Sei sulla pagina 1di 2

VICO INDONESIA

JOB SAFETY ANALYSIS.

RIG 453
TASK NO Created OPEN HOLE LOGGING (SISEMIC SURVEY) 17 / 2 / 1997 TASK NO Review Date ADQ13 PAGE 1 OF 3 / / 19..

NO. 1. RIG UP.

STEP

HAZARD DROPPED TOOLS (DOWN HOLE ) PINCH POINTS TOOLS OVERHEAD OPENING RAMS PRESSURE UNDER RAMS

CONTROL CLOSE BLIND RAMS ENSURE HOLE COVER IN PLACE KEEP HANDS CLEAR DONT GET UNDER OVERHEAD LIFTS PERSONNEL CLEAR OF AREA WHEN OPENING RAMS. BLEED OFF VIA CHOKE - CONFIRM NO PRESSURE ENSURE BUSHINGS LOCKED. ENSURE HOLE FULL MONITOR DRINK RATE. CLOSE ANULAR - KILL WELL (IF UNSUCCESSFUL) CUT CABLE HAVE BOLT CUTTERS AND HYDRAULIC CUTTER READY DROP TOOL INTO HOLE CLOSE BLIND RAMS ENSURE MINIMUM OF 2 ON FLOOR AT ALL TIMES

2.

LOGGING

BUSHINGS NOT LOCKED WELL CONTROL WELL SWABS ANULAR FAILS TO SEAL

APPROPRIATE SAFETY CLOTHING AND EQUIPMENT MUST BE WORN AND USED

VICO INDONESIA
JOB SAFETY ANALYSIS.

RIG 453
TASK NO Created NO. OPEN HOLE LOGGING (SISEMIC SURVEY) 17 / 2 / 1997 STEP HAZARD TASK NO Review Date ADQ13 PAGE 2 OF 3 / / 19..

CONTROL ESTABLISH ALARM SYSTEM (PA SYSTEM) P.O.O.H SLOWLY MONITER VOLUMES ESTABLISH COMMUNICATIONS BETWEEN DRILL FLOOR AND WIRELINE OPERATOR MAKE SURE NEW CREW UNDERSTAND CONTROLS NEEDED

3.

PULL OUT OF HOLE

SWABBING

4.

CREW CHANGE

LACK OF COMMUNICATIONS BETWEEN CREWS

APPROPRIATE SAFETY CLOTHING AND EQUIPMENT MUST BE WORN AND USED

Potrebbero piacerti anche