shall be nine inches d) The minimum diagnostic length of each radiograph shall be twelve inches Reference: API-653, Paragraph 10.2.1.7 23. If the radiograph of an intersection between a new and old weld discloses discontinuities, which are unacceptable by current standards, what must be done? a) The unacceptable welds must be removed and made in accordance with current standards b) The unacceptable welds shall be repaired to bring them in to compliance c) The existing welds may be evaluated according to the original standard of construction d) The existing welds shall be evaluated using the acceptance criteria of ASME Section VIII Reference: API-653, Paragraph 10.2.2 24. Radiographs and radiograph records of all repaired welds shall be marked with what letter(s)? a) "RW" (Repaired Weld) b) "WR" (Weld Repair) c) "A" (Accepted repair) d) "R" Reference: API-653, Paragraph 10.2.3.2 25. Hydrostatic testing is required for reconstructed tanks and tanks that have undergone major repairs or alterations. What is the minimum length of time the hydrostatic test must be held? a) The time is up to the discretion of the Inspector b) Twenty-four hours c) The time is up to the discretion of the owner/operator d) Twelve hours Reference: API-653, Paragraph 10.3.1.1
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 50

26. Major repair and major alteration is defined by API-653 by which of the following? a) Cutting, addition, removal and/or replacement of the annular plate ring only if the plate is less than 1/2" thick b) Cutting, addition, removal an/or replacement of the annular plate ring, the shellto-bottom weld, or a sizeable portion of the shell c) Cutting, addition, removal an/or replacement of the annular plate ring, the shellto-bottom weld, or a 100 square inch portion of the shell d) Cutting, addition, removal an/or replacement of the annular plate ring, the shellto-bottom weld, or a sizeable portion of the shell in shell material greater than 3/4" thick Reference: API-653, Paragraph 10.3.1.2 27. Of the following, which would not be considered a major repair or alteration? a) The installation of a shell penetration NPS 12 above the design liquid level b) The installation of a shell penetration NPS 12 below the design liquid level c) Jacking of a tank shell d) The complete of partial removal and replacement of more than 12 inches of vertical weld joining shell plates, or radial weld joining the annular plate ring Reference: API-653, Paragraph 10.3.1.2 28. A full hydrostatic test of the tank is not required for major repairs and alterations when certain conditions are met. Where would you look for these conditions? a) API-650 Paragraph 5.3.6 b) API-RP-575 Paragraph 7.5 c) API-510 Paragraph 6.4 d) API-653 Paragraph 10.3.2 Reference: API-653, Paragraph 10.3.2.1
29. Hydrostatic testing is not required for shell repairs when all but which of the following are complied with? a) Impact test requirements shall follow appropriate portions of API-650 and must be specified in the repair procedure b) New vertical and horizontal shell butt-welds must have complete penetration and fusion c) New materials shall meet the current edition of ASME Section II Part A d) Finished weld must be examined by radiography Reference: API-653, Paragraph 10.3.22 30. If the owner/operator elects to utilize a fitness-for-service evaluation to exempt a repair form hydrostatic testing, who perform the evaluation? a) Fitness-for-service evaluations may not be used to exempt hydrostatic testing following a repair b) The Authorized Inspector c) Engineer experienced in storage tank design and the evaluation methods used d) Exemption of hydrostatic testing for repairs can only be given by the jurisdiction

Reference: API-653, Paragraph 10.3.2.6


API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 51

31. When settlement is anticipated, a tank that is to be hydrostatically tested shall: a) Have the plumbness checked b) Have the water tested to ensure it is potable c) Have the perimeter dike system checked d) Have the foundation checked for settlement Reference: API-653, Paragraph 10.5.1.1 32. The tank settlement shall initially be surveyed with the tank empty. What is the minimum number of settlement measurement points for a tank which is 110 feet in diameter? a) Minimum number of settlement points is 11 b) Minimum number of settlement points is 32 c) Minimum number of settlement points is 8 d) Minimum number of settlement points is 12 Reference: API-653, Paragraph 10.5.1.2 33. The tank settlement shall initially be surveyed with the tank empty. What is the minimum number of settlement measurement points for a tank which is 60 feet in diameter? a) Minimum number of settlement points is 12 b) Minimum number of settlement points is 6 c) Minimum number of settlement points is 8 d) Minimum number of settlement points is 4 Reference: API-653, Paragraph 10.5.1.2 34. Regardless of the minimum number of settlement measurement points required, what is the maximum spacing between settlement measurement points? a) 24 feet b) 32 feet c) 36 feet d) 40 feet Reference: API-653, Paragraph 10.5.1.2 35. When shall settlement be measured? a) Settlement shall be measured after the water reaches 100% of test level and again when the tank is emptied b) Settlement shall be measured during filling and when the water reaches 80% of test level c) Settlement shall be measured during filling and when the water reaches 100% of test level d) Settlement shall be measured during filling and when the water reaches 100% of test level and during emptying of the tank Reference: API-653, Paragraph 10.5.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 52

Answers to API-653 Section 10, Examination and Testing


Question Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 Answer c a d b c a d a b c b a b b d c d b a d c a c d b b a d c c d a c b c

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 53

Section 11 Marking
1. Tanks that are reconstructed, in accordance with API-653 shall be identified by a corrosionresistant metal nameplate. What is the size requirement for the letters and numerals to be used on this nameplate and how are they applied to the nameplate? a) Letters and numerals not less than 1/2" high shall be embossed, engraved, or stamped in the plate b) Letters and numerals not less than 1/4" high shall be embossed, engraved, or stamped in the plate c) Letters and numerals not less than 5/32" high shall be painted on the plate or embossed, engraved, or stamped in the plate d) Letters and numerals not less than 5/32" high shall be embossed, engraved, or stamped in the plate Reference: API-653, Paragraph 11.1.1 2. Where should the new nameplate be attached and what should be done with the existing nameplate a) The new nameplate shall be attached to the tank shell adjacent to the existing nameplate. The existing nameplate shall be cleaned or suitably reconditioned b) The new nameplate shall be attached to the tank shell adjacent to the existing nameplate. The existing nameplate shall be left attached to the tank c) The new nameplate shall be attached to the tank shell adjacent to the existing nameplate. The existing nameplate shall be removed and placed in the tank record file d) The new nameplate shall be attached to the tank shell adjacent to the existing nameplate. The existing nameplate shall then be discarded Reference: API-653, Paragraph 11.1.2 3. All but which of the following information shall be made part of the owner/operator's records for aboveground storage tanks? a) Names of all operators of the tank b) Calculations c) Construction and repair drawings d) Additional supporting data Reference: API-653, Paragraph 11.2.1, 11.2.2, 11.2.3 Answers to API-653 Section 11, Marking Question Number Answer 1 D 2 B 3 A Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 54

Appendix B Evaluation of Tank Bottom Settlement 1. External measurements for tank settlement shall be taken at points having a maximum spacing of ____ around the circumference. a) 24 feet b) 28 feet c) 32 feet d) 36 feet Reference: API-653 Appendix B, Paragraph B.2.1 and Figure B-1 2. Regardless of tank size, what is the minimum number of settlement point measurements? a) Four b) Eight c) Twelve D d) Based on the formula N = 10 Reference: API-653 Appendix B, Paragraph B.2.1 and Figure B-1 3. Internal measurement for tank bottom settlement taken across the diameter of the tank must be taken at what maximum spacing? a) 10 feet b) 24 feet c) 32 feet d) 4 feet Reference: API-653 Appendix B, Paragraph B.2.1 and Figure B-2 4. Which of the following is not listed as settlement component? a) Uniform settlement b) Rigid body tilting of a tank (planar tilt) c) Out-of-plane settlement (differential settlement) d) Soil undermining (total tank sinking) Reference: API-653 Appendix B, Paragraph B.2.2 5. What type of settlement is depicted here? a) Bottom settlement near tank shell b) Edge settlement c) Localized bottom remote from tank shell d) Planar settlement Reference: API-653 Appendix B & Fig. B-5
B

Original bottom position

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 55

6. Using the formula in B-3.2, determine the maximum permissible deflection (out of plane distortion) for a tank with the following data reported. Diameter Height Material Yield strength Arc length between measurements a) b) c) d) S = .09 feet S = .9 feet S = 9 feet S = .009 feet 110 feet 60 feet Carbon Steel (Young's modulus = 29,000,000 psi) 30,000psi 31.4 feet

Reference: API-653 Appendix B Paragraph B.3.2 7. What is the maximum depth of a local depression in a tank bottom if the radius of an inscribed circle is equal to 7.5 feet? a) B B = .2775 inches b) B B = 2.775 inches c) B B = 27.75 inches d) B B = .02775 inches Reference: API-653 Appendix B Paragraph B.3.3

Answers to API-653 Appendix B, Tank Bottom Settlement


Question Number 1 2 3 4 5 6 7 Answer C B A D B A B

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-653, Tank Inspection, Repair, Alteration, & Reconstruction

Issue Date 03/98

Revision Date 07/00

Page 56

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 1

Section 1 Scope 1. API 650 covers the design, materials, fabrication, erection, and testing of aboveground steel storage tanks. What is the maximum internal pressure for tanks not covered by appendix F of this standard? a) Maximum pressure shall not exceed 15 psig b) Maximum pressure shall not exceed 15 psia c) Maximum pressure shall not exceed the weight of the roof plates d) Maximum pressure shall not exceed the weight of the floor plates Reference: API-650, Paragraph 1.1.1 2. API-650 applies only to tanks whose entire bottom is uniformly supported and tanks in ___ that have a maximum operating temperature of _____F. a) Any petrochemical service and temperature not exceeding 120F b) Non-refrigerated service and temperature not exceeding 200F c) Non-refrigerated service and temperature not exceeding 120F d) Any petrochemical service and temperature not exceeding 200F Reference: API-650, Paragraph 1.1.1 3. An aboveground storage tank is to be subjected to a small internal service pressure. To which standard or Code may the tank be designed? a) API-650 providing the requirements of Appendix F are met b) API-653 providing the requirements of Appendix F are met c) ASME-Section VIII, Div. 1 providing the requirements of Appendix F are met d) ASME-Section VIII, Div. 2 providing the requirements of Appendix F are met Reference: API-650, Paragraph 1.1.1 4. According to Table 1-1, what is the status of Appendix O? a) This Appendix is a Recommendation b) This Appendix is a Requirement c) This Appendix is Mandatory d) This Appendix is Purchasers option Reference: API-650, Paragraph 1.1.19 and Table 1-1 5. What is the purpose of the ( ) next to a paragraph number? a) The paragraph requires a decision or action by the API b) The paragraph requires a decision or action by the Inspector c) The paragraph requires a decision or action by the purchaser d) The paragraph requires a decision or action by the fabricator Reference: API-650, Paragraph 1.1.2 and Note

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 2

Answers to API-Standard 650 Section 1, Scope


Question Number 1 2 3 4 5 Answer C B A D C

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 3

Section 2 Materials 1. API-650 lists materials to be used in the construction of tanks covered by the standard. Is it permissible to use materials other than those listed in the standard? a) No only materials listed in API-650 may be used in tank fabrication b) Yes as long as the manufacturer accepts full liability for tank failure c) Yes providing it is certified as meeting all requirements of a material listed in API-650 and is approved by the API-653 Inspector d) Yes providing it is certified as meeting all the requirements of a material listed in API-650 and is approved by the purchaser Reference: API-650, Paragraph 2.1.1 2. If a new or unused plate cannot be completely identified, may it still be used in the construction of tanks within the scope of API-650? a) Yes only if the material passes the tests prescribed in Appendix S b) Yes only if the material passes the tests prescribed in Appendix N c) Yes only if the material passes the tests prescribed in ASME Section V d) Yes only if the material passes the tests prescribed in ASME Section VIII, Div. 2 Reference: API-650, Paragraph 2.1.2 3. What is the maximum permitted underrun for shell, roof, and bottom plates? a) 0.10 inch from the computed design thickness or minimum permitted thickness b) 0.01 inch from the computed design thickness or minimum permitted thickness c) 0.001 inch from the computed design thickness or minimum permitted thickness d) 0.02 inch from the computed design thickness or minimum permitted thickness Reference: API-650, Paragraph 2.2.1.2.3 4. Shell plates are limited to what maximum thickness? a) Shell plates are limited to a maximum thickness of 1.250 inches b) Shell plates are limited to a maximum thickness of 1.875 inches c) Shell plates are limited to a maximum thickness of 1.750 inches d) Shell plates are limited to a maximum thickness of 1.075 inches Reference: API-650, Paragraph 2.2.1.4 5. Which of the following is not a requirement for shell plates that are thicker than 1.5 inches? a) Plates thicker than 1.5 inches shall be free of mill scale and painted b) Plates thicker than 1.5 inches shall be made to fine-grain practice c) Plates thicker than 1.5 inches shall be impact tested d) Plates thicker than 1.5 inches shall be normalized or quench tempered Reference: API-650, Paragraph 2.2.1.4

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 4

6. What is the maximum shell plate thickness permitted for a tank fabricated of ASTM A 36 material? a) This plate material is limited to 1.750 inches b) This plate material is limited to 1.075 inches c) This plate material is limited to 1.050 inches d) This plate material is limited to 1.500 inches Reference: API-650, Paragraph 2.2.2 a 7. What is the maximum shell plate thickness permitted for a tank fabricated of ASTM A 285, Grade C material? a) This plate material is limited to 1.000 inches b) This plate material is limited to 1.250 inches c) This plate material is limited to 1.500 inches d) This plate material is limited to 1.750 inches Reference: API-650, Paragraph 2.2.2 d 8. All welding to repair surface defects shall be done with ______. a) Cellulose coated electrode b) High nickel content electrode c) Low-hydrogen electrode d) Gas tungsten process Reference: API-650, Paragraph 2.2.6.2 9. When conducting impact tests, how many specimens are required from a single test coupon? a) Impact tests shall be performed on a single specimen taken from a single test coupon b) Impact tests shall be performed on two specimens taken from a single test coupon c) Impact tests shall be performed on three specimens taken from a single test coupon d) Impact tests shall be performed on four specimens taken from a single test coupon Reference: API-650, Paragraph 2.2.8.3 10. In situations where it is not possible to obtain full size specimens, what is the required width along the notch for subsize specimens? a) 60% of the material thickness b) 80% of the material thickness c) 90% of the material thickness d) 75% of the material thickness Reference: API-650, Paragraph 2.2.8.5

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 5

11. Unless data is available to justify a different temperature, what must the design metal temperature be for an aboveground storage tank to be installed in Birmingham, Alabama? a) The design temperature shall be assumed to be 25F b) The design temperature shall be assumed to be 15F c) The design temperature shall be assumed to be 20F d) The design temperature shall be assumed to be 10F Reference: API-650, Paragraph 2.2.9.3 and Figure 2-2 12. Unless data is available to justify a different temperature, what must the design metal temperature be for an aboveground storage tank to be installed in Indianapolis, Indiana? a) The design temperature shall be assumed to be 5F b) The design temperature shall be assumed to be -5F c) The design temperature shall be assumed to be 0F d) The design temperature shall be assumed to be 10F Reference: API-650, Paragraph 2.2.9.3 and Figure 2-2 13. What is the required average longitudinal impact value of three specimens taken from a 1.375 inch thick A 516M-60(415) normalized Group IIIA test coupon? a) 30 foot-pounds b) 20 foot-pounds c) 15 foot-pounds d) 13 foot-pounds Reference: API-650, Paragraph 2.2.10.2 and Figures 2-3 and 2-4 14. What is the required average longitudinal impact value of three specimens taken from a 1.5 inch thick A 516M-70(485) as rolled Group V test coupon? a) 35 foot-pounds b) 25 foot-pounds c) 20 foot-pounds d) 30 foot-pounds Reference: API-650, Paragraph 2.2.10.2 and Figures 2-3 and 2-4 15. Longitudinal impact tests are performed on three specimens, taken from a 1.5 inch thick A 516M-70(485) as rolled test coupon with the following results: Specimen #1 42 footpounds, Specimen #2 18 foot-pounds, Specimen # 3 31 foot-pounds. Is the impact test acceptable? a) Yes the average impact value exceeds 30 foot-pounds b) Yes only one specimen is less than 2/3 the specified minimum value c) No the average impact value of Specimen # 1 exceeds 2/3 the required average impact value and one specimen is less than 2/3 the specified minimum value d) No Specimen #2 is less than 2/3 the specified minimum Reference: API-650, Paragraph 2.2.8.3 and Figures 2-3 and 2-4
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 6

Answers to API-Standard 650 Section 2, Materials


Question Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Answer D B B C A D A C C B C A C D D

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 7

Section 3 Design 1. According to API-650, tack welds _______ a) May be installed by welders who need practice b) Can be considered as adding to the strength of a welded joint c) Are not considered as having any strength value in the finished structure d) Have strength value in the finished structure provided they are performed by a qualified welder to a qualified welding procedure Reference: API-650, Paragraph 3.1.3.2 2. What is the minimum size fillet weld permitted when joining a 1 thick plate to a thick plate? a) 3/16 b) 1/4 c) 3/8 d) 1/2 Reference: API-650, Paragraph 3.1.3.3 3. For lap-welded joints that are tack welded, what is the minimum amount of lap permitted? a) The lap need not exceed 2 b) The lap need not exceed 1 c) The joint shall be lapped at least 5 times the minimum required thickness of the thinner plate d) The joint shall be lapped at least 5 times the nominal thickness of the thinner plate Reference: API-650, Paragraph 3.1.3.5 4. The welded joint pictured here is defined as what type of joint? a) Double-V butt joint b) Square-groove butt joint c) Double-U butt joint d) Double-square butt joint Reference: API-650, Paragraph 3.1.5.1 5. Vertical shell joints may be partial penetration groove welds welded from both sides. a) True b) False Reference: API-650, Paragraph 3.1.5.2 a

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 8

6. API 650 requires the vertical joints in adjacent shell courses to be offset. What is the minimum required offset between the first course of an AST, which is 1.25 thick and the second course which is 1 thick? a) The minimum offset shall be 5 times the second shell course height b) The minimum offset shall be 5 times the thickness of the second course c) The minimum offset shall be 5 times the first shell course height d) The minimum offset shall be 5 times the thickness of the first shell course Reference: API-650, Paragraph 3.1.5.2 b 7. Three-plate laps in tank bottoms shall be at least ____ from each other, from the tank shell, from butt-welded annular-plate joints, and from joints between annular plates and the bottom. a) 1.2 inches b) 12 inches c) 1.2 feet d) 12 feet Reference: API-650, Paragraph 3.1.5.4 8. What is the maximum size of fillet weld permitted in the attachment between the lowest course shell plate and the bottom plate? a) 3/8 inch b) 5/16 inch c) 1/2 inch d) 1/4 inch Reference: API-650, Paragraph 3.1.5.7 9. What is the minimum size fillet weld required on each side of the shell plate attaching shell plate to the annular plate? The shell plate is 1.25 thick. a) 3/8 inch b) 3/16 inch c) 1/4 inch d) 5/16 inch Reference: API-650, Paragraph 3.1.5.7 10. A 110 ft diameter tank shall have a top angle not less than ____ inches. a) 2 X 2 X 3/8 b) 2 X 3 X 3/8 c) 3 X 3 X 3/8 d) 3 X 2 X 3/8 Reference: API-650, Paragraph 3.1.5.9

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 9

11. The ______ shall state the design metal temperature, the design specific gravity, the corrosion allowance, and the design wind velocity. a) The purchaser b) The fabricator c) The Inspector d) Erector Reference: API-650, Paragraph 3.2.1 12. According to API-650, tanks meeting the minimum requirements of the standard may be subjected to a partial vacuum of _____. a) One inch of mercury b) One inch of water pressure c) One pound per square inch absolute d) One centimeter of water pressure Reference: API-650, Paragraph 3.2.4 13. An AST is 116 ft in diameter and constructed of A 516M-70(485) Group V as rolled material. How many hardness tests are required on one circumferential weld? a) One b) Two c) Three d) Four Reference: API-650, Paragraph 3.3.4 14. The purchaser orders an aboveground storage tank and insists on a corrosion allowance in the bottom plates of .125 inches. What is the minimum thickness permitted for bottom plates in this tank? a) Minimum thickness of bottom plate is 1/4 inch b) Minimum thickness of bottom plate is 1/2 inch c) Minimum thickness of bottom plate is 3/8 inch d) Minimum thickness of bottom plate is 5/16 inch Reference: API-650, Paragraph 3.4.1 15. What is the minimum projection, of trimmed bottom plates, beyond the outside edge of the weld attaching bottom to the shell? a) Minimum projection is 0.01 inch b) Minimum projection is 0.10 inch c) Minimum projection is 1.00 inch d) Minimum projection is 10.0 inch Reference: API-650, Paragraph 3.4.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 10

16. Annular bottom plates shall have a radial width that provides at least ____ between the inside of the shell and any lap-welded joint in the remainder of the bottom. a) 12 inches b) 24 inches c) 1.2 inches d) 2.4 inches Reference: API-650, Paragraph 3.5.2 17. How far must annular bottom plates project outside the shell? a) Annular bottom plates shall project at least 1 inch when trimmed b) Annular bottom plates shall project at least 1/2 inch beyond the edge of the weld c) Annular bottom plates shall project at least 2 inches outside the shell d) Annular bottom plates shall project at least 5t (t = thickness of the shell course) outside the shell Reference: API-650, Paragraph 3.5.2 18. The thickness of the first shell course of an aboveground storage tank is 1&5/8th inches. The hydrostatic test stress in the first shell course is 33,000 psi. What is the minimum permissible thickness of the annular bottom plates? a) Minimum permitted thickness is 5/8th inch b) Minimum permitted thickness is 9/16th inch c) Minimum permitted thickness is 3/4 inch d) Minimum permitted thickness is 11/16th inch Reference: API-650, Paragraph 3.5.3 and Table 3-1 19. According to API-650, what is the minimum allowable nominal shell thickness of an AST that is 86 feet in diameter? a) Minimum nominal shell thickness is 3/16th inch b) Minimum nominal shell thickness is 1/4 inch c) Minimum nominal shell thickness is 9/32nd inch d) Minimum nominal shell thickness is 5/16th inch Reference: API-650, Paragraph 3.6.1.1 20. Unless otherwise agreed to by the purchaser, what is the minimum nominal width of shell plates? a) Minimum width of shell plates is 84 inches b) Minimum width of shell plates is 96 inches c) Minimum width of shell plates is 72 inches d) Minimum width of shell plates is 120 inches Reference: API-650, Paragraph 3.6.1.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 11

21. Aboveground storage tank manufacturers are required to furnish a drawing to the purchaser listing all but which of the following for each course? a) The material specification b) The allowable stress c) The nominal thickness used d) The nominal thickness of coatings Reference: API-650, Paragraph 3.6.1.7 22. In calculating the net plate thickness for an AST fabricated of A 516M Grade 450(60) material, what would be the product design stress value used in the calculation? a) 24,000 b) 21,300 c) 32,000 d) 23,300 Reference: API-650, Paragraph 3.6.2.1 and Table 3-2 23. The fabricator of an AST obtains the approval of the purchaser to use the alternative shell design permitted in Appendix A in the design of a 60 foot diameter tank using 3/8th inch A 516M Grade 450(60) plate. What allowable stress would be used in the design calculations? a) 21,300 b) 24,000 c) 21,000 d) 32,000 Reference: API-650, Paragraph 3.6.2.3 24. What is the maximum diameter of tank that permits the 1-foot method of calculation for required thickness? a) Tanks 50 feet in diameter and less b) Tanks 120 feet in diameter and less c) Tanks 180 feet in diameter and less d) Tanks 200 feet in diameter and less Reference: API-650, Paragraph 3.6.3.1 25. Openings in tank shells, larger than that required to accommodate a ____ flanged or threaded nozzle shall be reinforced. a) 2 inch b) 2.5 inch c) 3 inch d) 3.5 inch Reference: API-650, Paragraph 3.7.2.1

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 12

26. When installing openings in a shell plate, the edge of the fillet weld around the periphery of the reinforcing pad shall be spaced at least the greater of _______ from the centerline of any butt-welded shell joints. a) Eight inches or ten times the weld size b) Eight times the weld size or ten inches c) Eight times the weld size or six inches d) Eight inches or six times the weld size Reference: API-650, Paragraph 3.7.3.1 a 27. When installing openings adjacent to each other, how much space must there be between the welds around the periphery of the reinforcing plate? a) Eight times the larger weld or ten inches from each other b) Eight inches or six times the larger weld from each other c) Eight times the larger weld or six inches from each other d) Eight times the larger weld or eight inches from each other Reference: API-650, Paragraph 3.7.3.1 b 28. A minimum distance of ____ shall be maintained between the toe of a weld around a non-reinforced penetration and the toe of the shell-to-bottom weld. a) Ten inches b) Eight inches c) Six inches d) Three inches Reference: API-650, Paragraph 3.7.3.3 29. Subject to the acceptance of the purchaser, the manufacture may locate a circular shell opening in a horizontal butt-welded shell joint provided ______. a) Minimum spacing dimensions are met and a liquid penetrant examination of the welded joint is conducted b) Minimum spacing dimensions are met and a radiographic examination of the welded joint is conducted c) Minimum spacing dimensions are met and an ultrasonic examination of the welded joint is conducted d) Minimum spacing dimensions are met and a magnetic particle examination of the welded joint is conducted Reference: API-650, Paragraph 3.7.3.4 30. All flush-type clean-out fittings and flush-type shell connections shall be thermally stress relieved after assembly and prior to installation in the tank. What are the temperature range and time requirements for this stress relief activity? a) 1100F to 1200F for 1 hour per inch of reinforcing plate thickness b) 1100F to 1200F for 1/2 hour per inch of shell thickness c) 1100F to 1200F for 1 hour per inch of shell thickness d) 1100F to 1200F for 1 & 1/2 hour per inch of shell thickness Reference: API-650, Paragraph 3.7.4.1
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 13

31. Subject to the acceptance of the purchaser, the fabricator may stress relieve at a temperature of 1000F when it is impractical to stress relieve at a minimum temperature of 1100F providing _____. a) The shell plate is first pre-heated to 300F b) The holding time is increased to 2 hours per inch of thickness c) The holding time is increased to 4 hours per inch of thickness d) The holding time is increased to 10 hours per inch of thickness Reference: API-650, Paragraph 3.7.4.5 32. What is the minimum required thickness for a manhole cover plate to be used with a 24 inch manhole? The maximum design liquid level of the tank is 45 feet. a) Minimum thickness of cover plate is 9/16th inch b) Minimum thickness of cover plate is 5/8th inch c) Minimum thickness of cover plate is 1/2 inch d) Minimum thickness of cover plate is 11/16th inch Reference: API-650, Paragraph 3.7.5.1 and Table 3-3 33. What is the bolt circle diameter for a cover plate used with a 30 inch diameter manhole? a) 32 inch b) 36 inch c) 38 inch d) 42 inch Reference: API-650, Paragraph 3.7.5.2 and Table 3-5 34. The purchaser has ordered a 36 inch manhole to be installed in the first course of an AST. The thickness of the shell plate and the reinforcing plate is 1.375 inches. What is the required hole diameter that must be cut in the tank to accommodate this manhole? a) 36 & 1/4 inch b) 36 & 1/2 inch c) 36 & 3/4 inch d) 36 & 5/8 inch Reference: API-650, Paragraph 3.7.5.3 and Table 3-7 35. API 650 requires telltale holes in reinforcing plates. What is the required dimension of this hole and what should be done with it after the initial re-pad pressure test? a) The hole shall be 3/8 inch diameter and shall be left open to the atmosphere b) The hole shall be 1/4 inch diameter and shall be left open to the atmosphere c) The hole shall be 3/8 inch diameter and shall be closed after testing d) The hole shall be 1/4 inch diameter and shall be closed after testing Reference: API-650, Paragraph 3.7.6.1

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 14

36. What is the maximum size un-reinforced opening permitted in flat cover plates without increasing the thickness of the cover plate? a) 4 inch pipe size providing the edge of the opening is not more than the height or diameter of the opening closer to the center of the cover plate b) 3 inch pipe size providing the edge of the opening is not more than the height or diameter of the opening closer to the center of the cover plate c) 2 inch pipe size providing the edge of the opening is not more than the height or diameter of the opening closer to the center of the cover plate d) 1 & inch pipe size providing the edge of the opening is not more than the height or diameter of the opening closer to the center of the cover plate Reference: API-650, Paragraph 3.8.3.1 37. What is the maximum size opening that may be placed in a cover plate? a) 12 inches pipe size b) 8 inches pipe size c) 6 inches pipe size d) 3 inches pipe size Reference: API-650, Paragraph 3.8.3.2 38. An aboveground storage tank has a design liquid height of 40 feet. The purchaser intends to install product mixing equipment in the cover plate of a 30 inch manhole. What is the required minimum thickness of the cover plate? a) The minimum thickness shall be at least .625 inches b) The minimum thickness shall be at least .75 inches c) The minimum thickness shall be at least .9375 inches d) The minimum thickness shall be at least .875 inches Reference: API-650, Paragraph 3.8.3.2 39. A 24 inch manhole is to be installed in a roof plate and it is anticipated that work may be carried on through the manhole while the tank is in use. What is the diameter of the opening to be cut in the roof plate and what is the outside diameter of the reinforcing plate? a) The diameter of the opening is 24.625 and the OD of the reinforcing plate is 42 b) The diameter of the opening is 24.625 and the OD of the reinforcing plate is 46 c) The diameter of the opening is 24.750 and the OD of the reinforcing plate is 42 d) The diameter of the opening is 24.750 and the OD of the reinforcing plate is 46 Reference: API-650, Paragraph 3.8.4 40. What is the minimum thickness permitted for rectangular roof opening cover plates? a) Minimum thickness shall not be less than .875 inches b) Minimum thickness shall not be less than .750 inches c) Minimum thickness shall not be less than .625 inches d) Minimum thickness shall not be less than .500 inches Reference: API-650, Paragraph 3.8.6.2
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 15

41. Stiffening ring splice welds shall be located at least _____ from any vertical shell weld. a) 24 inches b) 18 inches c) 12 inches d) 6 inches Reference: API-650, Paragraph 3.9.3.4 42. When stiffening rings are to be used as walkways, what is the required width of the stiffening ring? a) The width shall be not less than 36 inches clear of the projecting curb angle on the top of the tank shell b) The width shall be not less than 3 feet 6 inches clear of the projecting curb angle on the top of the tank shell c) The width shall be not less than 24 inches clear of the projecting curb angle on the top of the tank shell d) The width shall be not less than 2 feet 4 inches clear of the projecting curb angle on the top of the tank shell Reference: API-650, Paragraph 3.9.4 43. How far below the top of the curb angle should a stiffening ring, that is to be used as a walkway, be located? a) 3 feet 6 inches b) 36 inches c) 6 feet 3 inches d) 63 inches Reference: API-650, Paragraph 3.9.4 44. All roofs and supporting structures shall be designed to support dead loads plus a uniform live load of not less than _____ of projected area a) 25 pounds per square inch b) 25 pounds per square foot c) 25 pounds per square yard d) 25 pounds per square meter Reference: API-650, Paragraph 3.10.2.1 45. What is the minimum nominal thickness permitted for roof plates? a) 3/16 inch or 5.76 pounds per square foot b) 3/16 inch or 6.75 pounds per square foot c) 3/16 inch or 7.65 pounds per square foot d) 3/16 inch or 12-gauge sheet Reference: API-650, Paragraph 3.10.2.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 16

46. A roof where the continuous fillet weld between the roof plates and the top angle does not exceed 3/16", the slope at the top angle attachment does not exceed 2" in 12", and the shell-to-roof compression ring details are limited to Figure F-2 (a)-(d) may be considered what type of roof? a) A 1 in 6 roof b) A dangerous roof design and should be avoided c) A roof with inherent compensation d) A frangible roof Reference API-650, Paragraph 3.10.2.5.1 47. Rafters shall be spaced so that in the outer ring, their centers are not more than _____ apart measured along the circumference of the tank. a) 3 feet or 9.42 feet b) 2 feet or 6.28 feet c) 4 feet or 12.56 feet d) 2.5 feet or 7.85 feet Reference: API-650, Paragraph 3.10.4.4

Answers to API-Standard 650 Section 3, Design


Question Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
API-653 Exam Prep Course

Answer C B D A B D B C D C A B D C C B C A B C D B C
(610) 594-9036

BAY Technical Associates, Inc.

