Ref. Drg.

Nos:

BAR BENDING SCHEDULE


Ref:
Project Start Date Project End Date BBS Date: Sheet No.

Construction Engineers and Project Management Consultants

Name of Work: Employer: Contract No: Contractor


Sr. No. Member details Bar Mark Dia of bar No. of bar No. of Member Total Nos. Shape Code Shape Cutting length Total Cutting length

Prepared by

Checked by

Dia of Bar Cutting Length Unit Wt. Weight Diawise Total Wt.

10

12

16

20

25

28

32

Date: FPM176 R2 03.11.2006

Date:

C/F. to:

Sheet ___ of ___

Ref.

SUMMARY SHEET FOR BAR BENDING SCHEDULE


Ref:
Contract Start Date Contract End Date BBS Date: Sheet No.

Construction Engineers and Project Management Consultants

Name of Work: Employer: Contract No: Contractor


Sr. No. B/F. from sheet No. Details Unit 8 mm 10 mm 12 mm 16 mm 20 mm

25 mm

28 mm

32 mm

Prepared by

Checked by Total Wt.

Date:

Date:

FPM176 R1 07.12.2005

Sheet ___ of ___