RIG 453
TASK NO Created RIG UP AND RUN CHEMICAL CUTTER / / 199 TASK NO Review Date ADQ18 PAGE 1 OF 3 / / 19..
NO. 1.
STEP SAFETY MEETING TO BE HELD BETWEEN RIG CREW AND SCHLUMBERGER CREW BEFORE ANY EQUIPMENT IS PICKED UP. STRING SHOT RUN IF CUTTING OLD TUBING. RIG UP CHEMICAL CUTTER AND CONNECT TO WIRELINE.
2.
3.
CHEMICAL SPILLAGE/HANDING
USE OF PROPER PPE IE. SPECIAL PROTECTIVE RAINCOATS, GLOVES, FACE MASKS. USE OF SEVERING HEAD COVER DURING RIG UP. HAVE A FRESH WATER HOSE AVAILABLE AT ALL TIMES WHILE RIGGING UP.
VICO INDONESIA
JOB SAFETY ANALYSIS.
RIG 453
TASK NO Created NO. RIG UP AND RUN CHEMICAL CUTTER / / 199 HAZARD TASK NO Review Date CONTROL CAREFUL HANDLING PROCEDURES. ADQ18 PAGE 2 OF 3 / / 19..
STEP
4.
PROPER PPE AS EXPLAINED ABOVE. BREATHING APPARATUS TO BE WORN. BLEED OFF PRESSURE AS SOON AS TOOL IS OUT OF THE HOLE. KEEP ALL UNNECESSARY PERSONNEL CLEAR. PROPER PPE AS EXPLAINED ABOVE. WASH DOWN THOROUGHLY WITH FRESH WATER. FLUSH WITH FRESH WATER AND REINSTALL END CAPS.
5.
BREAKING DOWN CHEMICAL CUTTER ASSY ONCE OFF THE RIG FLOOR.