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 17

Answers to API-Standard 650 Section 3, Design (continued)


24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 D A B C D B C C A B C B C A D B D D C A B C D B

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 18

Section 4 Fabrication 1. What method(s) is/are permitted for straightening material? a) Pressing or other non-injurious method prior to layout or shaping b) Heating and hammering after layout or shaping c) Jacking into shape after final assembly d) Jacking into shape and holding with tack welds Reference: API-650, Paragraph 4.1.1.2 2. When plates are to be butt-welded, shearing is limited to what maximum thickness? a) 5/8th inch b) 3/8th inch c) 3/16th inch d) Shearing is not permitted Reference: API-650, Paragraph 4.1.2 3. When plates are to be used in lap-welded joints, shearing is limited to what maximum thickness a) 3/16th inch b) 3/8th inch c) 1/2 inch d) 5/8th inch Reference: API-650, Paragraph 4.1.2 4. What are the requirements regarding mill test reports according to API-650? a) No material shall be used in the construction of an AST unless it is accompanied by a mill test report b) Mill test reports are required only on shell plate material c) Mill test reports shall be furnished to the purchaser only when specified in the original purchase order d) Mill test reports shall be furnished to the purchaser prior to final acceptance of the AST Reference: API-650, Paragraph 4.2.1 5. Mill and shop inspection releases the manufacturer from responsibility for replacing defective material. a) True b) False Reference: API-650, Paragraph 4.2.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 19

Answers to API-Standard 650 Section 4, Fabrication


Question Number 1 2 3 4 5 Answer A B D C B

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 20

Section 5 Erection 1. What welding process is not permitted when impact testing of the material is required? a) Shielded metal-arc b) Gas metal-arc c) Oxyfuel d) Submerged arc Reference: API-650, Paragraph 5.2.1.1 2. Welding may be performed manually, automatically, or semi-automatically according to the procedures described in ____ of the ASME Code. a) Section VIII, Division 1 b) B31.3 c) Section VIII, Division 2 d) Section IX Reference: API-650, Paragraph 5.2.1.1 3. No welding of any kind shall be performed when the temperature of the base metal is less than ____F a) Sixty b) Thirty-two c) Zero d) Negative fifteen Reference: API-650, Paragraph 5.2.1.2 4. When base metal thickness is greater than 1.25 inches or the base metal temperature is 0F -32F, what requirement must be met? a) The base metal within 3 inches of the starting point of the welding shall be heated to a temperature warm to the hand b) The base metal within 3 inches of the starting point of the welding shall be heated to a temperature of not less than 200F c) The base metal within 3 inches of the starting point of the welding shall be heated to a temperature of not less than 60F d) The base metal within 3 inches of the starting point of the welding shall be heated to a temperature of not less than 45F Reference: API-650, Paragraph 5.2.1.2 5. What is the maximum acceptable undercut for horizontal butt joints? a) 1/64th inch b) 1/32nd inch c) 3/64th inch d) 3/32nd inch Reference: API-650, Paragraph 5.2.1.4
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 21

6. What is the maximum acceptable undercut for vertical butt joints? a) 3/32nd inch b) 3/64th inch c) 1/32nd inch d) 1/64th inch Reference: API-650, Paragraph 5.2.1.4 7. What is the maximum permissible weld reinforcement for a vertical joint in plate thickness 1.25? a) 3/16th inch b) 1/8th inch c) 1/4th inch d) 3/32nd inch Reference: API-650, Paragraph 5.2.1.5 8. When tack welds are used during the assembly of vertical joints, what requirement is stipulated by API-650? a) Tack welds that are to be removed do not require a qualified procedure or welder b) Tack welds that are to be left in place shall be made using a qualified procedure only c) Tack welds that are to be removed may be made using a welder in training d) Tack welds that are to be left in place shall be made using a qualified procedure and welder Reference: API-650, Paragraph 5.2.1.8 9. What is the requirement when protective coatings are used on surfaces to be welded? a) The coating must be removed prior to welding b) The coating shall be included in the welders performance qualification tests c) The coating shall be included in the welding procedure qualification d) The coating shall be identified on the purchase order Reference: API-650, Paragraph 5.2.1.9 10. The welding of the ____ shall be practically complete prior to welding-out the bottom joints. a) Nozzle reinforcement periphery welds b) Shell-to-bottom weld c) All vertical and horizontal shell welds d) All external attachment welds Reference: API-650, Paragraph 5.2.2.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 22

11. In a vertical joint of an AST, what is the maximum misalignment of 1.5 thick plate? a) Maximum misalignment is .150 inch b) Maximum misalignment is .145 inch c) Maximum misalignment is .135 inch d) Maximum misalignment is .125 inch Reference: API-650, Paragraph 5.2.3.1 12. In a horizontal joint of an AST, what is the maximum projection of an upper plate beyond the face of the plate below it? The plate thickness is .25 inch. a) Maximum projection is .0625 inch b) Maximum projection is .0500 inch c) Maximum projection is .1250 inch d) Maximum projection is .09375 inch Reference: API-650, Paragraph 5.2.3.2 13. Multi-pass weld procedures are required for circumferential and vertical joints in tank shell courses constructed of material that is more than 1.5 inches thick. What is the maximum weld pass size permitted and what is the minimum pre-heat temperature? a) No weld pass over inch with a minimum pre-heat of 300F b) No weld pass over inch with a minimum pre-heat of 200F c) No weld pass over inch with a minimum pre-heat of 200F d) No weld pass over inch with a minimum pre-heat of 300F Reference: API-650, Paragraph 5.2.3.4 14. The initial weld pass inside the shell of the shell-to-bottom weld shall be cleaned and examined for its entire circumference. This examination shall be visually and by which of the following? a) Magnetic particle or ultrasonic or suitable liquid penetrant process b) Magnetic particle or suitable liquid penetrant process or a vacuum box and bubble method c) Magnetic particle or radiography or vacuum box and bubble method d) Magnetic particle or acoustic emission or eddy current Reference: API-650, Paragraph 5.2.4.1 15. The required examination of the initial weld pass as described in API-650 may be waived subject to agreement between the purchaser and the AST manufacturer provided all but which of the following examinations are performed on the entire circumference of the weld(s) a) Examine either side of the finished weld by MT, PT, or right angle vacuum box b) Visually examine the initial weld (inside and outside) c) Visually examine the finished joint welded surfaces (inside and outside the shell) d) Examine either side of the finished weld by MT, PT, UT, or RT Reference: API-650, Paragraph 5.2.4.2
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 23

16. What are the dimensions of a standard vacuum testing box? a) 6 wide by 30 long b) 6 wide by 24 long c) 6 wide by 36 long d) 6 wide by 32 long Reference: API-650, Paragraph 5.3.3.1 17. In an examination of a tanks bottom weld seams by vacuum box testing, what is the required partial vacuum pressure? a) At least 1 lbf/in2 gauge (psig) b) At least 2 lbf/in2 gauge (psig) c) At least 3 lbf/in2 gauge (psig) d) At least 4 lbf/in2 gauge (psig) Reference: API-650, Paragraph 5.3.3.4 18. If an alternative to vacuum box testing is used, whose approval is required? a) The Manufacturer b) The API-653 Inspector c) The local jurisdiction d) The purchaser Reference: API-650, Paragraph 5.3.3.5 19. After fabrication is completed but prior to filling an aboveground storage tank with test water, reinforcing plates shall be tested. What method of test and pressure shall be used? a) A hydrostatic pressure test at up to 15 lbf/in2 (psig) b) A pneumatic pressure test at up to 15 lbf/in2 (psig) c) A vacuum test at a partial pressure of 2 lbf/in2 (psig) d) A pneumatic pressure test at up to 25 lbf/in2 (psig) Reference: API-650, Paragraph 5.3.5 20. A new aboveground storage tank must be tested. If water is available for testing the shell, the tank shall be filled to any of the following levels except? a) To the maximum design liquid level b) Tanks with tight roofs, to 2 inches above the weld connecting the roof plate of compression bar to the top angle of the shell c) To overflowing to ensure all air is vented from the tank d) To a level lower than specified in a) or b) when restricted by overflows or freeboard agreement between the manufacturer and the purchaser Reference: API-650, Paragraph 5.3.6

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 24

21. The purchaser of an AST that is designed to be gas tight required the roof to be tested pneumatically. What maximum pressure would be applied to a tank with thick roof plates? a) The maximum pneumatic pressure permitted is .053 psi b) The maximum pneumatic pressure permitted is .071 psi c) The maximum pneumatic pressure permitted is .083 psi d) The maximum pneumatic pressure permitted is .091 psi Reference: API-650, Paragraph 5.3.7.1 and 3.10.2.2 Solution: 3/16 thick plate = 7.65 lb/ft 1/16 = 2.55 lb/ft 22. During the filling of an aboveground storage tank for testing, leakage was observed in a horizontal seam. Repairs are to be completed with the test water in the tank. The tank is 61 feet high and the leak is discovered 29 feet below the top of the tank. Where must the water level be during the repair? a) The water level shall be not less than 30 feet from the top of the tank b) The water level shall be not more than 32 feet from the bottom of the tank c) The water level shall be at the maximum design liquid level d) The water shall be removed from the tank Reference: API-650, Paragraph 5.4.4 23. A 60 foot high aboveground storage tank is designed with an internal floating roof. What is the maximum out-of-plumbness permitted on the 54.5 foot fixed roof columns? a) 2.94 inches b) 3.27 inches c) 1.31 inches d) 1.18 inches Reference: API-650, Paragraph 5.5.2 24. What is the maximum roundness tolerance (radius tolerance) permitted on an AST that is 110 feet in diameter and where is this tolerance applied? a) measured 10 feet above the bottom corner weld b) measured 1 foot below the top shell angle joint c) measured 1 foot above the bottom corner weld d) measured 10 feet below the top shell angle joint Reference: API-650, Paragraph 5.5.3 25. Peaking at vertical welds and banding at horizontal welds shall not exceed ____. a) 1 inch b) inch c) inch d) inch Reference: API-650, Paragraph 5.5.4 (a and b)
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 25

26. Peaking and banding are determined using a horizontal sweep board for peaking and a straight edge vertical sweep board for banding. What is the required length of these sweep boards? a) 48 inches b) 24 inches c) 42 inches d) 36 inches Reference: API-650, Paragraph 5.5.4 (a and b) 27. The top of the concrete ringwall (where installed) of an AST must be level within 1/8 in any 30 feet of circumference. What is the total circumferential tolerance measured from the average elevation? a) 1/8 b) 3/16 c) 1/2 d) 1/4 Reference API-650, Paragraph 5.5.5.2 (a) 28. Where a concrete ringwall is not provided, the foundation under the shell shall be level to within what tolerances? a) 1/8 in any 30 of the circumference and 1/2 in the total circumference measured from the average elevation b) 1/8 in any 10 of the circumference and 1/2 in the total circumference measured from the average elevation c) 1/8 in any 10 of the circumference and 1/4 in the total circumference measured from the average elevation d) 1/8 in any 30 of the circumference and 1/4 in the total circumference measured from the average elevation Reference API-650, Paragraph 5.5.5.2 (b) 29. For foundations specified to be sloped from a horizontal plane, the actual elevation shall not deviate from the calculated differences by more than which of the following where concrete ringwalls are provided? a) 1/8 in any 30 of the circumference and 1/4 in the total circumference measured from the average elevation b) 1/8 in any 10 of the circumference and 1/2 in the total circumference c) 1/8 in any 10 of the circumference and 1/2 in the total circumference measured from the average elevation d) 1/8 in any 30 of the circumference and 1/4 in the total circumference Reference API-650, Paragraph 5.5.5.3 (a)

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 26

30. For foundations specified to be sloped from a horizontal plane, the actual elevation shall not deviate from the calculated differences by more than which of the following where concrete ringwalls are not provided? a) 1/8 in any 30 of the circumference and 1/2 in the total circumference measured from the average elevation b) 1/8 in any 10 of the circumference and 1/2 in the total circumference c) 1/8 in any 10 of the circumference and 1/4 in the total circumference measured from the average elevation d) 1/8 in any 30 of the circumference and 1/4 in the total circumference Reference API-650, Paragraph 5.5.5.3 (b)

Answers to API-Standard 650 Section 5, Erection


Question Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Answer C D C A B D A D C B D A C B D Question Number 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Answer A C D B C B A B C C D D B D B

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 27

Section 6 Methods of inspecting Joints 1. With regards to radiographic examination of welded joints, API-650 considers plates to be the same thickness when the difference in their specified or design thickness is not greater than ____. a) 1/32nd inch b) 1/16th inch c) 3/32nd inch d) 1/8th inch Reference: API-650, Paragraph 6.1 2. Which of the following joints do not require radiographic examination? a) Bottom-plate welds b) Shell butt welds c) Flush-type connections with butt welds d) Annular-plate butt welds Reference: API-650, Paragraph 6.1.1 3. Vertical butt welds in plates not greater than 3/8th inch thick, require one spot radiograph to be taken in the first _____ of completed vertical joint of each type and thickness by each welder or welding operator. a) 100 feet b) 50 feet c) 25 feet d) 10 feet Reference: API-650, Paragraph 6.1.2.2(a) 4. One additional spot radiograph shall be taken in each additional ____ of vertical joint of the same type and thickness. a) 10 feet b) 200 feet c) 100 feet d) 25 feet Reference: API-650, Paragraph 6.1.2.2(a) 5. What percentage of the selected spot radiographs must be at junctions of vertical and horizontal welded joints? a) 25 percent b) 50 percent c) 75 percent d) 15 percent Reference: API-650, Paragraph 6.1.2.2(a)

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 28

6. For butt welded joints in plates over 3/8 to not over 1 in thickness are required to be radiographically examined to the same extent as plates 3/8 and less. What additional spot examination does API-650 require for these welded joints? a) 50 percent of all vertical and horizontal junctions b) 75 percent of all vertical and horizontal junctions c) 100 percent of all vertical and horizontal junctions d) 25 percent of all horizontal joints between the first and second course Reference: API-650, Paragraph 6.1.2.2(b) 7. The radiographic film for all junctions of vertical and horizontal joints shall show at least ____ of weld length on each side of the vertical intersection. a) 3 inches b) 2 inches c) 1 inch d) 4 inches Reference: API-650, Paragraph 6.1.2.2(b) and (c) 8. The butt weld around the periphery of an insert manhole or nozzle shall be ____. a) Completely examined by liquid penetrant methods b) Completely examined by ultrasonic methods c) Completely examined by magnetic particle methods d) Completely examined by radiographic methods Reference: API-650, Paragraph 6.1.2.2(d) 9. After the initial spot radiograph in the first 10 feet of horizontal butt joint, additional spot radiographs shall be taken at what increment? a) One radiograph shall be taken in each additional 200 feet b) One radiograph shall be taken in each additional 100 feet c) One radiograph shall be taken in each additional 300 feet d) One radiograph shall be taken in each additional 150 feet Reference: API-650, Paragraph 6.1.2.3 10. What is the minimum weld length that must be clearly shown on each radiograph? a) 2 inches b) 3 inches c) 6 inches d) 8 inches Reference: API-650, Paragraph 6.1.2.8

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 29

11. Personnel who perform and evaluate radiographic examinations according to API-650 shall be qualified and certified by the manufacturer as meeting the requirements as generally outlined in _____. a) Level II or Level III of ASNT SNAT-TC-1B b) Level II or Level III of ASNT SNT-TC-1B c) Level II or Level III of ASNT SNAT-TC-1A d) Level II or Level III of ASNT SNT-TC-1A Reference: API-650, Paragraph 6.1.3.2 12. The acceptance standards for radiographic examinations shall be in accordance with which of the following? a) Paragraph UW-51(b) in Section VIII of the ASME Code b) Paragraph PW-51(b) in Section I of the ASME Code c) Paragraph 341.3.2 in B31.3 Process Piping of the ASME Code d) Paragraph RB-3233 in the National Board Inspection Code (NBIC) Reference: API-650, Paragraph 6.1.5 13. If a section of weld is shown by a radiograph to be unacceptable under the provisions of API-650, paragraph 6.1.5 or the radiograph does not define the limits of the deficient welding, which of the following requirements apply? a) One additional spot shall be taken and at least 3 of weld shall be represented b) Two spots adjacent to the section shall be examined by radiography c) Two spots ten feet from each side of the original radiography shall be examined d) Two spots, chosen randomly by the purchasers inspector, shall be examined by radiography Reference API-650, Paragraph 6.1.6 14. After an aboveground storage tank is completed, what shall be done with the radiographs? a) They shall become the property of the insurance company b) They shall become the property of the manufacturer c) They shall become the property of the purchaser d) They shall become the property of the API Reference API-650, Paragraph 6.1.8.2 15. According to API-650, magnetic particle examination shall be performed to a written procedure. The examiner shall have his/her vision checked and be able to read which of the following? a) The magnetic particle written procedure at a distance not less than 12 inches b) A Jaeger Type 3 standard chart at a distance not less than 12 inches c) A Jaeger Type 1 standard chart at a distance not less than 12 inches d) A Jaeger Type 2 standard chart at a distance not less than 12 inches Reference API-650, Paragraph 6.2.2 and 6.2.3 (a)
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 30

16. Ultrasonic examination shall be performed in accordance with a written procedure. Examiners shall be qualified and certified by the manufacturer as meeting the requirements of certification as generally outlined in which of the following? a) Level II or Level III of ASNT SNAT-TC-1B b) Level II or Level III of ASNT SNT-TC-1B c) Level II or Level III of ASNT SNAT-TC-1A d) Level II or Level III of ASNT SNT-TC-1A Reference API-650, Paragraph 6.3.2 and 6.3.3 17. Liquid penetrant examination shall be performed in accordance with a written procedure. The examiner shall have his/her vision checked and be able to read which of the following? a) The liquid penetrant written procedure at a distance not less than 12 inches b) A Jaeger Type 2 standard chart at a distance not less than 12 inches c) A Jaeger Type 1 standard chart at a distance not less than 12 inches d) A Jaeger Type 3 standard chart at a distance not less than 12 inches Reference API-650, Paragraph 6.4.2 and 6.4.3 (a) 18. Undercutting of welds attaching nozzles, manholes, cleanout openings, and permanent attachments shall not exceed which of the following? a) Undercutting shall not exceed 1/64th inch b) Undercutting shall not exceed 3/32nd inch c) Undercutting shall not exceed 1/32nd inch d) Undercutting shall not exceed 3/64th inch Reference API-650, Paragraph 6.5.1 (b)

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 31

Answers to API-Standard 650 Section 6, Methods of Inspecting Joints


Question Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Answer D A D C A C B D A C D A B C D D B A

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 32

Section 7 Welding Procedure and Welder Qualifications 1. Who is responsible for preparing the welding procedure specification, performing the qualification tests, and preparing the procedure qualification record? a) The welding operator or welder b) The purchasers inspector c) The purchasers welding engineer d) The erection manufacturer or the fabrication manufacturer if other than the erection manufacturer

Reference API-650, Paragraph 7.2.1.1 2. The manufacturer has the approval of the purchaser to use a material listed in API-650 but not included in the applicable table of ASME Section IX. What Group number would this material be included in if the minimum tensile strength is specified at 73,000 psi? a) This material would be included in Group number 2 b) This material would be included in Group number 1 c) This material would be included in Group number 3 d) This material can not be used in AST construction Reference API-650, Paragraph 7.2.1.3 3. When impact tests of the heat-affected zone are required, how shall this requirement be treated? a) Heat treated condition of the base metal shall be a non-essential variable b) Heat treated condition of the base metal shall be an essential variable c) Heat treated condition of the base metal shall be a supplementary essential variable d) Heat treated condition of the base metal does not need to be addressed on the welding procedure specification Reference API-650, Paragraph 7.2.1.4 4. If a protective coating has been applied to weld edge preparations, how is this condition treated on the welding procedure specification? a) The coating shall be removed and does not affect the weld and therefore does not need to be addressed b) The coating shall be included as an essential variable c) The coating shall be included as a non-essential variable d) The coating shall be included as a supplementary essential variable Reference API-650, Paragraph 7.2.1.4

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 33

5. Materials to be used at a design metal temperature below ____, the qualification of the welding procedure for vertical joints shall include impact tests of the weld metal. a) 50F b) 32F c) 60F d) 0F Reference API-650, Paragraph 7.2.2.3 6. Welder qualification tests conducted by one manufacturer shall not qualify a welder or welding operator to do work for another manufacturer. a) True b) False Reference API-650, Paragraph 7.3.1 7. Traceability to a welder or welding operator, either by welders identification stamp or weld map, is required on all but which of the following? a) Shell horizontal weld joints b) Shell vertical weld joints c) Annular plate butt welds (when annular plates are required) d) Roof plate welds and flange-to-nozzle neck welds Reference API-650, Paragraph 7.4

Answers to API-Standard 650 Section 7, Welding Procedure and Welder Qualifications


Question Number 1 2 3 4 5 6 7 Answer D A C B A A D

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 34

Section 8 - Marking 1. A nameplate shall identify aboveground storage tanks made in accordance with API-650. Where must this nameplate be located on the completed tank? a) This nameplate shall be attached to the tank shell adjacent to a manhole or to a manhole reinforcing plate immediately to the right of the manhole b) This nameplate shall be attached to the tank shell adjacent to a vertical weld joint at least 48 above the shell-to-bottom weld joint c) This nameplate shall be attached to the tank shell adjacent to a manhole or to a manhole reinforcing plate immediately above the manhole d) This nameplate shall be attached to the tank shell adjacent to a manhole or to a manhole reinforcing plate immediately below the manhole Reference API-650, Paragraph 8.1.2 2. The manufacturer of an AST is required to certify to the purchaser that the tank has been constructed in accordance with API-650. How is this certification accomplished? a) The manufacturer shall provide the purchaser with a U-1 Data Report form b) The manufacturer shall provide the purchaser with letter c) The manufacturer shall provide the purchaser with an ASME acceptable Certificate of Compliance d) The manufacturer shall provide the purchaser with a notarized certificate of compliance Reference API-650, Paragraph 8.3

Answers to API-Standard 650 Section 8, Marking


Question Number 1 2 Answer C B

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 35

Appendix A Optional Design Basis for Small Tanks 1. What is the maximum shell thickness including corrosion allowance permitted for tanks that comply Appendix A of API-650? a) 7/8th inch b) 3/4th inch c) 5/8th inch d) 1/2 inch Reference API-650, Paragraph A.2.1 2. What is the maximum tensile strength, before the joint efficiency is applied, permitted in the design of small tanks in accordance with Appendix A of API-650? a) 21000 psi b) 21500 psi c) 21000 ksi d) 21500 ksi Reference API-650, Paragraph A.3.1 3. When computing the tension in each ring (course) of a small tank designed in accordance with Appendix A of API-650, where is this tension computed? a) The tension shall be computed 12 inches above the centerline of the course in question b) The tension shall be computed 12 inches above the centerline of the lower horizontal joint of the course in question c) The tension shall be computed 12 inches above the centerline of the tank in question d) The tension shall be computed 12 inches below the centerline of the upper horizontal joint of the course in question Reference API-650, Paragraph A.3.3 4. What joint efficiency factor shall be used in the design of small tanks designed in accordance with Appendix A of API-650 when spot radiographic examination is applied? a) 1.00 b) 0.90 c) 0.85 d) 0.70 Reference API-650, Paragraph A.3.4 5. What joint efficiency factor shall be used in the design of small tanks designed in accordance with Appendix A of API-650 when spot radiographic examination is omitted? a) 1.00 b) 0.90 c) 0.85 d) 0.70 Reference API-650, Paragraph A.3.4
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 36

Answers to API-Standard 650 Appendix A - Optional Design Basis for Small Tanks
Question Number 1 2 3 4 5 Answer D A B C D

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 37

Appendix B Recommendations for Design and Construction of Foundations for Aboveground Oil Storage Tanks 1. If the owner does not specify an alternative grade slope, the finished tank grade shall be crowned from its outer periphery to its center at a slope of _____. a) The slope shall be one inch in twelve feet b) The slope shall be one inch in ten feet c) The slope shall be one inch in eight feet d) The slope shall be one inch in six feet Reference API-650, Paragraph B.3.3 2. The owner decides that an earth foundation will be installed under a new tank installation. According to API-650 Appendix B, there are specific items that an earth foundation should accomplish. Of the following, which is not one of those items? a) Earth foundations should provide a stable plane for support of the tank b) Earth foundations should limit settlement to values used in the design of the connecting piping c) Earth foundations should not settle excessively at the perimeter due to the weight of the tank d) Earth foundations should reinforced with steel reinforcing bar to prevent sagging Reference API-650, Paragraph B.4.1.1 3. When does Appendix B of API-650 recommend the use of a concrete ringwall foundations? a) When there is some doubt whether the foundation will be able carry the shell load directly b) When there will be an area in the foundation open for passing cathodic protection equipment through c) When the tank is located in an area that is easily accessible for pouring the concrete d) When the tank erector decides a concrete foundation will be easier to install Reference API-650, Paragraph B.4.2.1 4. When a concrete ringwall is designed, what is the minimum thickness permitted? a) The ringwall shall not be less than 8 inches b) The ringwall shall not be less than 10 inches c) The ringwall shall not be less than 12 inches d) The ringwall shall not be less than 14 inches Reference API-650, Paragraph B.4.2.2 5. How far below the lowest adjacent finish grade must the bottom of the ringwall, if founded on soil, be located? a) The bottom of the ringwall shall be located 1 foot below grade b) The bottom of the ringwall shall be located 1.5 feet below grade c) The bottom of the ringwall shall be located 2.5 feet below grade d) The bottom of the ringwall shall be located 2 feet below grade Reference API-650, Paragraph B.4.2.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 38

Answers to API-Standard 650 Appendix B - Recommendations for Design of Foundations for Aboveground Oil Storage Tanks
Question Number 1 2 3 4 5 Answer B D A C D

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 39

Appendix C External Floating Roofs 1. Unless otherwise specified by the purchaser, all deck plates shall have a minimum nominal thickness of _____. a) 1/4 inch b) 1/8 inch c) 3/16 inch d) 3/32 inch Reference API-650, Paragraph C.3.3.2 2. What is the minimum slope required for the top decks of double-deck roofs and of pontoon sections? a) 3/16 inch in 12 inches b) 3/16 inch in 12 feet c) 3/16 inch in 10 inches d) 3/16 inch in 10 feet Reference API-650, Paragraph C.3.3.4 3. Pontoon type floating roofs shall have sufficient buoyancy to remain afloat on a liquid with a specific gravity of ____. a) 1.0 b) .87 c) .85 d) .70 Reference API-650, Paragraph C.3.4.1 4. What is the minimum size of roof drain required for a pan-type floating roof that is 110 feet in diameter. a) NPS 4 b) NPS 3 c) NPS 2 d) NPS 2.5 Reference API-650, Paragraph C.3.8 5. Floating roof support legs and attachments shall be designed to support the roof and a uniform live load of at least _____ per square foot. a) 100 pounds b) 75 pounds c) 50 pounds d) 25 pounds Reference API-650, Paragraph C.3.10.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 40

6. Manholes are required in floating roofs for access to the tank interior and for ventilation. What is the minimum nominal diameter of these manholes? a) 24 inches b) 20 inches c) 18 inches d) 15 inches Reference API-650, Paragraph C.3.11 7. If the sealing device between the outer periphery of the roof and the tank shell employs steel shoes, what material shall these shoes be made of and what is the minimum nominal thickness permitted? a) The shoes shall be made from galvanized sheet ASTM A 924 with a minimum thickness of 14 gauge b) The shoes shall be made from galvanized sheet ASTM A 924 with a minimum thickness of 16 gauge c) The shoes shall be made from galvanized sheet ASTM A 924 with a minimum thickness of 18 gauge d) The shoes shall be made from galvanized sheet ASTM A 924 with a minimum thickness of 20 gauge Reference API-650, Paragraph C.3.13 8. Drainpipe and hose systems of primary drains shall be tested with water at a pressure of ___. a) 0.5 psig b) 5.0 psig c) 50 psig d) 50 ksig Reference API-650, Paragraph C.4.5
Answers to API-Standard 650 Appendix C - External Floating Roofs

Question Number 1 2 3 4 5 6 7 8

Answer C A D B D A B C

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 41

Appendix G Structurally Supported Aluminum Dome Roofs 1. Aluminum dome roofs may be added to an existing tank. Who has the responsibility for providing reinforcement to enable the tank to support the roof? a) The fabricator if other than the erector b) The erector if other than the manufacturer c) The manufacturer d) The purchaser Reference API-650, Paragraph G.1.3.2 2. Aluminum dome roof shall be supported only from the rim of the tank. The design of the connection shall allow for thermal expansion. What is the minimum temperature range that must be used for the design? a) 110F b) 120F c) 125F d) 130F Reference API-650, Paragraph G.1.4.1 3. Aluminum panels shall be designed in accordance with ___ and Appendix G of API-650. a) AA ASM-35 b) AA ASM-135 c) AA ASM-53 d) AA ASM-315 Reference API-650, Paragraph G.3.2 4. The internal pressure of tanks with aluminum dome roofs shall not exceed the weight of the roof. In no case shall the maximum design pressure exceed ____ a) 9 psig b) 9 inches of mercury column c) 0.9 psig d) 9 inches of water column Reference API-650, Paragraph G.4.3 5. The maximum dome radius shall be ____ times the diameter of the tank. The minimum dome radius shall be ___ times the diameter of the tank unless other wise specified by the purchaser. a) 1.2 and 0.9 b) 1.2 and 0.5 c) 1.2 and 0.7 d) 1.2 and 0.8 Reference API-650, Paragraph G.6.2
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 42

