STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/ / PLANT AREA : ELECTRICAL SYSTEM TESTING SCHEDULE

: 500 MW STEAM TURBINE GENERATOR

SHEET 1 OF 3

1. PLANT DETAILS GENERATOR SYSTEM CONSISTS OF TURBOGENERTOR, EXCITER, GENERATOR PROTECTION, EXCITATION CONTROL SYSTEM. NAME PLATE DETAILS RATED DATA & O/P TURBO GEN. MAIN EXCITER PILOT EXCITER APPARENT POWER 588 MVA -----65 KVA ACTIVE POWER 500 MW 3780 KW -----CURRENT 16166 A 6300 A 195 A VOLTAGE 21 + 1.05 KV 600 V 220 + 22 V FREQUENCY 50 HZ -----400 HZ PF 0.85(LAG) ----------STATOR WDG CONN YY --------HYDROGEN PRESS 3.5 BAR --------CONT PERM UNBAL 8 % ----------LOAD RATED FIELD -----------VOLTAGE 340 V CURRENT 4040 A 2. TESTING OBJECTIVE TO TEST THE CHARACTERISTICS OF GENERATOR AND REACTIVE CAPABILITY RESPONSES OF GENERATOR. i) MEASUREMENT OF WINDING , INSULATION RESISTANCE ii) OPEN & SHORT CIRCUIT CHARACTERISTICS iii) REACTIVE CAPABILITY CURVE RESPONSE CHECKING 3.PROPOSAL I SHORT CIRCUIT CHARACTERISTIC GENERATOR PHASE TERMINALS ARE SHORTED TOGETHER. MACHINE IS EXCITED AT THE FULL SPEED OF PRIME MOVER(STEAM TURBINE). A CHARACTERISTIC CURVE IS PLOTTED BETWEEN EXCITATION CURRENT AND GENERATOR CURRENT II OPEN CIRCUIT CHARACTERISTIC GENERATOR PHASE TERMINALS ARE OPENED AS USUAL. MACHINE IS EXCITED AT THE FULL SPEED OF PRIME MOVER(STEAM TURBINE). A CHARACTERISTIC CURVE IS PLOTTED BETWEEN EXCITATION CURRENT AND GENERATOR TERMINAL VOLTAGE. GENERATOR PROTECTIONS ARE ONE-BY-ONE THROUGHLY CHECKED. GENERATOR PTs ARE PHASE IN-PHASE OUT WITH GRID

/var/www/apps/conversion/tmp/scratch_2/153906353.doc

STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/ / PLANT AREA : ELECTRICAL SYSTEM TESTING SCHEDULE : 500 MW STEAM TURBINE GENERATOR

SHEET 2 OF 3

PTs. WITHIN PERMISSIBLE LIMITS OF VOLTAGE DIFFERENCE (4%) & FREQUENCY (0.1 Hz) ,GENERATOR IS SYNCHRONISED WITH GRID. 4.SERVICES REQUIRED GENERATOR CIRCUIT BREAKER,EXCITATION SYSTEM,FIRE PROTECTION SYSTEM,220 V DC SUPPLY,DM CW SYSTEM, LUBE OIL SYSTEM,AUX COOLING WATER SYSTEM,HYDROGEN COOLING SYSTEM, GENERATOR PROTECTION SYSTEM 5.0 SAFETY PRECAUTIONS I) FIRE EXTINGUISHER SYSTEMS READINESS II) GENERATOR CABIN IS TO BE LOCKED AND INSPECTION WINDOW MUST BE GLASS COVERED. III) GENERATOR ONLINE/DANGER 21 KV CAUTION BOARD TO BE FIT IV) MEN & MATERIALS TO BE KEPT AWAY FROM GENRATOR 6. EMERGENCY PROCEDURE GENERATOR TO BE TRIPPED. EXCITATION & GENERATOR TRANSFORMER BACKCHARGING TO BE PUT OFF. CO2 WILL BE RELEASED ON FIRE DETECTION. 7. STATE OF THE PLANT AFTER THE ERECTION OF GENERATOR,H2 GAS TO BE FILLED IN THE ROTOR AFTER PASSING THE HYDROGEN LEAKAGE SYSTEM.COOLING SYSTEM TO BE IN CIRCULATWED MODE. BEARING COOLINGS TO BE ENSURED.POWER & CONTROL CIRCUIT OF GENERATOR & EXCITATION SYSTEM TO BE VERIFIED. FIRE PROTECTION SYSTEM KEPT READY. 8. COMMISSIONING PROCEDURE CHECK THE POLARISATION INDEX & WINDING RESISTANCE VALUES OF GENERATOR ARE WITHIN THE PERMISSIBLE LIMITS AS PER STANDARD. NO PROTECTION OPERATED .EXCITATION SYSTEM IS READY FOR GIVING FULL EXCITATION. THEN DO THE PROCEDURES AS IN SEC 3.0 9. COMPLETION CRETERIA

/var/www/apps/conversion/tmp/scratch_2/153906353.doc

STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/ / PLANT AREA : ELECTRICAL SYSTEM TESTING SCHEDULE : 500 MW STEAM TURBINE GENERATOR

SHEET 3 OF 3

GENERATOR IS WITHSTANDING FULL LOAD WITH PERMISSIBLE VARIATION OF ITS PARAMETERS LIKE WINDING TEMP,FRAME TEMP ETC. TRIAL RUN OF GENERATOR IS SUCESSFULLY COMPLETED 10. APPENDICES DRAWINGS: O & M MANUAL OF SYSTEM FILLING SCHEMATIC DRAWINGS OF STATOR COOLING,H2 SYSTEM LOG SHEETS : I) IR VALUES,WR VALUES OF GENERATOR II) OCC,SCC TEST REPORTS III) LIST OF PROTECTIONS INCLUED IV) READINESS OF AUX SYSTEMS GENERATOR,EXCITATION

---------------------------- * --------------------* -----------------