1. STRAP FOOTING DESIGN
FOOTINGDATA
Exterior Ftg

Interior Ftg

Footing Length, L =

1.000

Footing Width, B =

1.400

1.400 m

Footing Thickness, T =

0.300

0.300 m

Concrete Unit Wt., c =

24.000 kN/m

Soil Depth, D =
Soil Unit Wt., s =

0.600 m
18.000 kN/m

Pass. Press. Coef., Kp =

0.000

Coef. of Base Friction, =

0.400

Uniform Surcharge, Q =

0.000 kPa

Allow. SB Pressure, qa =

STRAPDATA

1.400 m

250 kPa

bs =

0.300 m

hs =

0.500 m

PIERDATA
Number of Pier(s) =
Fr Property Line

Pier #1

Nomenclature

Pier #2

Xp (m) =

0.125

4.375

Zp (m) =

0.000

0.000

Lpx (m) =

0.250

0.250

Lpz (m) =

0.250

0.250

h (m) =

0.600

0.600

PLAN

ELEVATIONXDIRECTION

JOB NO.
DOC. NO.

REV.
0
SHEET4OF43

CALCULATION
MATERIALPROPERTIES
CONCRETE
CompressiveStrength,c=
ModulusofElasticity,Ec=
Concretestrain,s=
Concreteprotection,cov=

30.00
25743

Mpa
Mpa

=4700cMpa

0.003
75

mm

REBARSS
YieldStrength,y=
ModulusofElasticity,Es=

422.00
200000.0

Mpa
Mpa

LOADDATA
CriticalL/C=
NodeNo.=

101:D+L+LR
10
Pier #1

Py (kN) =

-177.24

73
Pier #2

466.11

-288.87

WEIGHTSANDLOADS
FoundationCentriod
Xc=
0.00 m
Yc=
0.00 m
Foundation,SoilandSurcharge
BaseWt=
10.08
SoilWt=
15.12
SurchargeWt=
0.00
Wtotal=
25.20
Excess
PierWts=
Py=
Pty=

Pier #1

0.23
177.24
177.46

14.11
21.17
0.00
35.28

kN
kN
kN
kN

=LBTc
=LBDs
=LBQ
=BaseWt+SoilWt+SurchargeWt

Pier #2

0.45
466.11
466.56

0.23
288.87
289.10

TotalVerticalLoad

TotalVerticalLoad
Ptotal=

Pty=
Ptotal=

466.56 kN
527.04 kN

=(Appliedload+ExcessPierWt)
=Wtotal+Pty

202.66

324.38 kN

=Wtotal+Pty

SOILBEARINGPRESSURE
Pier #1
Pier #2
FootingArea
A=
1.40
1.96
A=
3.36 m2
Moment/Shear
e'=
L'=
M1=
V1=

0.375
3.875
76.00 kNm
19.61 kN

=L1/2Xp1
=Lce'
=Ptotal1e'
=M1/L'

Reactions
R1=
R2=

222.28 kN
304.76 kN

=Ptotal1+V1
=Ptotal2V1

JOB NO.
DOC. NO.

REV.
0
SHEET5OF43

CALCULATION
SoilBearingPressure
q=
158.77
155.49 kN
Hence,
<qa,Pass <qa,Pass
FACTOREDSOILBEARINGPRESSURE
CriticalL/C=

=R/A

201:1.2D+1.6L
Pier #1

Puy (kN) =

-284.72

Foundation,SoilandSurcharge
1.40
L.F.=
Wu=
35.28
Excess
L.F.PierWts=
Puy=
Puty=

Pier #1

Pier #2

655.54

-370.82

49.39 kN

=LoadfactorforDeadLoads
=BaseWt+SoilWt+SurchargeWt

Pier #2

0.32
284.72
285.03

0.32
370.82
371.14

320.31

420.53 kN

=Wu+Puty

FactoredSoilBearingPressure
qu=
250.93

198.74 kN

=Ru/A

FactoredMoment/Shear
e'=
L'=
Mu1=
Vu1=

0.375
3.875
120.12 kNm
31.00 kN

=L1/2Xp1
=Lce'
=Putotal1e'
=Mu1/L'

351.31 kN
389.53 kN

=Putotal1+Vu1
=Putotal2Vu1

TotalVerticalLoad
Putotal=

FactoredReactions
Ru1=
Ru2=

FOOTINGANALYSIS
FOOTINGANALYSISALONGXDIRECTION
BearingPressures
qu1=
351.31 kN/m
qu2=
278.24 kN/m

LengthofBearing
Brg.1=
g
Brg.2=

1.00 m
1.40 m

ELEVATIONXDIRECTION

JOB NO.
DOC. NO.