Answers to API-Standard 650 Appendix G - Structurally Supported Aluminum Dome Roofs


Question Number 1 2 3 4 5 Answer D B A D C

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 43

Appendix H Internal Floating Roofs 1. Internal floating roofs may be designed and built to float and rest in a reasonably flat position. A rim or skirt shall be provided around the roof periphery and all columns, ladders, and other roof openings. How far must this rim extend above the liquid? a) 3 inches b) 6 inches c) 9 inches d) 12 inches Reference API-650, Paragraph H.4.2.1 and 4.2.3 2. Internal floating roofs shall be designed to safely support at least _____. a) 500 pounds over 1 square foot b) 500 pounds over 1 square inch c) 500 pounds over 1 square yard d) 500 pounds over 1 square meter Reference API-650, Paragraph H.4.2.5 3. What is the minimum required thickness, excluding corrosion allowance, for a steel internal floating roof in contact with vapor? a) The minimum thickness shall be 0.094 inches b) The minimum thickness shall be 9 gauge c) The minimum thickness shall be 0.07 inches d) The minimum thickness shall be 7 gauge Reference API-650, Paragraph H.4.4 4. A peripheral seal shall be designed to accommodate ____ of local deviation between the floating roof and the shell. a) 2 inches b) 3 inches c) 4 inches d) 5 inches Reference API-650, Paragraph H.4.5.1 5. Which of the following is not permitted as a design for internal floating roofs in contact with the liquid? a) Double deck b) Pontoon c) Metallic Pan d) Metallic on floats Reference API-650, Paragraph H.5.1.1

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 44

6. Metallic internal roofs on floats shall be designed to be buoyant enough to support how much weight? a) Twice its dead weight b) Twice the weight of two men c) 500 pounds per square foot d) Three times its dead weight Reference API-650, Paragraph H.5.2.2 7. The maximum spacing between circulation vents shall be _____. a) 24 feet b) 32 feet c) 28 feet d) 30 feet Reference API-650, Paragraph H.6.2.2.1 8. What is the minimum number of circulation vents that must be located on the shell or fixed roof above the seal of the floating roof when the tank is full? a) 8 b) 4 c) 6 d) 2 Reference API-650, Paragraph H.6.2.2.1

9. How many and what size manholes must be provided in a fixed roof for access to the tank interior? a) At least two with a nominal diameter of 24 inches each b) At least three with a nominal diameter of 24 inches each c) At least one with a nominal diameter of 24 inches d) At least four with a nominal diameter of 24 inches each Reference API-650, Paragraph H.6.5.1 10. When specified by the purchaser, inspection hatches shall be located on the fixed roof to permit visual inspection of the seal region. What is the maximum spacing between these hatches? a) 32 feet b) 50 feet c) 75 feet d) 100 feet Reference API-650, Paragraph H.6.5.3

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 45

Answers to API-Standard 650 Appendix H - Internal Floating Roofs


Question Number 1 2 3 4 5 6 7 8 9 10 Answer B A D C D A B B C C

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 46

Remaining Appendixes Appendix D Technical Inquiries This appendix provides guidance for requesting interpretations of API Standard 650. The inquiry format is specific must be followed. Basically inquiries shall be formulated in such a way that they can be answered yes or no. Appendix E Seismic Design of Storage Tanks According the Body of Knowledge, question pertaining to this Appendix will be excluded on the API-653 examination. Appendix F Design of Tanks for Small Internal Pressures According the Body of Knowledge, question pertaining to this Appendix will be excluded on the API-653 examination. Appendix I Under-tank Leak Detection and Sub-grade Protection This appendix provides basic recommendations, which may be specified by the purchaser, for design and construction of tank and foundation systems that provide leak detection and sub-grade protection in the event of tank bottom leakage, and provides for tanks supported by grillage. Typically, this appendix would only be used as a guide. The body of knowledge states that questions pertaining to tanks supported by grillage will be excluded on the examination. Appendix J Shop Assembled Storage Tanks This appendix presents requirements covering the complete assembly of tanks that do not exceed 20 feet in diameter. Appendix K Application of the Variable-Design- Point Method According the Body of Knowledge, question pertaining to this Appendix will be excluded on the API-653 examination. Appendix L API Standard 650 Storage Tank Data Sheets This appendix provides data sheets to be used by the purchaser in ordering a storage tank and by the manufacturer upon completion of construction of the tank. Appendix M Requirements for Tanks Operating at Elevated Temperatures This appendix provides additional requirements for tanks with maximum operating temperatures from 200F to 500F.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 47

Appendix N Use of New Materials That Are Not Identified This appendix provides requirements for the use of new or unused plate and pipe materials that are not completely identified by this standard as complying with any listed specification. Appendix O Recommendations for Under-Bottom Connections This appendix contains recommendations for the design and construction of under-bottom connections for storage tanks Appendix P Allowable External Loads on Tank Shell Openings This appendix presents minimum recommendations for design of shell openings that conform to Table 3 8 that are subject to external piping loads. The purchaser or manufacturer may agree upon an alternative or supplemental design. According to the body of knowledge, questions pertaining to this appendix will not be asked on the examination. Appendix S Austenitic Stainless Steel Tanks According the Body of Knowledge, question pertaining to this Appendix will be excluded on the API-653 examination.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 650

Issue Date 06/98

Revision Date 02/00

Page 48

NOTES

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 1

Section 4 - Corrosion of Above Ground Steel Storage Tanks 1. According to API Recommended Practice - 651, there are four components in each corrosion cell. Theses components are an anode and all but which of the following? a) DC current supplied by batteries b) A cathode c) A metallic path connecting the anode and cathode d) An electrolyte Reference: API-651 Paragraph 4.1.1 2. The base metal goes into solution (corrodes) by releasing electrons and forming positive metal ions. This statement describes what takes place at what component of a corrosion cell? a) b) c) d) The cathode The electrolyte The metallic connection between the cathode and the anode The anode

Reference: API-651 Paragraph 4.1.1(a) 3. Which of the following is the most correct statement regarding the cathode? a) Moderate corrosion takes place at the cathode b) No corrosion takes place at the cathode c) All corrosion takes place at the cathode d) A chemical reaction takes place using electrons released at the electrolyte Reference: API-651 Paragraph 4.1.1(b) 4. The electrolyte contains ions and conducts positive current from the anode to the cathode. The most common electrolyte for external tank bottom surfaces is _______, while the most common for internal surfaces is _________. a) Water, sludge and moist soil b) Moist soil, water and sludge c) Acidic soil, water and sludge d) Moist soil, product and sludge Reference: API-651 Paragraph 4.1.1(d) 5. The two most common types of corrosion to tank bottoms are ______ and ______. a) Stress corrosion and galvanic b) Erosion and erosion/corrosion c) General and pitting d) Stray current and bimetallic Reference: API-651 Paragraph 4.1.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 2

6. Which type of corrosion results in relatively uniform metal loss? a) Erosion and erosion/corrosion b) Stray current c) General d) Pitting Reference: API-651 Paragraph 4.1.2 7. Which type of corrosion may only affect relatively small areas, while substantial areas of the surface are unaffected by corrosion? a) Galvanic b) General c) Brittle d) Pitting Reference: API-651 Paragraph 4.1.2 8. Composition of the metal is a factor in determining which areas become anodes and which become cathodes. What else can cause corrosion? a) Differences between weld metal, heat affected zone, and parent metal b) Differences in thickness between adjacent plates c) Improper fit-up of the welded joint d) Slag inclusion in the weld metal Reference: API-651 Paragraph 4.1.3 9. Which of the following is a correct statement regarding oxygen concentration of the electrolyte. a) Oxygen concentration in the electrolyte has no impact on the corrosion cell b) Areas of lower oxygen concentrations become anodic and areas of higher concentrations become cathodic. c) Areas of lower oxygen concentrations become cathodic and areas of higher concentrations become anodic d) Areas of lower oxygen concentrations become acidic and areas of higher concentrations become alkaline Reference: API-651 Paragraph 4.1.4 10. Soil characteristics substantially affect what? a) What type of product may be stored in the tank b) What the maximum fill height of the tank is c) The type and rate of corrosion on a structure in contact with soil d) Perk rate for dissipation of small leaks from the tank bottom Reference: API-651 Paragraph 4.1.5

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 3

11. What is another term used for "stray currents"? a) Short circuits b) Positive currents c) Impressed currents d) Interference currents Reference: API-651 Paragraph 4.2.1 12. The most common and potentially the most damaging stray currents are: a) Direct currents b) Alternating currents c) Intermittent currents d) Close proximity alternating currents Reference: API-651 Paragraph 4.2.1 13. Which of the following is not likely to be a source of stray currents? a) Static electricity b) Welding machines c) Impressed current cathodic protection systems d) Railroads Reference: API-651 Paragraph 4.2.1 14. Two metals with different compositions connected in an electrolyte is a general description of: a) A battery b) A current suppressor c) A short circuit d) Galvanic corrosion Reference: API-651 Paragraph 4.2.2 15. All but one of the following is listed as major factors which influence the severity of internal corrosion. Which is not a factor? a) The pH level of the fluid in contact with the steel bottom b) The amount of nitrogen in the fluid in contact with the steel bottom c) Suspended solids in the fluid in contact with the steel bottom d) Conductivity of the fluid in contact with the steel bottom Reference: API-651 Paragraph 4.2.3 16. Three major types of internal corrosion to be considered are general corrosion, pitting corrosion, and to a lesser extent in tanks, environmental cracking. a) True b) False Reference: API-651 Paragraph 4.2.3
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 4

Answers to API-651 Section 4, corrosion of Aboveground Steel Storage Tanks


Question Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Answer A D B B C C D A B C D A A D B A

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 5

Section 5 - Determination of Need for Cathodic Protection 1. API Recommended Practice 651 states that the need for cathodic protection must be determined for all storage facilities. Decisions governing the need for cathodic protection should be based on all but which of the following? a) Data from corrosion surveys and operating records b) National Board and ASME recommendations c) Prior test results with similar systems in similar environments d) National, state, and local code requirements and the recommendations in API-651 Reference: API RP 651, Paragraph 5.1 2. When should corrosion control by cathodic protection for new ASTs be provided? a) After final welding and before hydrostatic testing b) After all stress relief has been carried out c) In the initial design d) After the tank is in service for 6 months Reference: API RP 651, Paragraph 5.1.1 3. Generally tanks in petroleum service use ______ on the internal surfaces to control internal corrosion. a) AC Current instead of DC current cathodic protection systems b) Coatings c) Cathodic protection in conjunction with coatings d) Since pure hydrocarbon fluids are usually not corrosive experience shows that internal corrosion will never occur therefore, corrosion control is not necessary Reference: API RP 651, Paragraph 5.1.3 4. Cathodic protection is an effective means of corrosion control only if it is possible to pass electrical current between what two components? a) Anode and cathode b) Tank shell and roof support system c) Roof to bottom through roof support structures d) Tank shell and tank bottom Reference: API RP 651, Paragraph 5.1.4 5. A full evaluation of tank history should be performed prior to _______. a) Filling the tank for the 25th time b) Painting the exterior surface of the tank c) Temporarily removing the tank from service d) Determining the need for cathodic protection Reference: API RP 651, Paragraph 5.2.1

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 6

6. Such items as site plan, soil properties, previous repairs, existing cathodic protection of nearby structures, maintenance history, and expected life should be investigated and determined when conducting the ____________. a) Evaluation of the location of a refinery b) Probability study of tank settlement c) Evaluation of tank design/construction history d) Evaluation of tank repairs and alterations Reference: API RP 651, Paragraph 5.2.1.1 7. Of the following items which is not an item that should be investigated and determined in the evaluation of types of service? a) Type of product stored b) Product temperature c) Ambient temperature d) Presence and depth of water bottoms Reference: API RP 651, Paragraph 5.2.1.2 8. Such items as tank inspections per API Standard 653, corrosion rate records, stray current problems, design and performance of previous protection systems, and structure-to-soil potential surveys should be investigated and determined when conducting the ______. a) Evaluation of tank repair/alteration/construction history b) Evaluation of tank design/construction history c) Evaluation of types of service d) Evaluation of inspection/corrosion history Reference: API RP 651, Paragraph 5.2.1.3 9. The cushion material under the tank has a significant effect on external corrosion of the tank bottom. The material can also influence: a) The effectiveness and applicability of external cathodic protection b) The effectiveness and applicability of internal cathodic protection c) The decision to use or not use a rectifier or DC generator set to supply current d) The type of product that may be stored in the tank Reference: API RP 651, Paragraph 5.3.1.1 10. What is an advantage of using fine particles for the cushion material? a) The fine particles should be uniform which makes it easier to transport b) Fine particles provide a more dense cushion to help reduce the influx and outflow of oxygen c) Fine particles will not permit the passage of product should a leak occur in the tank bottom d) Fine particles will hold moisture longer permitting it to stabilize and prevent acid from forming in the electrolyte Reference: API RP 651, Paragraph 5.3.1.1
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 7

11. What is the main disadvantage in using large size particles in the soil cushion material? a) The large particles may puncture the tank bottom b) The large particles may trap moisture and allow general corrosion to form c) If large particles are used, differential aeration corrosion may result where the particles contact the tank bottom d) The large particles are more difficult to transport Reference: API RP 651, Paragraph 5.3.1.1 12. A soil resistivity of about 1250 OHM-CM would indicate the soil is probably ____. a) Mildly corrosive b) Very corrosive c) Corrosive d) Moderately corrosive Reference: API RP 651, Paragraph 5.3.1.2 13. The results of soil resistivity surveys can be used to determine ________. a) When it is time to replace the cushion material under the tank bottom b) The need for cathodic protection c) The amount of compression of the cushion material under the tank d) The best place to install a corrosion test bed Reference: API RP 651, Paragraph 5.3.1.2 14. A properly designed concrete tank cushion constructed on stable, properly prepared subsoil may be effective in all but which of the following? a) Cracks in the tank bottom weld seams b) Intrusion of groundwater c) Soil-side corrosion d) The need for cathodic protection Reference: API RP 651, Paragraph 5.3.2.1 15. Cracks through the concrete cushion may permit water and contaminants to permeate to the steel tank bottom and provide a path for proper electrical current flow. a) True b) False Reference: API RP 651, Paragraph 5.3.2.1 16. Corrosion of the steel tank bottom installed on a concrete cushion may result from moisture accumulation caused by all but which of the following? a) Condensation b) Blowing snow or rain c) Humidity in the air surrounding the tank d) Flooding Reference: API RP 651, Paragraph 5.3.2.2
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 8

17. Why would it be more important to provide proper support under cushions of new asphalt than for concrete? a) Asphalt is inherently alkaline and therefore does not have the potential of preventing corrosion b) Asphalt is not inherently alkaline and therefore does not have the potential of preventing corrosion c) Asphalt may degrade and become a corrosive substance d) Asphalt may crack allowing moisture to reach the tank bottom where it will react violently with the asphalt and the steel tank bottom Reference: API RP 651, Paragraph 5.3.3.1 18. How can the condition of the external surface of tank bottom and the asphalt cushion be determined? a) Raise the entire tank and inspect the tank bottom and the asphalt b) Take a core sample from the asphalt for testing. This test will reveal the amount of steel that has gone into solution and been trapped in the asphalt c) Conduct a soil resistivity survey around the periphery of the tank containment d) By cutting coupons from the tank bottom Reference: API RP 651, Paragraph 5.3.3.2 19. A soil analysis reveals the pH of a native soil cushion to be 6.25. This soil is considered to be: a) Moderately corrosive b) Mildly corrosive c) Corrosive d) Very corrosive Reference: API RP 651, Paragraph 5.3.4.1 and Table 2 20. A soil analysis reveals the sulfates level of a native soil cushion to be 5525ppm. This soil is considered to be a) Moderately corrosive b) Mildly corrosive c) Corrosive d) Very corrosive Reference: API RP 651, Paragraph 5.3.4.1 and Table 2 21. What is the most common material used as a cushion beneath storage tank bottoms? a) Clean concrete b) Clean sand c) Clean Asphalt d) Clean modified aggregate Reference: API RP 651, Paragraph 5.3.5

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 9

22. The use of oiled sand beneath tank bottoms does not eliminate the need for cathodic protection and in fact may cause cathodic protection to be less effective because: a) The oiled sand has higher resistivity b) The sand is unable to conduct electrical current c) The oil acts as an insulator and blocks all current flow d) The oil creates a vapor bearer entrapping water and contaminants next to the tank bottom Reference: API RP 651, Paragraph 5.3.5 23. There are several ways the tank cushion can become contaminated. Three of the following are methods of cushion contamination, which one is not? a) In coastal areas salt spay may be washed down the side of the tank b) Fertilizer from spraying operations in rural areas c) Airborne chemicals from industrial operations d) Residual build-up of electrons in the sand cushion Reference: API RP 651, Paragraph 5.3.6.1 24. Leakage of product from the tank bottom can cause accelerated corrosion by creating ____. a) Stray current corrosion b) Corrosion cells where none existed before c) More positively charged electrons d) A film that would block electrical current flow Reference: API RP 651, Paragraph 5.3.6.2 25. When a layer of crushed-limestone or clam-shell is used for the tank cushion, why is it important to ensure the particles are fine and uniform? a) Large particles could puncture the tank bottom b) Differential aeration corrosion cells will cause pitting at contact areas between the large particles and the metal c) Large particles may allow the formation of dissolved gas pockets which could become a hazard if hot tap work is performed on the tank bottom d) Large particle will eventually fracture and create voids in the tank cushion Reference: API RP 651, Paragraph 5.3.7 26. What is an advantage of using crushed-limestone or clam-shell under tank bottoms? a) This material is plentiful and relatively inexpensive b) Contamination is easier to detect because of discoloration c) Water from rain or groundwater makes the environment under the tank alkaline, which may reduce corrosion d) The use of this material eliminates the need for cathodic protection Reference: API RP 651, Paragraph 5.3.7

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 10

27. Heated tanks or tanks storing hot product can cause: a) Increased water intrusion due to causing snow to melt and run down the tank sides b) Excessive drying out of concrete foundations resulting in premature deterioration and failure c) Accelerated corrosion on the internal surface especially in tanks with water bottoms d) Accelerated corrosion on the external surface due to elevated temperature is the area is wet Reference: API RP 651, Paragraph 5.4.1 28. There are a variety of methods for secondary containment, which of the following is not an accepted method of secondary containment. a) Dual bottom tank design b) Sand bags c) Use of impervious clay pad in tank dike d) Impervious nonmetallic membrane Reference: API RP 651, Paragraph 5.4.3.1 29. During the installation of a new steel bottom over an existing steel bottom, which has been repaired, if water or other electrolyte intrudes into the annulus, what can happen? a) A galvanic cell may form which will cause the new steel tank bottom to corrode at an accelerated rate b) An electrochemical reaction may take place creating hazardous gasses c) A galvanic cell may form which will cause the old tank bottom to corrode at an accelerated rate d) A galvanic cell may form which will turn the old tank bottom into an anode Reference: API RP 651, Paragraph 5.4.3.2 30. With the installation of _____ in a diked area prior to new tank construction, most cathodic protection systems are rendered ineffective. a) A secondary containment system utilizing a perforated impervious membrane b) A secondary containment system utilizing an impervious membrane c) A secondary containment system utilizing a metallic impregnated screen membrane d) A secondary containment system utilizing a non-impervious membrane Reference: API RP 651, Paragraph 5.4.3.3

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 11

Answers to API-651 Section 5, Determination of Need for Cathodic Protection


Question Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Answer B C B A D C C D A B C D B A B C B D C D B A D B B C D B A B

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 12

Section 6- Methods of Cathodic Protection for Corrosion Control 1. What is the basic principle that makes cathodic protection effective. a) Cathodic protection is a technique for preventing corrosion by making the entire surface of the metal to be protected act as the rectifier b) Cathodic protection is a technique for preventing corrosion by making the entire surface of the metal to be protected act as the corrosion cell c) Cathodic protection is a technique for preventing corrosion by making the entire surface of the metal to be protected act as the cathode d) Cathodic protection is a technique for preventing corrosion by making the entire surface of the metal to be protected act as the anode Reference: API-651, Paragraph 6.1 2. What are the two systems of cathodic protection? a) Galvanic and repressed current b) Galvanic and impressed current c) Galvanic and reversed current d) Galvanic and induced current Reference: API-651, Paragraph 6.1 3. Galvanic cathodic protection systems use a metal, that is more active than the structure to be protected, to supply the current required to stop corrosion. What is another term(s) used to describe this material? a) Anode, commonly referred to as a galvanic or sacrificial anode b) Cathode, commonly referred to as a galvanic or sacrificial cathode c) Ribbon cathode, commonly referred to as a sacrificial ribbon cathode d) Impressed current anode, commonly referred to as the impressed anode Reference: API-651, Paragraph 6.2.1 4. Where on the galvanic series is clean and shiny mild steel? a) Clean and shiny mild steel has a value of 1.1 volts b) Clean and shiny mild steel has a value of 1.0 volts c) Clean and shiny mild steel has a value of 0.8 volts d) Clean and shiny mild steel has a value of 0.5 to -0.8 volts Reference: API-651, Paragraph 6.2.1 and Table 3 5. The most common metals used as galvanic anodes in soil are: a) Lead and copper b) Aluminum alloy (5% zinc) and Mild steel (clean and shiny) c) Magnesium and zinc d) Mild steel in concrete and cast iron Reference: API-651, Paragraph 6.2.1

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 13

6. Of the following, which is not an advantage of galvanic cathodic protection systems? a) No external power is needed b) Capital investment is low for small-diameter tanks c) Method is limited to use in low-resistivity soils d) Interference problems (stray currents) are rare Reference: API-651, Paragraph 6.2.2 7. Impressed current cathodic protection systems use: a) Alternating current b) Direct current usually provided by a rectifier c) Direct current usually provided by a dry cell battery d) Either direct current or alternating current depending upon which is available Reference: API-651, Paragraph 6.3.1 8. Of the following, which is not a disadvantage of impressed current cathodic protection systems? a) High current output b) High maintenance costs c) High operating costs d) High capital cost for small installations Reference: API-651, Paragraph 6.3.3 9. A cathodic protection rectifier has two major components; what are they? a) A step-down transformer to reduce the AC supply voltage and rectifying elements to convert DC to AC output b) A step-down transformer to reduce the AC supply voltage and rectifying elements to convert AC to DC output c) A step-down transformer to reduce the DC supply voltage and rectifying elements to convert DC to AC output d) A step-down transformer to reduce the AC supply voltage and rectifying elements to regulate the AC output Reference: API-651, Paragraph 6.3.3 10. Impressed current anodes used in soil are not made of: a) Graphite b) High silicon cast iron c) Zinc d) Mixed metal oxides on titanium Reference: API-651, Paragraph 6.3.5 11. Impressed current anodes may be installed underneath the tank. a) True b) False Reference: API-651, Paragraph 6.3.5
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 14

Answers to API-651 Section 6, Methods of Cathodic Protection for Corrosion Control


Question Number 1 2 3 4 5 6 7 8 9 10 11 Answer C B A D C C B A B C A

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 15

Section 7 Design of Cathodic Protection Systems 1. It has been decided to install an impervious membrane under a new storage tank being installed in a diked area. Cathodic protection of the tank bottom is required. Where must the anodes be placed? a) Anodes shall be placed outside the diked area b) Directly under the membrane beneath the tank c) As close as possible to the rectifier d) Between the membrane and the tank bottom Reference: API 651, Paragraph 7.2.3.1 2. Inspection experience has disclosed the need for cathodic protection for an existing tank in a diked area. There is a membrane installed under the tank. What would be an option for installing anodes under this tank? a) Jack the tank up on the side opposite the fill and discharge lines and slide the ribbon anodes under b) Bore under the tank at a very shallow angle and install the anodes c) Bore under the membrane at a very shallow angle and install the anodes d) Install deep ground bed anodes in coke breeze backfill outside the diked area Reference: API 651, Paragraph 7.2.3.2 3. If an existing tank bottom is protected by cathodic protection and/or if cathodic protection is planned for the new bottom (by deep or shallow groundbeds), what should be done with the old bottom? a) The old tank bottom should be electrically connected to the cathodic protection system to now act as an anode b) The old tank bottom should be painted with a corrosion resistant coating and left in place c) The old tank bottom should be completely removed d) Nothing needs to be done with the old tank bottom Reference: API 651, Paragraph 7.2.4.3 4. It has been decided to install a new tank bottom in a tank with cathodic protection. What would be the result of leaving the old bottom in place and not properly prepared? a) The old bottom forms a shield that collects the cathodic current flowing through the ground and prevents cathodic protection of the new tank bottom b) The old bottom forms a shield that collects the anodic current flowing through the ground and prevents cathodic protection of the new tank bottom c) The old bottom forms a shield that collects the galvanic current flowing through the ground and prevents cathodic protection of the new tank bottom d) The old bottom forms a shield that collects the stray current flowing through the ground and prevents cathodic protection of the new tank bottom Reference: API 651, Paragraph 7.2.4.3

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 16

5. Industry experience has shown that if a conductive electrolyte exists between an old and a new tank bottom: a) The current flow and metal loss will be from the old bottom b) The current flow and metal loss will be from the new bottom c) The current flow will be from the old bottom and metal loss will be from the new bottom d) The current flow will be from the new bottom and metal loss will be from the old bottom Reference: API 651, Paragraph 7.2.4.3 6. There are several advantages to installing a secondary containment. Of the following, which would not be considered an advantage? a) Provides a means of detecting and containing leaks and preventing ground contamination b) Prevents the natural current flow between the old bottom and the new bottom c) Permits the addition of cathodic protection at a later date d) May reduce the entry of groundwater into the space between the bottoms Reference: API 651, Paragraph 7.2.5.1.1 7. There are several disadvantages to installing a secondary containment. Of the following, which would not be considered a disadvantage a) The membrane may act as a basin to contain water or any other electrolyte that might wet the sand between the bottoms b) The membrane could entrap hydrocarbon products, which would require extra care for hot work c) Makes the future addition of cathodic protection virtually impossible d) Acts as a barrier to groundwater Reference: API 651, Paragraph 7.2.5.1.2 8. When an external cathodic protection system is being designed, there are several items to be considered. Of the following four items, which one would not be a consideration? a) Selection and design of the cathodic protection system for optimum economy of installation, maintenance, and operation b) Specification of materials and installation practices that meet applicable codes, such as National Electrical Manufacturers Association standards, NACE recommended practices, and federal, state, and local regulations c) Provisions for monitoring the cathodic protection system d) Specification of materials and installation practices that meet applicable codes, such as American Society of Mechanical Engineers standards, NACE recommended practices, and federal, state, and local regulations Reference: API 651, Paragraph 7.3.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 17

9. Information that is useful for design of an external cathodic protection system can be divided into three categories: a) Specifications, site conditions, and jurisdictional requirements b) Specifications and practices, site conditions, and U.S. Geological survey reports c) Specifications and practices, site conditions, and field survey, corrosion test data, and operating experience d) Specifications and practices, tank shell conditions, and field surveys Reference: API 651, Paragraph 7.3.3 10. What are the two types of cathodic protection systems most commonly used? a) Galvanic cathode system and impressed voltage system b) Galvanic anode system and impressed current system c) Galvanic anode system and interference current system d) Galvanic anode system and interference voltage system Reference: API 651, Paragraph 7.3.5.1 and 7.3.5.2 11. Galvanic cathodic protection systems are more economical on: a) Small-diameter tanks b) Large-diameter tanks c) Bare, poorly coated structures d) Multiple large tanks in a diked area Reference: API 651, Paragraph 7.3.5.1.1 12. The three most common galvanic anode materials used for soil installations are: a) High potential magnesium alloys, zinc, and pure aluminum b) High potential magnesium alloys, Standard magnesium, and Copper c) High potential magnesium alloys, standard magnesium, and zinc d) High potential magnesium alloys, standard magnesium, and stainless steel Reference: API 651, Paragraph 7.3.5.1.2 13. What are the advantages of using a special backfill with anodes for installation in soil environments? a) Reduces the possibility of contaminating the environment and promotes anode efficiency b) Promotes anode efficiency, lengthens the life of the anode, dissipates stray currents c) Promotes anode efficiency, lengthens anode life, and keeps anode environment moist d) Promotes anode efficiency, keeps anode environment moist, and prevents total deterioration of the anode Reference: API 651, Paragraph 7.3.5.1.3

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 18

14. The number of anodes required to provide cathodic protection depends upon what two factors? a) The distance from the galvanic anode to the tank bottom and soil discharge rate b) Total current requirements and the expected individual anode discharge rate in the soil c) Total stray currents expected and the total current requirements d) Total current requirements and the expected individual cathode discharge rate in the soil Reference: API 651, Paragraph 7.3.5.1.4 15. In placing the anodes, how is better current distribution and more uniform polarization obtained? a) By distributing anodes uniformly around the tank or under the membrane for new construction b) By distributing anodes uniformly around the diked area or under the tank for new construction c) By distributing the cathodes uniformly around the tank or under the tank for new construction d) By distributing the anodes uniformly around the tank or under the tank for new construction Reference: API 651, Paragraph 7.3.5.1.4 16. How are impressed current anodes installed? a) These anodes are installed either fully coated or in special backfill material b) These anodes are installed either bare or in special backfill material c) These anodes are installed either directly on the tank bottom or in special backfill material d) These anodes are installed either bare or in special liquid filled cylinders Reference: API 651, Paragraph 7.3.5.2.1.1 17. Impressed current anodes are connected with an insulated conductor: a) Singly to the positive terminal of a DC source b) In groups to the positive terminal of a DC source c) Either singly or in groups to the negative terminal of an DC source d) Either singly or in groups to the positive terminal of an DC source Reference: API 651, Paragraph 7.3.5.2.1.1 18. Of the following, which is not the preferred material for impressed current anodes used in soil installations? a) Graphite b) Zinc c) High silicon cast iron d) Mixed metal oxide Reference: API 651, Paragraph 7.3.5.2.1.2
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 19

