1. The ABC Company has been a producer of picture tubes for television sets and certain printed circuits for radios. The company has just expanded into full scale production and marketing of AM and AM-FM radios. It has built a new plant that can operate 48 hours per week. Production of an AM radio in the new plant will require 2 hours and production of an AM-FM radio will require 3 hours. Each AM radio will contribute Rs 40 to profits while an AM-FM radio will contribute Rs 80 to profits. The marketing department, after extensive research has determined that a maximum of 15 AM radios and 10 AM-FM radios can be sold each week. (a) Formulate a linear programming model to determine the optimum production mix of AM and FM radios that will maximize profits. (b) Solve the above problem using the graphic method.

2. Vitamins V and W are found in two different foods F 1 and F 2 . One unit of food F 1 contains 2 units of vitamin V and 5 units of vitamin W. One unit of food F 2 contains 4 units of vitamin V and 2 units of vitamin W. One unit of food F 1 and F 2 cost Rs. 30 and 25 respectively. The minimum daily requirements (for a person) of vitamin V and W is 40 and 50 units respectively. Assuming that anything in excess of daily minimum requirement of vitamin V and W is not harmful, find out the optimal mixture of food F 1 and F 2 at the minimum cost which meets the daily minimum requirement of vitamins V and W. Formulate this as a linear programming problem. 1

Ans Vitamin V Vitamin W Cost (Rs.)

Food 1 Food 2 Min. daily reqmt. X1 X2 2 4 40 5 2 50 30 25 Minimize Z = 30 X1 + 25 X2 Subject to : 2X1 + 4X3 40 5X1 + 2X2 50 X1, X2, 0

Dual: Sunject to:

Max. Z = 40Y1 + 50Y2 2Y1 + 5Y2 30 4Y1 + 2Y2 25 Yi 0

Dual Solution

3. Use graphical method to solve the following LP problem Maximise Z = 3x 1 + 3x 2 subject to the constraints x1 - x2 1 x1 + x2 3 and x1, x2 0

Solution: The problem is depicted graphically in Fig. The solution space is shaded and is bound by A and B from below.
X2

A (0,3) 2

Unboun ded Feasible Region

X1 - X2 = 1

B (2,1)

1 X1 + X2 = 3 0 1 2 3 4 X1

It is noted here that the shaded convex region (solution space) is unbounded. The two corners of the region are A = (0, 3) and B = (2, 1). The values of the objective function at these corners are: Z(A) = 6 and Z(B) = 8. But there exist number of points in the shaded region for which the value of the objective function is more than 8. For example the point (10,12) lies in the region and the function value at this point is 70 which is more than 8. Thus both the variables x 1 and x 2 can be made arbitrarily large and the value of Z also increased. Hence, the problem has an unbounded solution. Remark: An unbounded solution does not mean that there is no solution to the given LP problem, but implies that there exist an infinite number of solutions.

4. (Problem with inconsistence system of constraints) Use graphical method to solve the following LP problem: Maximise Z = 6x 1 - 4x 2 subject to the constraints 4

2x 1 + 4x 2 4 4x 1 + 8x 2 16 and x1, x2 0 Solution: The problem is shown graphically in Fig. The two inequalities that form the constraint set are inconsistent. Thus, there is no set of points that satisfies all the constraints. Hence, there is no feasible solution to this problem.

X2

4X1 + 8X2 = 16 2

2X1 + 4X2 = 4

X1

5. Solve graphically the following LPP: Maximise Z = 8x 1 + 16x 2 Subject to x 1 + x 2 200 x 2 125 3x 1 + 6x 2 900 x1, x2 0

Solution: The constraints are shown plotted on the graph in Figure. Also, iso -profit lines have been graphed. We observe that iso -profit lines are parallel to the equation f or third constraint 3x 1 + 6x 2 = 900. As we move the iso-profit line farther from the origin, it coincides with the portion BC of the constraint line that forms the boundary of the feasible region. It implies that there are an infinite number of optimal s olutions represented by all points lying on the line segment BC, including the extreme points represented by B (50, 125) and C (100, 100). Since the extreme points are also included in the solutions, we may disregard all other solutions and consider only t hese ones to establish that the solution to a linear programming problem shall always lie at an extreme point of the feasible region. The extreme points of the feasible region are given and evaluated here. 5

