Sei sulla pagina 1di 8

ID 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39

Task Name MILESTONES COMPLETION MILESTONES EFFECTIVE DATE PERFORMANCE BANK GURANTEE CONTRACT COOORDINATION MANUAL DETAILED TIME SCHEDULE (E&P) FIRST FOUNDATION DRAWINGS START FOUNDATION CASTING ON SITE PURCHASE ORDER ORDER STEEL STRUCTURE MODULES PRE-FABRICATIO ISSUE REQUISITION FOR ITEMIZED EQUIPMENT COMPLETED FIRST GENERAL ARRANGEMENT & EQUIPMENT LAYOUT DRAWINGS HAZOP REVIEW COMPLETED FIRST PIDs 3D MODEL REVIEW FOR PROCESS UNITS COMPLETED 2-YEARS MAINTENANCE/OPERATIONAL SPARE PART ISSUE TO COMPANY START STEEL STRUCTURE ERECTION ON SITE 95% OF BULK MATERIAS PURCHASE ORDER PLACED FIRST HEAVY EQUIPMENT LIFTED ON SITE FIRST LAYING DOWN OF PIPING ON PIPE RACKS ON SITE FAT FOR DCS/ESD/PLC COMPLETED MAJOR EQUIPMENT AND EQUIPMENT PACKAGES FOUNDATION COMPLETE READY FOR START UP - BUILDING READY FOR COMMISSIONING - BUILDING DELIVERY OF MAJOR EQIPMENT AND EQUIPMENT PACKAGES COMPLETED READY FOR COMMISSIONING - WASTE GAS TREATMENT SYSTEM READY FOR COMMISSIONING FUEL GAS SYSTEM READY FOR COMMSSIONING - COMMON - SAFETY SYSTEM READY FOR COMMISSIONING - FIRE WATER SYSTEM READY FOR START UP - FIRE WATER SYSTEM READY FOR COMMISSIONING - COMMON - ELECTRICAL SYSTEM READY FOR COMMISSIONING - COMMON - DCS SYSTEM FIRST PRE- START UP SAFETY REVIEW MEETING READY FOR START UP - COMMON - ELECTRICAL SYSTEM READY FOR COMMISSIONING - UTILITY AIR SYSTEM READY FOR COMMISSIONING - SAMPLING SYSTEM INCLUDING LABORATOR READY FOR START UP- COMMON - SAFETY SYSTEM READY FOR COMMISSIONING - INSTRUMENT AIR SYSTEM READY FOR COMMISSIONING FLARE SYSTEM READY FOR START UP - COMMON - DCS SYSTEM Task Milestone Summary Project Summary Page 1

Duration 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day?

Start M Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 External Tasks External Milestone Deadline T W T

Project: Level 3- Project Schedule - Ga Date: Wed 3/6/13

Split Progress

ID 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78

Task Name READY FOR START UP - INSTRUMENT AIR SYSTEM READY FOR COMMSSIONING - PIPE RACK READY FOR START UP PIPE RACK READY FOR COMMISSIONING - LPG STORAGE LOADING/ OFF LOADING READY FOR START UP UTILITY AIR SYSTEM READY FOR COMMISSIONING CONDENSATE SYSTEM READY FOR START UP CONDENSATE SYSTEM READY FOR START UP RECYCLE GAS TO EP SYSTEM READY FOR START UP FUEL GAS SYSTEM READY FOR START UP LPG STORAGE LOADING/ OFF LOADING READY FOR START UP WASTE GAS TREATMENT SYSTEM READY FOR COMMISSIONING COOLING WATER SYSTEM READY FOR START UP COOLING WATER SYSTEM READY DOR COMMISSIONING CHILLED WATER SYSTEM READY FOR START UP CHILLED WATER SYSTEM READY FOR COMMISSIONING WATER SYSTEM READY FOR START UP WATER SYSTEM READY FOR START UP FLARE SYSTEM READY FOR COMMISSIONING COMPRESSION SYSTEM NOTICE OF ANTICIPATED COMPLETION / START OF JOINT INSPECTION READY FOR COMMISSIONING - SPEARATION SYSTEM READY FOR COMMISSIONING - ROADS & PAVING READY FOR START UP - ROADS & PAVING READY FOR START UP - COMPRESSION SYSTEM FINAL DOCUMENTATION HANDED OVER TO COMPANY READY FOR FEED IN PAYMENT MILE STONES DOWN PAYMENT DETAILED WORK TIME SCHEDULE COMMENCEMENT OF MOBILIZATION TO SITE PURCHASE ORDER OF FIRST MTO PLACED START FOUNSATION CASTING ON SITE PURCHASE ORDER STEEL STRUCTURE MODULES PREFABRICATION PLACE ISSUE REQUISITION FOR ITEMIZED EQUIPMENT COMPLETED HAZOP REVIEW COMPLETED START STEEL STRUCTURE ERECTION ON SITE 95% OF BULK MATERIALS PURCHASE ORDER PLACED FIRST LAYING DOWN OF PIPING ON PIPE RACKS ON SITE FAT FOR DCS/ESD/PLC COMPLETED Task Milestone Summary Project Summary Page 2

Duration 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day?