19. Of the following, which is not the best material for impressed current anodes used in water installations a) Titanium b) Tantalum c) Copper d) Platinized niobium Reference: API 651, Paragraph 7.3.5.2.1.2 20. In an impressed current cathodic protection system, proper groundbed design should do which of the following? a) Avoid physical interference with existing facilities, provide uniform current distribution, and avoid stray current interference with off-site structures b) Provide for direct connection with existing facilities, provide uniform current distribution, and avoid stray current interference with off-site structures c) Avoid physical interference with existing facilities, provide random current distribution, and avoid stray current interference with off-site structures d) Avoid physical interference with existing facilities, provide uniform current distribution, and intercept stray current interference with off-site structures Reference: API 651, Paragraph 7.3.5.2.1.3 21. In an impressed current system why would additional anodes be considered in the distributed anode design? a) To provide uniform current distribution and provide back-up anodes for replacement b) To provide uniform current distribution and provide allowance in case of isolated cathode connection failure or partial cathode depletion c) To provide uniform current distribution and provide allowance in case of isolated anode connection failure or partial anode depletion d) To provide random current distribution and provide allowance in case of isolated anode connection failure or partial anode depletion Reference: API 651, Paragraph 7.3.5.2.1.4 22. The current required for cathodic protection should be calculated using the results of current requirement tests. In lieu of this test, what is the generally accepted protective current density? a) Between 0.5 and +0.5 milliamps per square foot at ambient conditions b) Between 0.01 and 0.1 milliamps per square foot at ambient conditions c) Between 0.1 and 0.2 milliamps per square foot at ambient conditions d) Between 1 and 2 milliamps per square foot at ambient conditions Reference: API 651, Paragraph 7.3.5.2.2.1

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 20

23. The current requirement test can only be performed on existing tanks using a temporary groundbed and an appropriate source of direct current. Depending on the current required, the power source can vary by how much? a) From a 24 volt storage battery to a 300-amp welding unit b) From a 12 volt storage battery to a 300-amp welding unit c) From a 6 volt storage battery to a 300-amp welding unit d) From a 1.2 volt solar panel to a 300-amp welding unit Reference: API 651, Paragraph 7.3.5.2.2.1 24. During the current requirement test, how is maximum contact of the tank bottom with the cushion material ensured? a) The tank is filled to an adequate liquid level to ensure maximum bottom contact b) The tank is pressurized with an inert gas to ensure maximum bottom contact c) The tank is completely filled and subjected to a hydrostatic pressure d) The tank is emptied and concrete weights are installed and the tank filled to half design liquid level Reference: API 651, Paragraph 7.3.5.2.2.2 25. The voltage necessary to drive the required amount of current depends largely on what two factors? a) The type of power source available and the resistivity of the soil b) The number and location of anodes and the resistivity of the soil c) The number and location of cathodes and the resistivity of the soil d) The number and location of the anodes and the resistivity of the special backfill Reference: API 651, Paragraph 7.3.5.2.2.3 26. In an impressed current system, rectifiers with a moderated excess capacity should be selected to allow for adjustments during the life of the cathodic protection system and to prevent damage due to overloads. What is the typical excess capacity of such rectifiers? a) 40% to 50% b) 30% to 50% c) 20% to 50% d) 10% to 50% Reference: API 651, Paragraph 7.3.5.2.3 27. Electrical grounding of electrical equipment is an essential element in personnel safety. a) True b) False Reference: API 651, Paragraph 7.3.6.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 21

28. Condition and type of coating (if any), minimum and maximum water level in tank, compatibility of stored liquid with anodes and cables, and internal inspection interval of tank which affects design life are all factors that: a) Influence the design of an external cathodic protection system b) Influence the design of a depressed current cathodic protection system c) Influence the design of an internal cathodic protection system d) Influence the design of the rectifier used in a cathodic protection system Reference: API 651, Paragraph 7.4.1

Answers to API-651 Section 7, Design of Cathodic Protection Systems


Question Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Answer D B C A B C D D C B A C C B D B D B C A C D B A B D A C

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 22

Section 8 Criteria for Cathodic Protection 1. API-651 provides criteria for determining the adequacy of cathodic protection of aboveground storage tanks. What document is referenced for a more detailed description? a) ASME Section V, Nondestructive Examination b) API-Standard 650, Welded Steel Tanks for Oil Storage c) API-Standard 653, Tank Inspection, Repair, Alteration, and Reconstruction d) NACE RP-01-69 Reference: API-651, Paragraph 8.2.1 2. In determining if adequate cathodic protection is being achieved, which of the following would be correct? a) A negative (cathodic) potential of at least 850 mV with cathodic current applied b) A positive (cathodic) potential of at least 850 mV with cathodic current applied c) A negative (cathodic) potential of at least 85.0 mV with cathodic current applied d) A positive (cathodic) potential of at least 85.0 mV with cathodic current applied Reference: API-651, Paragraph 8.2.2.1 3. How must the required negative potential be measured? a) This potential shall be measured with respect to a saturated copper/copper sulfate reference electrode (CSE) contacting the metal tank bottom b) This potential shall be measured with respect to a saturated copper/copper sulfate reference electrode (CSE) contacting the electrolyte c) This potential shall be measured with respect to a saturated copper/copper sulfate reference electrode (CSE) contacting the metal casing of the rectifier d) This potential shall be measured with respect to a saturated copper/copper sulfate reference electrode (CSE) contacting the positive terminal of the power source Reference: API-651, Paragraph 8.2.2.1 4. In determining if adequate cathodic protection is being achieved, which of the following would be correct? a) Negative polarized potential of at least 8.50 mV relative to a CSE b) Negative polarized potential of at least 85.0 mV relative to a CSE c) Negative polarized potential of at least 850 mV relative to a CSE d) Negative polarized potential of at least .850 mV relative to a CSE Reference: API-651, Paragraph 8.2.2.2 5. Name a common method of measuring polarized potential. a) Measuring the distance between the tank bottom and the anode b) Measuring the AC current relative to the DC current c) Using the instant on method d) Using the instant off method Reference: API-651, Paragraph 8.2.2.2
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 23

6. In determining if adequate cathodic protection is being achieved, which of the following would be correct? a) A minimum of 1000 mV of cathodic polarization measured between the tank bottom metallic surface and a standard reference electrode contacting the electrolyte b) A minimum of 850 mV of cathodic polarization measured between the tank bottom metallic surface and a standard reference electrode contacting the electrolyte c) A minimum of 100 mV of cathodic polarization measured between the tank bottom metallic surface and a standard reference electrode contacting the electrolyte d) A minimum of -0.85 mV of cathodic polarization measured between the tank bottom metallic surface and a standard reference electrode contacting the electrolyte Reference: API-651, Paragraph 8.2.2.3 7. The standard method of determining the effectiveness of cathodic protection on a tank bottom is the __________ measurement a) Resistivity b) DC current c) Tank-to-soil d) Interference current Reference: API-651, Paragraph 8.3.1 8. How is the tank-to-soil potential measurement performed? a) This measurement is performed using a low-impedance voltmeter and a stable, reproducible reference electrode contacting the electrolyte b) This measurement is performed using a high-impedance voltmeter and a stable, regenerative reference electrode contacting the electrolyte c) This measurement is performed using a high-impedance voltmeter and a stable, reproducible reference electrode contacting the electrolyte d) This measurement is performed using a high-impedance voltmeter and an unstable, non-reproducible reference electrode contacting the electrolyte Reference: API-651, Paragraph 8.3.1 9. Tank-to-soil potential measurements are typically taken with current applied; however, corrections for ______ in the soil must be made. a) IW drop(s) b) IR drop(s) c) ER drop(s) d) IE drop(s) Reference: API-651, Paragraph 8.3.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 24

10. Correction for IR drop in the soil is often necessary for measurements made at the tank perimeter even if the reference electrode is placed immediately adjacent to the tank. This is especially true if ______ is/are close to the tank. a) Distributed anodes b) The cathodic protection power supply rectifier c) The sacrificial anode d) The DC power supply (battery) Reference: API-651, Paragraph 8.3.2 11. Monitoring the actual structure-to-soil potential under the tank should be considered. How can this be accomplished? a) Permanently installed reference electrode or by burying reference electrode every 20 feet around the perimeter of the tank b) Inserting a reference electrode under the tank through a perforated tube or attaching a reference electrode to the tank shell c) Permanently installed reference electrode or by inserting a reference electrode under the tank through a perforated tube d) Permanently installed bare copper wire connected to the tank bottom or by inserting a reference electrode under the tank through a perforated tube Reference: API-651, Paragraph 8.3.4 12. Other standard reference electrodes may be substituted for the saturated copper/copper sulfate reference electrode. Which of the following is not a common substitute? a) Reference electrode Zinc, Voltage +0.25 b) Reference electrode Saturated KCI calomel Voltage -0.78 c) Reference electrode Silver/silver chloride Voltage -0.80 d) Reference electrode Aluminum alloy (5% zinc) Voltage +0.08 Reference: API-651, Paragraph 8.4 and Table 4

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 25

Answers to API-651 Section 8, Criteria for Cathodic Protection


Question Number 1 2 3 4 5 6 7 8 9 10 11 12 Answer D A B C D C C C B A C D

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 26

Section 9 - Installation of Cathodic Protection Systems 1. Installation of cathodic protection systems shall be in strict accordance with the drawings and specifications. Exceptions may be made only with the approval of which of the following? a) The API-653 Inspector or personnel qualified and trained by the Inspector b) The National Board Inspector or personnel qualified and trained by the Inspector c) The owner, operator, or personnel qualified by the owner or operator d) The manufacturer of the tank or the authorized representative of the tank manufacturer Reference: API-651, Paragraph 9.1.2 2. Packaged galvanic anodes should be back-filled with ______. a) Compacted special backfill material such as coke breeze b) Compacted sand c) Compacted limestone or clam shell backfill material d) Compacted native soil Reference: API-651, Paragraph 9.2.1 3. How may galvanic anodes, used to protect the internal surfaces of tank bottoms, be installed? a) Bolted or welded to the tank bottom b) Laid on the tank bottom at specific intervals around the perimeter and in the center c) Held in place with a special adhesive or welded d) Held in place by epoxy coating that will adhere to the tank bottom Reference: API-651, Paragraph 9.2.3 4. When installing galvanic anodes, care must be taken during the backfilling operation to a) Ensure the limestone or clamshell backfill is not disturbed b) Prevent damage to the lead wires and connections c) Ensure the proper impervious membrane has been installed under the anode d) Prevent damage to the AC/DC rectifier Reference: API-651, Paragraph 9.2.5 5. Which if the following is a true statement with regards to installing galvanic anodes? a) It is customary to carry the anode to the site by the lead wire to ensure its tightness b) The lead wire should only be long enough to reach the tank bottom with no slack c) Anodes should not be carried or lowered into the excavation by the lead wires d) The anode should be stored in a container of water until it is placed in the excavation Reference: API-651, Paragraph 9.2.5
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 27

6. In an impressed current cathodic protection system, care must be taken not to crack or damage the anode during handling and installation. Of the following, which would be a true statement? a) Anodes with very small cracks near the bottom of the anode may be used without repair b) Cracked anodes should be inspected to ensure the insulation on the lead wires is not damaged before installing the anode c) Anodes with cracks greater than 0.0625" in width shall not be used d) Cracked anodes should not be used Reference: API-651, Paragraph 9.3.1.1 7. How can the life of an impressed current anode be increased? a) By installing a timing device that activates the current at thirty-second intervals b) Properly installing the backfill material c) Use a substitute anode material d) Using AC current instead of DC current Reference: API-651, Paragraph 9.3.1.2 8. Of the following, which is not a principal point that needs to be observed in the installation of impressed current anodes? a) The anode should be installed so that at least one side is in contact with the soil b) Buried connections must be protected against the entrance of moisture c) Anodes and cable should be installed at a sufficient depth to protect against accidental damage d) Care should be taken to protect the cable connection to the anode Reference: API-651, Paragraph 9.3.1.3 9. For a typical vertical anode installation, the hole is excavated ____ inches in diameter by approximately ______ feet deep. a) Six to ten, five to ten b) Eight to twelve, ten to twenty c) Twelve to eighteen, twelve to twenty-four d) Eighteen to twenty-four, eighteen to thirty Reference: API-651, Paragraph 9.3.2.1 10. When it is necessary to install an impressed current anode in the horizontal position, a layer of crushed coke breeze is laid in the trench and the anode is laid on top of the coke breeze. Compacted native soil is then filled in on top of the anode. a) True b) False Reference: API-651, Paragraph 9.3.2.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 28

11. For impressed current cathodic protection systems, when would installation of the anode in the horizontal position be acceptable or practical? a) Where rock is encountered at a shallow depth or where soil resistivity decreases markedly with depth b) Where sand is encountered at a shallow depth or where soil resistivity decreases markedly with depth c) Where rock is encountered at a shallow depth or where soil resistivity increases markedly with depth d) Where sand is encountered at a shallow depth or where soil resistivity increases markedly with depth Reference: API-651, Paragraph 9.3.2.2 12. To improve current distribution to the center of the tank in an impressed current cathodic protection system, it may be desirable to do which of the following? a) Install fifty percent more anodes b) Extend the shallow groundbed an additional twenty-five percent greater diameter around the tank c) Use AC current instead of DC current d) Install anodes in holes drilled at an angle under the perimeter of the tank bottom Reference: API-651, Paragraph 9.3.2.3 13. In situations where a deep groundbed installation is required, why is it important to consider the environmental aspects of this type of installation? a) The groundbed may be located in contaminated soil, which could allow contamination of the atmosphere b) The groundbed installation may fracture bedrock and permit the release of radon contamination c) The groundbed installation may be located through underground aquifers d) The groundbed installation may cause cracking of foundations of nearby structures during the drilling process Reference: API-651, Paragraph 9.3.3 14. An impressed current cathodic protection system is installed; the installing contractor connected the positive connection of the rectifier to the tank. Is this a satisfactory installation? a) Yes it does not matter how the leads are connected b) No the positive lead should have been connected to anode so the tank bottom would be the anode c) Yes the connection is correct the tank bottom will act as the anode as intended d) No the connection is incorrect, the tank bottom will now act as the anode resulting in rapid corrosion of the tank bottom Reference: API-651, Paragraph 9.3.4.3

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 29

15. What is the preferred means of connecting the negative rectifier lead wire to the structure to be protected? a) A powder weld connection (Cadweld, Thermite, or equivalent) b) Brazed c) Soldered d) Any arc welding process Reference: API-651, Paragraph 9.3.4.4 16. All positive cable connections and wire splices should be waterproofed and covered with electrical insulating material. What should be done if mechanical connections are used? a) Mechanical connections should be buried to protect them from vandalism b) Mechanical connections should not be buried c) Mechanical connections should be buried to protect them from accidental damage d) Mechanical connections should not be used for rectifier installation Reference: API-651, Paragraph 9.3.4.4 17. Underground splices of the positive lead wire to the groundbed should be ______. a) Braided and soldered b) Made up with mechanical splices c) Avoided d) Close to the surface for ease of maintenance Reference: API-651, Paragraph 9.3.5.2 18. One of the problems with monitoring cathodic protection systems on the tank bottom is the inability to place a portable reference electrode in close proximity to the underside. How can this situation be remedied during new construction of a tank? a) Permanently installed reference electrodes and lead wires to the roof support structure where provided b) Installing polyvinyl chloride or fiber reinforced plastic pipe for use in profiling the tank-to-soil potential from the perimeter to the center c) Installing polyvinyl chloride or terracotta pipe for use in profiling the tank-to-soil potential from the perimeter to the center d) Installing perforated polyvinyl chloride or fiber reinforced plastic pipe for use in profiling the tank-to-soil potential from the perimeter to the center Reference: API-651, Paragraph 9.9.4.4 19. For existing tanks, not scheduled for bottom repair or replacement, how can installation of permanent reference electrodes be accomplished? a) Air lance or mechanical procedures b) Water jetting or mechanical procedures c) Steam blast or mechanical procedures d) Controlled explosives or mechanical procedures Reference: API-651, Paragraph 9.4.6
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 30

20. Why is it a good practice to install permanent test leads, grounding lugs, or short pieces of cable for measuring tank-to-soil potential? a) Repeated contact with the tank by a knife or ice pick will eventually puncture the tank b) Repeated contact with the tank by a knife or ice pick can cause short circuiting of the cathodic protection system c) Repeated contact with the tank by a knife or ice pick can cause early failure of the tank's paint system. d) Repeated contact with the tank by a knife or ice pick can cause stress risers due to cutting the tank surface Reference: API-651, Paragraph 9.4.7

Answers to API-651 Section 9, Installation of Cathodic Protection Systems


Question Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Answer C D A B C D B A B B C D C D A B C D B C

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 31

Section 10 - Interference Currents 1. What can be a problem caused by the installation of a new impressed current cathodic protection system? a) A new impressed cathodic protection system may cause an unacceptable drain on the electrical substation for the refinery b) A new impressed cathodic protection system may cause interference with neighboring structures c) A new impressed cathodic protection system may cause interference with certain radio signals d) A new impressed cathodic protection system may cause interference with operating controls of nearby process units Reference: API-651, Paragraph 10.1.1 2. What is the most common source of "constant current" interference currents? a) Rectifiers energizing nearby cathodic protection systems b) Electromagnetic fields set up by the operation of very large motors close to the cathodic protection system c) Electromagnetic fields caused by transformers in nearby substations d) Electromagnetic fields caused by overhead high tension wire Reference: API-651, Paragraph 10.2.1 3. With regard to "fluctuating current", which of the following is not a normal source for this type of stray current? a) Underground mining electrical systems b) Electric railways c) Rapid transit systems d) AC to DC rectifiers Reference: API-651, Paragraph 10.2.2 4. During a corrosion control survey, the inspector noticed a positive shift of the structureto-soil potential on the affected structure at a point where current may be discharged from the affected structure. What would this indicate? a) Interference from the cathodic protection system rectifier b) Interference from a nearby lighting circuit c) Interference from a neighboring source d) Interference from a galvanic anode system Reference: API-651, Paragraph 10.3 5. Interference currents have been detected. How could this problem be resolved? a) Design, proper bonding, and use of sacrificial anodes b) Design, relocation of the tank, use of sacrificial anodes c) Design, proper bonding, removal of cathodic protection system d) Design, proper bonding, different choice of coating on the structure Reference: API-651, Paragraph 10.4.1
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 32

Answers to API-651 Section 10, Interference Currents


Question Number 1 2 3 4 5 Answer B A D C A

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 33

Section 11 - Operation and Maintenance of Cathodic Protection Systems 1. Why is it important to conduct potential surveys when there is an adequate liquid level in a tank? a) Bottom-to-electrolyte potential readings may indicate adequate protection for the portion of the tank in contact with the soil but when the tank is full and all of the bottom is in contact, protection may not be sufficient b) Bottom-to-anode potential readings may indicate adequate protection for the portion of the tank in contact with the soil but when the tank is full and all of the bottom is in contact, protection may not be sufficient c) Bottom-to-cathode potential readings may indicate adequate protection for the portion of the tank in contact with the soil but when the tank is full and all of the bottom is in contact, protection may not be sufficient d) Bottom-to-electrolyte potential readings may indicate adequate protection for the portion of the tank in contact with the soil but when the tank is full and all of the bottom is in contact, protection may be far more than necessary Reference: API-651, Paragraph 11.1.3 2. Measurements of the native structure-to-soil potential should be made ________. a) Immediately after any cathodic protection system is energized b) Within two days after any cathodic protection system is energized c) Within 6 months after any cathodic protection system is energized d) Prior to energizing a new cathodic protection system Reference: API-651, Paragraph 11.3.1 3. After a system has been energized, it may take _____ for polarization to a steady state to take place. a) Two and a half years b) One year c) Several months d) Fifteen minutes Reference: API-651, Paragraph 11.3.1 4. To ensure the effectiveness of cathodic protection, how often should cathodic protection surveys be taken? a) Every two years b) Annually c) Bi-annually d) Quarterly Reference: API-651, Paragraph 11.3.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 651 Cathodic Protection

Issue Date 03/98

Revision Date 07/00

Page 34

5. How often should all sources of impressed current be checked? a) At intervals not exceeding two years b) At intervals not exceeding one year c) At intervals not exceeding two months d) At intervals not exceeding two weeks Reference: API-651, Paragraph 11.3.3.1 6. Tank bottoms shall be examined for evidence of corrosion at least once each year by conducting an internal inspection and taking coupon cutouts. a) True b) False Reference: API-651, Paragraph 11.3.3.4 7. Records to demonstrate the need for corrosion control measures should be retained for a) 5 years b) 10 years c) 15 years d) As long as the facility remains in service Reference: API-651, Paragraph 11.4.7 8. Records related to the effectiveness of cathodic protection should be retained for a ______ period unless a shorter period is specifically permitted by regulation a) 5 years b) 10 years c) 15 years d) As long as the facility remains in service Reference: API-651, Paragraph 11.4.7

Answers to API-651 Section 11, Operation and Maintenance of Cathodic Protection Systems
Question Number 1 2 3 4 5 6 7 8 Answer A D C B C B D A

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API RP 652 Lining Aboveground Tanks

Issue Date 03/98

Revision Date 07/00

Page 1

Section 4 - Corrosion Mechanisms 1. Several common mechanisms of internal storage tank bottom corrosion are listed in API652. Which of the following is not a common corrosion mechanism? a) Galvanic cell corrosion b) Concentration cell corrosion c) Chloride stress corrosion d) Corrosion caused by sulfate-reducing bacteria Reference: API-652, Paragraph 4.1 2. Product cleanup tanks, chemical storage tanks, and wastewater treatment tanks may be susceptible to which type of corrosion? a) Galvanic cell corrosion b) Chemical corrosion c) Erosion-corrosion d) Concentration cell corrosion Reference: API-652, Paragraph 4.2 3. Concentration cell corrosion will most likely result in which of the following conditions? a) Pitting and possibly significant localized metal loss b) Pitting and possibly uniform metal loss over a large area c) Pitting and possibly the loss of external cathodic protection d) Pitting and possibly grooving of the outer perimeter of the tank bottom Reference: API-652, Paragraph 4.3 4. Pitting caused by concentration cell corrosion of a bare steel tank bottom may be as high as a) 20 mils per year b) 40 mils per year c) 60 mils per year d) 80 mils per year Reference: API-652, Paragraph 4.3 5. What is another name for the thin layer of oxide found on the surface of hot-rolled carbon steel, typically used for the construction of petroleum storage tanks? a) Patina b) Iron oxide c) Mill scale d) Rust Reference: API-652, Paragraph 4.4

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 652 Lining Aboveground Tanks

Issue Date 03/98

Revision Date 07/00

Page 2

6. With regard to galvanic cell corrosion, what adverse affect could the large differences in the microstructure of steel bottom plates caused by welding have? a) They can provide a built in area of localized cracking b) They can provide a built in stress concentration c) They can provide a built in break in the external cathodic protection d) They can provide a built in galvanic couple Reference: API-652, Paragraph 4.4 7. Sulfate-reducing bacteria (SRB) corrosion is universally recognized. The physical presence of bacterial deposits can promote aggressive _________ mechanism. a) Uniform metal loss over a wide area similar to erosion-corrosion b) Pitting by corrosion similar to concentration cell corrosion c) Pitting by corrosion similar to Chemical corrosion d) Pitting by corrosion similar to galvanic cell corrosion Reference: API-652, Paragraph 4.5 8. SRB colonies derive energy from the reduction of sulfates to sulfide which _______. a) Promotes the appearance of a non-corrosive coating b) Promotes the natural corrosion inhibitors of the steel plates c) Is corrosive to steel d) Is non-corrosive to steel Reference: API-652, Paragraph 4.5 9. Iron sulfide corrosion is _____ to the base steel and may promote pitting by a galvanic corrosion mechanism. a) An anode b) Ionic c) Cationic d) Cathodic Reference: API-652, Paragraph 4.5 10. Erosion-corrosion may occur in wastewater treating or mixing tanks where ___ is present a) Sulfate-reducing bacteria and anaerobic condition b) Soil or small abrasive aggregate c) Sulfuric acid or ballast water d) An anode or cathode Reference: API-652, Paragraph 4.6 11. Erosion-corrosion causes ______. a) Scattered pitting in a random pattern b) High localized metal loss in a random pattern c) Scattered pitting in a well defined pattern d) High localized metal loss in a well defined pattern Reference: API-652, Paragraph 4.6
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API RP 652 Lining Aboveground Tanks

Issue Date 03/98

Revision Date 07/00

Page 3

Answers to API-652 Section 4, Corrosion Mechanisms


Question Number 1 2 3 4 5 6 7 8 9 10 11 Answer C B A D C D B C D B D

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 652 Lining Aboveground Tanks

Issue Date 03/98

Revision Date 07/00

Page 4

Section 5 - Determination of the Need for Tank Bottom Lining 1. Aboveground storage tank bottoms are usually fabricated from ____ inch thick carbon steel plate. a) 1 b) 3/4 c) 1/2 d) 1/4 Reference: API-652, Paragraph 5.1 2. Annular floor plates of storage tanks are frequently ____ to ___ inch thick. a) 1/4 to 1/2 b) 1/2 to 3/4 c) 3/4 to 1 d) to 1-1/4 Reference: API-652, Paragraph 5.1 3, The need for an internal tank bottom lining in an aboveground storage tank is generally based upon several considerations. Which of the following would not be a consideration in determining the need for tank bottom lining? a) Tank design b) Environmental considerations c) Method of external cathodic protection employed d) Federal, state, and local regulations Reference: API-652, Paragraph 5.1 4. Internal tank bottom lining may be necessary if the minimum thickness is less than: a) 0.010 inch b) 0.100 inch c) 1.000 inch d) 0.1875 inch Reference: API-652, Paragraph 5.2 5. Of the following what would not be considered important to consider when determining the need for tank bottom lining? a) Where is the corrosion b) What type of corrosion is occurring c) How high is the design fill level d) What is the corrosion rate Reference: API-652, Paragraph 5.4

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 652 Lining Aboveground Tanks

Issue Date 03/98

Revision Date 07/00

Page 5

6. Flexing of the steel tank bottom may cause ______. a) An internal bottom lining to fail by cracking b) An internal bottom lining to fail by tearing c) An internal bottom lining to fail by blistering d) An internal bottom lining to fail by separating from the bottom plate Reference: API-652, Paragraph 5.4.1 7. In old tanks, which of the following may complicate the problem of poor coverage? a) The diameter of the tank b) The thickness of the tank bottom c) Uneven settlement of the tank bottom d) Chemical contaminants Reference: API-652, Paragraph 5.4.2 8. A properly applied internal bottom lining provides leak prevention by _______. a) Creating a cathodic protection barrier on the internal surface b) Enhancing the effectiveness of the external cathodic protection system c) Limiting internal corrosion of the steel tank bottom d) Limiting internal corrosion of the support columns and landing pads Reference: API-652, Paragraph 5.5 9. In setting priorities for the application of linings to the bottom of aboveground storage tanks, which of the following does not need to be considered? a) The potential for groundwater contamination b) Type of external cathodic protection system c) Presence of secondary containment and leak detection systems d) Location of facility Reference: API-652, Paragraph 5.5 10. A properly applied tank bottom lining may provide ___ years of service life in a particular product. a) 20 to 30 b) 10 to 20 c) 5 to 10 d) 1 to 5 Reference: API-652, Paragraph 5.6 11. A lining that has provided adequate protection in one product may not provide the same level of protection for another product. a) True b) False Reference: API-652, Paragraph 5.6
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API RP 652 Lining Aboveground Tanks

Issue Date 03/98

Revision Date 07/00

Page 6

Answers to API-652 Section 5, Determination of the Need for Tank Bottom Lining
Question Number 1 2 3 4 5 6 7 8 9 10 11 Answer D A C B C A D C B B A

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 652 Lining Aboveground Tanks

Issue Date 03/98

Revision Date 07/00

Page 7

Section 6 - Tank Bottom Lining Selection 1. Thin film linings are typically what thickness? a) 20 mils or less b) 30 mils or less c) 40 mils or less d) 50 mils or less Reference: API-652, Paragraph 6.1 2. Thick film linings are typically what thickness? a) Greater than 20 mils b) Greater than 30 mils c) Greater than 40 mils d) Greater than 50 mils Reference: API-652, Paragraph 6.1 3. Why must all linings be resistant to water? a) Water must be present at the tank bottom to act as a shield between the stored product and the lining b) Water must be present at the tank bottom to prevent contamination of the soil should a leak occur. The water will be detect before any product leakage c) Water must be present at the tank bottom for electrochemical corrosion to occur d) Water must be present at the tank bottom for electromotive corrosion to occur Reference: API-652, Paragraph 6.2 4. Which of the following type of lining would be used for a tank bottom containing water, distillates, crude, and gasoline at 195F a) Thin-film Coal tar epoxy b) Thick film isophthalic polyester c) Thick film epoxy d) Thin film epoxy with an amine curative Reference: API-652, Paragraph 6.2 and Table 1 5. What are two advantages of thin-film linings? a) Lower cost and can be used to cover very irregular surfaces b) Lower cost and ease of application c) Lower cost and surface preparation is not critical d) Requires no special training and lower cost Reference: API-652, Paragraph 6.2.1

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 652 Lining Aboveground Tanks

Issue Date 03/98

Revision Date 07/00

Page 8

6. Which of the following type of lining wold be used for a tank bottom containing water, crude oil, distillates, and gasoline at 150F a) Thin film coal tar b) Thick film vinyl ester c) Thin film epoxy with a polyamide curative d) Thick film isophthalic polyester Reference: API-652, Paragraph 6.3 and Table 2 7 Thick-film linings are commonly reinforced with which of the following? a) Sand and small diameter gravel b) Copper wire, stainless steel wire, and low alloy steel mesh fabric c) Chopped PVC piping, copped ABS piping, and Resin beads d) Glass flake, chopped glass fibers, and organic fibers

Reference: API-652, Paragraph 6.3 8. One advantage of thick-film lining is _________. a) It can provide a good surface to attach internal corrosion monitoring devices b) It can provide sufficient strength to bridge over large perforations in the tank bottom c) It can provide sufficient strength to bridge over small perforation in the tank bottom d) It can provide sufficient strength to prevent leakage should the tank bottom completely corrode away Reference: API-652, Paragraph 6.3.1 9. Special consideration must be given to what area of the tank bottom with regard to thickfilm lining? a) The center because this is the area that will be subjected to the most stress b) The critical zone c) Any butt weld joints in the tank bottom d) The coving at the transition from the tank bottom to the shell Reference: API-652, Paragraph 6.3.1 10. What are two disadvantages of thick-film linings? a) They are more expensive than thin-film linings and require more time to apply b) They are available in only one color and require more time to apply c) They are more expensive and require a curative d) They are more expensive and require high temperature airflow for curing Reference: API-652, Paragraph 6.3.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 652 Lining Aboveground Tanks