Point 0 A B C

x1 0 0 50 100

x2 0 125 125 100

Z = 8x 1 + 16x 2 0 2000 2400 2400 }

D 200 0 1600 The point B and C clearly represent the optima. In this example, the constraint to which the objective function was parallel, was the one which formed a side of the boundary of the space of the feasible region. As mentioned in condition (a), if such a constraint (to which the objective function is parallel) does not form an edge or boundary of the feasible region, then multiple solutions would not exist.
X2

200

Optimal Solutions 150 A B 100 C X2 = 125

50

FEASIBLE
Iso-profit lines

REGION
0 100 D 200

E
300 X1

6. A firm produces three products A, B, and C, each of which passes through three departments: Fabrication, Finishing and Packaging. Each unit of product A requires 3, 4 and 2; a unit of product B requires 5, 4 and 4, while each unit of product C requires 2, 4 and 5 hours respectively in the three departments. Everyday, 60 hours are available in the fabrication department, 72 hours are available in the finishing department, and 100 hours in the packaging department. The unit contribution of product A is Rs. 5, of product B is Rs. 10 and of product C is Rs. 8. Required: a. Formulate the problem as an LPP and determine the number of units of each of the products that should be made each day to maximize the total contribution. Also determine if any capacity would remain unutilized. 6

b. If the optimal solution obtained does not require the production of some product, explain as to why such product would not be produced. In this context indicate the quantity (quantities) of other product/s that would be foregone for producing such product. c. What would be the effect on the solution of each of the following: i. Obtaining an order for 6 units of product A which has to be met. ii. An increase of 20% capacity in the fabrication department. d. The firm is contemplating introduction of a new product D with a likely profit margin of Rs. 8. The product shall consume 3 hours each in the fabrication and finishing departments and 2 hours in the packaging department. Should the firm introduce this product? Solution: 6.

a. X1 = 0, X2 = 8, X3 = 10. Unutilized capacity = 18 hours in the packaging department. b. X1 is not produced as producing 1 unit of X1 will reduce the objective function by 3.6667 If one were to produce 1 unit of X1, then X2 will reduce by .3333 units and X3 will reduce by .6667 units. Surplus packaging hours will increase by 2.6667. c. If an order for 6 units of product were to be met, then X2 will become 8-6*.3333 = 6.0002; X3 will become 10 6*.6667 = 5.9998 and packaging hours left over will be 18+6*2.6667 = 34.0002; Z = 160 6*3.6667 = 138.

ii. An increase of 20% capacity in the fabrication department will result in an increase in the objective function by 12*.6667 = 8.0004 (20% increase = .2*60 = 12); increase in production of X2 by 12*.3333 = 3.9996; decrease in X3 by 12*.3333 = 3.9996 packaging hours will increase by 12*.3333 = 3.9996 New solution will be X2 = 11.9996; X3 = 6.0004; S3 = 21.9996 and Z = 168.0002. d. Contribution of D = 8. Worth of resources consumed by D = 3*.6667 + 3*1.6667 = 7.0002 8. Therefore firm should produce product D.

7. A manufacturing company is engaged in producing three types of products: A, B and C. The production department produces, each day, components sufficient to make 50 units of A, 25 units of B and 30 units of C. The management is confronted with the problem of optimizing the daily production of products in assembly department where only 100 man-hours are available daily to assemble the products. The following additional information is available.
Type of Product Profit Contribution per Assembly Time per Unit of Product (Rs) Product (hrs) 12 0.8 20 45 1.7 2.5

