Sei sulla pagina 1di 26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

Purpose Use this procedure to perform profit center distribution. Assessment and distribution of relevant overhead costs is performed at period closing (actual data) or plan closing (plan data). This is usually done directly in CO. It is then reflected in the data in Profit Center Accounting. If you have a service profit center or allocation profit center in your profit center hierarchy, you may need to assess or distribute costs again in Profit center Accounting. In Profit Center Accounting, the allocation function allows you to allocate the following plan and actual data. Costs (assessment and/or distribution) Revenues and sales deductions (assessment and/or distribution) Balance sheet items (distribution)

Assessment is made using a special cost/revenue element. In distribution, the original cost/revenue element/account number is retained. Trigger Perform this procedure when need to perform profit center distribution test run. Menu Path Use the following SAP Easy Access menu path(s) to begin this transaction: Accounting > Controlling > Profit Center Accounting > Actual Posting > Period-End Closing > 4KE5 - Distribution

Transaction Code 4KE5

Thursday, January 22, 2009

CO_4KE5_THL_Profit Center Distribution Test Run.udc

1/26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

Screen Flow

Thursday, January 22, 2009

CO_4KE5_THL_Profit Center Distribution Test Run.udc

2/26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

Thursday, January 22, 2009

CO_4KE5_THL_Profit Center Distribution Test Run.udc

3/26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

Procedure 1. In SAP, start the transaction using the menu path or transaction code. SAP Easy Access

2. Double-click the Accounting node 3. Double-click the Controlling node

. . .

4. Double-click the Profit Center Accounting node

Thursday, January 22, 2009

CO_4KE5_THL_Profit Center Distribution Test Run.udc

4/26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

5. Double-click the Actual Postings node 6. Double-click the Period-End Closing node 7. Click the Scroll down button . 8. Double-click the 4KE5 - Distribution node You can also enter "4KE5" in the command field " " and click Enter " transaction. Execute Actual Distribution: Initial Screen

. . . " to go directly to this

Thursday, January 22, 2009

CO_4KE5_THL_Profit Center Distribution Test Run.udc

5/26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

Thursday, January 22, 2009

CO_4KE5_THL_Profit Center Distribution Test Run.udc

6/26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

9. As required, complete/review the following fields: R Period, R/O/C 12 months as a rule, for which the company is to create its inventory and balance sheet. The fiscal year can be the same as the calendar year, but does not have to be. R Unit of time when the activity ends. Unit of time into which a fiscal year is subdivide d. Company data can
Thursday, January 22, 2009

Description

CO_4KE5_THL_Profit Center Distribution Test Run.udc

7/26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

be analyzed on a particular date in each period. In accountin g, a fiscal year can be subdivide d into a maximum of 16 periods. The fiscal year itself is a period Field Example: 2008 Fiscal Year Example: 11 Period To Example: 11 R Period

10 Click the Document Type edit field .


Thursday, January 22, 2009

CO_4KE5_THL_Profit Center Distribution Test Run.udc

8/26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

11 Click the Document Typepossible entries button .

Thursday, January 22, 2009

CO_4KE5_THL_Profit Center Distribution Test Run.udc

9/26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

FI-SL Document Type (1) 3 Entries found

12 Double-click the A0 list item .


Thursday, January 22, 2009

CO_4KE5_THL_Profit Center Distribution Test Run.udc

10/26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

Execute Actual Distribution: Initial Screen

13 Click the Cycle edit field .

. .

14 Click the Cyclepossible entries button .

Thursday, January 22, 2009

CO_4KE5_THL_Profit Center Distribution Test Run.udc

11/26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

Cycle (1) 83 Entries found

15 Double-click the 2632list item .


Thursday, January 22, 2009

CO_4KE5_THL_Profit Center Distribution Test Run.udc

12/26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

Execute Actual Distribution: Initial Screen

16 Click the Executebutton .

Thursday, January 22, 2009

CO_4KE5_THL_Profit Center Distribution Test Run.udc

13/26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

Display EC-PCA: Actual Distribution Basic List

17 Click the Warninglink .

Thursday, January 22, 2009

CO_4KE5_THL_Profit Center Distribution Test Run.udc

14/26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

EC-PCA: Actual Distribution: Display messages

18 Click the Enterbutton .

Thursday, January 22, 2009

CO_4KE5_THL_Profit Center Distribution Test Run.udc

15/26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

Display EC-PCA: Actual Distribution Basic List

19 Click the Sender button .

Thursday, January 22, 2009

CO_4KE5_THL_Profit Center Distribution Test Run.udc

16/26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

Display EC-PCA: Actual Distribution Sender List

20 Click the Basic list button .

Thursday, January 22, 2009

CO_4KE5_THL_Profit Center Distribution Test Run.udc

17/26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

Display EC-PCA: Actual Distribution Basic List

21 Click the Receiver button .

Thursday, January 22, 2009

CO_4KE5_THL_Profit Center Distribution Test Run.udc

18/26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

Display EC-PCA: Actual Distribution Receiver List

22 Click the Scroll down button . 23 Click the Basic list button .

. .

Thursday, January 22, 2009

CO_4KE5_THL_Profit Center Distribution Test Run.udc

19/26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

Display EC-PCA: Actual Distribution Basic List

24 Click the Backbutton . Exit list

Thursday, January 22, 2009

CO_4KE5_THL_Profit Center Distribution Test Run.udc

20/26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

Thursday, January 22, 2009

CO_4KE5_THL_Profit Center Distribution Test Run.udc

21/26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

25 Click the Yes button .

Execute Actual Distribution: Initial Screen

26 Click the Test Run check box . 27 Click the Execute button . .

Thursday, January 22, 2009

CO_4KE5_THL_Profit Center Distribution Test Run.udc

22/26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

Display EC-PCA: Actual Distribution Basic List

28 Click the Back button . Exit list

Thursday, January 22, 2009

CO_4KE5_THL_Profit Center Distribution Test Run.udc

23/26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

Thursday, January 22, 2009

CO_4KE5_THL_Profit Center Distribution Test Run.udc

24/26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

29 Click the Yes button .

Execute Actual Distribution: Initial Screen

30 Click the Exitbutton .

Thursday, January 22, 2009

CO_4KE5_THL_Profit Center Distribution Test Run.udc

25/26

Work Instruction

4KE5 - THL - Perform Profit Center Distribution Test Run

Result You have executed profit center distribution.