REV.
0
SHEET6OF43

CALCULATION
CHECKFORPUNCHINGSHEAR
Shearstrengthprovidedbyconcrete
Vc=v0.33cMpa2(box+boz)de
where
StrengthReductionFactor

[ACI318M08Para11.3.1.1]
v=

0.85

Perimeteraroundpier/column:
Pier #1

de=
box,m=
boz,m=
2(box+boz)=

Vc,kN=

0.20
0.35
0.45
1.60

Pier #2

0.20
0.45
0.45
1.80

Shearstrengthprovidedbyconcrete:
495.02
557.09

Punchingshear
Areaofpunchingshear,m
Totalforcefromcolumn/pier
Pier #1

Ap=
Puy=

0.16
289.01

Ap = boxboz
Puy = Puty +LF[Ap(Tc+Ds+Q)]

Pier #2

0.20
376.26

Totalforceactingonpunchedarea
39.67
40.42

Rqn = quApn

Rqn=

Netpunchingshear
249.35
335.84

Vup = Puy Rqn

Vup=

Vc>Vup=

Checkiftheshearstrengthprovidedbyconcretegreaterthanpunchingshear
PASS
PASS

CHECKFORWIDEBEAMSHEAR
WidebeamalongXdirection
Pier #1

x1=
Vu1=

0.35
87.58

Pier #2

0.35
97.10

Shearstrengthprovidedbyconcrete
Vc=v0.17cMpaBde
Vc,kN=
222.72
222.72
PASS
PASS
Vc>Vup=
where
StrengthReductionFactor

[ACI318M08Para11.3.1.1]

v=

0.85

WidebeamalongZdirection
Pier #1

x1=
Vu1=

0.17
61.13

Pier #2

0.37
104.06

Shearstrengthprovidedbyconcrete

p
Vc=v0.17cMpaBde
Vc,kN=
159.08
222.72
PASS
PASS
Vc>Vup=

[[ACI318M08Para11.3.1.1]]

JOB NO.
DOC. NO.

REV.
0
SHEET7OF43

CALCULATION
FOOTING1
CHECKFORFLEXURALSTRENGTH
XDirection:Bottom
Rebarsize
Rebarsnos

D16
7

Rebarpitch
b
i h

mm

208 mm

BarArea=
ProvidedAs=
b=
d
d=
h=

201
1407
1400
20
201
300

mm
mm
mm
mm
mm

MaximumNegativeMoment
MaxMu=
0.00 kNm
StrengthReductionFactor
=
0.9
Rn=Mu/bd
Rn=
0.0000 N/mm2
r=
0.0000
r=0.85c/y[1(12Rn/0.85c)]
Minimum1=0.0018
min=
0.0018
[ACI318M08Para10.5.4
Minimum21=4/3*r
=
0.0000
andPara7.12.2.1]
Minimum22=0.25*f'c^0.5/fy
=
0.0032
Hence,use
2=max(r,min/2)=
0.0009
Asreq.=2bh
Asreq.=
378 mm2
<ProvideAs=
1407 mm2
Ratio=
0.27
PASS
XDirection:Top
Rebarsize
Rebarsnos

D16
7

Rebarpitch

mm

208 mm

BarArea=
ProvidedAs=
b=
d=
h=

201
1407
1400
201
300

mm
mm
mm
mm
mm

MaximumNegativeMoment
MaxMu=
0.00 kNm
StrengthReductionFactor
=
0.9
Rn=Mu/bd
Rn=
0.0000 N/mm2
r=
0.0000
r=0.85c/y[1(12Rn/0.85c)]
Minimum1=0.0018
min=
0.0018
[ACI318M08Para10.5.4
Minimum21=4/3*r
=
0.0000
andPara7.12.2.1]
Minimum22=0.25*f'c^0.5/fy
=
0.0032
Hence,use
2=max(r,min/2)=
0.0009
Asreq.=2bh
Asreq.=
378 mm2
<ProvideAs=
1407 mm2
Ratio=
0.27
PASS
ZDirection:Bottom
Rebarsize
Rebarsnos
Rebarpitch