Issue Date 03/98

Revision Date 07/00

Page 9

11. Storage tank bottom linings generally cover the entire tank bottom and extend ________ up the shell of the tank. a) 12 to 18 inches b) 18 to 24 inches c) 24 to 30 inches d) 30 to 36 inches Reference: API-652, Paragraph 6.4 12. For thin-film lining systems, application of ______ coats is often required to achieve the desired film thickness a) 7 to 8 b) 5 to 6 c) 1 to 4 d) 2 to 3 Reference: API-652, Paragraph 6.4 13. For thick-film lining systems, ______ coats may be required to obtain the thickness of the desired lining. a) 5 to 8 b) 2 to 3 c) 1 to 4 d) 3 to 7 Reference: API-652, Paragraph 6.4 14. When only internal corrosion is taking place, regardless of the age of the tank, ______ thick linings may be used. a) 80 to 120 mil b) 55 to 80 mil c) 35 to 55 mil d) 10 to 35 mil Reference: API-652, Paragraph 6.4 15. What type and thickness of lining can be used for older tank bottoms that have corroded both internally and externally? a) Glass reinforced - 80 to 120 mil b) Glass reinforced - 55 to 80 mil c) Glass reinforced - 35 to 55 mil d) Glass reinforced - 10 to 35 mil Reference: API-652, Paragraph 6.4

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 652 Lining Aboveground Tanks

Issue Date 03/98

Revision Date 07/00

Page 10

16. Besides the corrosion history and the potential for corrosion, what two exceptional circumstances must be taken into account during the selection o a tank bottom lining? a) b) c) d) Specific gravity of the product and elevated temperature Product purity and fill/empty cycles Elevated temperatures and product purity Elevated temperatures and product viscosity

Reference: API-652, Paragraph 6.5

Answers to API-652 Section 6, Tank Bottom Lining Selection


Question Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Answer A A C D B D D C D A B D C C A C

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 652 Lining Aboveground Tanks

Issue Date 03/98

Revision Date 07/00

Page 11

Section 7 - Surface Preparation 1. What is meant by "anchor pattern" as it pertains to surface preparation for tank bottom lining? a) The grid pattern of mechanical fixtures that hold the lining in place b) The grid pattern of adhesive use to hold the lining to the tank bottom c) The surface profile or roughness d) The grid pattern of the bottom plate to plate welds Reference: API-652, Paragraph 7.1 2. Abrasive blast cleaning to a ______ finish is often specified as the minimum degree of surface cleanliness. a) White metal b) Near white metal c) Smooth metal d) Rough Reference: API-652, Paragraph 7.1 3. To facilitate inspection and to ensure good adhesion of the lining, surface preparation should extend _______ beyond the area to be lined. a) Several inches b) Several feet c) Not less than 6 inches d) Not less than 12 inches Reference: API-652, Paragraph 7.1 4. What is the preferred technique for the repair of perforations of the tank bottom? a) Thread the perforation and install a suitable pipe plug b) Install an entirely new tank bottom over the old bottom c) Fill the perforation with amber acrylic d) Welding of steel patches Reference: API-652, Paragraph 7.3 5. Abrasive blasting should not be performed if the temperature of the steel surface is less than _____ above the dew point or if the humidity is greater than ______ percent. a) 10F - 80 b) 5F - 80 c) 15F - 80 d) 25F - 80 Reference: API-652, Paragraph 7.4

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 652 Lining Aboveground Tanks

Issue Date 03/98

Revision Date 07/00

Page 12

6. The anchor pattern typically required for linings is ____ and generally increases with the thickness of the lining. a) 3.5 to 6 mils b) 2.5 to 5 mils c) 1.5 to 4 mils d) 0.5 to 3 mils Reference: API-652, Paragraph 7.5 7. What is the problem with having small mounts of contaminants such as dirt, clay, watersoluble salts, or oil in the abrasive used for storage tank bottom cleaning? a) This contamination in small amounts will not affect the quality and service life of the lining b) This contamination in small amounts will cause ripples in the lining surface c) This contamination in small amounts will cause the abrasive material to stick together and clog the cleaning equipment d) This contamination in small amounts will reduce the useful life of the lining Reference: API-652, Paragraph 7.6

Answers to API-652 Section 7, Surface Preparation


Question Number 1 2 3 4 5 6 7 Answer C B A D B C D

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 652 Lining Aboveground Tanks

Issue Date 03/98

Revision Date 07/00

Page 13

Section 8 - Lining Application 1. For thick-film linings, the manufacturer may specify that the prime coat be applied at a film thickness less than that of the anchor pattern. Why is it important to follow these requirements? a) Failure to follow these requirements could result in the nullification of the lining warranty b) Failure to follow these requirements could result in the lining cracking at the first filling of the tank c) Failure to follow these requirements could result in disbonding or delamination of the lining d) Failure to follow these requirements could result in pitting of the lining surface Reference: API-652, Paragraph 8.1 2. What should be done if there are differences between the owner's specifications and the lining manufacturer's recommendations? a) These differences should be resolved prior to beginning the job b) These differences should be resolved at each step to see which is more advantageous c) Disregard the manufacturer's recommendations d) Disregard the owner's specifications Reference: API-652, Paragraph 8.2 3. As a general rule, the temperature of the steel surface should be ____ and the humidity should be _______ during the application and curing of the lining. a) 25F above the dew point - below 80% b) 5F above the dew point - below 80% c) 5F below the dew point - above 80% d) 5F above the dew point - above 80% Reference: API-652, Paragraph 8.3 4. What is a common cause of failure of thick-film lining systems? a) Abrasive blasting to a white metal finish b) Abrasive blasting to a near white metal finish c) Primer coating at a thickness less than the anchor pattern d) Excess primer thickness Reference: API-652, Paragraph 8.4 5. What two factors are the major causes of premature lining failure? a) Forced curing and improper application b) Improper application and inadequate curing c) Abrasive blasting to white metal finish and inadequate curing d) Abrasive blasting to white metal finish and improper application Reference: API-652, Paragraph 8.5
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API RP 652 Lining Aboveground Tanks

Issue Date 03/98

Revision Date 07/00

Page 14

Answers to API-652 Section 8, Lining Application


Question Number 1 2 3 4 5 Answer C A B D B

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 652 Lining Aboveground Tanks

Issue Date 03/98

Revision Date 07/00

Page 15

Section 9 - Inspection 1. To ensure the lining meets the specification, it should be inspected during ___ and ___. a) Application and at the next scheduled internal inspection; not to exceed 20 years b) Application and at the next scheduled internal inspection; not to exceed 10 years c) Application and at the next scheduled internal inspection; not to exceed 5 years d) Application and upon completion of the work Reference: API-652, Paragraph 9.1 2. All lining inspectors should demonstrate a thorough knowledge of lining and coating practices or be _____ certified. a) National Board b) API-510 c) NACE d) API-653 Reference: API-652, Paragraph 9.2 3. How is holiday testing of thick film linings accomplished? a) Holiday testing of thick film linings shall be carried out with a low-voltage detector in accordance with NACE RP-01-88 b) Holiday testing of thick film linings shall be carried out with a high-voltage detector in accordance with NACE RP-01-88 c) Holiday testing of thick film linings shall be carried out with a low-wattage detector in accordance with NACE RP-01-88 d) Holiday testing of thick film linings shall be carried out with an infrared detector in accordance with NACE RP-01-88 Reference: API-652, Paragraph 9.2

Answers to API-652 Section 9, Inspection


Question Number 1 2 3 Answer D C B

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API RP 652 Lining Aboveground Tanks

Issue Date 03/98

Revision Date 07/00

Page 16

Section 10 - Repair of Tank Bottom Linings 1. A service life of ______ years should be expected from a properly selected and applied lining system. a) 10 to 20 b) 15 to 30 c) 20 to 30 d) 25 to 30 Reference: API-652, Paragraph 10.1 2. When should repairs to the tank be accomplished when it is necessary to make repairs to the lining? a) All repairs to the tank should be completed immediately after lining repairs to permit proper curing b) All repairs to the tank should be completed only after the lining repair has had time to cure c) All repairs to the tank should be completed prior to any repair of the lining d) All repairs to the tank should be started before the repair of the lining and finished as soon as the work on the lining is complete. Reference: API-652, Paragraph 10.1 3. Before deciding how to repair a lining, the cause and extent must be established. In addition, what three possible failure modes must be considered as possible causes of lining failure? a) Environmental, mechanical, cathodic protection b) Mechanical, improper installation, environmental c) Improper installation, wrong inspection technique, environmental d) Mechanical, environmental, placement of galvanic anodes Reference: API-652, Paragraph 10.2 4. Of the following, which is not one of the three basic types of lining repair? a) Top-coating of an existing lining b) Complete relining c) Spot repairs d) Installing metallic plugs in lining breaks Reference: API-652, Paragraph 10.3 5. Who should be consulted to access the compatibility of new coats with existing lining in the top-coating repair method? a) The API-653 Inspector b) The owner or operator c) The lining manufacturer d) NACE RP-01-84 Reference: API-652, Paragraph 10.3.2
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API RP 652 Lining Aboveground Tanks

Issue Date 03/98

Revision Date 07/00

Page 17

Answers to API-652 Section 10, Repair of Tank Bottom Linings


Question Number 1 2 3 4 5 Answer A C B D C

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 652 Lining Aboveground Tanks

Issue Date 03/98

Revision Date 07/00

Page 18

Section 11 - Safety 1. In addition to proper safe work procedures and training of employees, what else is required prior to the application of internal tank linings? a) Provision of the necessary supervision and/or inspection before and after the job is done b) Provision of the necessary supervision and/or inspection prior to the start of the lining application c) Provision of the necessary supervision and/or inspection throughout the progress of the job d) Provision of the necessary supervision and/or inspection provided by the employee with the most experience Reference: API-652, Paragraph 11.1 2. All necessary precautions to protect _____ shall be taken prior to entry of and while working in a storage tank. a) The thick film tank bottom lining b) Personnel c) Any cathodic protection system d) The environment Reference: API-652, Paragraph 11.2 3. Working in a petroleum storage tank presents certain hazards. Which of the following would not be a hazard associated with this activity? a) Drowning b) Respiratory c) Fire d) Explosion Reference: API-652, Paragraph 11.2 4. In order to properly protect themselves, employees should consult ______. a) Their immediate supervisor b) The owner/operator's specifications c) Previous inspection reports d) Material Safety Data Sheets (MSDS) Reference: API-652, Paragraph 11.4 General note to participants: The purpose of an MSDS is to tell the worker: a) A material's physical properties which make is hazardous to handle b) The type of personal protective equipment needed c) The first aid treatment is exposed to a hazard d) The planning needed for safely handling normal operation, as well as emergencies such as spills and fires e) The appropriate response to accidents The applicable MSDS should be consulted prior to conducting any work
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API RP 652 Lining Aboveground Tanks

Issue Date 03/98

Revision Date 07/00

Page 19

Answers to API-652 Section 11, Safety


Question Number 1 2 3 4 Answer C B A D

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP 652 Lining Aboveground Tanks

Issue Date 03/98

Revision Date 07/00

Page 20

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Pub. 2207 Tank Bottom Hot Work

Issue Date 03/98

Revision Date 07/99

Page 1

Section 1 - General 1. An operation that can produce a spark or flame hot enough to ignite flammable vapors is the definition, used by API 2207, for _____. a) Flame work b) Hot work c) Flash work d) Burning work Reference: API-2207, Paragraph 1.1 2. Tanks that have contained flammable or combustible liquids must be inspected and proven safe for hot work. These inspections include gas testing to determine an oxygen content of between ____ and _____ is present. a) 19.5 and 22.5 ppm b) 19.5 and 22.5 ppb c) 19.5 and 22.5 percent d) 19.5 and 22.5 ml per cubic foot Reference: API-2207, Paragraph 1.1 Section 3 - Precautions 1. During the entry and hot work activity, a/an ______ should be in operation. a) Electrical light stationed at the tank entrance b) Electrical air mover c) Cathodic protection system d) Gasoline powered air mover Reference: API-2207, Paragraph 3.2.2 2. Tank surfaces that have been in contact with leaded gasoline should be: a) Scraped down to bare metal b) Thoroughly flushed with potable water c) Steam cleaned d) Air lanced and cleaned with a solvent Reference: API-2207, Paragraph 3.2.4 3. As an alternative to scraping down to bare metal, welders should: a) Preheat the area to be welded to a minimum of 200F b) Wear chemical and gasoline resistant shoes and gloves c) Take frequent breaks by leaving the area at least every 15 minutes d) Use supplied-air respiratory equipment Reference: API-2207, Paragraph 3.2.4

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Pub. 2207 Tank Bottom Hot Work

Issue Date 03/98

Revision Date 07/99

Page 2

4. Grounding leads from welding machines should be attached to: a) The rectifier for the tank where hot work is being performed b) A bared surface on a tank in close proximity to the one in which hot work is being performed c) A bared surface on the tank shell on which hot work is to be performed d) A grounding rod driven deep in the ground out side the diked area of the tank in which hot work is being performed Reference: API-2207, Paragraph 3.2.5 5. Compressed gas cylinders used for cutting operations should be kept: a) Inside the tank to prevent tampering b) Outside the tank next to the opening c) Outside the tank at a safe distance from open manholes d) Inside the tank as long as there is at least 20 feet separating the cylinder from the hot work area Reference: API-2207, Paragraph 3.2.6 Section 4 Inspection Procedures 1. In preparation for performing hot work on a tank bottom, the repair organization places small openings in the tank bottom. Why would these openings be cut into the tank bottom? a) These openings facilitate inspection and complete draining of the tank b) These openings facilitate inspection and freeing the interior from gas c) These openings facilitate installation of jigs for alignment d) These openings facilitate inspection and testing the soil under the tank Reference: API-2207, Paragraph 4.2 Section 5 Safe Work Procedures 1. Minor welded repairs, if the tank bottom is not in good shape, may be made using which of the following procedures? a) Drill and tap a hole for pipe, connect a supply of inert gas to the tap, establish a flow of inert gas before starting the hot work, ensure oxygen content of atmosphere of 19.5 to 22.5 percent, plug the hole and back weld. b) Drill and tap a hole for 1/4 pipe, connect a supply of inert gas to the tap, establish a flow of inert gas before starting the hot work, ensure oxygen content of atmosphere of 19.5 to 22.5 percent, plug the hole and back weld. c) Drill and tap a hole for pipe, connect a supply of inert gas to the tap, establish a flow of inert gas immediately after starting the hot work, ensure oxygen content of atmosphere of 19.5 to 22.5 percent, plug the hole and back weld. d) Drill and tap a hole for pipe, connect a supply of inert gas to the tap, establish a flow of inert gas before starting the hot work, ensure oxygen content of atmosphere of 16.5 to 29.5 percent, plug the hole and back weld. Reference: API-2207, Paragraph 5.2
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API Pub. 2207 Tank Bottom Hot Work

Issue Date 03/98

Revision Date 07/99

Page 3

2. Major repairs involving most of the tank bottom can be accomplished by constructing a dike around the tanks outer shell and flooding beneath the tank bottom with: a) Solution of soap and water b) Solution of soda ash and water c) Light diesel oil d) Water Reference: API-2207, Paragraph 5.3 3. When it is necessary to perform welded repairs around the perimeter of a tank, excavation for a minimum of ____ beyond the point of any hot work area should be made. a) Twelve feet b) Twelve inches c) Six feet d) Six inches Reference: API-2207, Paragraph 5.4 4. When a tank double bottom is constructed, how much sand or other sealing material should be placed over the existing floor. a) Approximately 12 inches b) Approximately 8 inches c) Approximately 6 inches d) Approximately 4 inches Reference: API-2207, Paragraph 5.5

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Pub. 2207 Tank Bottom Hot Work

Issue Date 03/98

Revision Date 07/99

Page 4

Answers to API-2207 Section 1, General


Question Number 1 2 Answer B C

Answers to API-2207 Section 2, Precautions


Question Number 1 2 3 4 5 Answer B A D C C

Answers to API-2207 Section 3, Inspection Procedures


Question Number 1 Answer B

Answers to API-2207 Section 4, Safe Work Procedures


Question Number 1 2 3 4 Answer A D B D

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 1

Section 1 - General 1. API Standard 2015 provides direction to the user covering activities from ___ to ____ a) Construction to decommissioning b) Construction to repair c) Decommissioning to re-commissioning d) Removal from location to reconstruction at another location Reference: API-2015, Paragraph 1.1 2. Of the following, which would be the most correct answer? a) The appendixes are specifications and their use is mandatory in API-2015 b) The appendixes are guidance and are not part of API-2015 c) The appendixes are guidance and are considered as part of API-2015 d) The appendixes are specifications and their use is not mandatory in API-2015 Reference: API-2015, Paragraph 1.1 3. API-2015 does not apply to which of the following? a) Stationary tanks used in the petroleum and petrochemical industry b) Low-pressure aboveground storage tanks c) Tanks used in crude oil terminals d) Underground low-pressure storage tanks Reference: API-2015, Paragraph 1.1 4. API-2015 is intended to be consistent with which of the following regulations? a) Title 29 of the U.S. Code of Federal Regulations b) Title 25 of the U.S. Code of Federal Regulations c) Title 19 of the U.S. Code of Federal Regulations d) OSHA 29 CFR 1910.119 Reference: API-2015, Paragraph 1.2 5. If any provision of API-2015 conflicts with statutory or regulatory requirements _____. a) API-2015 shall govern b) The owner/operators specifications shall govern c) The statute and regulation shall govern d) API-2015 in conjunction with the owner/operators specifications Reference: API-2015, Paragraph 1.2 Note to Student: Section 1 of API-2015 contains a list of definitions, which should be studied. The exam may not ask questions that require you to choose the correct definition but the questions may contain the terms and your knowledge of definitions would be required.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 2

Answers to API-2015 Section 1, General


Question Number 1 2 3 4 5 Answer C B D A C

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 3

Section 2 Administrative Controls 1. Who is responsible for developing and implementing administrative controls and written plans for tank work from decommissioning through re-commissioning? a) The Inspector b) The regulatory agency c) The tank manufacturer d) The employer Reference: API-2015, Paragraph 2.1 2. Which of the following would not be addressed in the administrative controls and written plans for tank work? a) Use of qualified person(s) at the job site to supervise and perform activities b) Wage administration of employees involved with tank work c) An emergency plan d) Evaluation of contractors and/or subcontractors Reference: API-2015, Paragraph 2.1 3. API-2015 uses the term qualified person throughout the document. Which of the following best defines qualified person a) Person or persons who have passed written examinations administered by the American Petroleum Institute b) Person or persons who have been certified by OSHA to supervise tank work c) Person or persons designated by an employer as having the necessary training and competence to perform and/or supervise tasks or activities in accordance with the employers policy, procedures, and programs. d) Person or persons certified by an employer as having the necessary training and competence to perform and/or supervise tasks or activities in accordance with the requirements of API-653. Reference: API-2015, Paragraph 2.2 4. Which of the following duties must be performed by a qualified person? a) Atmospheric testing, issuing permits, and attendant duties b) Atmospheric testing, product testing, and attendant duties c) Atmospheric testing, issuing permits, and repair activities d) Atmospheric testing, issuing tools, and attendant duties Reference: API-2015, Paragraph 2.2 5. The ______ shall advise the contractor of known potential hazards associated with the tank in which work is to be performed and the surrounding area. a) Inspector b) Contract administrator c) A qualified person d) The owner and/or operator Reference: API-2015, Paragraph 2.4
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 4

Answers to API-2015 Section 2, Administrative Controls


Question Number 1 2 3 4 5 Answer D B C A D

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 5

Section 3 Storage Tank Hazards 1. All tanks that have contained petroleum or petroleum products may present all but which of the following hazards during some phase of preparing a tank for entry and cleaning? a) Fires and explosions b) Low temperature hazards c) Toxic substances d) Oxygen deficiency or enrichment Reference: API-2015, Paragraph 3.1 2. It is well known that the vapors of some hydrocarbons, stored in aboveground tanks, are heavier than air and will displace or dilute oxygen. What can cause depletion of oxygen in a tank that has been closed? a) The presence of carbon dioxide from the decomposition of water and sludge b) The presence of carbon monoxide from steam cleaning c) The presence of oxidation d) The presence of sulfuric acid from the evaporation of the hydrocarbon Reference: API-2015, Paragraph 3.3 3. According to API-2015, oxygen enrichment occurs when the oxygen level exceeds __ %. a) 23.5% b) 22.5% c) 21.5% d) 19.5% Reference: API-2015, Paragraph 3.3
(Note to the student: API-2207 states the upper limit of breathable oxygen is 22.5%. Be very careful and be sure you understand the question and which API document is being referred in the question. Questions relating to this topic must be read very carefully and if there is doubt list the question and your comment on the form provided for that purpose during the exam.)

4. Where would you look to find the source of excess oxygen during the cleaning or other tank work? a) An air mover that is to large for the tank b) Leaking vents c) Improperly operating analyzer d) Leaking oxygen bottles or cylinders Reference: API-2015, Paragraph 3.3 5. According to API-2015, toxic substances can cause all but which of the following? a) Irritation b) Hallucinations c) Death d) Injury Reference: API-2015, Paragraph 3.3
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 6

6. Exposure to toxic substances can be by any of the following routes except _____. a) Skin or eye absorption b) Inhalation c) Injection or ingestion d) Casual contact with fellow workers Reference: API-2015, Paragraph 3.4 7. During the production, storage, and refining of sour crude oil and crude oil fractions ____ is produced. This substance is extremely toxic and flammable. a) Calcium Chloride b) Sulfur dioxide c) Hydrogen sulfide d) Hydrogen sulfate Reference: API-2015, Paragraph 3.4 8. Who is required to procure and review information on materials contained in the tank to be worked on? a) The appropriate qualified person b) The appropriate inspector c) The appropriate owner/operator d) The appropriate employer Reference: API-2015, Paragraph 3.4 9. Personnel who are to be performing work or other activities in and around the tank should review the appropriate _____. a) Work orders b) Material safety data sheets c) Owner/operator specifications related to the operation of the tank d) Previous inspection reports Reference: API-2015, Paragraph 3.4 10. In addition to fire and explosion hazards, oxygen deficiency and enrichment hazards, and toxic substance hazards, physical hazards are also present during tank work. Of the following, which would not be a physical hazard? a) Tripping hazards caused by internal tank structures and equipment related to the tank work b) Heat stress in hot weather c) Falling into a sump d) Lightning Reference: API-2015, Paragraph 3.5

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 7

Answers to API-2015 Section 3, Storage Tank Hazards


Question Number 1 2 3 4 5 6 7 8 9 10 Answer B C A D B D C A B D

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 8

Section 4 Preparing the Tank for Entry and Cleaning 1. Prior to commencing work in and around a tank the hazards that can be encountered must be controlled by pre-planning the job. The essential elements for safe entry and cleaning include: a) Review of tank configuration, piping, and site layout, reviewing information related to the products contained in the tank and surrounding tanks, and preparation of a workers entry log b) Review of tank configuration, piping, and site layout, reviewing information related to the products contained in the tank and surrounding tanks, and preparation of a safety and work plan for isolation, entry, and cleaning c) Review of tank configuration, piping, and site layout, reviewing information related to the products contained in the tank and surrounding tanks, and reviewing all previous inspection records since the tank was commissioned d) Review of tank configuration, piping, and site layout, reviewing information related to the products contained in the tank and surrounding tanks, and review of the effectiveness of the cathodic protection system Reference: API-2015, Paragraph 4.1 2. Unrecoverable product that remains in the tank below the discharge nozzle: a) Shall be covered with an impenetrable membrane b) Can be left as long as it is no more than 6 deep and below the work area c) Shall be removed in accordance with the safety and work plan d) Shall be removed by a sub-contractor who specializes in that type of removal Reference: API-2015, Paragraph 4.2 3. What should workers in and around the tank do in the event of an electrical storm do? a) Continue working, the tank will act as a lightning rod protecting the workers b) Discontinue work that involves electrical equipment c) Double-check the bond and ground cables and clamps to ensure integrity d) Leave the tank and move to a designated safe place Reference: API-2015, Paragraph 4.4.5 4. Why are pyrophoric deposits a concern during entry and cleaning operations? a) Pyrophoric deposits may decay and become air borne toxic vapors b) Pyrophoric deposits may accumulate and create a slipping hazard c) Pyrophoric deposits may decay and become extremely acidic d) Pyrophoric deposits may spontaneously ignite upon exposure to air Reference: API-2015, Paragraph 4.4.6 and Appendix C.7 5. The procedure for testing of the tank atmosphere shall be established prior to the initiation of tank cleaning a) True b) False Reference: API-2015, Paragraph 4.7
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 9

Answers to API-2015 Section 4, Preparing the Tank for Entry and Cleaning
Question Number 1 2 3 4 5 Answer B C D D A

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 10

Section 5 Testing the Tank Atmosphere 1. Documentation of ______ shall be maintained for each instrument used for atmospheric testing. a) Instrument usage b) Instrument calibration c) Instrument maintenance d) Instrument repair Reference: API-2015, Paragraph 5.1 2. Of the following, which is not one of three types of atmospheric testing equipment discussed in API-2015? a) Oxygen analyzers b) Flammable vapor analyzers c) Carbon Dioxide analyzers d) Toxic substance indicators Reference: API-2015, Paragraph 5.1.1, 5.1.2, & 5.1.3 3. Generally, flammable vapor analyzers depend on the presence of adequate ___ levels to obtain accurate readings. a) Oxygen b) Hydrogen c) Carbon dioxide d) Nitrogen Reference: API-2015, Paragraph 5.2 4. What is the required order of testing prescribed by OSHA 29 CFR 1910.146? a) Toxic vapors, oxygen content, flammable vapors b) Oxygen content, toxic vapors, flammable vapors c) Flammable vapors, oxygen content, toxic vapors d) Oxygen content, flammable vapors, toxic vapors Reference: API-2015, Paragraph 5.2 5. Which of the following instruments will detect or determine if a tank to be entered is or has been in leaded gasoline service prior to cleaning and drying? a) Mass spectrometer with infrared capabilities b) Lead in air analyzer c) Toxic substance indicator d) There is none Reference: API-2015, Paragraph 5.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 11

6. Where and why should the exterior tank atmospheric test be conducted during tank vapor freeing? a) Adjacent to the inlet of the air mover to be sure fresh air is being used for venting b) Near the base of the tank because most vapors are heavier than air will tend to settle near the ground c) At a point where vapors are being exhausted and the area around the tank to ensure flammable and toxic vapors are not present above acceptable levels d) At a point where vapors are being exhausted and the area around the tank to ensure flammable and toxic vapors are present above acceptable levels proving they are being vented from the tank Reference: API-2015, Paragraph 5.2.1 7. The internal tank atmosphere shall be tested to ensure permissible conditions exist throughout the tank. How long should ventilating equipment be shut down prior to testing the interior? a) 30 minutes b) 15 minutes c) 5 minutes d) Ventilating equipment should never be shut down Reference: API-2015, Paragraph 5.2.2 8. Atmospheric testing should be conducted _____ to ensure proper atmospheric conditions are maintained. a) As necessary b) At least every 15 minutes c) At least every 30 minutes d) At least every 45 minutes Reference: API-2015, Paragraph 5.3 9. In addition to the results of testing, the time of testing, what else is required to be recorded on or attached to the entry permit? a) The signature of each person entering the tank b) The signature of the person in charge of the tank work c) The signature of the person who performed the test d) The signature of the Inspector Reference: API-2015, Paragraph 5.4

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 12

Answers to API-2015 Section 5, Testing the Tank Atmosphere


Question Number 1 2 3 4 5 6 7 8 9 Answer B C A D D C B A C

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 13

Section 6 Hazard Assessment for Entry Permits 1. The entry level and the precautions for entry shall be based on atmospheric and physical conditions. API-2015 lists three levels of precaution, what are they? a) Entry with special precautions, entry with restrictions, entry with caution b) Entry without special precautions, entry with restrictions, entry without restrictions c) Entry with special precautions, entry with minimal precautions, entry without restrictions d) Entry with special precautions, entry with restrictions, entry without restrictions Reference: API-2015, Paragraph 6.1 2. Which of the entry level precautions are assigned to activities that may subject employees to the risk of death, incapacitation, inability to self-rescue, serious injury, or acute illness? a) Entry without restrictions b) Entry with special precautions c) Entry with restrictions d) Entry with extreme caution Reference: API-2015, Paragraph 6.2 3. Who is required to issue an entry permit regardless of the level of precaution? a) A qualified person b) An inspector c) An employer d) A supervisor Reference: API-2015, Paragraph 6.2, 6.3, & 6.4 4. After cleaning a tank for entry it is necessary to close the tank to restrict entry during an extended period of inactivity. Which of the following would be a correct statement? a) The tank shall be re-tested but only for oxygen content b) The tank shall be re-tested by any employee entering the tank c) The tank shall be re-tested as though it were the initial test d) The tank shall be re-tested but only for flammable vapors Reference: API-2015, Paragraph 6.5 Note to Student: Read paragraph 6.3 carefully notice the oxygen content must be between 19.5% and 23.5%. This is the industry standard and should be your answer to any question pertaining to this requirement. Should the question refer to API 2207 and this range is not one of the answers, use the range stated in 2207 and comment on the provided exam question discrepancy form.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 14

Answers to API-2015 Section 6, Hazard Assessment for Entry Permits


Question Number 1 2 3 4 Answer D B A C

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 15

Section 7 Personal Protective Equipment 1. What is a situation that can arise due to wearing impervious clothing? a) The employee can pass out due to no oxygen reaching the skin b) The employee may be susceptible to skin rash from chaffing c) The employee may be susceptible to heat stress d) The employee may not be aware of contamination Reference: API-2015, Paragraph 7.1(a) 2. Who is responsible for providing appropriate respirators? a) The employer b) The employee c) The qualified person d) The inspector Reference: API-2015, Paragraph 7.2.1 3. The employer shall comply with what standard or regulation with regard to a respiratory protection program? a) API-653 b) OSHA 29 CFR 1910.119 c) The owner/operators specifications d) OSHA 29 CFR 1910.134 Reference: API-2015, Paragraph 7.2.3 4. A respirator shall be checked by whom each time it is put on? a) The employer b) The wearer c) The qualified person d) The supervisor Reference: API-2015, Paragraph 7.2.4 5. Breathing air supply shall be secured to protect it from: a) Theft and physical damage b) Being used for flame cutting and contamination c) Physical damage and contamination d) Physical damage and being moved while in use Reference: API-2015, Paragraph 7.2.6