A B C

The company has a daily order commitment for 20 units of products A and a total of 15 units of products B and C. Formulate this problem as an LP model so as to maximize the total profit. Plant A Plant B Plant C X1 X2 X3 Maximise Z = 12 X1 + 20 X2 + 45 X3 Subject to : X1 <= 50 X2 <=25 X1 >=20 X3 <=30 X2 + X3 >=15 0.8 X1 + 1.7 X2 + 2.5 X3 <=100 X1, X2, X3 >=0 8. A company has two plants, each of which produces and supplies two products: A and B. The plants can each work up to 16 hours a day. In plant 1, it takes three hours to prepare and pack 1,000 gallons of A and one hour to prepare and pack one quintal of B. In plant 2, it takes two hours to prepare and pack 1,000 gallons of A and 1.5 hours to prepare and pack a quintal of B. In plant 1, it costs Rs 15,000 to prepare and pack 1,000 gallons of A and Rs 28,000 to prepare and pack a quintal of B, whereas these costs are Rs 18,000 and Rs 26,000, respectively in plant 2. The company is obliged to produce daily at least 10 thousand gallons of A and 8 quintals of B. Formulate this problem as an LP model to find out as to how the company should organize its production so that the required amounts of the two products be obtained at minimum cost. 8

Ans Product A Product B Plant 1 Plant 2 X1 X2 X3 X4 Minimise Z = 15000 X1 + 18000 X2 + 28000X3 + 26000 X4 Subject to : 3X1 + X3 <= 16 2X2 + 1.5X4 <=16 X1 + X2 >=10 X3 + X4 >=8 X1, X2, X3,X4>=0

9. An electronic company is engaged in the production of two components C1 and C2 used in radio sets. Each unit of C1 costs the company Rs 5 in wages and Rs 5 in material, while each of C2 costs the company Rs 25 in wages and Rs 15 in material. The company sells both products on oneperiod credit terms, but the companys labour and material expenses must be paid in cash. The selling price of C1 is Rs 30 per unit and of C2 it is Rs 70 per unit. Because of the strong monopoly of the company for these components, it is assumed that the company can sell at the prevailing prices as many units as it produces. The companys production capacity is, however, limited by two considerations. First, at the beginning of period 1, the company has an initial balance of Rs 4,000 (cash plus bank credit plus collections from past credit sales). Second, the company has available in each period 2,000 hours of machine time and 1,400 hours of assembly time. The production of each C1 requires 3 hours of machine time and 2 hours of assembly time, whereas the production of each C2 requires 2 hours of machine time and 3 hours of assembly time. Formulate this problem as an LP model so as to maximize the total profit to the company. C1 C2 X1 X2 Maximise Z = 20 X1 + 30 X2 Subject to : 10X1 + 40X2 <= 4000 3X1 + 2X2 <= 2000 2X1 + 3X2 <= 1400 X1, X2 >=0 10. A company has two grades of inspectors 1 and 2, who are to be assigned for a quality control inspection. It is required that at least 2,000 pieces be inspected per 8 hour day. Grade 1 inspector can check pieces at the rate of 40 per hour, with an accuracy of 97 per cent. Grade 2 inspector checks at the rate of 30 pieces per hour with an accuracy of 95 per cent. The wage rate of a Grade 1 inspector is Rs 5 per hour while that of a Grade 2 inspector is Rs 4 per hour. An error made by an inspector costs Rs 3 to the company. There are only nine Grade 1 inspectors and eleven Grade 2 inspectors available in the company. The company wishes to assign work to the available inspectors so as to minimize the total cost of the inspection. Formulate this problem as an LP model so as to minimize daily inspection cost. Grade 1 Grade 2 X1 X2 Minimize 68.8 X1 + 68 X2 Subject to: 320X1 + 240 X2 >=2000 X1<=9 9

X2<=11 X1, X2 >=0 11. Let us assume that you have inherited Rs. 1,00,000 from your father -in-law that can be invested in a combination of only two stock portfolios, with the maximum investment allowed in either portfolio set at Rs. 75,000. The first portfolio has an average rate of return of 10%, whereas the second has 20%. In terms of risk factors associated with these portfolios, the first has a risk rating of 4 (o n a scale from 0 to 10), and the second has 9. Since you wish to maximise your return, you will not accept an average rate of return below 12% or a risk factor above 6. Hence, you then face the important question. How much should you invest in each portfol io? Formulate this as a Linear Programming Problem . Ans: Maximise Z = 0.1X1 + 0.2X2 Subject to : 4X1 + 9X2 6(X1 + X2) 0.1X1 + 0.2X2 0.12(X1 + X2) X1 + X2 1,00,000 X1 75,000 X2 75,000 X1 , X2 >=0 12. An electronic company produces three types of parts for automatic washing machines. It purchases casting of the parts from a local foundry and then finishes the part on drilling, shaping and polishing machines. The selling prices of parts A, B and C, respectively are Rs 8, Rs 10 and Rs 14. All parts made can be sold. Castings for parts A, B and C, respectively cost Rs 5, Rs 6 and Rs 10. The shop possesses only one of each type of machine. Costs per hour to run each of the three machines are Rs 20 for drilling, Rs 30 for shaping and Rs 30 for polishing. The capacities (parts per hour) for each part on each machine are shown in the following table: Machine