D16
5

mm

213 mm

Leverarm
MaximumNegativeMoment
StrengthReductionFactor
Rn=Mu/bd

/y [ (
/
)]
r=0.85c/y[1(12Rn/0.85c)]
Minimum1=0.0018
Minimum21=4/3*r
Minimum22=0.25*f'c^0.5/fy

BarArea=
ProvidedAs=
b=
d=
h=
a=
MaxMu=
=
Rn=

r=
min=
=
=

201
1005
1000
185
300
0.55
53.14
0.9
1.7250
0.0042
0.0018
0.0056
0.0032

mm
mm
mm
mm
mm
m
kNm
N/mm2
[ACI318M08Para10.5.4
andPara7.12.2.1]

JOB NO.
DOC. NO.

REV.
0
SHEET8OF43

CALCULATION
Hence,use
Asreq.=2bd
Asreq.=

2=max(r,min/2)=
784 mm2

0.0042

<ProvideAs=

1005 mm2
0.78

Ratio=

PASS

ZDirection:Top
Rebarsize
Rebarsnos
b

D16
5

Rebarpitch

mm

213 mm

BarArea=
ProvidedAs=
id d
b=
d=
h=

201
1005
00
1000
185
300

mm
mm
mm
mm
mm

MaximumNegativeMoment
MaxMu=
0.00 kNm
StrengthReductionFactor
f=
0.9
Rn=Mu/fbd
Rn=
0.0000 N/mm2
r=
0.0000
r=0.85c/y[1(12Rn/0.85c)]
Minimum1=0.0018
min=
0.0018
[ACI318M08Para10.5.4
Minimum21=4/3*r
=
0.0000
andPara7.12.2.1]
Minimum22=0.25*f'c^0.5/fy
=
0.0032
Hence,use
2=max(r,min/2)=
0.0009
Asreq.=2bh
Asreq.=
270 mm2
<ProvideAs=
1005 mm2
Ratio=
0.27
PASS
REBARARRANGEMENTFORFOOTINGSLAB
XDirection
Bottom
7D16@208mmO.C.
Top
7D16@208mmO.C.
ZDirection
Bottom
5D16@212mmO.C.
Top
5D16@212mmO.C.

FOOTING2
CHECKFORFLEXURALSTRENGTH
XDirection:Bottom
Rebarsize
Rebarsnos

BarArea=
201
ProvidedAs=
1407
b=
1400
Rebarpitch
208 mm
d=
201
h=
300
Leverarm
a=
0.58
MaximumNegativeMoment
MaxMu=
46.00
StrengthReductionFactor
=
0.9
Rn=
0.9036
Rn=Mu/bd
/
r=0.85c/y[1(12Rn/0.85c)]
r=
0.0022
Minimum1=0.0018
min=
0.0018
Minimum21=4/3*r
=
0.0029
Minimum22=0.25*f'c^0.5/fy
=
0.0032
Hence,use
2=max(r,min/2)=
0.0022
Asreq.=2bd
Asreq.=
614 mm2
<ProvideAs=
Ratio=
p
XDirection:Top
Rebarsize
Rebarsnos
Rebarpitch

D16
7

D16
7

mm

mm

208 mm

BarArea=
ProvidedAs=
b=
d=

201
1407
1400
201

mm
mm
mm
mm
mm
m
kNm
N/mm2
/
[ACI318M08Para10.5.4
andPara7.12.2.1]

1407 mm2
0.44

mm
mm
mm
mm

PASS

JOB NO.
DOC. NO.

REV.
0
SHEET9OF43

CALCULATION
h=

300 mm

MaximumNegativeMoment
MaxMu=
0.00 kNm
StrengthReductionFactor
=
0.9
Rn=Mu/bd
Rn=
0.0000 N/mm2
r=
0.0000
r=0.85c/y[1(12Rn/0.85c)]
Minimum1=0.0018
min=
0.0018
[ACI318M08Para10.5.4
Minimum21=4/3*r
i i
2
/3 *
=
0 0000
0.0000
andPara7.12.2.1]
d
22 ]
Minimum22=0.25*f'c^0.5/fy
=
0.0032
Hence,use
2=max(r,min/2)=
0.0009
Asreq.=2bh
Asreq.=
378 mm2
<ProvideAs=
1407 mm2
Ratio=
0.27
PASS
ZDirection:Bottom
Rebarsize
Rebarsnos