Start M Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 External Tasks External Milestone Deadline T W T

Project: Level 3- Project Schedule - Ga Date: Wed 3/6/13

Split Progress

ID 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117

Task Name DELIVERY OF MAJOR EQUIPMENT AND EQUIPMENT PAKCAGES COMPLETE PIPING ERECTION ON PIPE RACKS COMPLETED READY FOR FEED IN PROVISIONAL ACCEPTANCE CE&O MILESTONES MASTER PROCUREMENT LIST HANDOVER OF BASIC PROCESS ENGINEERING PACKAGE HANDOVER OF BASIC PIPING ENGINEERING PACKAGE HANDOVER OF BASIC INSTRUMENTATION PACKAGE HANDOVER OF BASIC CIVIL ENGINEERING PACKAGE HANDOVER OF BASIC LAYOUT ENGINEERING PACKAGE HANDOVER OF BASIC ELECTRICAL ENGINEERING PACKAGE CONSOLIDATION PACKAGE COMPLETE (HAZOP STUDY CHECK) HANDOVER OF BASIC EQUIPMENT ENGINEERING PACKAGE AWARD OF CONSTRUCTION SERVICES GENERAL READINESS FOR COMMENCEMENT OF CONSTRUCTION WORKS READINESS FOR COMMENCEMENT OF CONCRETE WORK CONSUMER LIST READINESS FOR COMMENCEMENT OF PIPING INSTALLATION PRESSURE LOOPS & "CLEANING & TESTING PROCEEDURES" OF PIPING SY READINESS FOR COMMENCEMENT OF STEEL STRUCTURE ERECTION INPUT OF PROCESS ENGINEERING FOR FUNCTIONAL & LOGIC PLANS READINESS FOR COMMENCEMENT OF EQUIPMENT INSTALLATION READINESS FOR COMMENCEMENT OF PIPING PRE-FABRICATION READINESS FOR COMMENCEMENT OF PIPING INSTALLATION COMMISSIONING ENGINEERING READINESS FOR COMMENCEMENT OF ELECTRICAL & INSTRUMENTATION I WP 1- PROJECT MANAGEMENT PROJECT EXECUTION INSTRUCTIONS/PREPARATORY WORK/CONTROLLING ENGINEERING MANAGEMENT COMMERCIAL CONTRACT EXECUTION COST CONTROLLING PROGRESS CONTROLLING PROCUREMENT MANAGEMENT WP 2 - ENGINEERING PROCESS GENERAL PIPING & INSTRUMENTATION DIAGRAMS HAZOP Task Milestone Summary Project Summary Page 3

Duration 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day?

Start M Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 External Tasks External Milestone Deadline T W T

Project: Level 3- Project Schedule - Ga Date: Wed 3/6/13

Split Progress

ID 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 156

Task Name DESCRIPTION & MANUALS FINAL DOCUMENTATION HEALTH, SAFETY , ENVIRONMENT GENERAL HAZOP STUDIES PLOT PLAN & EQUIPMENT ARRANGEMENT GENERAL PLANT LAYOUT FINAL DOCUMENTATION STATIC EQUIPMET / PACKAGE UNITS GENERAL MAJOR EQUIPMENT STD EQUIPMENT PACKAGE UNITS FINAL DOCUMENTATION MACHINERY / PACKAGE UNITS / HVAC /FF GENARAL MAJORE EQUIPMET STD EQUIPMENT PACKAGE UNITS FINAL DOCUMENTATION INSTRUMENTATION GENERAL PROCUREMENT ENGINEERING WIRING AND INSTALLATION DRAWINGS FINAL DOCUMENTATION ELECTRICAL GENERAL PROCUREMENT ENGINEERING WIRING 7 INSTALLATIPN DRAWINGS FINAL DOCUMENTATION PIPING GENERAL PIPING DESIGN STRESS ANALYSIS MATERIAL TAKE OFF PIPING LAYOUT FINAL DOCUMENTATION Task Milestone Summary Project Summary Page 4

Duration 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day?

Start M Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 External Tasks External Milestone Deadline T W T

Project: Level 3- Project Schedule - Ga Date: Wed 3/6/13

Split Progress

ID 157 158 159 160 161 162 163 164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183 184 185 186 187 188 189 190 191 192 193 194 195

Task Name CIVIL GENERAL PILING CALCULATIONS & DRAWINGS FOUNDATION / CONCRETE CALCULATIONS & DRAWINGS STEEL CALCULATION & DRAWINGS FINAL DOCUMENTATION ERECTION ENGINEERING GENERAL EQUIPMENT ERECTION PIPING ERECTION WP 3 - PROCUREMENT GAS SWEETNING AMINE CONTRACTING COLUMN AMINE FLASH TANK RICH/LEAN AMINE HEAT EXCHANGER AMINE SURGE TANK AMINE BOOSTER PUMPS LEAN AMINE COOLER AMINE STILL COLUMN AMINE PARTICULATE FILTER AMINE CARBON FILTER AMINE CHARGE PUMPS AMINE REBOILER MAKEUP TANKS PIPING INSTRUMENTATION REFERIGERATION PACKAGE GAS/GAS HEAT EXCHANGER GAS/CONDENSATE HEAT EXCHANGER CHILLER LOW TEMPERATURE SEPARATOR DE-ETHANIZER TOWER DE-ETHANIZER REBOILER GLYCOL PUMPS GLYCOL RECONCENTRATOR GLYCOL PARTICULATE FILTER CHARCOL FILTER GLYCOL / HC FLASH SEPARATOR OVERHEADS CONDENSOR Task Milestone Summary Project Summary Page 5

Duration 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day?