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 16

Answers to API-2015 Section 7, Personal Protective Equipment


Question Number 1 2 3 4 5 Answer C A D B C

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 17

Section 8 Entering and Working Inside the Tank 1. Before entry into a tank, a written permit shall be issued. Where must this permit be during the entry period? a) The employer shall keep the permit on file b) The permit shall be posted next to the breathable air storage area (when supplied air is required) c) The permit shall be posted at the entry point of the tank d) The permit shall be kept by the qualified person who issued it Reference: API-2015, Paragraph 8.2 2. At least one attendant shall be provided when a tank is entered under which of the following levels of precaution? a) Entry with extreme caution b) Entry with special precautions c) Entry with restrictions d) Entry without restrictions Reference: API-2015, Paragraph 8.3 3. API-2015 lists many qualifications for the attendant and the employer shall ensure that each attendant meets these requirements. Which of the following would not be considered as an item the attendant should be familiar with or trained for? a) Know the hazards that may be faced during entry b) Remains outside the permit space during entry operations until relieved c) Summons rescue and other emergency services d) Perform CPR and other first aid Reference: API-2015, Paragraph 8.3 4. In addition to an emergency plan for summoning rescue personnel and other emergency personnel, a plan shall also exist for _______. a) Environmental emergencies b) Evacuation of the refinery c) Evacuating the tank d) Collecting the required breathing apparatus Reference: API-2015, Paragraph 8.4

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 18

Answers to API-2015 Section 8, Entering and Working Inside the Tank


Question Number 1 2 3 4 Answer C B D A

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 19

Section 9 Hot Work and Tank Repairs 1. Hot work is defined by API-2015 as: a) Any work that produces enough energy to ignite paper b) Any work that produces enough energy to be a potential lethal vapor source c) Any work that produces enough energy to be a potential ignition source d) Any work that produces enough energy to be a potential flammable vapor source Reference: API-2015, Paragraph 9.1 2. Frequent tests shall be conducted to verify the atmosphere in the tank is not in excess of ___ percent of the lower flammable limit and that the PEL/TLV for toxic substance are not exceeded. a) Ten b) Fifteen c) Twenty d) Twenty-five Reference: API-2015, Paragraph 9.1 3. Who is responsible for issuing a hot work permit? a) The inspector b) A qualified person c) The contractor d) The employer Reference: API-2015, Paragraph 9.2 4. Fire fighting equipment in working order, such as extinguishers and/or pressurized hoses, shall be available where hot work is to be performed. What consideration should be given to the personnel who might have to operate this equipment? a) The personnel must be big enough to handle the pressurized hose b) The personnel must be strong enough to lift and use a fire extinguisher c) The personnel must be instructed in the use of this equipment d) The personnel must be stationed at least sixty feet from the hot work area Reference: API-2015, Paragraph 9.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 20

Answers to API-2015 Section 9, Hot Work and Tank Repairs


Question Number 1 2 3 4 Answer C A B C

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 21

Section 10 Returning the Tank to Service

1. What important function must be performed prior to installing the manway covers? a) The tank shall be washed down with clean water b) The tank shall have warm dry air circulated to remove moisture c) The tank shall be completely coated to prevent corrosion d) The tank shall be inspected to ensure all personnel have exited Reference: API-2015, Paragraph 10.2 2. If the product being pumped into the tank during filling is capable of emitting flammable vapors, the flow rate shall be reduced to minimize the creation of static electricity. This fill rate is usually ______ for steel pipe. a) 3 feet per second b) 3 feet per minute c) 3 inches per second d) 3 inches per minute Reference: API-2015, Paragraph 10.4 3. When would it be permissible for personnel to go onto the top of a floating roof either internal or external after re-floating the roof? a) Personnel should not go on top of the roof for at least 24 hours after re-floating the roof b) Personnel should not go on top of the roof for at least 18 hours after re-floating the roof c) Personnel should not go on top of the roof for at least 12 hours after re-floating the roof d) Personnel should not go on top of the roof for at least 6 hours after re-floating the roof Reference: API-2015, Paragraph 10.4 4. Why should the fill rate be reduced as product nears the pontoons and/or lower deck surface? a) To prevent overfilling the tank and causing environmental contamination b) To prevent toxic or flammable vapors uncontrolled escaping into the atmosphere c) To prevent damage to the roof d) To prevent dislodgment of the wind girders Reference: API-2015, Paragraph 10.4

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 22

Answers to API-2015 Section 9, Hot Work and Tank Repairs


Question Number 1 2 3 4 Answer D A B C

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 23

Appendix A Description of Petroleum Storage Tank Hazards Note to the student: API-2015 states that the appendixes are offered as guidance and do not from part of the standard. It should be pointed out however the examination can ask questions relating to the information provided in the appendixes. For that reason, we will address some highlights and important topics in this study guide. The student is encouraged to read all of the appendixes and be familiar with their layout and content. 1. What are the three elements necessary for a fire? a) Flammable vapor, air (oxygen), and chemical decomposition b) Flammable vapor, hydrogen, and an ignition source c) Flammable vapor, air (oxygen), and an endothermic reaction d) Flammable vapor, air (oxygen), and an ignition source Reference: API-2015, Appendix A.2 2. What is the flammable range of methane? a) 5 to 15 percent in air b) 5 to 15 PPM c) 5 to 15 PPB d) 5 to 15 parts per liter Reference: API-2015, Appendix A.2 and Table A-1 3. Why would it be necessary to take oxygen content tests at various levels in a storage tank? a) So the workers will know what level they can work at b) To verify the results of the previous test c) Because the atmosphere may become stratified d) Oxygen content tests are only taken at the bottom of the tank Reference: API-2015, Appendix A.3 4. You are assigned as an attendant for workers inside a tank. You notice one worker on the far side of the tank having difficulty using a simple tool. Would you be concerned and what might be the reason for the workers difficulty? a) There is no reason for concern, the worker has probably not used that tool before b) There is no reason for concern, the tool is probably broken c) There is reason for concern, the worker probably broke the tool d) There is reason for concern, loss of reasoning is one sign of an oxygen deficient environment Reference: API-2015, Appendix A.3

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 24

5. You have been designated as a qualified person for tank entry attendant. Where would you go for information about health and safety risks of a substance? a) The inspector b) The employer or supplier c) The supervisor in charge of the entry work d) The operator of the tank Reference: API-2015, Appendix A.4 6. A substance that causes minor or transient but possibly painful injuries that heal without scars and produce no known aftereffects are known as _____. a) Inconveniences b) Scrapes and brush burns c) Irritants d) Non-toxic substances Reference: API-2015, Appendix A.4 7. Hydrofluoric acid, sulfuric acid, and caustics are classified as _____. a) Corrosives b) Carcinogens c) Chronically toxic substances d) Critical mass substances Reference: API-2015, Appendix A.4 8. ___________ and ________ are terms commonly used to describe the concentration in air of an airborne toxic substance below which nearly all workers may be repeatedly exposed without adverse affects. a) Permissible limit values (PLV) and Threshold exposure limits (TEL) b) Threshold exposure values (TEV) and Permissible exposure values (PEV) c) Permissible threshold limits (PTL) and Permissible exposure limits (PEL) d) Permissible exposure limits (PEL) and Threshold limit values (TLV) Reference: API-2015, Appendix A.4 9. Who is responsible for determining which toxic substance(s) is/are likely to be present in a tank to be entered? a) The qualified person designated as the attendant b) The qualified person supervising the job c) The qualified inspector for the repair d) The qualified person responsible for breathing apparatus Reference: API-2015, Appendix A.4

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 25

10. You are in an area and detect a rotten-egg odor. What would you attribute this smell to? a) The exhaust of a truck parked nearby b) A bank of portable toilets c) Hydrogen sulfide d) Sulfur dioxide Reference: API-2015, Appendix A.4.1 11. Since hydrogen sulfide has such a distinct odor, why should you not rely on your sense of smell to detect its presence? a) Instantaneous exposure to higher concentrations of the gas immediately paralyze the sense of smell b) Instantaneous exposure to lower concentrations of the gas immediately paralyze the sense of smell c) Prolonged exposure to higher concentrations of the gas become tolerable to the sense of smell d) Prolonged exposure to low concentrations of the gas become tolerable to the sense of smell Reference: API-2015, Appendix A.4.1 12. Lead alkyls are toxic via which of the four routes of exposure a) Skin and eye absorption only b) Inhalation, skin and eye absorption, ingestion, and injection c) Injection and ingestion only d) Inhalation and ingestion only Reference: API-2015, Appendix A.4.2 13. You are assigned the duties of entry attendant for a tank, you notice several of the workers inside the tank appear to be intoxicated. What might be the cause? a) These workers consumed alcoholic beverages at lunch b) The workers arrived at work in this condition c) The workers are inhaling high concentrations of hydrocarbon vapors d) The workers are inhaling high concentrations of nitrous oxide vapors Reference: API-2015, Appendix A.4.4 14. Workers wearing semi-impermeable or impermeable clothing can encounter heat stress at temperatures as low as ___F. a) 40 b) 50 c) 60 d) 70 Reference: API-2015, Appendix A.4.5

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 26

Answers to API-2015 Appendix A, Description of Petroleum Storage Tank Hazards


Question Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Answer D A C D B C A D B C A B C D

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 27

Appendix B Vapor Freeing the Tank 1. Of the following, which would not be a method of vapor freeing a tank? a) Mechanical ventilation b) Natural ventilation c) Liquid flooding d) Inert gas purging Reference: API-2015, Appendix B.1 2. Mechanical ventilation uses ____ or ___ that are driven by electric motors, air, or steam. a) Pumps or compressors b) Blowers or eductors c) Eductors or pumps d) Blowers or compressors Reference: API-2015, Appendix B.1 3. Steam ventilation may be advantageous in certain cases, however steam jets generate __. a) Static electricity b) Excessive noise c) Excessive heat d) Excessive moisture Reference: API-2015, Appendix B.3 4. Natural ventilation is the preferred method regardless of the availability of other methods. a) True b) False Reference: API-2015, Appendix B.4 5. Tanks that have contained asphalt, aromatic tars, or sour stock are more susceptible to which of the following? a) High concentrations of solidified product b) Accelerated corrosion when the product is removed c) Pyrophoric deposits d) Brittle fracture Reference: API-2015, Appendix B.5

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 28

Answers to API-2015 Appendix B, Vapor Freeing the Tank


Question Number 1 2 3 4 5 Answer C B A B C

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 29

Appendix C Control of Ignition Sources 1. Personnel should leave a tank cleaning site if _____ while the tank is being ventilated or cleaned. a) Vehicular traffic has to pass within 50 feet of the tank b) An electrical storm is in progress or threatening c) A rain shower is in progress or threatening d) A snow storm is in progress or threatening Reference: API-2015, Appendix C.3 2. The use of artificial lights except flashlights should be avoided when there is a potential of flammable vapors exceeding ____ of the lower flammable limit. a) 10% b) 10 parts per million c) 10 parts per billion d) 10 parts per thousand Reference: API-2015, Appendix C.4 Note to the Student: The remainder of the appendixes will not be covered in this study guide, you should read the information contained in these appendixes. Appendix D deals with specific tank designs and products. Appendix E provides a Planning Checklist, and appendix F discusses oxygen and flammable vapor analyzers. We do not expect questions relating to appendixes D, E, or F to be on the exam however, reading them will not be a waste of time.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API Standard 2015 Safe Entry & Cleaning of Tanks

Issue Date 03/98

Revision Date 07/00

Page 30

Answers to API-2015 Appendix C, Control of Ignition Sources


Question Number 1 2 Answer B A

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP-575 Inspection of Storage Tanks

Issue Date 03/98

Revision Date 07/00

Page 1

Section 3 Selected Nondestructive Examination Methods 1. In ultrasonic thickness measurements, dual-element transducers have the ability to operate from thin sections of ____ inch a) 0.500 1.000 b) 0.050 0.100 c) 0.050 1.000 d) 0.005 1.000 Reference: API-575, Paragraph 3.1 2. In performing ultrasonic thickness measurements _____ transducers are recommended for measurements on penetrations and floors and _____ transducers are recommended on shells where coating thickness may not be uniform. a) Dual-element, Single crystal contact b) Single crystal contact, Dual-element c) High-temperature, Low-temperature d) Low-temperature, High-temperature Reference: API-575, Paragraph 3.1 3. What is the minimum overlap for ultrasonic thickness readings according to the ASME? a) 10 percent based on the thickness of the part being examined b) 10 percent based on the diameter of the transducer c) 10 percent based on the thickness of the calibration block d) 10 percent based on the diameter of the transducer cable Reference: API-575, Paragraph 3.2 4. What ultrason method can be used to assist in the discrimination between inclusions in the metal and laminations? a) A scan b) B scan c) Straight beam d) Shear wave Reference: API-575, Paragraph 3.3 5. The primary advantage of magnetic floor testing using a floor scanner is the ability to detect topside pitting and underside corrosion. Additional inspection is required to quantify flaws detected above certain thresholds. Generally, what method of examination is used for this purpose? a) Liquid penetrant b) Eddy current c) Ultrasonic d) Radiography Reference: API-575, Paragraph 3.4
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API RP-575 Inspection of Storage Tanks

Issue Date 03/98

Revision Date 07/00

Page 2

Answers to API-RP-575 Section 3, Selected Nondestructive Examination Methods


Question Number 1 2 3 4 5 Answer C A B D C

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP-575 Inspection of Storage Tanks

Issue Date 03/98

Revision Date 07/00

Page 3

Section 4 Types of Storage Tanks 1. API-575 states that atmospheric storage tanks are used for fluids having a true vapor pressure at the storage temperature that is _____. a) equal to or greater than atmospheric pressure b) at least 2.5 psi above atmospheric c) at least 2.5 pounds per square foot above atmospheric d) substantially below atmospheric Reference: API-575, Paragraph 4.2.2 2. What type of tank does API-575 consider the simplest type of atmospheric storage tank? a) Cone-roof b) Dome-roof c) Umbrella-roof d) Pan-type floating roof Reference: API-575, Paragraph 4.2.3 3. The floating roof atmospheric storage tank is designed to do which of the following? a) Allow the tank to filled completely to the top rim and provide self-venting b) Prevent personnel for falling into the tank and keep birds out of the storage area c) Eliminate or minimize the vapor space above the stored liquid d) Create or maximize the vapor space above the stored liquid Reference: API-575, Paragraph 4.2.3 4. The pan-type floating roof is the simplest type of floating roof design. Which of the following is the most correct? a) This design is susceptible to collapse b) This design is susceptible to sinking c) This design is more susceptible to corrosion d) This design is not suited for hydrocarbon storage tanks Reference: API-575, Paragraph 4.2.3 5. Storage tanks that are designed to operate at pressures, in their gas or vapor spaces, exceeding 2.5 psi but not more than 15 psi are described as which of the following? a) Atmospheric storage tanks b) High-pressure storage tanks c) Intermediate pressure storage tanks d) Low-pressure storage tanks Reference: API-575, Paragraph 4.3.1

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP-575 Inspection of Storage Tanks

Issue Date 03/98

Revision Date 07/00

Page 4

Answers to API-RP-575 Section 4, Types of Storage Tanks


Question Number 1 2 3 4 5 Answer D A C B D

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP-575 Inspection of Storage Tanks

Issue Date 03/98

Revision Date 07/00

Page 5

Section 5 Reasons for Inspection and Causes of Deterioration 1. In general, why are storage tanks inspected? a) To determine their physical condition and cycles of use b) To determine their physical condition and rate of deterioration c) To determine their physical dimensions and rate of deterioration d) To determine their physical condition and type of design Reference: API-575, Paragraph 5.1 2. What is the prime cause of deterioration of steel storage tanks and accessories? a) Erosion b) Upset c) Settlement d) Corrosion Reference: API-575, Paragraph 5.2 3. A sand pad beneath a tank bottom is found to be contaminated with gravel and crushed stones. What type of problem could this contamination cause? a) Pitting corrosion at points of contact b) Punctures of the tank bottom at points of contact c) Air spaces which provide even corrosion d) Cracking at the point of contact Reference: API-575, Paragraph 5.2.1 4. If soil movement raises the grade level to cover the lower portion of the shell, what would you as the inspector look for? a) Severe external corrosion of the shell beneath the soil level b) Severe external corrosion of the shell just above the soil line c) Severe internal corrosion of the shell beneath the soil level d) Severe internal corrosion of the shell just above the soil line Reference: API-575, Paragraph 5.2.1 5. Atmospheric corrosion can occur on all external parts of a tank. During your inspection, you notice considerable damage to the protective coating and accelerated corrosion rates. What would you suspect the cause to be? a) Hydrogen and oxygen rich atmosphere b) Nitrogen and oxygen rich atmosphere c) Sulfurous or acidic atmosphere d) Carbon dioxide and nitrogen rich atmosphere Reference: API-575, Paragraph 5.2.1

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP-575 Inspection of Storage Tanks

Issue Date 03/98

Revision Date 07/00

Page 6

6. Internal corrosion in the vapor space above the liquid of crude oil and petroleum product tanks is commonly caused by _________. a) Hydrogen sulfide vapor, water vapor, caustic vapors or any combination of the three b) Hydrogen sulfide vapor, nitrogen vapors, oxygen or any combination of the three c) Hydrogen sulfide vapor, water vapor, oxygen or any combination of the three d) Hydrogen sulfide vapor, water vapor, nitrogen or any combination of the three Reference: API-575, Paragraph 5.2.2 7. Of the following, which is not a point where cracks are most likely to occur? a) Around nozzle connections b) Around rivet holes c) Bottom-to-shell connections d) In the roof rafters Reference: API-575, Paragraph 5.4 8. Why is inspection for cracking of the lower-shell-to-sketch-plate weld critical? a) This area is more susceptible to cracking because it is subjected to internal and external atmosphere b) This area is critical because in relatively large or hot tanks, it has more potential for cracking c) This area is critical because in relatively large or hot tanks, it has more potential for corrosion d) This area is critical because in relatively small or cold tanks, it has more potential for cracking Reference: API-575, Paragraph 5.4 9. Why is it important to check roof drains? a) Plugged drains can cause enough rainwater to accumulate on the roof to prevent the tank from being pumped full b) Plugged drains can cause enough rainwater to accumulate on the roof to increase the vapor pressure enough to cause the tank to rupture c) Plugged drains can cause enough rainwater to accumulate on the roof to force product out of the vents creating an environmental hazard d) Plugged drains can cause enough rainwater to accumulate on the roof to sink a pan-type or pontoon-type floating roof Reference: API-575, Paragraph 5.5

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP-575 Inspection of Storage Tanks

Issue Date 03/98

Revision Date 07/00

Page 7

Answers to API-RP-575 Section 5, Reasons for Inspection and Causes of Deterioration


Question Number 1 2 3 4 5 6 7 8 9 Answer B D A B C C D B D

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP-575 Inspection of Storage Tanks

Issue Date 03/98

Revision Date 07/00

Page 8

Section 7 Methods of Inspection and Inspection Scheduling 1. Some of the first items to inspect when conducting an internal inspection of a storage tank should be which of the following? a) The tank bottom and the annular ring plate if one is installed b) The water draw-off pipe and product drain c) The base of all roof support structures d) Overhead parts and all supports Reference: API-575, Paragraph 7.1 2. Where should the recommended inspection of overhead parts and supports be conducted from? a) A bosuns chair suspended through the roof vent after the tank has been gas freed b) The entry point or other observations points before entering the tank c) From the very center of the tank bottom with a powerful sealed beam portable light d) From ladders or scaffolding Reference: API-575, Paragraph 7.1 3. The inspector should thoroughly review __________ prior to conducting internal or external inspections. a) The repair plan and/or re-commissioning plan b) The operating history of the tank and list of products that have been in the tank c) The inspection and maintenance records d) The tank entry permit and qualification of the entry attendant Reference: API-575, Paragraph 7.1 4. When any work is being done on the outside or close to the tank, especially on the roof, during inspection ________ should be kept informed. The owner/operator The qualified person Personnel working inside the tank Personnel working under the tank Reference: API-575, Paragraph 7.1 5. When should the majority of external inspection activity be conducted? a) As soon as the tank is taken out of service and is drained b) Six months before the tank is removed from service for the internal inspection c) While the tank is being drained d) While the tank is in service Reference: API-575, Paragraph 7.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP-575 Inspection of Storage Tanks

Issue Date 03/98

Revision Date 07/00

Page 9

6. During the external in-service inspection, ladder and stair treads should be checked. What condition(s) would you be looking for? a) Missing rungs and wear b) Corrosion or broken parts c) Corrosion and missing rungs d) Tread-to-tread distance and handrail height Reference: API-575, Paragraph 7.2.1 7. Inspection of pipe connections to the tank should include bolting at flanged joints. Piping that enters the ground should be inspected at the soil-to-air interface by excavating ___ to ___ inches to permit visual and ultrasonic thickness examination. a) 18 to 24 b) 12 to 18 c) 6 to 12 d) 4 to 8 Reference: API-575, Paragraph 7.2.5 8. If during your inspection, you find distortion around a nozzle connection, what additional action would you recommend? a) All seams and the shell in this area should be examined b) All horizontal welds around the tank in the course that contains the nozzle should be examined c) All vertical welds within 36 inches of the nozzle should be examined d) An area measuring two nozzle diameters square should be examined around the nozzle Reference: API-575, Paragraph 7.2.5 9. Grounding connections should be visually checked for corrosion at the point where they enter the earth. What is the approximate total resistance from the tank to earth? a) Should not exceed 100 ohms b) Should not exceed 75 ohms c) Should not exceed 50 ohms d) Should not exceed 25 ohms Reference: API-575, Paragraph 7.2.6 10. Where would you expect to find paint blisters? a) On the roof and on the side of the tank on the north side b) On the roof and on the side of the tank subjected to mist over-spray from cooling towers c) On the roof and on the side of the tank adjacent to another tank d) On the roof and on the side of the tank receiving the most sunlight Reference: API-575, Paragraph 7.2.7

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP-575 Inspection of Storage Tanks

Issue Date 03/98

Revision Date 07/00

Page 10

11. Why is it recommended that inspectors not walk on insulated roof? a) The inspector may damage the insulation b) The insulation may contain hazardous substances c) The roof plates may not be strong enough to support the inspectors weight d) The inspector may cause indentations in the insulation where water can collect Reference: API-575, Paragraph 7.2.8 12. The inspector finds corrosion during the shell inspection and requires ultrasonic thickness measurements to be taken. How many measurements would normally be taken? a) At least one thickness measurement on each shell ring b) At least two thickness measurements on each shell ring c) At least three thickness measurements on each shell ring d) At least one thickness measurement in the immediate area of the corrosion Reference: API-575, Paragraph 7.2.9.1 13. In obtaining shell thickness measurements, special attention should be given to the upper __ inches of un-coated shells of floating-roof tanks. a) Twelve b) Twenty-four c) Eighteen d) Thirty-six Reference: API-575, Paragraph 7.2.9.1 14. Where would you expect to find caustic stress corrosion cracking (caustic embrittlement) during an inspection of a storage tank used to store amine? a) At the liquid to vapor interface b) At the roof supports on the tank bottom c) Around connections for internal heating coils or units d) At the shell-to-bottom connection Reference: API-575, Paragraph 7.2.9.3 15. What should be done if an indication of leakage through a crack is discovered on an inservice tank? a) A soft patch should be applied over the crack and the area observed for 24 hours b) It may be possible to caulk the crack to stop the leakage c) The tank shall immediately be removed from service, drained, opened, and repaired d) The tank should be removed from service as soon as possible and a complete inspection with subsequent repairs made Reference: API-575, Paragraph 7.2.9.5

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP-575 Inspection of Storage Tanks

Issue Date 03/98

Revision Date 07/00

Page 11

16. Welded tanks that have significant distortions may cause the weld seams to be overstressed. In addition to the bottom-to-shell joint, what other welds are susceptible to cracking? a) Horizontal shell seams b) Vertical shell seams c) Wind girder attachment welds d) Reinforcement pad peripheral welds Reference: API-575, Paragraph 7.2.9.5 17. When a tank is of welded construction and has significant distortion, weld seams may crack. When cracking is suspected, what is the preferred method of nondestructive examination? a) Radiography b) Ultrasonic c) Liquid Penetrant d) Magnetic Particle Reference: API-575, Paragraph 7.2.9.5 18. When conducting a tank roof inspection on a floating roof, in addition to the recommendation that the inspector walk on weld seams, what other precaution should be taken? a) The tank should be empty and the roof siting on the lower support stops b) The roof should be in the high-gauge position if volatile liquid is in the tank c) Inert gas should be applied under the roof if volatile liquid is in the tank d) The roof vent(s) should be plugged to prevent vapor escape while the inspector is on the roof Reference: API-575, Paragraph 7.2.10 19. External corrosion on roof surfaces will usually be most severe at depressions where water can remain until it evaporates. a) True b) False Reference: API-575, Paragraph 7.2.10 20. Which of the following is the correct procedure for pressure testing roof drain lines and joints? a) First test at about 1.5 times design pressure for approximately hour then reduce pressure to design pressure and hold for another hour b) First test at about 15 psi for approximately hour then reduce pressure to 5 psi and hold for another hour c) First test at about 30 psi for approximately hour then reduce pressure to 5 psi and hold for another hour d) First test at about 3.0 times design pressure for approximately hour then reduce pressure to design pressure and hold for another hour Reference: API-575, Paragraph 7.3.3
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API RP-575 Inspection of Storage Tanks

Issue Date 03/98

Revision Date 07/00

Page 12

21. In conducting a preliminary internal visual inspection, what is the recommended sequence of the inspection? a) The bottom, shell, internal supports, and roof in that order b) The shell, bottom, internal supports, and roof in that order c) The internal supports, roof, shell, and bottom in that order d) The roof, internal supports, shell, and bottom in that order Reference: API-575, Paragraph 7.4.2 22. An inspector should be aware of the possibility of accumulation of dry pyrophoric deposits that could ignite during the inspection. What should be done with these deposits if they can not be removed prior to the inspection? a) These deposits should be kept moist b) These deposits should be kept dry c) These deposits should be covered with foam d) These deposits should be left alone and the inspector should stay at least 12 feet from them Reference: API-575, Paragraph 7.4.2 23. Where would you expect to find significant internal corrosion in a tank in sour refinery fluid service? a) On the surfaces of the bottom plates b) In vapor space above the stored liquid c) Adjacent to the product drain nozzle d) Adjacent to the manway entrance nozzle Reference: API-575, Paragraph 7.4.3 24. Caustic stress corrosion cracking (caustic embritlement) is prevalent when the temperature rises above ____F. a) 100 b) 125 c) 150 d) 175 Reference: API-575, Paragraph 7.4.3 25. When the statistical methods are used to assess the probable condition of a tank bottom, what is the typical amount of the floor that should be randomly scanned? a) 30 to 50 percent b) 20 to 30 percent c) 10 to 20 percent d) 5 to 10 percent Reference: API-575, Paragraph 7.4.4

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API RP-575 Inspection of Storage Tanks

Issue Date 03/98

Revision Date 07/00

Page 13

26. Tanks with a bottom angle between the shell and the bottom should be checked for cracks in the shell adjacent to any welded butt joints in this angle. What method of examination should be used? a) Ultrasonic or radiography b) Liquid penetrant or magnetic particle c) Eddy current or acoustic emission d) Light diesel oil or vacuum box Reference: API-575, Paragraph 7.4.5 27. To test for leaks through shell plates, sometimes a penetrating oil can be sprayed or brushed on one side and the other side observed for leakage. What period of time might be required to conduct this type of test? a) 48 hours b) 36 hours c) 24 hours d) 72 hours Reference: API-575, Paragraph 7.4.6 28. API-575 discusses several methods of inspecting the bottoms of tanks that are resting on pads or on the soil. The methods require a temporary clay dam to be placed around the outside of the tank bottom. Which of the following is not one of the methods discussed? a) Cover the inside surface with a soap solution and inject air at not more than 3 inches of water pressure under the tank b) Inject a solution of light diesel oil under the tank at a pressure not more that 3 psi and observe the tank bottom from the inside for wicking of the oil c) Pump about 6 inches of water into the tank and then place air at not more than 9 inches of water pressure under the tank d) Pump water under the tank to depth of about 6 inches above the level of the highest point of the tank bottom and holding the water with the clay dam Reference: API-575, Paragraph 7.4.6 29. Atmospheric tanks that are designed for not more than 0.5 psig over the static pressure of the liquid contained in the tank are normally tested: a) By filling the tank with the liquid to be stored b) By filling the tank with an inert gas c) By filling the tank with water d) By filling the tank with a soap solution Reference: API-575, Paragraph 7.5 30. What should be the deciding factor(s) in determining the need for tank repair or renewal? a) Structural integrity and leak avoidance b) Economics c) Age of the tank d) Product stored in the tank Reference: API-575, Paragraph 7.6
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API RP-575 Inspection of Storage Tanks

Issue Date 03/98

Revision Date 07/00

Page 14

Answers to API-RP-575 Section 7, Reasons for Inspection and Causes of Deterioration


Question Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Answer D B C C D B C A D D C A B C D B D B A C D A B C D B C B C A

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 1

WELDING REQUIREMENTS 1. Of the following, which best defines Butt Joint. a) b) c) d) A joint between two members aligned within 30 of the same plane A joint between two members aligned in approximately the same plane. A joint between two members aligned within 45 of the same plane A joint between two members aligned at any angle less than 90

REF: Section IX, QW-492 2. ASME Section IX defines a corner joint as which of the following? a) b) c) d) A joint between two members located approximately at right angles to each other. A joint created by welding from around the outer edge of a rectangular vessel A joint made up of two members aligned within 30 or less from centerline A joint made up of two members aligned within 60 or more from centerline

REF: Section IX, QW-492 3. Define fillet weld. a) A weld used to fill the root of a butt weld b) A weld of approximately rectangular cross section joining two members in approximately the same plane c) A weld of approximately triangular cross section joining two surfaces approximately at right angles to each other in a lap joint, tee joint or corner joint. d) A weld of approximately trapezoidal cross section joining two surfaces approximately at right angles to each other in a dimpled vessel plug joint REF: Section IX, QW-492 4. How does ASME Section IX, Welding Qualifications, defines groove weld? a) A weld made in a groove formed with a single member or in the groove between two members to be joined. b) A weld of approximately triangular shape used to join two members at an angle of up to 90 c) A weld only used in boiler construction d) A weld that may only be made using the Shielded Metal Arc Welding process REF: Section IX, QW-492

API-510 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 2

5. Of the following which is not listed as a standard type of groove weld? a) b) c) d) Single Vee groove weld Single-U groove weld Double-Vee groove weld Double-flare-barrel groove weld

REF: Section IX, QW-492 6. In what Article of Section IX are general requirements found? a) b) c) d) Article I Article II Article III Article IV

REF: Section IX, Introduction 7. Welding procedure requirements are located in which Article of ASME Section IX? a) b) c) d) Article I Article II Article III Article IV

REF: Section IX, Introduction 8. In what Article of Section IX are requirements for performance qualifications found? a) b) c) d) Article I Article II Article III Article IV

REF: Section IX, Introduction 9. In what Article of Section IX is the welding data found? a) b) c) d) Article I Article II Article III Article IV

REF: Section IX, Introduction 10. Section IX provides information on how to weld? a) True b) False REF: Section IX, Introduction
API-510 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 3