Capacity Per Hour


Part A 25 25 40 Part B 40 20 30 Part C 25 20 40

Drilling Shaping Polishing

The management of the shop wants to know how many parts of each type it should produce per hour in order to maximize profit for an hours run. Formulate this problem as an LP model so as to maximize total profit to the company. Ans A B C X1 X2 X3 Maximize Z = 0.25 X1 + X2 + 0.95 X3 Subject to : X1/25 + X2/40 + X3/25 <=1 X1/25 + X2/20 + X3/20 <=1 X1/40 + X2/30 + X3/40 <=1 X1, X2, X3 >=0 10

13. A media campaign has to be designed for a new footwear company with an ad budget of Rs. 20 lakhs. The media, cost and its effectiveness are displayed in the table below: Advertising Cost per Estimated Media unit (RS) no. of exposure Newspaper 20,000 100,000 Radio 40,000 500,000 Television 100,000 1,000,000 The client wishes that at least 5,000,000 exposure must be achieved. Also newspaper advertising should not exceed 500,000. Design a media plan. Ans: X1 : No.of releases in newspaper X2 : No. of releases on radio X3 : No. of releases on Television Maximise Z = 100,000 X1 + 500,000X2 + 1000,000X3 Subject to: 20,000 X1 + 40,000X2 + 100,000X3 2000,000 100,000 X1 + 500,000 X2 + 1000,000 X3 5000,000 20,000 X1 500,000 X1, X2, X3 0 14. A company engaged in producing tinned food, has 300 trained employees on the rolls, each of whom can produce one can of food in a week. Due to the developing taste of the public for this kind of food, the company plans to add existing labour force by employing 150 people, in a phased manner, over the next 5 weeks. The newcomers would have to undergo a two week training program before being put to work. The training to be given by employees from among existing ones and it is known that one employee can train three trainees. Assume that there will be no production from trainers and the trainees during the training period as the training is off-the-job. However the trainees would be remunerated at the rate of Rs 300 per week, the same rate as for the trainers. The company has booked following orders to supply during the next five weeks : Week No of cans 1 280 2 298 3 305 4 360 5 400

Assume that The production in any week would not be more than the number of cans ordered for , so that every delivery of the food would be fresh Formulate this problem as an LP model to develop a training schedule that minimizes the labour costs over the five week period. Ans: Minimize Z= 5X1 + 4X2 + 3X3 + 2X4 + X5 Subject to 300 X1/3 >=280 300 X1/3 X2/3 >=298 300 + X1 X2/3 X3/3 >=305 300 + X1 + X2 X3/3 X4/3 >=360 300 + X1 + X2 + X3 X4/3 X5/3 >=400 X1 + X2 + X3 + X4 + X5 =150 11

X1,X2,X3,X4 & X5>=0 15. A firm plans to purchase at least 200 tons of scrap containing high grade Metal H and Low grade metal L. The firm wants to end up with at least 100 tons of H and not more than 35 tons of L. The contents of scrap from two dealers A and B is given in the table Metal Supplier A Supplier B H 25% 75% L 10% 20% Cost (per 200 400 ton) Formulate the buying plan to minimise the cost. Let X1 tons from Supplier A and X2 tons from Supplier B Minimise Z = 200X1 + 400X2 Subject to : X1+X2>=200 0.25X1+0.75X2>=100 0.1X1+0.2X2 <=35 X1, X2, >=0 16. A public limited company is planning its capital structure that will consist of equity capital, 15% debentures and term-loan. Debentures are to be repaid on face value, interest rate is payable half yearly and annualised cost of issue of debenture is 1/2%. Interest on term-loan is 18% p.a. to be paid annually while the cost of equity is estimated at 20%. It is decided not to have outsiders funds more than 2 times of equity funds; also the amount of term -loan must be at least 50% of the debenture amount. Formulate a suitable linear programming model so as to minimise average cost of capital of the company. Ans: Equity Debentures X1 X2 Minimize Z= 0.2X1 + 0.155X2 + 0.18X3 Subject to X2 + X3 2X1 X3 0.5X2 X1,X2,X3, 0 Term Loan X3