Start M Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 External Tasks External Milestone Deadline T W T

Project: Level 3- Project Schedule - Ga Date: Wed 3/6/13

Split Progress

ID 196 197 198 199 200 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215 216 217 218 219 220 221 222 223 224 225 226 227 228 229 230 231 232 233 234

Task Name DE-BUTANIZER REFLUX DRUM DE-BUTANIZER REFLUX PUMPS DE-BUTANIZER TOWER DE-BUTANIZER REBOILER CONDENSATE PRODUCT COOLER PROPANE ACCUMULATOR PROPANE DRIER PROPANE CONDENSOR PROPANE REFERIGERATION PACKAGE HOT OIL MEDIUM PACKAGE INSTRUMENTATION PIPING EXPORT GAS COMPRESSION UNIT EXPORT GAS COMPRESSOR INLET GAS COMPRESSION UNIT INLET GAS COMPRESSOR RECYCLE GAS COMPRESSION UNIT RECYCLE GAS COMPRESSOR SALES GAS METERING SKID GAS CHROMATOGRAPH H2S ANALYZER MOISTURE ANALYZER LPG METERING SKID INSTRUMENTATION PIPING CONDENSATE METERING SKID CONDENSATE METERING SKID INLET SPEARATATION SKID INLET SPEARATOR INSTRUMENTATION PIPING FUEL GAS & FLASH GAS SKID FUEL GAS SCRUBBER FLASH GAS COMPRESSOR INSTRUMENTATION PIPING FLARE SYSTEM HP FLARE KNOCK OUT DRUM LP FLARE KNOCK OUT DRUM Task Milestone Summary Project Summary Page 6

Duration 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day?

Start M Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 External Tasks External Milestone Deadline T W T

Project: Level 3- Project Schedule - Ga Date: Wed 3/6/13

Split Progress

ID 235 236 237 238 239 240 241 242 243 244 245 246 247 248 249 250 251 252 253 254 255 256 257 258 259 260 261 262 263 264 265 266 267 268 269 270 271 272 273

Task Name HP FLARE KO DRUM PUMP FLARE STACK LP FLARE KO DRUM PUMP INSTRUMENTATION PIPING CLOSED DRAIN VESSEL CLOSED DRAIN VESSEL CLOSED DRAIN PUMPS INSTRUMENTATION PIPING INSTRUMENT AIR PACKAGE AIR COMPRESSORS AIR FILTERS INSTRUMENTATION PIPING POWER GENERATION GAS GENERATORS DIESEL GENERATOR INSTRUMENTATION PIPING CHEMICAL INJECTION SKID METHANOL INJECTION PUMP ANTI-FOAM PUMP CORROSION INHIBITOR PUMP SCALE INHIBITOR PUMP INSTRUMENTATION PIPING PRODUCED WATER STORAGE PRODUCED WATER STORAGE TANK WATER TRANSFER PUMPS INSTRUMENTATION PIPING CONDENSATE STORAGE CONDENSATE STORAGE TANKS CONDENSATE PUMP TRUCK LOADING PUMPS INSTRUMENTATION PIPING LPG STORAGE Task Milestone Summary Project Summary Page 7

Duration 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day?

Start M Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 External Tasks External Milestone Deadline T W T

Project: Level 3- Project Schedule - Ga Date: Wed 3/6/13

Split Progress

ID 274 275 276 277 278 279 280 281 282 283 284 285 286 287 288 289 290 291 292 293 294 295 296

Task Name LPG STORAGE TANKS LPG LOADING PUMPS INSTRUMENTATION PIPING LPG METERING CONTROL UNIT INSTRUMENTATION PIPING INLET PRESSURE CONTROL & COOLER INLET COOLER INSTRUMENTATION PIPING FIRE WATER SYSTEM FIRE WATER STORAGE TANK FIRE WATER PUMPS JOCKEY PUMP AMINE/DEMIN WATER STORAGE & DISTRIBUTION AMINE/DEMIN WATER STORAGE TANK AMINE/DEMIN WATER PUMP WP 4 - PROCUREMENT AND SUPPLY OF BULK MATERIALS PIPING EQUIPMENT INSTRUMENTATION EQUIPMENT ELECTRICAL EQUIPMENT

Duration 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day?

Start M Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 Wed 3/6/13 T W T

Task Project: Level 3- Project Schedule - Ga Date: Wed 3/6/13 Split Progress

Milestone Summary Project Summary Page 8

External Tasks External Milestone Deadline

Potrebbero piacerti anche