11. What is the purpose of the Welding Procedure Specification (WPS) and the Procedure Qualification Record (PQR)? a) The purpose of the WPS and PQR is to determine that the weldment, proposed for construction, is capable of having the required properties for its intended application. b) The purpose of the WPS and PQR is to determine the welders or welding operators ability to deposit sound welds c) The purpose of the WPS and PQR together is to provide direction to the welder d) The purpose of the WPS and PQR is to design the welded joint prior to welding REF: Section IX, Introduction, QW-100.1 12. One purpose of qualifying a WPS is to establish the skill of the personnel performing the welding? (True or False) a) True b) False REF: Section IX, Introduction 13. What is the purpose of qualifying welders? a) b) c) d) To determine their ability to follow the instructions in the WPS To determine their ability to follow the instructions in the PQR To determine their ability to deposit sound metal. To determine their ability to react to fabrication change

REF: Section IX, Introduction 14. What is the purpose of qualifying a welding operator? a) b) c) d) To determine their ability to follow the instructions in the WPS To determine their ability to follow the instructions in the PQR To determine their ability to deposit sound metal. To determine their ability to operate the welding equipment

REF: Section IX, Introduction 15. What is the intent of the WPS? a) b) c) d) To provide direction to the welder or welding operator To provide direction to the fabrication supervisor To qualify the welding to be used in production To determine the ability of the welder to deposit sound weld metal

REF: Section IX, QW-100.1

API-510 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 4

16. Under what conditions may welding procedures qualified prior to 1962 be used on new Code vessels? a) WPSs, PQRs, and WPQs made in accordance with the requirements of Section IX prior to 1962 are not permitted in new construction b) WPSs, PQRs, and WPQs made in accordance with the requirements of Section IX prior to 1962, in which all requirements of the 1962 Edition or later Editions are met, may be used. c) WPSs, PQRs, and WPQs made in accordance with the requirements of Section IX prior to 1962, may be used provided they are brought up to date with the latest edition of Section IX d) WPSs, PQRs, and WPQs made in accordance with the requirements of Section IX prior to 1962 may be used only if they meet the requirements of the 1972 Edition or later Editions REF: Section IX, QW-100.3 17. Flat position with the plate in the horizontal plane and the weld metal deposited from above is the description given in Section IX for which welded plate position? a) b) c) d) 4G Position 3G Position 2G Position 1G Position

REF: Section IX, QW-121.1 18. Horizontal position with the plate in a vertical plane and the axis of the weld is horizontal is the description given in Section IX for which welded plate position? a) b) c) d) 4G Position 3G Position 2G Position 1G Position

REF: Section IX, QW-121.2 19. Vertical position with the plate in a vertical plane with the axis of the weld vertical is the description given in Section IX for which welded plate position? a) b) c) d) 4G Position 3G Position 2G Position 1G Position

REF: Section IX, QW-121.3

API-510 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 5

20. Overhead position with the plate in a horizontal plane with the weld deposited from underneath is the description given in Section IX for which welded plate position? a) b) c) d) 4G Position 3G Position 2G Position 1G Position

REF: Section IX, QW-121.4 21. Flat position with the axis of the pipe horizontal and the pipe is rolled during welding so that the weld metal is deposited from above, is the description given in Section IX for which welded pipe position? a) b) c) d) 1G Position 2G Position 5G Position 6G Position

REF: Section IX, QW-122.1 22. Horizontal position with the axis of the pipe vertical and the axis of the weld in a horizontal plane. The pipe shall not be rotated during welding. a) b) c) d) 1G Position 6G Position 5G Position 2G Position

REF: Section IX, QW-122.2 23. A multiple position qualification with the axis of the pipe horizontal and the welding groove in a vertical plane; welding shall be done without rotating the pipe. This is a description of which welded pipe position? a) b) c) d) 5G Position 2G Position 1G Position 6G Position

REF: Section IX, QW-122.3

API-510 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 6

24. A multiple position qualification with the axis of the pipe 45 to the horizontal; welding shall be done without rotating the pipe. This is a description of which welded pipe position? a) b) c) d) 1G Position 2G Position 5G Position 6G Position

REF: Section IX, QW-122.4 25. What do tension tests determine in procedure qualification of groove welds? a) b) c) d) Tension tests are used to determine the overall ductility of the welded joint Tension tests are used to determine the notch toughness of the welded joint Tensile tests are used to determine the ultimate strength of groove weld joints Tension tests are used to determine the hardness of the weld and base metal

REF: Section IX, QW-141.1 26. What do guided bend tests determine in procedure qualification of groove welds? a) b) c) d) Bend tests are used to determine the size, soundness, and contour of the weld Bend tests are used to determine the soundness and ductility of groove weld joints Bend tests are used to determine the ultimate strength of groove weld joints Bend tests are used to determine the notch toughness of the weldment

REF: Section IX, QW-141.2 27. When performing tension tests for procedure qualifications on thicknesses greater than 1, multiple specimens are always required. a) True b) False REF: Section IX, QW-151.1(b) 28. When performing tension tests for procedure qualifications on pipe with an outside diameter of ___ or less, a full section specimen may be used. a) b) c) d) 9 inches 6 inches 4 inches 3 inches

REF: Section IX, QW-151.4

API-510 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 7

29. Which of the following is not an acceptance criteria for tension tests for procedure qualifications? The specimen shall have a tensile strength that is not less than: a) The specified minimum tensile strength of the base metal. b) The specified minimum tensile strength of the weaker of the two if the two metals of different strengths are used. c) The specified minimum yield strength of the weld metal when the applicable Section provides for the use of weld metal having lower room temperature strength than the base metal. d) If the specimen breaks in the base metal outside the weld or fusion line, the test shall be accepted as meeting the requirements provided the strength is not more than 5% below the specified minimum tensile strength. REF: Section IX, QW-153.1 30. Define transverse side bend. a) The weld is transverse to the longitudinal axis of the specimen, which is bent so that one of the side surfaces becomes the convex surface of the bent specimen. b) The weld is transverse to the longitudinal axis of the specimen, which is bent so that one of the side surfaces becomes the concave surface of the bent specimen. c) The weld is transverse to the circumferantial axis of the specimen, which is bent so that one of the side surfaces becomes the convex surface of the bent specimen. d) The weld is parallel to the longitudinal axis of the specimen, which is bent so that one of the side surfaces becomes the convex surface of the bent specimen. REF: Section IX, QW-161.1 31. Define transverse face bend. a) The weld is parallel to the longitudinal axis of the specimen, which is bent so that the face surface becomes the convex surface of the bent specimen. b) The weld is transverse to the longitudinal axis of the specimen, which is bent so that the face surface becomes the convex surface of the bent specimen. c) The weld is transverse to the longitudinal axis of the specimen, which is bent so that the face surface becomes the concave surface of the bent specimen. d) The weld is transverse to the circumferential axis of the specimen, which is bent so that the face surface becomes the convex surface of the bent specimen. REF: Section IX, QW-161.2 32. In a transverse root bend, the weld is transverse to the longitudinal axis of the specimen, which is bent so that the root surface becomes the convex surface of the bent specimen. a) True b) False REF: Section IX, QW-161.3
API-510 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 8

33. Open defects not exceeding ___ inches, measured in any direction on the convex surface of the specimen after bending, are acceptable criteria for guided bend tests? a) b) c) d) 1/64th 1/32nd 1/16th 1/8th

REF: Section IX, QW-163 34. In guided bend test acceptance criteria, open defects on the corners of the specimen during testing: a) Shall be reason to reject the test b) Shall not be considered unless there is definite evidence that they result from internal defects c) Shall not be considered unless there is definite evidence that they result from external defects d) Shall not be considered unless there is definite evidence that they exceed 3/16th inch dimension in any direction REF: Section IX, QW-163 35. Where are the acceptance criteria for radiographic examination for welder qualifications found in Section IX? a) b) c) d) QW-321.2 QW-302.2 QW-191 Welders may not be qualified using radiographic examination

REF: Section IX, QW-191.2.2 36. A welder qualifies by radiography on a 3/8 coupon. A 3/16 slag inclusion is shown on the radiograph. Is the welder qualified? Why or why not? a) b) c) d) No, the maximum slag inclusion allowed for this thickness is 1/8 Yes, slag inclusions are not to be considered in qualification No, slag inclusion of any dimension is reason for qualification failure Yes, the maximum slag inclusion allowed for this thickness is

REF: Section IX, QW-191.2.2(a)(2)

API-510 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 9

37. A welder qualifies by radiography on a 1 coupon. A slag inclusion is shown on the radiograph. Is the welder qualified? Why or why not? a) b) c) d) No, the maximum slag inclusion allowed for this thickness is 1/8t or 1/8 Yes, slag inclusions are not to be considered in qualification No, slag inclusion of any dimension is reason for qualification failure Yes, the maximum slag inclusion allowed for this thickness is 1/3t or 1/3

REF: Section IX, QW-191.2.2(a)(2) 38. In qualifying a welder by radiography on a 1 1/4" thick coupon, a 1/4" length crack is shown. Would this be acceptable? a) Yes, the maximum length of crack or zone of incomplete fusion for this thickness is 1/3t or 1/3 b) No, any type of crack or zone of incomplete fusion or penetration is unacceptable c) Yes, the maximum length of crack or zone of incomplete fusion for this thickness is d) No, the maximum length of crack or zone of incomplete fusion for this thickness is 1/8t or 1/8 REF: Section IX, QW-191.2.2(a)(2) 39. Define a linear indication as it relates to welder qualification by radiography. a) b) c) d) A linear indication is one in which the length is more than 2 times the width A linear indication is one in which the length is more than 3 times the width A linear indication is one in which the length is more than 4 times the width A linear indication is one in which the length is more than 5 times the width

REF: Section IX, QW-191.2.1 40. Where would you find the acceptance standards for welding operators who qualify by radiography on production welds? a) b) c) d) QW- 191.2.2 QW-304.1 Referencing Code Section Referencing Repair Code

REF: Section IX, QW-191.2.3

API-510 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 10

41. Of the following, which best defines a Welding Procedure Specification (WPS). a) A written document that outlines the extent of production welding b) A written qualified document that certifies the welder is capable of producing sound welds in production c) A written qualified welding procedure prepared to provide direction to the welder/welding operator to assure compliance with the Code requirements d) A written document that must be available to the welder which details the methods used in qualifying the welding procedure REF: Section IX, QW-200.1(a) 42. Who is responsible for preparing written Welding Procedure Specifications? a) Each manufacturer and contractor shall prepare written WPSs b) Each owner/operator shall prepare written WPSs to be used in the fabrication of their vessel, tank, piping system, or boiler c) Each Authorized Inspector shall prepare written WPSs to be used by a manufacturer d) Each welding supervisor shall prepare written WPSs to be used by the welders he/she supervises Ref: Section IX, QW-200.1 43. The completed WPS shall describe all but which of the following? a) b) c) d) Essential Variables Welder's Essential Variables Supplemental Essential Variable, when required Non-Essential Variables

Ref: Section IX, QW200.1(b) 44. According to ASME Section IX, the WPS shall be supported by and make reference to which of the following documents? a) b) c) d) The manufacturer's design drawings and calculations The Welder's Performance Qualification Record (WPQR) The Procedure Qualification Record (PQR) The Welding Process Guide (WPG)

Ref: Section IX, QW-200.1(b)

API-510 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 11

45. Changes to a WPS require re-qualification when all but which of the following changes are made? a) b) c) d) Changes to Supplemental Essential Variables (when they are required) Changes to Essential variables Changes of a Non-Essential Variable to suit production Any change affecting the ability of the weldment to meet Code requirements

Ref: Section IX, QW-200.1(c) 46. A record of the welding data used to test a welded test coupon is a definition of which of the following documents? a) b) c) d) Procedure Qualification Record Welders Performance Qualification Record Welding Procedure Specification Process Qualification Record

REF: Section IX, QW-200.2(a) 47. Those in which a change, as described in the specific variables, is considered to affect the mechanical properties of the weldment and shall require re-qualification of the WPS. This is a definition of what type of welding variable? a) b) c) d) Supplemental Essential Variable Essential Variable Non-Essential Variable Supplemental Non-Essential Variable

REF: Section IX, QW-251.2, QW-401.1 48. Those in which a change, as described in the specific variables, may be made to the WPS without re-qualification. This is a definition of what type of variable a) b) c) d) Supplemental Essential Variable Essential Variable Non-Essential Variable Supplemental Non-Essential Variable

REF: Section IX, QW-251.3, QW-401.4 49. A change in a welding condition which will affect the notch-toughness properties of the weldment. a) b) c) d) Supplemental Non-Essential Variable Essential Variable Non-Essential Variable Supplemental Essential Variable

REF: Section IX, QW-251.2, QW-401.3


API-510 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 12

50. Which of the following is not required to be addressed on the WPS? a) b) c) d) Essential Variables Manufacturer of the welding equipment used in the welding process Procedure Qualification Record identification Non-Essential Variable

REF: Section IX, QW-200.1(b) 51. What information must be contained in the PQR? a) b) c) d) All Non-Essential Variables All recorded variables (including ranges) used during the welding of the test coupon. Instructions to the welder All recorded variable (including ranges) to be used during production welding

REF: Section IX, QW-200.2(b) 52. A change in a non-essential variable requires re-qualification of the procedure. a) True b) False REF: Section IX, QW-200.1(c) 53. Changes to non-essential variables of a WPS, to suit production requirements, without requalification must be documented with respect to the essential, non-essential, and where required, supplementary variables for each process. This may be by amendment to the WPS or by the use of a new WPS. a) b) c) d) The changes must be documented on a revised PQR The changes do not need to be documented Concurrence of the Authorized Inspector must be obtained and documented This may be by amendment to the WPS or by the use of a new WPS

REF: Section IX, QW-200.1(c) 54. If a variable is not monitored during the welding of the test coupon, must it be recorded on the PQR? a) b) c) d) It shall be recorded on the PQR All variables monitored or not shall be recorded on the PQR It shall not be recorded on the PQR It shall be recorded in the fabrication guidelines

REF: Section IX, QW-200.2(b)

API-510 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 13

55. It is the intent of Section IX that the full range of variables to be used in production be qualified? a) True b) False REF: Section IX, QW-200.2(b) 56. Who is required to certify the PQR? a) b) c) d) The PQR shall be certified by the Authorized Inspector The PQR shall be certified by the owner/user The PQR does not require certification The PQR shall be certified by the manufacturer or contractor.

REF: Section IX, QW-200.2(b) 57. What type of changes are permitted to a PQR a) b) c) d) No change of any type is permitted Editorial corrections or addenda to the PQR are permitted. Only changes such as the welders name The manufacturer can change the PQR to meet production requirements

REF: Section IX, QW-200.2(c) 58. Which of the following changes to a PQR require re-qualification? a) b) c) d) All changes Only editorial changes dealing with "A" Numbers Only editorial changes dealing with "P" Number Only changes caused by Code revisions.

REF: Section IX, QW-200.2(b) 59. Which of the following is an example of an editorial change to a PQR. a) Section IX adopts a new F-No., which may allow the manufacturer to expand the use of filler metals within that F-No. b) A change to correct an assignment of an incorrect P-No., F-No., or A-No. c) Change to the actual thickness of the weld test coupon d) Change in the welding process used to weld the test coupon REF: Section IX, QW-200.2(c)

API-510 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 14

60. Which of the following is an example of an addendum to a PQR. a) Section IX adopts a new F-No., which may allow the manufacturer to expand the use of filler metals within that F-No. b) A change to correct an assignment of an incorrect P-No., F-No., or A-No. c) Change to the actual thickness of the weld test coupon d) Change in the welding process used to weld the test coupon REF: Section IX, QW-200.2(c) 61. The PQR shall be available, upon request, to which of the following? a) b) c) d) The welder performing the production welds The welding supervisor in charge of fabrication The Authorized Inspector The jurisdiction where the vessel, tank, piping system, or boiler will be located

REF: Section IX, QW-200.2(e) 62. The PQR must be available to the welder or welding operator? a) True b) False REF: Section IX, QW-200.2(e) 63. Based on process alone, and assuming all other variables are addressed correctly, how many welding procedures may be written from a multi-process PQR qualified using GTAW and SMAW? a) b) c) d) Only one for the combined processes Two, one for GTAW and one for SMAW Three one for each process and one for the combined processes Four two for each process

REF: Section IX, QW-200.2(f), QW-200.4(a) 64. More than one PQR may be used to qualify a single WPS? a) True b) False REF: Section IX, QW-200.2(f)

API-510 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 15

65. Can a single PQR support more than one WPS? a) Yes b) No REF: Section IX, QW-200.2(f) 66. A procedure qualified for the root deposit only on a thick coupon may be used to support a WPS for: a) b) c) d) Base metal that is not more than thick Procedures can only support a single WPS Base metal thickness with a maximum thickness of 1 Any thickness of base metal

REF: Section IX, QW-200.4(b) 67. A procedure qualified for the root deposit only in which weld metal is deposited may be used to deposit ___ thickness of weld metal in production? a) b) c) d) 5/8th inch inch inch 9/16th inch

REF: Section IX, QW-200.4(b) 68. Qualification for groove welds qualifies for all fillet welds except which of the following? a) b) c) d) Some P-34 metals Some P-45 metals Some P-8 metals Some P-11 metals

REF: Section IX, QW-202.2(c) 69. Can a procedure qualified on plate be used to weld on pipe in production? a) Yes b) No REF: Section IX, QW-211

API-510 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 16

70. What paragraph in Section IX allows simultaneous qualification of welders? a) b) c) d) QW-300.1 QW-300.2 QW-300.3 QW-304

REF: Section IX, QW-300.3 71. During simultaneous qualification of welders, each participant organization must have _______ present? a) b) c) d) An employee who is responsible for welder performance qualification An Authorized Inspector representing the inspection agency A member of upper management A primary welder and a back-up welder

REF: Section IX, QW-300.3 72. During simultaneous qualification of welders, each WPS to be used by each participating organization must be identical for all the essential except for which of the following? a) b) c) d) P - Numbers F Numbers A Number Preheat and Postweld Heat Treatment

REF: Section IX, QW-300.3) 73. Welders making welds using all but which of the following SMAW, GTAW, SAW, and GMAW (except the short-circuiting mode) may be qualified using radiography? a) b) c) d) SMAW GTAW SAW GMAW short circuiting mode

Ref. Section IX, QW- 304 74. Welders qualifying using the SAW process may be qualified by radiography except when using which of the following? a) b) c) d) P-2X Metals P-8 Metals P-4X Metals P-2 Metals

Ref. Section IX, QW- 304


API-510 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 17

75. When a welders test coupon fails by radiography, how is the welder re-tested? a) b) c) d) The immediate re-test shall be by visual examination The immediate re-test shall be by radiography The immediate re-test shall be by mechanical testing The immediate re-test shall be by both mechanical testing and radiography

Ref. Section IX, QW- 321.3 76. When a welder fails a qualification test, by mechanical tests (bends), an immediate re-test may be performed using radiography. a) True b) False Ref. Section IX, QW- 321.2 77. How does a welder maintain his or her qualification in a particular process? a) b) c) d) The welder must use the process in Code construction at least once every 12 months The welder must use the process in Code construction at least once every 6 months The welder must use the process at least once every 12 months The welder must use the process at least once every 6 months

Ref. Section IX, QW- 322 78. Of the following, which is not a requirement for a welder whose qualifications have expired due to time limitations? Renewal of qualification may be made for any process by welding a single test coupon: a) b) c) d) In any position Testing of the coupon must be by radiography In either plate or pipe Of any material, thickness or diameter

Ref. Section IX, QW-322.2(a) 79. Which of the following is a true statement regarding welder/welding operator variables? a) Essential, Non-Essential and Supplemental Essential variables shall be addressed on the Welder/Welding Operator Performance Qualification (WPQ) b) Only Non-Essential and Supplemental Essential variables shall be addressed on the Welder/Welding Operator Performance Qualification (WPQ) c) Only Essential variables shall be addressed on the Welder/Welding Operator Performance Qualification (WPQ) d) Only the variables listed in the manufacturers design drawing and/or engineering design need to be addressed Ref. Section IX, QW-351
API-510 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 18

80. Which of the following is the most correct definition for P Numbers? a) P Number assignments are based on comparable base metal characteristics such as chemical composition, mechanical properties, and weldability b) P Number assignments are based on identical base metal characteristics such as chemical composition, and weldability c) P Number assignments are based on comparable base metal characteristics such as mechanical properties, and weldability d) P Number assignments are based on comparable base metal characteristics such as chemical composition and mechanical properties Ref. Section IX, QW- 200.3, and QW-420.1 81. Define F Number a) F - numbers are based on the usability characteristics of the base metal and the electrode b) F - numbers are based on the mechanical characteristics of the electrode c) F - numbers are based on the chemical composition of the electrode d) F - numbers are based on the usability characteristics of the electrode Ref. Section IX, QW- 431 82. What is an A Number? a) The identification of base metal, for ferrous metals, based on chemical analysis of the as-poured metal. b) The identification of weld metal, for ferrous metals, based on chemical analysis of the as-deposited metal. c) The identification of base metal, for non-ferrous metals, based on chemical analysis of the as-poured metal. d) The identification of weld metal, for non-ferrous metals, based on chemical analysis of the as-deposited metal. Ref. Section IX, QW- 441 83. An SMAW WPS specifies an amperage range of 50 300 amps for E-7018 electrodes. The welder wants to use 400 amps to weld a groove. What, if anything, must be done to the WPS? a) b) c) d) The WPS must be re-qualified? The WPS shall be re-qualified and revised Nothing is required since amperage is not an essential variable The WPS must be revised

Ref. Section IX, QW- 200.1(c) and QW-253

API-510 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 19

84. A SAW welding operator is attempting to qualify by radiography on a 6 thick test coupon. Elongated slag inclusions are measured to be 0.625 long. Is the operator qualified? a) b) c) d) Yes, slag inclusions are less than No, slag inclusions exceed No, slag inclusions exceed Yes, slag inclusions up to 1/3t are permitted

Ref. Section IX, QW- 191.2.2(a)(2)(c) 85. May a welder, qualified on a 2G plate coupon with SMAW, make a 6 circumferential pipe weld in the horizontal position using the SMAW process? (Assume no F or P Number changes) a) b) c) d) No, qualification on plate only qualifies for welding on plate Yes, qualification on plate in the 2G position also qualifies on pipe 2 7/8 and over No, Welder is only qualified for pipe over 24 diameter Yes, qualification on plate in the 2G position also qualifies on pipe 2 7/8 and over

Ref. Section IX, QW- 461 86. A repair organization has a WPS, which states it is qualified for P-8 to P-8 material welded with either E308, E309, or E316 electrodes (SMAW process). The PQR supporting this WPS states the weld test coupons were SA-240 Type 304L material, welded with E308 electrodes. Is the WPS properly qualified for the base material listed? a) b) c) d) No, SA-240 Type 304L is not P-8 Material Yes, SA-240 Type 304L is P-11 Material No, SA-240 Type 304L is P-11 Material Yes, SA-240 Type 304L is P-8 Material

Ref. Section IX, QW- 420.1 and QW/QB-422 87. A groove weld WPS is qualified using an 8 thick test coupon. The testing equipment, for tensile and bend tests, is only capable of accepting maximum size 1.5 X 1.5 specimens. Only one welding process, F-Number, and base metal was used. How many tensile specimens are required? (Assume the minimum number of tests are performed.) a) Six strips, of approximately equal dimensions, are required 8 1.5 = 5.33 coupons. Since the minimum number of tests are performed, 6 X 4 = 24 Tension tests b) Six strips, of approximately equal dimensions, are required 8 1.5 = 5.33 coupons. Since the minimum number of tests are performed, 6 X 6 = 36 Tension tests c) Six strips, of approximately equal dimensions, are required 8 1.5 = 5.33 coupons. Since the minimum number of tests are performed, 6 X 2 = 12 Tension tests d) Six strips, of approximately equal dimensions, are required 8 1.5 = 5.33 coupons. Since the minimum number of tests are performed, 6 X 1 = 6 Tension tests Ref. Section IX, QW- 151.1 and QW- 451
API-510 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 20

88. May an individual using the Automatic SAW process be qualified by radiography on a 6 production weld and meet Section IX requirements? a) b) c) d) No, qualification by RT requires at least 2 feet of production weld. No, qualification by RT requires at least 1 foot of production weld. No, qualification by RT requires at least 3 feet of production weld. No, qualification by RT requires at least 6 feet of production weld.

Ref. Section IX, QW- 305.1 89. A welder is qualified in the 2G position on plate with backing, using GTAW process, the welder is also qualified to use which of the following positions? a) b) c) d) Pipe groove welds in the F and H position Plate Groove welds in the H and V positions Plate or pipe over 24 OD Groove welds in the F and V positions Plate Groove welds in the V position

Ref. Section IX, QW- 461.9 90. May a welder, qualified in the 2G position of thick plate, weld a 1 outside diameter pipe, thick in the horizontal position without re-qualification? a) Yes b) No Ref. Section IX, QW- 403.16 91. A welder may deviate from the parameters specified in a WPS if they are a non-essential variable. a) True b) False Ref. Section IX, QW- 200.1 92. May a welder, who is qualified using a double groove weld, make a single V-groove weld without backing with out re-qualification? a) b) c) d) Yes, the welder is qualified with or without backing No, the welder welded the second side of the weld with backing in qualification Yes, backing is not a welders variable Yes, the type of joint is not a welders variable

Ref. Section IX, QW- 402.2

API-510 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 21

93. A welder qualified with a P-1 test coupon (using SMAW E7018 electrodes). May the welder weld P-4 material using E-8028 electrodes in production (Assume the P-4 procedure using E-8028 electrodes has been qualified). a) b) c) d) No, the welder is only qualified to weld P-1 to P-1 material No, the welder must requalify using a WPS for P-1 to P-4 Yes, P numbers are not a welders variable Yes, qualification with P-1 also qualifies through P-11

Ref. Section IX, QW- 403.18 and QW-423.1 94. Under what conditions does the inspector have the right to call for re-qualification of welders or welding operators? a) When there is a specific reason to question the welder's/welding operator's ability to make welds that meet the specification, all of the welders qualifications shall be revoked b) When there is a specific reason to question the welder's/welding operator's ability to make welds that meet the specification, the welders qualification supporting the welding in question shall be extended an additional three hours. All other qualifications not questioned remain in effect. c) When there is a specific reason to question the welder's/welding operator's ability to make welds that meet the specification, the qualification supporting the welding in question shall be revoked. All other qualifications not questioned remain in effect. d) When there is a specific reason to question the welder's/welding operator's ability to make welds that meet the specification, the welder shall be given the opportunity to regain his/her composure and re-weld the joint. Ref. Section IX, QW- 322(b) 95. In order for a welder to be qualified for all positions in pipe welding, what minimum positions must he or she qualify in? a) b) c) d) 5G and 1G 5G and 2F 5G and 1G 5G and 2G

Ref. Section IX, QW- 303 and QW-461.9 96. In performance qualification of pipe groove welds, which positions require more than two guided bend tests for qualification? a) b) c) d) 5G or 6G 5G and 2G 5G or 2G 5G and 2F

Ref. Section IX, QW- 452, footnote 4


API-510 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 22

97. Does qualification on groove weld qualify a welder for any size, diameter and thickness of fillet weld? a) Yes b) No Ref. Section IX, QW- 303.1 98. A welder is qualified in the 5G pipe position. This welder is also qualified for all but which of the following? a) b) c) d) All positions of fillet welds SP, F F, H F, V, O

Ref. Section IX, QW- 461.9 99. Groove design is an essential variable for the SMAW, SAW, GMAW, and GTAW processes. a) True b) False Ref. Section IX, QW- 253, 254, 255, & 256 100. SMAW procedure is qualified with backing. May the WPS indicate welding with or with out backing? a) Yes b) No Ref. Section IX, QW- 253 101. When are group numbers required to be documented on the WPS, for an SMAW or a GTAW procedure? a) b) c) d) Group numbers are never addressed on a WPS Group numbers are only addressed on a PQR When hardness tests are required When impact testing is required

Ref. Section IX, QW- 253 & 256

API-510 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 23

102. An SMAW procedure is qualified using a coupon, thick. What is the widest base metal thickness range that can be listed on the WPS? a) b) c) d) 1/16 to 1 3/16 to 8 3/16 to 1 1/16 to 8

Ref. Section IX, QW- 253 & 451.2 103. A GMAW procedure is qualified using a coupon, 3/4 thick. What is the widest base metal thickness range that can be listed on the WPS? a) b) c) d) 1/16 to 1 3/16 to 1 1/16 to 8 3/16 to 8

Ref. Section IX, QW- 255 & 451.2 104. An SMAW procedure is qualified using a coupon 1 thick. What is the widest base metal thickness range that can be listed on the WPS? a) b) c) d) 1/16 to 2 3/16 to 4 1/16 to 4 3/16 to 2

Ref. Section IX, QW- 253 & 452.1 105. An SAW procedure is qualified using a coupon, 1 1/2 thick. What is the widest base metal thickness range that can be listed on the WPS? a) b) c) d) 3/16 to 8 1/16 to 8 3/16 to 3 1/16 to 3

Ref. Section IX, QW- 254 & 452.1 106. An SMAW procedure qualified using P-8 material may be used to weld a P-1 to P-8 weld provided all other variables are the same. a) True b) False Ref. Section IX, QW- 253 & 403.11

API-510 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 24

107. A GTAW procedure is qualified and weld metal is deposited. What is the maximum qualified thickness of deposited weld metal can be listed on the WPS? a) b) c) d) 4 Inch 3 Inch 2 Inch 1 Inch

Ref. Section IX, QW- 256 & 451.2 108. An SAW procedure is qualified using 200F preheat. What is the minimum preheat temperature that may be listed on the WPS? a) b) c) d) 300F 200F 100F 50F

Ref. Section IX, QW- 254 & 406.1 109. An SMAW procedure is qualified using a preheat of 75F. The WPS is later revised to indicate a preheat of 200F. Is this acceptable, or must the procedure be re-qualified? a) The procedure must be re-qualified and change greater than 100F must be requalified b) The WPS must be revised to reflect the increased preheat temperature c) Preheat is an essential variable and any change must be qualified by a PQR d) It is acceptable as it is written. This variable only addresses a decrease in preheat temperature. Ref. Section IX, QW- 253 & 406.1 110. An SAW procedure is qualified with PWHT. We wish to use this procedure on a system that does not require PWHT. Is this acceptable? a) It is not acceptable, PWHT is an essential variable and re-qualification is required. b) It is acceptable providing the owner gives their concurrence to the elimination of PWHT c) It is not acceptable because PWHT is always required using the SAW process d) It is acceptable since PWHT is a non-essential variable Ref. Section IX, QW- 254 & 407.1

API-510 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 25

111. In tension testing of plate, full thickness specimens are required for thickness up to and including what dimension? a) b) c) d) 1/2" 3/4" 1" 1 1/4"

