PROPOSED PROJECT CONSTRUCTION SCHEDULE

Bid Number: BPMC/DES/800016/T13/01 Project Name: Construction of Pasir Puteh-Lumut 275kV Transmission Line Client: BPMC (Berakas Power Management Company)
DURATION NO
A B C D E Tender>
Month

DESCRIPTION
Mobilization Construction Survey Soil Investigation Line Clearing and Access Foundation(Civil) Works

<-LOA
Month 1 Month 2 Month 3

2013
Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10 Month 11 Month 12

2014
Month 13 Month 14 Month 15 Month 16 Month 17

Toac>
Month 18

REMARKS

-01 Design and Approval -02 Pile Manufacturing -03 Transportation & Pilling Works -04 Excavation -05 Rebar Work -06 Anchor Bolt Setting -07 Concrete mix + Placing

Lattice Tower
-01 Design and Approval -02 Tower Plotting -03 Tower Testing -04 Manufacturing -05 Transportation -06 Tower Sorting -07 Tower Erection -08 Tower Inspection

Insulators & Fittings

-01 Design and Approval -02 Manufacturing -03 Shipping -04 C/C & XPTN -05 Attachment

Conductors

-01 Design and Approval -02 Manufacturing -03 Shipping -04 C/C & XPTN -05 Stringing -06 Sagging & Clamping

OPGW &Approach Cable


-01 Design and Approval -02 Manufacturing -03 Shipping -04 C/C & XPTN -05 Paying-Out & Sagging -06 Termination & Splicing -07 OTDR TESTING

Testing
-01 Foundation test(Include Pile Test) -02 Tower Type Load Test -03 Other test If required -07 Hipot Test & OPGW Test

K L

Access & Miscellaneous Commissioning & Hand Over