Supplying, fabrication etc of M.S.

rod in RCC works in all floors: minimum fy = 415 Mpa (Present Market Price) Considering 50 kg of work A. Cost of materials: i) M.S. rod: 60 grade 50 kg @ ii) G.I. wire 1.5 kg @ B. Cost of labour i) Rod binder 0.2 Nos. @ ii) Helper to rod binder 0.75 Nos. @ iii) Local carriage, T & P etc.

60 grade deformed bar with

Tk. Tk. Tk. Tk.

66.00 100.00 450.00 350.00

Per kg. = Tk. Per kg. = Tk. each each L.S. Total 0.00% 0.00% = = = = = =

3,300.00 150.00 90.00 262.50 50.00 3,852.50 3,852.50 3,852.50 7,705.00

Tk. Tk. Tk. Tk. Contractor's profit Tk. Overhead expenses Tk. Tk. VAT 0.00% = Tk. Grand total = Tk. Rate per quintal = Tk. Say, Tk. 7,705 .00 Per quintal

Supplying, fabrication etc of M.S. rod in RCC works in all floors: minimum fy = 415 Mpa (Recorded Highest Price) Considering 50 kg of work A. Cost of materials: i) M.S. rod: 60 grade 50 kg @ ii) G.I. wire 1.5 kg @ B. Cost of labour i) Rod binder 0.2 Nos. @ ii) Helper to rod binder 0.75 Nos. @ iii) Local carriage, T & P etc.

60 grade deformed bar with

Tk. Tk. Tk. Tk.

78.00 100.00 450.00 350.00

Per kg. = Tk. Per kg. = Tk. each each L.S. Total 0.00% 0.00% = = = = = =

3,900.00 150.00 90.00 262.50 50.00 4,452.50 4,452.50 4,452.50 8,905.00

Tk. Tk. Tk. Tk. Contractor's profit Tk. Overhead expenses Tk. Tk. VAT 0.00% = Tk. Grand total = Tk. Rate per quintal = Tk. Say, Tk. 8,905 .00 Per quintal