Ref. Section IX, QW-151.1(a) 112. In tension testing of pipe, having an outside diameter greater than 3", full thickness specimens are required for thickness up to and including what dimension? a) b) c) d) 1/2" 3/4" 1" 1 1/4"

Ref. Section IX, QW-151.2(a) 113. Is it possible for a single Welding Procedure Specification to cover a thickness range from 1/16 through 1 ? a) Yes as long as a supporting Procedure Qualification Record exists for both 1/16 through 3/16 and 3/16 through 1 thickness ranges b) Yes as long as a supporting Procedure Qualification Record exists for the 1/16 through 1 thickness range c) No the WPS can only cover one thickness range d) No the WPS can only cover a single essential variable regardless of the number of supporting PQRs exist. Ref. Section IX, QW-200.2(f)

API-510 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 26

Answers to ASME Section IX, Welding Questions


Question Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Answer b a c a d a b c d b a b c d a b d c b a a d a d c b b d

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-510 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 27

Answers to ASME Section IX, Welding Questions


Question Number 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 Answer c a b a d b c a d b b c c a b c c a b c d b b b d c b d

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-510 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 28

Answers to ASME Section IX, Welding Questions


Question Number 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 Answer b a b a c b c a a d b d a c a d d a b b d b c a d b d a

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-510 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 29

Answers to ASME Section IX, Welding Questions


Question Number 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 Answer b d c c a b b b d c d a a b b a d c b d a b d c d a c c a

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-510 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject API-510 Exam Prep ASME Welding

Issue Date 03/98

Revision Date 10/99

Page 30

API-510 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject NDE ASME Section V

Issue Date 03/98

Revision Date 06/00

Page 1

ASME Section V NDE Requirements 1. Which of the following is a true statement regarding ASME Section V. a) The requirements contained in this Code Section shall be mandatory for all ASME Construction b) The requirements contained in this Code Section shall be mandatory for all Repair situations c) This Code section is a required construction Code d) This Code section is a Reference Code REF: Section V, T-110(a) 2. Which of the following is not a method of NDE covered by Section V. a) b) c) d) Ultrasonic examination Ultimate tensile strength testing Liquid Penetrant examination Magnetic Particle examination

REF: Section V, T-110(a) 3) Subsection A of Section V lists the methods of NDE methods to be used, which have been: a) b) c) d) Referenced by other Code Sections Accepted as standards Accepted by the purchaser Referenced by the purchaser

REF: Section V, T-120(a) 4. Subsection B of Section V lists Standards covering NDE which have been: a) b) c) d) Referenced by other Code Sections Accepted as standards Accepted by the purchaser Referenced by the purchaser

REF: Section V, T-120(b) 5. The standards referenced in Subsection B of Section V are mandatory? a) True b) False REF: Section V, T-120(b)
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject NDE ASME Section V

Issue Date 03/98

Revision Date 06/00

Page 2

6. According to ASME Section V, Nondestructive Examination Personnel shall be qualified by which of the following? a) SNT-TC-1A (1996 edition), recommended Practice for NDE Personnel Qualification and Certification b) ANSI/ASNT CP-189-1995 (1995 edition), ASNT Standard for Qualification and Certification of Nondestructive Testing Personnel c) Both A or B d) Neither A or B Reference: Section V, T-140(a) 7. When required by referencing Code Sections, all NDE methods performed under Section V shall be done _______. a) b) c) d) To the acceptance of the verbal specifications of the purchaser To the applicable requirements of any construction Code To the satisfaction of the purchaser To a written procedure in accordance with Section V

REF: Section V, T-150(c) 8. How should weld surface irregularities be removed prior to radiographic examination? a) They shall be removed by any suitable means to such a degree that the resulting radiographic image due to any irregularities cannot mask or be confused with the image of any discontinuity. b) They shall be removed by air arcing only to such a degree that the resulting radiographic image due to any irregularities cannot mask or be confused with the image of any discontinuity. c) They shall be removed by grinding only to such a degree that the resulting radiographic image due to any irregularities cannot mask or be confused with the image of any discontinuity. d) They shall not be removed by any means because removal may result in masking discontinuities in the radiographic image. REF: Section V, T-222.2 9. The purpose of the lead letter B placed on the back of each film holder during each exposure of a radiograph is to determine if backscatter radiation is exposing the film. a) True b) False REF: Section V, T-223
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject NDE ASME Section V

Issue Date 03/98

Revision Date 06/00

Page 3

10. What are the minimum dimensions of the lead letter B used to measure backscatter? a) b) c) d) in height and 1/16 in thickness in height and 3/16 in thickness in height and 1/16 in thickness in height and 3/16 in thickness

REF: Section V, T-223 11. Which of the following is correct with regard to the identification for the radiograph traceable to the weld or weld seam? a) b) c) d) The identification must appear as a radiographic image The identification shall be produced permanently on the radiograph The identification shall be placed on the film holder The identification need only be maintained until construction is completed

REF: Section V, T-224 12. What must be used to judge film density? a) b) c) d) A radiographic mass spectrometer comparison light A suitable black light specifically designed for radiographic film evaluation A green laser or fluorescent light viewing box A densitrometer or step wedge comparison film

REF: Section V, T-225 13. According to ASME Section V, radiographic film selection shall be in accordance with what requirement? a) Film selection shall be in accordance with SE-2815, Standard Test Method for Film Systems for Industrial Radiography. b) Film selection shall be in accordance with SE-1816, Standard Test Method for Film Systems for Industrial Radiography. c) Film selection shall be in accordance with SE-1815, Standard Test Method for Film Systems for Industrial Radiography. d) Film selection shall be in accordance with SE-2816, Standard Test Method for Film Systems for Industrial Radiography. REF: Section V, T-231.1

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject NDE ASME Section V

Issue Date 03/98

Revision Date 06/00

Page 4

14. When may intensifying screens be used per Section V? a) b) c) d) Intensifying screens may be used as necessary without restrictions Intensifying screens may be used only if permitted by the purchaser Intensifying screens may be used unless restricted by the referencing Code Intensifying screens are not permitted

REF: Section V, T-232 15. Where will the extent of radiographic examination be specified? a) The extent of any examination will be dictated by the Authorized Inspector based on his/her experience b) The extent of examination shall be as specified by the referencing Code. c) The extent of examination will be as specified in SNT-TC-1A (1996 edition) d) As required by the Material Specification REF: Section V, T-226 16. Define Image Quality Indicator. a) A device whos demonstrated image provides visual or quantitative data, or both, to determine radiographic quality and sensitivity b) A device whos demonstrated image provides visual data to determine radiographic quality and sensitivity c) A device whos demonstrated image provides quantitative data to determine radiographic quality and sensitivity d) A device whos demonstrated image provides visual or quantitative data, or both, to determine radiographic quality and density REF: Section V, Article 30 (SE-1316) 17. Penetrameter is an alternative term for Image Quality Indicator. a) True b) False REF: Section V, Article 30 (SE-1316) 18. What is the diameter of the 2T hole for a penetrameter with a 10 designation? a) b) c) d) 0.010 0.10 0.020 0.20

REF: Section V, T-233, Table T-233.1


API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject NDE ASME Section V

Issue Date 03/98

Revision Date 06/00

Page 5

19. What is the diameter of the 2T hole for a penetrameter with a 12 designation? a) b) c) d) 0.125 0.0125 0.250 0.025

REF: Section V, T-233, Table T-233.1 20. What is the diameter of the 2T hole for a penetrameter with a 20 designation? a) b) c) d) 0.070 0.040 0.020 0.20

REF: Section V, T-233, Table T-233.1 21. How are step wedge comparison films and densitrometers calibrated? a) In accordance with paragraph 5 of SE-1079, Calibrated of Transmission Densitometers, using a calibrated step wedge film traceable to a National Standard. b) In accordance with paragraph 5 of SE-2079, Calibrated of Transmission Densitometers, using a calibrated step wedge film traceable to a National Standard. c) In accordance with paragraph 3 of SE-1079, Calibrated of Transmission Densitometers, using a calibrated step wedge film traceable to a National Standard. d) In accordance with paragraph 3 of SE-2079, Calibrated of Transmission Densitometers, using a calibrated step wedge film traceable to a National Standard. REF: Section V, T-262

22. What is the preferred exposure technique used for radiography? a) b) c) d) Double-wall exposure Triple-wall exposure Shear-wave exposure Single-wall exposure

REF: Section V, T-271

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject NDE ASME Section V

Issue Date 03/98

Revision Date 06/00

Page 6

23. Explain the single-wall radiographic technique. a) The radiation passes through only one wall of the base (material) which is viewed for acceptance on the radiograph. b) The radiation passes through only one wall of the weld (material) which is viewed for acceptance on the radiograph. c) The radiation passes through only one wall of the weld (material) and one wall of the base (material) which is viewed for acceptance on the radiograph. d) The radiation source is placed on the inside only and passes through only one wall of the weld (material) which is viewed for acceptance on the radiograph. REF: Section V, T-271.1 24. Single-wall and double-wall viewing are the two double-wall radiographic techniques permitted in Section V. a) True b) False REF: Section V, T-271.2 (a) and (b) 25. Explain the single-wall viewing radiographic technique. a) A technique in which radiation passes through two walls and only the base (material) on the film sidewall is viewed for acceptance on the radiograph. b) A technique in which radiation passes through two walls and only 120 of the weld (material) on the film sidewall is viewed for acceptance on the radiograph. c) A technique in which radiation passes through two walls and only the weld (material) on the film sidewall is viewed for acceptance on the radiograph. d) A technique in which radiation passes through two walls and only 120 of the base (material) on the film sidewall is viewed for acceptance on the radiograph. REF: Section V, T-271.2(a) 26. Describe the double-wall viewing radiographic technique. a) A technique in which the radiation passes through one wall and the weld (material) in both walls is viewed for acceptance on the radiograph. b) A technique in which the radiation passes through one wall and the base (material) in both walls is viewed for acceptance on the radiograph. c) A technique in which the radiation passes through two walls and the base (material) in both walls is viewed for acceptance on the radiograph. d) A technique in which the radiation passes through two walls and the weld (material) in both walls is viewed for acceptance on the radiograph. REF: Section V, T-271.2(b)
API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject NDE ASME Section V

Issue Date 03/98

Revision Date 06/00

Page 7

27. When may the double-wall viewing radiographic technique be used? a) b) c) d) For materials and for welds in components 3-1/2 or less in nominal inside diameter For materials and for welds in components 3-1/2 or less in nominal outside diameter For materials and for welds in components 3-1/2 or less in nominal thickness For materials and for welds in components 3-1/2 or less in minimum diameter

REF: Section V, T-271.2(b) 28. For the double-wall viewing radiographic technique, only a ______ penetrameter may be used. a) b) c) d) Film side Film side using a shim Source side Double thickness

REF: Section V, T-271.2(b) 29. In radiographic examination, the location markers ________ on the film. a) b) c) d) Shall appear as radiographic images Do not have to appear Shall be attached to the cassette and not appear Shall be taped

REF: Section V, T-275 30. May a thicker or thinner penetrameter, than that specified, be used provided equivalent penetrameter sensitivity is maintained? a) Yes b) No REF: Section V, T-276 31. Upon which side of the part should a penetrameter be placed? a) b) c) d) The film side The source side The penetrameter should not be placed on the part The penetrameter should be taped to the cassette

REF: Section V, T-277.1


API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject NDE ASME Section V

Issue Date 03/98

Revision Date 06/00

Page 8

32. When may a penetrameter be placed on the film side of the part? a) b) c) d) Never Where inaccessibility prevents hand placing the penetrameter on the source side. Anytime Only with the concurrence of the purchaser

REF: Section T-277.1(b) 33. How is a film side penetrameter identified on a radiograph? a) b) c) d) By lead letters FS placed on or adjacent to the penetrameter. By lead letters FSP placed on or adjacent to the penetrameter. By a lead letter F placed on or adjacent to the penetrameter. Penetrameters shall not be placed on the film side

REF: Section V, T-277.1(b) 34. Which of the following would be a true statement regarding placement of hole type penetrameters in radiographic examination? a) The penetrameter shall be placed adjacent to the weld b) The penetrameter shall be placed adjacent to the weld with the identifying number facing left c) The penetrameter may be placed on or adjacent to the weld provided when the penetrameter is placed on the weld, the next smaller size penetrameter is used d) The penetrameter may be placed on or adjacent to the weld REF Section V, Article 2, T-277.1(c) 35. In radiography, how shall wire penetrameters be placed? a) Wire penetrameters shall be placed parallel to the length of the weld b) Wire penetrameters shall be placed perpendicular to the length of the weld c) Two wires shall be placed to the right of the area of interest and the other two to the left and the fifth wire shall be placed in the center of the area of interest perpendicular to the length of the weld d) Two wires shall be placed to the right of the area of interest and the other two to the left and the fifth wire shall be placed in the center of the area of interest parallel to the length of the weld REF Section V, Article 2, T-277.1(d)

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject NDE ASME Section V 36. What is the purpose of a shim?

Issue Date 03/98

Revision Date 06/00

Page 9

a) An item placed between the part and the penetrameter, if needed, so that the radiographic density throughout the area of interest is no more than 5% from (lighter than) the radiographic density through the penetrameter. b) An item placed between the part and the penetrameter, if needed, so that the radiographic density throughout the area of interest is no more than 10% from (lighter than) the radiographic density through the penetrameter. c) An item placed between the part and the penetrameter, if needed, so that the radiographic density throughout the area of interest is no more than minus 15% from (lighter than) the radiographic density through the penetrameter. d) An item placed between the part and the penetrameter, if needed, so that the radiographic density throughout the area of interest is no more than 25% from (lighter than) the radiographic density through the penetrameter. REF: Section V, T-277.3 37. From what material is a shim made? a) b) c) d) Material made of weldable quality Material radiographically similar to the weld metal. Shims may not be used in radiographic examination of ASME Code fabricated items Any type of material that will not absorb radiation

REF: Section V, T-277.3 38. What is the size relationship between the shim and the penetrameter? a) The shim dimension shall not exceed the penetrameter dimension b) The shim dimension shall exceed the penetrameter dimension such that the outline of at least three sides of the penetrameter image shall be visible in the radiograph. c) The shim dimension shall exceed the penetrameter dimension such that the outline of at least two sides of the penetrameter image shall be visible in the radiograph. d) Shims are not permitted REF: Section V, T-277.3 39. What size hole penetrameter is to be used when radiographing a weld thick? The penetrameter is a source side penetrameter. a) b) c) d) 15 12 20 17

REF: Section V, Table T-276


API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject NDE ASME Section V

Issue Date 03/98

Revision Date 06/00

Page 10

40. What size hole penetrameter is to be used when radiographing a weld 1 & 1/4 thick? The penetrameter is a source side penetrameter. a) b) c) d) 30 25 35 20

REF: Section V, Table T-276 41. What size hole penetrameter is to be used when radiographing a weld 1-1/4 thick? The penetrameter is a film side penetrameter. a) b) c) d) 30 25 35 20

REF: Section V, Table T-276 42. What is the transmitted density limit between the body of the penetrameter and the area of interest for single film viewing for radiographs using an X-Ray source? a) b) c) d) 4.8 3.8 2.0 1.8

REF: Section V, T-282.1 43. What is the transmitted density limit between the body of the penetrameter and the area of interest for single film viewing using a Gamma-Ray source? a) b) c) d) 1.8 2.0 0.2 0.18

REF: Section V, T-282.1

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject NDE ASME Section V

Issue Date 03/98

Revision Date 06/00

Page 11

44. What is the maximum allowable transmitted density through the radiographic image of the body of a hole penetrameter and the area of interest? a) b) c) d) 1.3 1.8 2.0 4.0

REF: Section V, T-282.1 45. In radiography, a dark image of a B on a lighter background is not cause for rejection. a) True b) False REF: Section V, T-284 46. What article in Section V covers Liquid Penetrant Examination (PT)? a) b) c) d) Article 4 Article 5 Article 6 Article 7

REF: Section V, Article 6 47. Liquid Penetrant is used to detect surface discontinuities? a) True b) False REF: Section V, T-600 48. Liquid penetrant examination is capable of detecting all but which of the following? a) b) c) d) Cracks Laps Laminations Slight sub-surface

REF: Section V, T-600

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject NDE ASME Section V

Issue Date 03/98

Revision Date 06/00

Page 12

49. Must Liquid Penetrant examination be performed to a written procedure? a) b) c) d) Yes, regardless of the requirements of the referencing Code No, Liquid Penetrant is the only method that does not require written procedures Yes, unless exempted by the referencing Code No, except for the fluorescent method

REF: Section V, T-610.2 50. Which of the following is not required to be addressed on a written procedure for Liquid Penetrant Examination? a) b) c) d) Type of each penetrant, penetrant remover, emulsifier, and developer Name and Level of qualification of the examiner The materials, shapes, or sizes to be examined, and the extent of the examination Processing details for removing excess penetrant from the surface before applying the developer

REF: Section V, T-621.1 51. A revision to a Liquid Penetrant procedure is required whenever a change or substitution is made in all but which of the following? a) b) c) d) To the type or family group of penetrant materials or in the processing techniques In the type of precleaning materials or processes Any change in part processing that can close surface openings of discontinuities A change or substitution in examiners

REF: Section V, T-621.2(a) 52. Name the two types of penetrants used in Code Liquid Penetrant processes. a) b) c) d) Instant drying and fluorescent penetrant. Oil based Color contrast and fluorescent penetrant. Metallic Particle and fluorescent penetrant. Color contrast and fluorescent penetrant.

REF: Section V, T-651

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject NDE ASME Section V

Issue Date 03/98

Revision Date 06/00

Page 13

53. Of the following, which is not a Liquid Penetrant process? a) b) c) d) Metallic Particle Water Washable Post-emulsifying Solvent removable

REF: Section V, T-651 54. What is the allowable temperature range of the Liquid Penetrant and the part to be processed? a) b) c) d) Not less than 60F. Not less than 50F. Not less than 50F. Not less than 60F. No more than 125F throughout the examination period No more than 600F throughout the examination period No more than 125F throughout the examination period No more than 600F throughout the examination period

REF: Section V, T-652 55. What article in Section V covers magnetic particle examination? a) b) c) d) Article 9 Article 8 Article 7 Article 6

REF: Section V 56. Magnetic Particle examination can detect which of the following discontinuities? a) b) c) d) Surface only Surface and slight sub-surface Slight sub-surface and all sub-surface Sub-surface and opposite side

REF: Section V, Article 7, T-720 57. Describe the sensitivity of Magnetic Particle Examination. a) b) c) d) The sensitivity is greatest at the surface and diminishes rapidly with increasing depth. The sensitivity is greatest at the surface and diminishes slightly with increasing depth. The sensitivity is weakest at the surface and increases rapidly with increasing depth. The sensitivity is weakest at the surface and increases slightly with increasing depth.

REF: Section V, Article 7, T-720


API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject NDE ASME Section V

Issue Date 03/98

Revision Date 06/00

Page 14

58. Name three typical discontinuities that can be detected by Magnetic Particle Examination. a) b) c) d) Cracks, porosity, laps, cold shuts and laminations Cracks, seams, laps, cold shuts and laminations Cracks, seams, slag inclusions, cold shuts and laminations Cracks, seams, laps, incomplete penetration and laminations

REF: Section V, Article 7, T-720 59. In Magnetic Particle examination, each area should be examined at least twice with the lines of flux during examination approximately ____ to the lines of flux during the other? a) b) c) d) 60 120 90 Parallel

REF: Section V, Article 7, T-720 60. Which of the following is not required to be addressed in a Magnetic Particle examination procedure? a) b) c) d) Materials, shapes, or sizes to be examined and the extent of the examination Equipment to be used for magnetization The ferromagnetic particles to be used in a Magnetic Particle examination The name and qualification level of the examiner

REF: Section V, Article 7, T-750 61. Describe the continuous method of Magnetic Particle testing. a) The magnetizing current remains on while the piece being examined is passed through the magnetic field b) The magnetizing current remains on only while the excess of the examination medium is being removed. c) The magnetizing current remains on while the examination medium is being applied and while excess of the examination medium is being removed. d) The magnetizing current remains on only while the examination medium is being applied REF: Section V, Article 7, T-751

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject NDE ASME Section V

Issue Date 03/98

Revision Date 06/00

Page 15

62. Which of the following is not a type of magnetization technique that may be used in Magnetic Particle testing? a) b) c) d) Prod Circular Yoke Immersion

REF: Section V, Article 7, T-752 63. Under what condition may Magnetic Particle examination be performed on a part with a coating such as paint left on the part? a) It must be demonstrated, in accordance with Mandatory Appendix II, that indications can be detected through the maximum coating thickness applied b) It must be demonstrated, in accordance with ASME Section VIII, Div. 2, that indications can be detected through the maximum coating thickness applied c) It must be demonstrated, in accordance with Mandatory Appendix I, that indications can be detected through the maximum coating thickness applied d) All coatings shall be removed prior to Magnetic Particle examination, the coatings could mask discontinuities REF: Section V, Article 7, T-741.1(d)

64. What three types of particles are used in Magnetic Particle examination? a) b) c) d) Wet, Damp, and Fluorescent Wet, Dry, and Fluorescent Wet, Dry, and Red Iron Filings Wet, Dry, and Gray Iron Filings

REF: Section V, Article 7, T-752

65. What is the maximum surface temperature, of the part being examined, permitted for Magnetic Particle examination using dry particles? a) b) c) d) 600F 125F 135F 175F

REF: Section V, Article 7, T-731(a)


API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject NDE ASME Section V

Issue Date 03/98

Revision Date 06/00

Page 16

66. During Magnetic Particle examination using the dry particle technique, the dry particles must provide a color contrast between the particles and the part being examined? (True or False) a) True b) False REF: Section V, Article 7, T-731(a) 67. In Magnetic Particle examination, using the wet particle technique, the particles need not provide a color contrast between the particles and the part being examined? (True or False) a) True b) False REF: Section V, Article 7, T-731(b) 68. In Magnetic Particle examination, using the wet particle technique, what is the maximum temperature of the wet particle suspension and the surface of the part permitted according to ASME Section V? a) b) c) d) 600F 125F 135F 175F

REF: Section V, Article 7, T-731(b) 69. In Magnetic Particle examination using fluorescent particles, what is another term used for ultraviolet light? a) b) c) d) Infrared light Blue light Laser light Black light

REF: Section V, Article 7, T-731(c) 70. How long must the examiner be in the darkened room prior to performing Magnetic Particle examination using the fluorescent particle technique? a) b) c) d) 10 minutes 5 minutes There is no minimum time 30 minutes

REF: Section V, Article 7, T-731(c)(2)


API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject NDE ASME Section V

Issue Date 03/98

Revision Date 06/00

Page 17

71. How often should the black light intensity be check for the fluorescent particle technique of Magnetic Particle examination? a) b) c) d) Every 8 hours and whenever the workstation is changed Every 4 hours and whenever the workstation is changed Every 4 hours and whenever the examiners are changed Every 8 hours and whenever the examiners are changed

REF: Section V, Article 7, T-731(c)(4) 72. Is demagnetization of the part always required after Magnetic Particle examination? a) Yes, residual magnetism, in the part, could interfere with subsequent processing or usage b) No, when residual magnetism, in the part, could interfere with subsequent processing or usage, the part shall be demagnetized anytime after completion of the examination. c) No, residual magnetism, in the part, can not interfere with subsequent processing or usage d) Yes, demagnetization is always required after Magnetic Particle examination REF: Section V, Article 7, T-755 73. In fluorescent particles type MT, what is the minimum length of time, permitted in Section V, for warming up the black light? a) b) c) d) 60 minutes 30 minutes 10 minutes 5 minutes

REF: Section V, Article 7, T-731(c)(3) 74. For Magnetic Particle, how often should magnetizing equipment with an ammeter be calibrated? a) Once a year or whenever the equipment has been subjected to major electrical repair, periodic overhaul or damage. b) Once each five years or whenever the equipment has been subjected to major electrical repair, periodic overhaul or damage. c) Once each six months or whenever the equipment has been subjected to major electrical repair, periodic overhaul or damage. d) Once each three months or whenever the equipment has been subjected to major electrical repair, periodic overhaul or damage. REF: Section V, Article 7, T-761(a)

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject NDE ASME Section V

Issue Date 03/98

Revision Date 06/00

Page 18

75. If, after calibration, Magnetic Particle equipment is stored for over a year, must it be calibrated prior to the next use? a) No, since the equipment was in storage, it should still be in calibration b) Yes, if the equipment has not been in use for a year or more, calibration shall be done prior to use REF: Section V, Article 7, T-761(a) 76. In Magnetic Particle examination, the units meter reading shall not deviate by more than ___ of full scale, relative to the actual current value as shown by the test meter. a) b) c) d) The units meter reading shall not deviate more than 30% The units meter reading shall not deviate more than 20% The units meter reading shall not deviate more than 10% The units meter reading shall not deviate more than 00%

REF: Section V, Article 7, T-761(c) 77. In Magnetic Particle testing using the prod technique, what type of current and what are the current ranges in amps/in., required by Section V, for materials or greater in thickness? a) Direct or alternating magnetizing current shall be used and 90 amp/in. (minimum) to 110 amps/in. (maximum) of prod spacing. b) Direct or alternating magnetizing current shall be used and 100 amp/in. (minimum) to 125 amps/in. (maximum) of prod spacing. c) Direct or rectified magnetizing current shall be used and 90 amp/in. (minimum) to 110 amps/in. (maximum) of prod spacing. d) Direct or rectified magnetizing current shall be used and 100 amp/in. (minimum) to 125 amps/in. (maximum) of prod spacing. REF: Section V, Article 7, T-773.2 78. In Magnetic Particle testing using the prod technique, what are the current ranges in amps/in., required by Section V, for materials less than in thickness? a) b) c) d) 90 amps/in. (minimum) to 110 amps/in.(maximum) of prod spacing. 80 amps/in. (minimum) to 110 amps/in.(maximum) of prod spacing. 90 amps/in. (minimum) to 125 amps/in.(maximum) of prod spacing. 80 amps/in. (minimum) to 125 amps/in.(maximum) of prod spacing.

REF: Section V, Article 7, T-773.2

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject NDE ASME Section V

Issue Date 03/98

Revision Date 06/00

Page 19

79. In the prod technique of Magnetic Particle testing, what is the maximum prod spacing allowed? a) b) c) d) 12 inches 8 inches 6 inches 3 inches

REF: Section V, Article 7, T-773.3 80. In the prod technique of Magnetic Particle testing, prod spacing of less than three inches is strongly recommended? (True or False) a) True b) False REF: Section V, Article 7, T-773.3 81. The yoke technique of Magnetic Particle testing shall only be used to detect what type of discontinuities? a) b) c) d) Slight sub-surface discontinuities Laminations Discontinuities that are open to the surface Lack of penetration

REF: Section V, Article T-776.1 82. A.C. yokes are superior to D.C. yokes in Magnetic Particle testing for materials greater than in thickness? (True or False) a) True b) False REF: Section V, Article 7, T-776.2 (Note) 83. What are the lifting power requirements for A.C. yokes used in Magnetic Particle testing? a) b) c) d) They must lift 30 pounds at the maximum pole spacing to be used. They must lift 10 pounds at the maximum pole spacing to be used. They must lift 40 pounds at the maximum pole spacing to be used. They must lift 20 pounds at the maximum pole spacing to be used.

REF: Section V, Article 7, T-762(b)


API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject NDE ASME Section V

Issue Date 03/98

Revision Date 06/00

Page 20

84. What are the lifting power requirements for D.C. yokes used in Magnetic Particle testing? a) b) c) d) They must lift 30 pounds at the maximum pole spacing to be used. They must lift 10 pounds at the maximum pole spacing to be used. They must lift 40 pounds at the maximum pole spacing to be used. They must lift 20 pounds at the maximum pole spacing to be used.

REF: Section V, Article 7, T-763(c) 85. Localized surface irregularities due to machining marks may produce false indications during Magnetic Particle testing? a) True b) False REF: Section V, Article 7, T-780(b) 86. How much overlap is required in Ultrasonic Testing for each pass of a search unit? a) b) c) d) 20% of the transducer dimension perpendicular to the direction of the scan 10% of the thickness of the part being examined perpendicular to the direction of the scan 20% of the thickness of the part being examined perpendicular to the direction of the scan 10% of the transducer dimension perpendicular to the direction of the scan

REF: Section V, Article 5, T-523.1 87. What is the maximum rate of search unit movement, permitted in Section V, for Ultrasonic Examination? a) b) c) d) 6/hr. unless calibration is verified at scanning speed. 6/sec. unless calibration is verified at scanning speed. 6/min. unless calibration is verified at scanning speed. 6/sec. unless calibration is verified at scanning speed.

REF: Section V, Article 5, T-523.2 88. For contact examination, the temperature of the examination and basic calibration block surfaces shall be within _____F a) b) c) d) 50 25 15 10

REF: Section V, Article 4, Appendix B, B-1


API-653 Exam Prep Course BAY Technical Associates, Inc. (610) 594-9036

Subject NDE ASME Section V

Issue Date 03/98

Revision Date 06/00

Page 21

89. Ultrasonic search units may contain single or dual transducer elements? (True or False) a) True b) False REF: Section V, Article 5, T-536(a) 90. For search units, with contoured contact wedges, how is calibration accomplished? a) Calibration shall be done with contact wedges of similar material as those used during the examination b) Calibration shall be done with basic calibration contact wedges c) Calibration shall be done with contact wedges that are at least 75% of the dimension as the contact wedges used during the examination d) Calibration shall be done with the contact wedges used during the examination REF: Section V, Article 5, T-536(b)

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject NDE ASME Section V

Issue Date 03/98

Revision Date 06/00

Page 22

Answers to ASME Section V, NDE Questions


Question Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 Answer d b a b b c d a a c b d c c b a a c d b a d b a c d b c a a b b c d b c

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject NDE ASME Section V

Issue Date 03/98

Revision Date 06/00

Page 23

Answers to ASME Section V, NDE Questions


Question Number 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 Answer b b d a b d b d a c a d c b d d a c c b a b c d c d c b

API-653 Exam Prep Course

BAY Technical Associates, Inc.

(610) 594-9036

Subject NDE ASME Section V

Issue Date 03/98

Revision Date 06/00

Page 24

Answers to ASME Section IX, NDE Questions


Question Number 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 Answer a a b c d b a b d b b c d a b a c a b c a d b b a d

Should you find a mistake or disagree with any answer listed, please bring it to our attention for correction or clarification. BAY Technical Associates, Inc. has attempted to provide answers developed from paragraphs of the respective Code, Standard, or Recommended Practice. You can reach BAY Tech by phone at (610) 594-9036, by fax at (610) 594-2612, or by e-mail at byagle@gte.net.

API-653 Exam Prep Course

BAY Technical Associates, Inc.