17. Smart Ltd. makes two types of adhesives Quik and Tuff. The table gives the raw material consumed by the two brands.: Raw material Price Quik Tuff (Rs / ton) N 600 350 200 A 400 50 100 P 400 50 100 I 200 550 600 1000kg 1000kg

12

Quik can be blended at 1000 Kg per hour, whereas Tuff at 1250 Kg per hour. The respective selling prices are Rs. 1010 and Rs. 845. (per Ton)Variable costs are Rs. 500 per hour of plant production time. The Maximum availability of raw materials is given below. Raw material Max. available (kg) N 1000 A 300 P 250 I 1800 Find the optimum product mix to maximise profits. Ans Maximize Z = 150 X1+ 125X2 Subject to 350X1+200X2<=1000 50X1+100X2<=300 50X1+100X2<=250 550X1+600X2<=1800 X1,X2>=0

13

18. A company has four machines on which three jobs have to be done. Each job can be assigned to one and only one machine. The cost of each job on each machine is given in the following Table. P 18 8 10 Q 24 13 15 R 28 17 19 S 32 19 22

Job

problem to find assignments which will minimize the cost. Ans: Let the allocation of jobs to machines be as under: A B C Demand P X11 X21 X31 1 Q X12 X22 X32 1 R X13 X23 X33 1

A B C

Formulate this as an LP model out the job

Job

S X14 X24 X34 1

Supply 1 1 1

Minimse Z = 18 X11 + 24X12 + 28 X13 + 32 X14 + 8 X21+ 13 X22 + 17X23 + 19X24 + 10X31 + 15 X32 + 19X33 + 22X34 Subject to: X11 + X12 + X13 + X14 = 1 X21 + X22+ X23 + X24 = 1 X31 + X32 + X33 + X34 = 1 X11 + X21 + X31 1 X12 + X22 + X32 1 X13 + X23+ X33 1 X14 + X24 + X34 1 X11, X12, X13, X14, , X21, X22, X23, X24, X31, X32, X33, X34, 0 19. A manufacturer has distribution centers at X , Y, & Z. these centers have availability 40, 20 and 40 units of his product. His retail outlets at A, B, C, D & E require 25, 10, 20, 30 & 15 units respectively. The transportation cost ( in Rs) per unit between each center and outlet are given below. Distribution Centers X Y Z Retail outlets A 55 35 40

B 30 30 60

C 40 100 95

D 50 45 35

E 50 60 30

Formulate this problem as an LP model to find out how many units from each distributers should be transported to which retail outlets so as to minimize cost. Ans: Let the allocation of units from the distributor to the retail outlets be as under: Distribution Retail B C D E 14

Centers X Y Z Requirement

outlets A X11 X21 X31 25

Availability X12 X22 X32 10 X13 X23 X33 20 X14 X24 X34 30 X15 X25 X35 15 40 20 40

Minimse Z = 55 X11 + 30 X12 + 40 X13 + 50 X14 + 50X15 + 35 X21+ 30 X22 + 100 X23 + 45X24 +60 X25 + 40X31 + 60 X32 + 95X33 + 35 X34 + 30X35 Subject to: X11 + X12 + X13 + X14 + X15 = 40 X21 + X22+ X23 + X24 + X25 = 20 X31 + X32 + X33 + X34 + X35 = 40 X11 + X21 + X31= 25 X12 + X22 + X32 = 10 X13 + X23+ X33 = 20 X14 + X24 + X34 = 30 X15 + X25 + X35 = 15 X11, X12, X13, X14, X15, X21, X22, X23, X24, X25, X31, X32, X33, X34, X35 0 20. Manager of an oil refinery has to decide the optimum mix of two possible blending processes of which inputs and outputs per production run are given in the table. Input Output Process Crude Crude Gasoline Gasoline A B X Y I 5 3 5 8 II 4 5 4 4 The maximum amounts of Crude A and B available are 200 units and 150 units respectively. Market requirements show that at least 100 units of Gasoline X and 80 units of Gasoline Y must be produced. Profits per production run from Process I and Process II are Rs. 4000 and Rs. 5000 respectively. Determine the optimum production runs of each process to maximise profits.