BarArea=
201
ProvidedAs=
1407
b=
1400
Rebarpitch
208 mm
d=
185
h=
300
Leverarm
a=
0.55
MaximumNegativeMoment
MaxMu=
42.08
StrengthReductionFactor
=
0.9
Rn=Mu/bd
Rn=
0.9759
r=
0.0024
r=0.85c/y[1(12Rn/0.85c)]
Minimum1=0.0018
min=
0.0018
Minimum21=4/3*r
=
0.0031
Minimum22=0.25*f'c^0.5/fy
=
0.0032
Hence,use
2=max(r,min/2)=
0.0024
Asreq.=2bd
Asreq.=
611 mm2
<ProvideAs=
Ratio=
ZDirection:Top
Rebarsize
Rebarsnos
Rebarpitch

D16
7

D16
7

mm

mm

208 mm

BarArea=
ProvidedAs=
b=
d=
h=

201
1407
1400
185
300

mm
mm
mm
mm
mm
m
kNm
N/mm2
[ACI318M08Para10.5.4
andPara7.12.2.1]

1407 mm2
0.43

PASS

mm
mm
mm
mm
mm

MaximumNegativeMoment
MaxMu=
0.00 kNm
StrengthReductionFactor
f=
0.9
Rn=
0.0000 N/mm2
Rn=Mu/fbd
/
/
r=0.85c/y[1(12Rn/0.85c)]
r=
0.0000
Minimum1=0.0018
min=
0.0018
[ACI318M08Para10.5.4
Minimum21=4/3*r
=
0.0000
andPara7.12.2.1]
Minimum22=0.25*f'c^0.5/fy
=
0.0032
Hence,use
2=max(r,min/2)=
0.0009
Asreq.=2bh
Asreq.=
378 mm2
<ProvideAs=
1407 mm2
Ratio=
0.27
PASS
REBARARRANGEMENTFORFOOTINGSLAB
XDirection
Bottom
7D16@208mmO.C.
Top
7D16@208mmO.C.
ZDirection
Bottom
7D16@208mmO.C.
Top
7D16@208mmO.C.

JOB NO.
DOC. NO.

REV.
0
SHEET10OF43

CALCULATION
TIEBEAM
CHECKFORFLEXURALSTRENGTH
XDirection:Bottom
Rebarsize
Rebarsnos

D16
6

Rebarpitch
b
i h

mm

30 mm

BarArea=
ProvidedAs=
b=
d
d=
h=

201
1206
300
401
0
500

mm
mm
mm
mm
mm

MaximumNegativeMoment
MaxMu=
68.17 kNm
StrengthReductionFactor
=
0.9
Rn=Mu/bd
Rn=
1.5701 N/mm2
r=
0.0038
r=0.85c/y[1(12Rn/0.85c)]
Minimum1=1.4/fy
min=
0.0033
[ACI318M08Para10.5.4
Minimum21=4/3*r
=
0.0051
andPara7.12.2.1]
Minimum22=0.25*f'c^0.5/fy
=
0.0032
Hence,use
2=max(r,min)=
0.0051
Asreq.=2bd
Asreq.=
616 mm2
<ProvideAs=
1206 mm2
Ratio=
0.51
PASS
XDirection:Top
Rebarsize
Rebarsnos
Rebarpitch

D16
6

mm

30 mm

BarArea=
ProvidedAs=
b=
d=
h=

201
1206
300
401
500

mm
mm
mm
mm
mm

MaximumNegativeMoment
MaxMu=
105.98 kNm
StrengthReductionFactor
=
0.9
Rn=Mu/bd
Rn=
2.4410 N/mm2
r=
0.0061
r=0.85c/y[1(12Rn/0.85c)]
Minimum1=0.0018
min=
0.0018
[ACI318M08Para10.5.4
Minimum21=4/3*r
=
0.0081
andPara7.12.2.1]
Minimum22=0.25*f'c^0.5/fy
=
0.0032
Hence,use
2=max(r,min/2)=
0.0081
Asreq.=2bd
Asreq.=
977 mm2
<ProvideAs=
1206 mm2
Ratio=
0.81
PASS