Maximise Z = 4000X1 + 5000X2 Subject to : 5 X1 + 4X2 <=200 3X1 + 5X2 <=150 5 X1 + 4X2 >=100 8X1 + 4X2 >=80

X1 , X2 >=0

21. A cooperative farm owns 100 acres of land and has Rs 25,000 in funds available for investment. The farm members can produce a total of 3500 man -hours worth of labour during the months September -May and 4000 man-hours during June-August. Cash income can be obtained from the three main crops and two types of livestock: dairy cows and laying hens. No investment funds are needed for the crops. However, 15

each cow will require an investment outlay of Rs 3200 and each hen will require Rs 15. Moreover, each cow will require 1.5 acres of land, 100 man -hours during the summer and 50 man-hours during June-Aug. Each cow will produce a net annual cash income of Rs 3500 for the farm. The corresponding figures for each hen are: no acreage, 0.6 man-hours during September-May; 0.4 man-hours during June-August, and an annual net cash income of Rs 200. The chicken house can accommodate a maximum of 4000 hens and the size of the cattle-shed limits the members to a maximum of 32 cows. Estimated man-hours and income per acre planted in each of the three crops are: Paddy Bajra Jowar Man-hours September-May 40 20 25 June-August 50 35 40 Net annual cash income (Rs) 1200 800 850 The cooperative farm wishes to determine how much acreage should be planted in each of the crops and how many cows and hens should be kept to maximise its net cash income.
LP model formulation: The data of the problem is summarised as follows: Constraints Cow Man-hours Sept-May June-Aug Land Cow Hens Net annual Cash income (Rs) 3500 Decision variables: Let x 1 and x 2 x 3 , x 4 and x 5 The LP model Maximise (net cash income) Z = 3500 x 1 + 200 x 2 + 1200 x 3 + 800 x 4 + 850 x 5 subject to the constraints (i) Man-hours constraints 100 x 1 + 0.6 x 2 + 40 x 3 + 20 x 4 + 25 x 5 3500 50 x 1 + 0.4 x 2 + 50 x 3 + 35 x 4 + 40 x 5 4000 (ii) Land availability constraints 1.5 x 1 + x 3 + x 4 + x 5 100 (Sept.-May duration) (June-Aug. duration) = number of dair y cows and laying hens respectively = average of paddy crop, bajra crop and jowar crop respectively 200 1200 800 850 100 50 1.5 1 0.6 0.4 1 15 40 50 1 20 35 1 25 40 1 3500 4000 100 32 4000 25000 Hens Crop Paddy Bajra Jowar Total availability

Investment Outlay 3200

16

(iii)

Livestock constraints x 1 32 (dair y cows) x 2 4000 (laying hens)

(iv)

Funds availability constraint 3200 x 1 + 15 x 2 25000 x1, x2, x3, x4, x5 0

and

22. A firm is engaged in producing two products : P1 and P2. The relevant data are given here: Per Unit Product P1 Product P2 (i) Selling price Rs 200 Rs 240 (ii) Direct materials Rs. 45 Rs. 50 (iii) Direct wages Dept A 8 hrs @ Rs. 2 / hr 10 hrs @ Rs 2 /hr Dept B 10 hrs @ Rs 2.25 / hr 6 hrs @ Rs 2.25 /hr Dept C 4 hrs @ Rs 2.5 / hr 12 hrs @ Rs 2.5 / hr (iv) Variable overheads Rs. 6.50 Rs 11.50 Fixed overhead = Rs 2,85,000 per annum No of employees in the three departments: Dept A = 20 Dept B = 15 Dept C = 18 No. of hours / employee / week = 40 in each department No. of weeks per annum = 50 (a) Formulate the given problem as a linear programming problem and solve graphically to determine (i) the product mix as will maximize the contribution margin of the firm (ii) the amount of contribution margin and profit obtainable per year (a) From the graph, do you observe any constraint that is redundant? Which one, if yes?

17

Yes the constraint 8X1 + 10 X2 <=40000 is redundant. 23. Solve graphically: Minimise Z = 6x 1 + 14x 2 Subject to 5x 1 + 4x 2 60 3x 1 + 7x 2 84 x 1 + 2x 2 18 x1, x2 0 Solution: The restrictions in respect of the given problem are depicted graphically in Figure 4.6. The feasible area has been shown shaded. It may be observed here that although the iso -cost line is parallel to the second constraint line represented by 3x 1 + 7x 2 = 84, and this constraint does provide a side of the area of feasible solutions, yet the problem has a unique optimal solution, given by the point D. Here condition (b) mentioned earlier, is not satisfied. This is because, being a minimisation problem, the optimal movement of the objective function would be towards the origin and the constraint forms a boundary on the opposite side. Since the constraint is not a binding one, the problem does not have multiple optima.

18

X2 15

12 B 9

6 A 3

FEASIBLE REGION D
6 12 18 24 C 30 X1

We can show the uniqueness of the solution by evaluating various extreme points as done here. Point A B C D x1 8 84/23 28 18 x2 5 240/23 0 0 Z = 6x 1 + 14x 2 118 168 148 108

The optimum solution is 108 units for x 1 = 18 and x 2 = 0. 24. Cashewco has two grades of cashew nuts: Grade I 750 kg and Grade II 1,200 kg. These are to be mixed in two types of packages of one kilogram each- economy and special. The economy pack consists of grade I and grade II cashews in the proportion of 1:3, while the special pack combines the two in equal proportion. The profit margin on the economy and special packs is, respectively, Rs. 5 and Rs. 8 a pack. (a) Formulate this as a linear programming problem. (b) Ascertain graphically the number of packages of economy and special types to be made that will maximize the profits.

19

Would your answer be different if the profit margin on a special pack be Rs. 10? Yes. It would change. X1 = 0, X2 = 1500, Z = 15000. Upper bound is 10 Therefore solution changes for 10 and above. 25. A local travel agent is planning a charter trip to a major sea resort. The eight day/seven-night package includes the fare for round-trip travel, surface transportation, and boarding and loading and selected tour options. The charter trip is restricted to 200 persons and past experience indicates that there will not be any problem for getting 200 persons. The problem for the travel agent is to determine the number of Deluxe, Standard, and Economy tour packages to offer for this charter. These three plans differ according to seating and service for the fight, quality of accommodations, meal plans and tour options. The following table summarizes the estimated prices for the three packages and the corresponding expenses for the travel agent. The travel agent has hired an aircraft for the flat fee of Rs 2,00,000 for the entire trip. Prices and Costs for Tour Packages per Person Tour Plan Deluxe Standard Economy Price (Rs) 10,000 7,000 6,500 Hotel Costs (Rs) 3,000 2,200 1,900 Meals & Other Expenses (Rs) 4,750 2,500 2,200

In planning the trip, the following considerations must be taken into account: (i) At least 10 per cent of the packages must be of the deluxe type. (ii) At least 35 per cent but no more than 70 per cent must be of the standard type. (iii) At least 30 per cent must be of the economy type. (iv) The maximum number of deluxe packages available in any aircraft is restricted to 60. 20

The hotel desires that at least 120 of the tourists should be on the deluxe and standard packages together. The travel agent wishes to determine the number of packages to offer in each type so as to maximize the total profit. (a) Formulate this problem as a linear programming problem. (b) Restate the above linear programming problem in terms of two decision variables, taking advantage of the fact that 200 packages will be sold. (c) Find the optimum solution using graphical method for the restated linear programming problem and interpret your results.

(v)

Ans : 20 D , 100 S, 80 E Profit = 280000 13000 = 267000.